Download - VGM Method Statement

Transcript
  • 8/19/2019 VGM Method Statement

    1/11

    VGM MStmt Ver2012(Jan) Page 1

    METHOD STATEMENT

    FOR

    ELMICH GREEN WALL

    VERTICAL GREENING MODULE (VGM)

    PREPARED BY

    ELMICH PTE LTD

  • 8/19/2019 VGM Method Statement

    2/11

    VGM MStmt Ver2012(Jan) Page 2

    METHOD STATEMENT

    ELMICH GREEN WALL

    VERTICAL GREENING MODULE (VGM)

    1. VGM

    1.1  Assemble VGM modules leaving removable top open

    1.2   Yellow triangle on front and back panels should be at the top

    1.3  Insert custom-fit planting media bag into module

    1.4 

    Fill media bag with planting medium flush with top of module

    1.5  Fold mouth of media bag to prevent spillage of media andattach VGM cover

    Media Bag Planting MediumVGM top open  Assembled VGM

  • 8/19/2019 VGM Method Statement

    3/11

    VGM MStmt Ver2012(Jan) Page 3

    2. Pre-plant VGMs in Nursery Environment

    2.1  Make slits in media bag and insert selected green wallplants,1 plant per aperture

    2.2  If side planting is required, cut and remove centre disk of side

    panel

    Make slit in Media Bag to insert plant

    Centre disk removed

    Centre disk of side panel Planted side panel

  • 8/19/2019 VGM Method Statement

    4/11

    VGM MStmt Ver2012(Jan) Page 4

    2.3  Allow at least 12 weeks for plants to firmly establish in nurseryenvironment

    2.4  Orientate plants to growth from a wall by progressively tilting

    VGM modules from horizontal to vertical over the 12 weeks

    3. Prepare Wall for VGM Installation

    3.1  Prime RC wall and/or construct framework (including

    waterproofing, painting, welding, etc) according to project

    requirements

    RC Wall Staging Framework

    VGMs tilted to orientate plants

  • 8/19/2019 VGM Method Statement

    5/11

    VGM MStmt Ver2012(Jan) Page 5

    3.2  Vertical beams of framework MUST correspond prec isely with

    VGM width for pilaster installation

    3.3  Erec t staging for work on high wall

    4. Install Pilasters

    4.1  Take vertical and horizontal wall measurements to determine

    position of first pilaster (anchor rails) according to projec t

    requirements

    4.2  Drill holes at all securing points to required depth using drill bit

    diameter corresponding with anchor used. Blow out dust and

    fragments

    Beam does not correspondwith VGM width

    Setting Tool

    Threaded Wedge Anchor

    Stainless Steel Bolt

    Stainless Steel Washer

    Beam does not correspondwith VGM width

    Wedge, Washer & Bolt

  • 8/19/2019 VGM Method Statement

    6/11

    VGM MStmt Ver2012(Jan) Page 6

    4.3  Pilaster positions MUST register with width of VGM and all

    pilaster mounting slots align

    4.3 

    Use assembled VGM modules to assist in accurate alignmentof pilasters

    4.5  Sec ure pilaster with stainless steel Stud or Wedge anchorstighten with torque wrench for RC wall or sec ure with stainless

    steel nuts and bolts for a constructed framework accordingly

     Assembled VGM modules assist in alignment of pilasters

    Pilasters

    VGM

    Pilaster

    Stainless Steel Bolt & Washer Stainless Steel Bolt & Nut

    RC Wall Framework

  • 8/19/2019 VGM Method Statement

    7/11

    VGM MStmt Ver2012(Jan) Page 7

    5. Irrigation and Fertigator System

    5.1  Secure irrigation tubing to pilasters at spec ifically spacedholes provided along length of pilasters with cable ties 

    5.2 Insert arrow drippers into separate points either at rear or rear

    and front of each VGM to evenly distribute water supply

    Cable-tie

    Hole for securingtubing

    Cable-tie

    Hole for securingtubing

    Distribute drippers evenly

    Dripper to bottom half ofVGM

    Dripper to top half of VGM

    Yellow triangle at top of VGM

  • 8/19/2019 VGM Method Statement

    8/11

    VGM MStmt Ver2012(Jan) Page 8

    5.3  Install irrigation system, including controller, solenoid valve,pressure regulator, filters and valves linked to fertiliser supply,

    to projec t requirements or as advised, to deliver irrigation and

    fertiliser at programmable intervals for controlled durations

    5.4  A rain sensor (optional) may be installed to overrideprogrammed water release when the green wall receives

    sufficient water from rain

    Solenoid Valve

    Controller

    Rain Sensor

    Over-pressure valve

  • 8/19/2019 VGM Method Statement

    9/11

    VGM MStmt Ver2012(Jan) Page 9

    6. Mounting

    6.1  Attach stainless steel mounting brackets to the 4 corners ofeach VGM and cover each with its plastic cover

    6.2 Secure mounting bracket to VGM with self-tapping screw toprevent bracket dislodgement before mounting

    6.3  Anchor VGM to the pilasters beginning from the bottom row

     Anchor VGM to Pilaster

     Attach Self-tappingScrew here

     Attach Self-tappingScrew here

  • 8/19/2019 VGM Method Statement

    10/11

    VGM MStmt Ver2012(Jan) Page 10

    6.4  Insert anti-lift arm between tops of mounted VGMs and push,from front to back, until arm clasp locks into pilaster slots

    6.5  Plug connectors of manifold/s into corresponding emitters

    along horizontal irrigation tubing as each VGM row is installed

    6.6  Install subsequent rows until all VGM rows are installed

    Emitters along tubing

    Emitters along tubing

     Arm clasp locked intopilaster slots

    Insert Anti-lift Arm

    Plug connectors intoemitters

    Plug connectors intoemitters

  • 8/19/2019 VGM Method Statement

    11/11

    VGM MStmt Ver2012(Jan) Page 11

    7. Inspection & Maintenance

    7.1  Follow a routine inspection and maintenance regime

    7.2  Ensure smooth running of irrigation system

    7.3  Weed away invasive unwanted growth

    7.4  Prune as necessary

    Install bottom row followed bysubsequent rows above

    Plug in connectors to emitters aseach VGM row is installed