VGM Method Statement
-
Upload
ambarinidian -
Category
Documents
-
view
238 -
download
0
Transcript of VGM Method Statement
-
8/19/2019 VGM Method Statement
1/11
VGM MStmt Ver2012(Jan) Page 1
METHOD STATEMENT
FOR
ELMICH GREEN WALL
VERTICAL GREENING MODULE (VGM)
PREPARED BY
ELMICH PTE LTD
-
8/19/2019 VGM Method Statement
2/11
VGM MStmt Ver2012(Jan) Page 2
METHOD STATEMENT
ELMICH GREEN WALL
VERTICAL GREENING MODULE (VGM)
1. VGM
1.1 Assemble VGM modules leaving removable top open
1.2 Yellow triangle on front and back panels should be at the top
1.3 Insert custom-fit planting media bag into module
1.4
Fill media bag with planting medium flush with top of module
1.5 Fold mouth of media bag to prevent spillage of media andattach VGM cover
Media Bag Planting MediumVGM top open Assembled VGM
-
8/19/2019 VGM Method Statement
3/11
VGM MStmt Ver2012(Jan) Page 3
2. Pre-plant VGMs in Nursery Environment
2.1 Make slits in media bag and insert selected green wallplants,1 plant per aperture
2.2 If side planting is required, cut and remove centre disk of side
panel
Make slit in Media Bag to insert plant
Centre disk removed
Centre disk of side panel Planted side panel
-
8/19/2019 VGM Method Statement
4/11
VGM MStmt Ver2012(Jan) Page 4
2.3 Allow at least 12 weeks for plants to firmly establish in nurseryenvironment
2.4 Orientate plants to growth from a wall by progressively tilting
VGM modules from horizontal to vertical over the 12 weeks
3. Prepare Wall for VGM Installation
3.1 Prime RC wall and/or construct framework (including
waterproofing, painting, welding, etc) according to project
requirements
RC Wall Staging Framework
VGMs tilted to orientate plants
-
8/19/2019 VGM Method Statement
5/11
VGM MStmt Ver2012(Jan) Page 5
3.2 Vertical beams of framework MUST correspond prec isely with
VGM width for pilaster installation
3.3 Erec t staging for work on high wall
4. Install Pilasters
4.1 Take vertical and horizontal wall measurements to determine
position of first pilaster (anchor rails) according to projec t
requirements
4.2 Drill holes at all securing points to required depth using drill bit
diameter corresponding with anchor used. Blow out dust and
fragments
Beam does not correspondwith VGM width
Setting Tool
Threaded Wedge Anchor
Stainless Steel Bolt
Stainless Steel Washer
Beam does not correspondwith VGM width
Wedge, Washer & Bolt
-
8/19/2019 VGM Method Statement
6/11
VGM MStmt Ver2012(Jan) Page 6
4.3 Pilaster positions MUST register with width of VGM and all
pilaster mounting slots align
4.3
Use assembled VGM modules to assist in accurate alignmentof pilasters
4.5 Sec ure pilaster with stainless steel Stud or Wedge anchorstighten with torque wrench for RC wall or sec ure with stainless
steel nuts and bolts for a constructed framework accordingly
Assembled VGM modules assist in alignment of pilasters
Pilasters
VGM
Pilaster
Stainless Steel Bolt & Washer Stainless Steel Bolt & Nut
RC Wall Framework
-
8/19/2019 VGM Method Statement
7/11
VGM MStmt Ver2012(Jan) Page 7
5. Irrigation and Fertigator System
5.1 Secure irrigation tubing to pilasters at spec ifically spacedholes provided along length of pilasters with cable ties
5.2 Insert arrow drippers into separate points either at rear or rear
and front of each VGM to evenly distribute water supply
Cable-tie
Hole for securingtubing
Cable-tie
Hole for securingtubing
Distribute drippers evenly
Dripper to bottom half ofVGM
Dripper to top half of VGM
Yellow triangle at top of VGM
-
8/19/2019 VGM Method Statement
8/11
VGM MStmt Ver2012(Jan) Page 8
5.3 Install irrigation system, including controller, solenoid valve,pressure regulator, filters and valves linked to fertiliser supply,
to projec t requirements or as advised, to deliver irrigation and
fertiliser at programmable intervals for controlled durations
5.4 A rain sensor (optional) may be installed to overrideprogrammed water release when the green wall receives
sufficient water from rain
Solenoid Valve
Controller
Rain Sensor
Over-pressure valve
-
8/19/2019 VGM Method Statement
9/11
VGM MStmt Ver2012(Jan) Page 9
6. Mounting
6.1 Attach stainless steel mounting brackets to the 4 corners ofeach VGM and cover each with its plastic cover
6.2 Secure mounting bracket to VGM with self-tapping screw toprevent bracket dislodgement before mounting
6.3 Anchor VGM to the pilasters beginning from the bottom row
Anchor VGM to Pilaster
Attach Self-tappingScrew here
Attach Self-tappingScrew here
-
8/19/2019 VGM Method Statement
10/11
VGM MStmt Ver2012(Jan) Page 10
6.4 Insert anti-lift arm between tops of mounted VGMs and push,from front to back, until arm clasp locks into pilaster slots
6.5 Plug connectors of manifold/s into corresponding emitters
along horizontal irrigation tubing as each VGM row is installed
6.6 Install subsequent rows until all VGM rows are installed
Emitters along tubing
Emitters along tubing
Arm clasp locked intopilaster slots
Insert Anti-lift Arm
Plug connectors intoemitters
Plug connectors intoemitters
-
8/19/2019 VGM Method Statement
11/11
VGM MStmt Ver2012(Jan) Page 11
7. Inspection & Maintenance
7.1 Follow a routine inspection and maintenance regime
7.2 Ensure smooth running of irrigation system
7.3 Weed away invasive unwanted growth
7.4 Prune as necessary
Install bottom row followed bysubsequent rows above
Plug in connectors to emitters aseach VGM row is installed