(UPDATED 10.7.2012)
Office of the Executive Engineer,National Highway Division No. IX, Nashik.
Phone No: - 0253-2573270 Email:[email protected]
No. NH-IX/AB/Tender-2/591/ 2012 Date. 10 / 07 / 2012
To,
The e-tendering Tenderers
SUB:- 1)Improvement to Riding Quality of Existing Carriage way in Km
161/570 to Km. 166/000 of Kalyan Ahmadmagar Pathardi Nanded
Nirmal Road N.H.222 in the State of Maharashtra
System Tender No.47
2) Improvement to Riding Quality of Existing Carriage way in
Km.218/500 to Km. 230/000 of Kalyan Ahmadmagar Pathardi Nanded
Nirmal Road N.H.222 in the State of Maharashtra
System Tender No.48
3) Improvement to Riding Quality of Existing Carriage way in Km
295/00 to Km. 303/100 of Kalyan Ahmadmagar Pathardi Nanded
Nirmal Road N.H.222 in the State of Maharashtra
System Tender No.49
REF:- Pre bid meeting held in the office Chief Engineer, National Highway
(P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs.
The CSD for the System Tender No. 47,48,49 were already uploaded on dated
09/07/2012. However Updated CSD is enclosed herewith ( dated 10/07/2012).
The Bidders are requested to submit their offer considering the Updated CSD
and that offers shall be unconditional. The conditional offers are liable for
rejection.
D.A.- Updated CCoommmmoonn SSeett OOff DDeevviiaattiioonn
Executive Engineer
National Highway Division No. IX
Nashik
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc
UPDATED 10.7.2012
Office of the Executive Engineer,National Highway Division No. IX, Nashik.
Phone No: - 0253-2573270 Email:[email protected]
No. NH-IX/AB/Tender-2/591/ 2012 Date. 07 / 07 / 2012
To,
The e-tendering Tenderers
SUB:- Improvement to Riding Quality of Existing Carriage way in Km
161/570 to Km. 166/000 of Kalyan Ahmadmagar Pathardi Nanded
Nirmal Road N.H.222 in the State of Maharashtra
System Tender No.47
REF:- Pre bid meeting held in the office Chief Engineer, National Highway
(P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs.
Please find enclosed herewith CSD of the pre bid meeting held in the office of the
Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on 29/06/2012 in
pursuant to the clause 7.3 of Volume I of the bidding document for the above mentioned
work.
1. The CSD issued herewith shall be part of the bidding document & the
bidders are requested to submit the CSD on line along with the bidding
document.
2. No any other changes in terms & condition of Bid document except that are
mentioned in CSD
3. The Bidders are requested to submit their offer considering the CSD and that
offers shall be unconditional. The conditional offers are liable for rejection.
D.A.- CCoommmmoonn SSeett OOff DDeevviiaattiioonn
Executive Engineer
National Highway Division No. IX
Nashik
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc
COMMON SET OF DEVIATION (UPDATED 10.7.2012)
Name of Work. :- Improvement to Riding Quality of Existing Carriageway in Km.161/570 to Km.166/000 of Kalyan Ahmednagar
Pathardi Nanded Nirmal Road N.H.222 in the State of Maharashtra. (System Tender No. 47)
Sr
No
NIT
Page
No.
Clause
/Condition/I
tem/Line
No.
NIT Provisions Read as
1 Vol.II
Page
No.3
Section –I
Details of
works
Time Stipulated for Completion :- Nine (9) Calendar Months
which will include the monsoon period, if any.
Time Stipulated for Completion :- Thirteen (13) Calendar
Months which will include the monsoon period, if any.
2 Vol.II
Page
No.4
Tender
Notification
under e-
Procuremen(I
st Call)
Column No.7
Period of Completion :- Nine calendar months including
mons0on.
Period of Completion :- Thirteen (13) calendar months
including monsoon.
3 Vol.II
Page
No.6
General
Information
of Contract
Sr.No.8
Time stipulated for :- Nine (9) Calendar Months form the
date of written order to start work including monsoon period.
Thirteen (13) Calendar Months form the date of written order
to start work including monsoon period.
4 Vol.II
Page
No.7
Notice
inviting
tender
Sr.No.3
Time Limit for Completion of work :- Nine (9) months
including monsoon.
Time Limit for Completion of work :- Thirteen (13) months
including monsoon.
5 Vol.II
Page
No.9
Check List of accompaniments with the tender
Sr.No.4
Earnest money in the form of term Deposit Receipt for a period of
one year issued by Scheduled bank in the name of the Executive
Engineer, National Highway Division No 3, Thane from the last
date of receipt of tender or Certificate for Exemption for Earnest
Money if applicable.
Earnest money in the form of term Deposit Receipt for a period of
one year issued by Scheduled bank in the name of the Executive
Engineer, National Highway Division No.9, Nashik from the last
date of receipt of tender or Certificate for Exemption for Earnest
Money if applicable.
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc
-2-
Sr
N
o
NIT
Page
No.
Clause
/Condition/
Item/Line
No.
NIT Provisions Read as
6 Vol.II
Page
No.12
Section –II
Tender Data
Clause
No.2.1.4
Sr.No.2,3,8
&10
Sr. No.
Particulars of Machinery Quantity
2 Dozer 2 Nos.
3 Front End loader 1 No.
8 Water Tankar 3 Nos.
10 Tandom Roller 1 No.
Sr. No.
Particulars of Machinery Quantity
2 Excavator 1 No.
3 Front End loader 1 No.
8 Water Tankar 1No.
10 Tandom Roller --.
7 Vol.II
Page
No.14
Section –III
Contract
Data
Sr.No.2(f)
f)Time allowed for the work from date of written order to
commence :- Nine (9) Calendar Months Including Monsson.
f)Time allowed for the work from date of written order to
commence :- Thirteen (13) Calendar Months Including
Monsson.
Vol.II
Page
No.15
Section –III
Contract
Data
Sr.No.3
Levy of Compensation:
Milestone (Part duration with
respect to period of
completion)
Cumulative
physical
target to be
achieved
If not
achieved the
compensation
payable per
day
Milestone No. No. Months
form the date
of work order
I 3 1% Rs.5000.00
II 9 100% Rs.10000.00
Levy of Compensation:
Milestone (Part duration with
respect to period of
completion)
Cumulative
physical
target to be
achieved
If not
achieved the
compensation
payable per
day
Milestone No. No. Months
form the date
of work order
I 2 Months 1% Rs.5000.00
II 6 Months 60% Rs.10000.00
III 13 Months 100% Rs.15000.00
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc
9 Vol.II
Page
No.15
Section –III
Contract
Data
Sr.No.6
PPrriiccee Variation Clause :
1) Labour Component : N.A.
2) Material Component other than Bitumen and cement : N.A.
3) POL Component : N.A.
4) Bitumen Component : N.A.
5) HYSD & Mild Steel Component : N.A.
6) Cement Component : N.A.
Consumer Price Index (New Series ) for Industrial workers for
Mumbai center.
Average price of H. S. D. for Mumbai Center.
Star Rates for
1. Bitumen VG30 : Rs N.A.
2. Cement : Rs. N.A.
3. Steel : Rs. N.A.
PPrriiccee Variation Clause :
1) Labour Component : 6 %
2) Material Component other than Bitumen and cement : 25%
3) POL Component : 6%
4) Bitumen Component : 63%
5) HYSD & Mild Steel Component : ActualVo
6) Cement Component : Actual
7) C.I. & D.I Pipe Component : ActualIII.
Consumer Price Index (New Series ) for Industrial workers
for Mumbai center.
Average price of H. S. D. for Mumbai Center.
Star Rates for
1. Bitumen VG30 : Rs 45877 / M.T.
2. Bitumen VG10 : Rs. 44847 / M.T.
10 Vol.II
Page
No.21
Section IV Memorandu
m
(d)
d. Give Schedule (where
necessary) of dates by which
various items are to be
completed.
Time allowed for the work
from date of written order to
commence Nine (9) calendar
Months including Monsoon
d. Give Schedule (where
necessary) of dates by
which various items are to
be completed.
Time allowed for the
work from date of written
order to commence
Thirteen (13) calendar
Months including
Monsoon
12 Vol.II
Page
No.
Section XII
Drawing
BAR CHART The Modified Barchart is enclosed herewith as Annexture-A
13 16 Section III
Contract
Data
Sr.No.10
Sr.No. Section No. Particulars
10 24.1
Section I F
Performance Security
i) Performance
Security for
Mobilization of Plant
Rs.15.00 Lakh
Sr.No. Section No. Particulars
10 24.1
Section I F
Performance Security
i) Performance
Security for
Mobilization of Plant
5.00 Lakh
O.C. Approved by C.E.
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc
(UPDATED 10.7.2012)
Office of the Executive Engineer,National Highway Division No. IX, Nashik.
Phone No: - 0253-2573270 Email:[email protected]
No. NH-IX/AB/Tender-2/ 592/ 2012 Date. 07 / 07 / 2012
To,
The e-tendering Tenderers
SUB:- Improvement to Riding Quality of Existing Carriage way in
Km 218/500 to Km. 230/000 of Kalyan Ahmadmagar
Pathardi Nanded Nirmal Road N.H.222
in the State of Maharashtra
System Tender No.48
REF:- Pre bid meeting held in the office Chief Engineer, National
Highway (P.W.) Konkan Bhavan, Navi Mumbai on Dated
29/06/2012 at 14.00 hrs.
Please find enclosed herewith CSD of the pre bid meeting held in the office of the
Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on 29/06/2012 in
pursuant to the clause 7.3 of Volume I of the bidding document for the above mentioned
work.
1. The CSD issued herewith shall be part of the bidding document & the
bidders are requested to submit the CSD on line along with the bidding
document.
2. No any other changes in terms & condition of Bid document except that are
mentioned in CSD
3. The Bidders are requested to submit their offer considering the CSD and that
offers shall be unconditional. The conditional offers are liable for rejection.
D.A.- CCoommmmoonn SSeett OOff DDeevviiaattiioonn
Executive Engineer
National Highway Division No. IX
Nashik
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc
COMMON SET OF DEVIATION (UPDATED 10.7.2012)
Name of Work. :- “Improvement to Riding Quality of Existing Carriageway in Km.218//550 to Km. 230/000 of Kalyan Ahmednagar Pathardi
Nanded Nirmal Road N.H.222 in the State of Maharashtra” (System Tender No. 48)
Sr
No
NIT
Page
No.
Clause
/Condition/I
tem/Line
No.
NIT Provisions Read as
1 Vol.II
Page
No.3
Section –I
Details of
works
Time Stipulated for Completion :- Eleven (11) Calendar
Months which will include the monsoon period, if any.
Time Stipulated for Completion :- Thirteen (13) Calendar
Months which will include the monsoon period, if any.
2 Vol.II
Page
No.4
Tender
Notification
under e-
Procuremen(I
st Call)
Column No.7
Period of Completion :- EElleevveenn calendar months including
mons0on.
Period of Completion :- Thirteen (13) calendar months
including monsoon.
3 Vol.II
Page
No.6
General
Information
of Contract
Sr.No.8
Time stipulated for :- EElleevveenn ((1111))Calendar Months form the
date of written order to start work including monsoon period.
Thirteen (13) Calendar Months form the date of written order
to start work including monsoon period.
4 Vol.II
Page
No.7
Notice
inviting
tender
Sr.No.3
Time Limit for Completion of work :- EElleevveenn ((1111)) months
including monsoon.
Time Limit for Completion of work :- Thirteen (13) months
including monsoon.
5 Vol.II
Page
No.9
Check List of accompaniments with the tender
Sr.No.4
Earnest money in the form of term Deposit Receipt for a period of
one year issued by Scheduled bank in the name of the Executive
Engineer, National Highway Division No 3, Thane from the last
date of receipt of tender or Certificate for Exemption for Earnest
Money if applicable.
Earnest money in the form of term Deposit Receipt for a period of
one year issued by Scheduled bank in the name of the Executive
Engineer, National Highway Division No.9, Nashik from the last
date of receipt of tender or Certificate for Exemption for Earnest
Money if applicable.
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc
-2-
Sr
N
o
NIT
Page
No.
Clause
/Condition/
Item/Line
No.
NIT Provisions Read as
6 Vol.II
Page
No.12
Section –II
Tender Data
Clause
No.2.1.4
Sr.No.2,3,8
&10
Sr. No.
Particulars of Machinery Quantity
2 Dozer 2 Nos.
3 Front End loader 1 No.
8 Water Tankar 3 Nos.
10 Tandom Roller 1 No.
Sr. No.
Particulars of Machinery Quantity
2 Excavator 1 No.
3 Front End loader 1 No.
8 Water Tankar 1No.
10 Tandom Roller --.
7 Vol.II
Page
No.14
Section –III
Contract
Data
Sr.No.2(f)
f)Time allowed for the work from date of written order to
commence :- Eleven (11) Calendar Months Including Monsson.
f)Time allowed for the work from date of written order to
commence :- Thirteen (13) Calendar Months Including
Monsson.
8 Vol.II
Page
No.15
Section –III
Contract
Data
Sr.No.3
Levy of Compensation:
Milestone (Part duration with
respect to period of
completion)
Cumulative
physical
target to be
achieved
If not
achieved the
compensation
payable per
day
I 3 Months 1.36% Rs.5000.00
II 11 Months 100% Rs.10000.00
Levy of Compensation:
Milestone (Part duration with
respect to period of
completion)
Cumulative
physical
target to be
achieved
If not
achieved the
compensation
payable per
day
Milestone No. No. Months
form the date
of work order
I 2 Months 1.36% Rs.5000.00
II 6 Months 60% Rs.10000.00
III 13 Months 100% Rs.10000.00
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc
9 Vol.II
Page
No.15
Section –III
Contract Data
Sr.No.6
PPrriiccee Variation Clause :
1) Labour Component : N.A.
2) Material Component other than Bitumen and cement : N.A.
3) POL Component : N.A.
4) Bitumen Component : N.A.
5) HYSD & Mild Steel Component : N.A.
6) Cement Component : N.A.
Consumer Price Index (New Series ) for Industrial workers for Mumbai
center.
Average price of H. S. D. for Mumbai Center.
Star Rates for
1. Bitumen VG30 : Rs N.A.
2. Cement : Rs. N.A.
3. Steel : Rs. N.A.
PPrriiccee Variation Clause :
1) Labour Component : 6.03 %
2) Material Component other than Bitumen and cement : 21.94 %
3) POL Component : 3 .47%
4) Bitumen Component : 68.31 %
5) HYSD & Mild Steel Component : 0.19ActualVo
6) Cement Component : 0.06 Actual
Consumer Price Index (New Series ) for Industrial workers for
Mumbai center.
Average price of H. S. D. for Mumbai Center.
Star Rates for
1. Bitumen VG30 : Rs 45877/ M.T.
2. Bitumen VG10 : Rs. 44847 / M.T.
2. Cement : Rs. 4600 / M.T.
3. Steel : Rs. 45000 / M.T.
10 Vol.II
Page
No.21
Section IV Memorandu
m
(d)
d. Give Schedule (where
necessary) of dates by which
various items are to be
completed.
Time allowed for the work
from date of written order to
commence EElleevveenn ((1111))
calendar Months including
Monsoon
d. Give Schedule (where
necessary) of dates by
which various items are to
be completed.
Time allowed for the
work from date of written
order to commence
Thirteen (13) calendar
Months including
Monsoon
11 16 Section III
Contract
Data
Sr.No.10
Sr.No. Section No. Particulars
10 24.1
Section I F
Performance Security
i) Performance
Security for
Mobilization of Plant
Rs.25,00,000/-
Sr.No. Section No. Particulars
10 24.1
Section I F
Performance Security
i) Performance
Security for
Mobilization of Plant
5.00 Lakh
12 Vol.II
Page
No.
Section XII
Drawing
BAR CHART The Modified Barchart is enclosed herewith as Annexture-A
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc
(UPDATED 10.7.2012)
Office of the Executive Engineer,National Highway Division No. IX, Nashik.
Phone No: - 0253-2573270 Email:[email protected]
No. NH-IX/AB/Tender-2/593/ 2012 Date. 07 / 07 / 2012
To,
The e-tendering Tenderers
SUB:- Improvement to Riding Quality of Existing Carriage way in Km
295/00 to Km. 303/100 of Kalyan Ahmadmagar Pathardi Nanded
Nirmal Road N.H.222 in the State of Maharashtra
System Tender No.49
REF:- Pre bid meeting held in the office Chief Engineer, National Highway
(P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs.
Please find enclosed herewith CSD of the pre bid meeting held in the office of the
Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on 29/06/2012 in
pursuant to the clause 7.3 of Volume I of the bidding document for the above mentioned
work.
1. The CSD issued herewith shall be part of the bidding document & the
bidders are requested to submit the CSD on line along with the bidding
document.
2. No any other changes in terms & condition of Bid document except that are
mentioned in CSD
3. The Bidders are requested to submit their offer considering the CSD and that
offers shall be unconditional. The conditional offers are liable for rejection.
D.A.- CCoommmmoonn SSeett OOff DDeevviiaattiioonn
Executive Engineer
National Highway Division No. IX
Nashik
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc
COMMON SET OF DEVIATION (UPDATED 10.7.2012)
Name of Work. :- Improvement to Riding Quality to Kalyan Ahmednagar Pathardi Nanded Nirmal Road N.H.222 in Km. 295/000 to 303/100 in
the State of Maharashtra. (System Tender No. 49)
Sr
No
NIT
Page
No.
Clause
/Condition/I
tem/Line
No.
NIT Provisions Read as
1 Vol.II
Page
No.3
Section –I
Details of
works
Time Stipulated for Completion :- Eight (8) Calendar Months
which will include the monsoon period, if any.
Time Stipulated for Completion :- Thirteen (13) Calendar
Months which will include the monsoon period, if any.
2 Vol.II
Page
No.4
Tender
Notification
under e-
Procuremen(I
st Call)
Column No.7
Period of Completion :- EEiigghhtt calendar months including
mons0on.
Period of Completion :- Thirteen (13) calendar months
including monsoon.
3 Vol.II
Page
No.6
General
Information
of Contract
Sr.No.8
Time stipulated for :- EEiigghhtt ((88)) Calendar Months form the
date of written order to start work including monsoon period.
Thirteen (13) Calendar Months form the date of written order
to start work including monsoon period.
4 Vol.II
Page
No.7
Notice
inviting
tender
Sr.No.3
Time Limit for Completion of work :- EEiigghhtt ((88)) months
including monsoon.
Time Limit for Completion of work :- Thirteen (13) months
including monsoon.
5 Vol.II
Page
No.9
Check List of accompaniments with the tender
Sr.No.4
Earnest money in the form of term Deposit Receipt for a period of
one year issued by Scheduled bank in the name of the Executive
Engineer, National Highway Division No 3, Thane from the last
date of receipt of tender or Certificate for Exemption for Earnest
Money if applicable.
Earnest money in the form of term Deposit Receipt for a period of
one year issued by Scheduled bank in the name of the Executive
Engineer, National Highway Division No.9, Nashik from the last
date of receipt of tender or Certificate for Exemption for Earnest
Money if applicable.
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc
-2-
Sr
N
o
NIT
Page
No.
Clause
/Condition/
Item/Line
No.
NIT Provisions Read as
7 Vol.II
Page
No.15
Section –III
Contract
Data
Sr.No.2(e)
e)Time allowed for the work from date of written order to
commence :- Eight (8) Calendar Months Including Monsson.
e)Time allowed for the work from date of written order to
commence :- Thirteen (13) Calendar Months Including
Monsson.
8 Vol.II
Page
No.15
Section –III
Contract
Data
Sr.No.3
Levy of Compensation:
Milestone (Part duration with
respect to period of
completion)
Cumulative
physical
target to be
achieved
If not
achieved the
compensation
payable per
day
Milestone No. No. Months
form the date
of work order
I 4 61% Rs.1000.00
II 4 100% Rs.5000.00
Levy of Compensation:
Milestone (Part duration with
respect to period of
completion)
Cumulative
physical
target to be
achieved
If not
achieved the
compensation
payable per
day
Milestone No. No. Months
form the date
of work order
I 2 0.31% Rs.5000.00
II 7 40% Rs.10000.00
III 13 100% Rs.15000.00
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc
9 Vol.II
Page
No.16
Section –III
Contract
Data
Sr.No.6
PPrriiccee Variation Clause :
1) Labour Component : N.A.
2) Material Component other than Bitumen and cement : N.A.
3) POL Component : N.A.
4) Bitumen Component : N.A.
5) HYSD & Mild Steel Component : N.A.
6) Cement Component : N.A.
Consumer Price Index (New Series ) for Industrial workers for
Mumbai center.
Average price of H. S. D. for Mumbai Center.
Star Rates for
1. Bitumen VG30 : Rs N.A.
2. Bitumen VG10 : Rs N.A.
3. Cement : Rs. N.A.
4. Steel : Rs. N.A.
PPrriiccee Variation Clause :
1) Labour Component : 5%
2) Material Component other than Bitumen and cement : 9%
3) POL Component : 29%
4) Bitumen Component : 57%
5) HYSD & Mild Steel Component : ActualVo
6) Cement Component : Actual
7) C.I. & D.I Pipe Component : ActualIII.
Consumer Price Index (New Series ) for Industrial workers
for Mumbai center.
Average price of H. S. D. for Mumbai Center.
Star Rates for
1. Bitumen VG30 : Rs. 45877.00 / M.T.
2. Bitumen VG10 : Rs 44847.00 / M.T.
10 16 Section III
Contract
Data
Sr.No.10
Sr.No. Section No. Particulars
10 24.1
Section I F
Performance Security
i) Performance
Security for
Mobilization of Plant
20.00 Lakh
Sr.No. Section No. Particulars
10 24.1
Section I F
Performance Security
i) Performance
Security for
Mobilization of Plant
5.00 Lakh
11 Vol.II
Page
No.21
Section IV Memorandu
m
(d)
d. Give Schedule (where
necessary) of dates by which
various items are to be
completed.
Time allowed for the work
from date of written order to
commence Eight (8) calendar
Months including Monsoon
d. Give Schedule (where
necessary) of dates by
which various items are to
be completed.
Time allowed for the
work from date of written
order to commence
Thirteen (13) calendar
Months including
Monsoon
C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc
12 Vol.II
Page
No.
29
Section VIII
III 69 to 72 54 Price variation clause Deleted
Deleted
13 Vol.II
Page
No.
Section XII
Drawing
BAR CHART The Modified Barchart is enclosed herewith as Annexure-A
O.C. Approved by C.E.