(UPDATED 10.7.2012) Office of the Executive Engineer,National Highway Division No. IX, Nashik. Phone No: - 0253-2573270 Email:-[email protected] No. NH-IX/AB/Tender-2/591/ 2012 Date. 10 / 07 / 2012 To, The e-tendering Tenderers SUB:- 1)Improvement to Riding Quality of Existing Carriage way in Km 161/570 to Km. 166/000 of Kalyan Ahmadmagar Pathardi Nanded Nirmal Road N.H.222 in the State of Maharashtra System Tender No.47 2) Improvement to Riding Quality of Existing Carriage way in Km.218/500 to Km. 230/000 of Kalyan Ahmadmagar Pathardi Nanded Nirmal Road N.H.222 in the State of Maharashtra System Tender No.48 3) Improvement to Riding Quality of Existing Carriage way in Km 295/00 to Km. 303/100 of Kalyan Ahmadmagar Pathardi Nanded Nirmal Road N.H.222 in the State of Maharashtra System Tender No.49 REF:- Pre bid meeting held in the office Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs. The CSD for the System Tender No. 47,48,49 were already uploaded on dated 09/07/2012. However Updated CSD is enclosed herewith ( dated 10/07/2012). The Bidders are requested to submit their offer considering the Updated CSD and that offers shall be unconditional. The conditional offers are liable for rejection. D.A.- Updated Common Set Of Deviation Executive Engineer National Highway Division No. IX Nashik

Transcript of UPDATED 10.7.2012) Office of the Executive Engineer ... · C: \Users \Mahadeo \Desktop \nashik \CSD...

(UPDATED 10.7.2012)

Office of the Executive Engineer,National Highway Division No. IX, Nashik.

Phone No: - 0253-2573270 Email:[email protected]

No. NH-IX/AB/Tender-2/591/ 2012 Date. 10 / 07 / 2012

To,

The e-tendering Tenderers

SUB:- 1)Improvement to Riding Quality of Existing Carriage way in Km

161/570 to Km. 166/000 of Kalyan Ahmadmagar Pathardi Nanded

Nirmal Road N.H.222 in the State of Maharashtra

System Tender No.47

2) Improvement to Riding Quality of Existing Carriage way in

Km.218/500 to Km. 230/000 of Kalyan Ahmadmagar Pathardi Nanded

Nirmal Road N.H.222 in the State of Maharashtra

System Tender No.48

3) Improvement to Riding Quality of Existing Carriage way in Km

295/00 to Km. 303/100 of Kalyan Ahmadmagar Pathardi Nanded

Nirmal Road N.H.222 in the State of Maharashtra

System Tender No.49

REF:- Pre bid meeting held in the office Chief Engineer, National Highway

(P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs.

The CSD for the System Tender No. 47,48,49 were already uploaded on dated

09/07/2012. However Updated CSD is enclosed herewith ( dated 10/07/2012).

The Bidders are requested to submit their offer considering the Updated CSD

and that offers shall be unconditional. The conditional offers are liable for

rejection.

D.A.- Updated CCoommmmoonn SSeett OOff DDeevviiaattiioonn

Executive Engineer

National Highway Division No. IX

Nashik

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc

UPDATED 10.7.2012

Office of the Executive Engineer,National Highway Division No. IX, Nashik.

Phone No: - 0253-2573270 Email:[email protected]

No. NH-IX/AB/Tender-2/591/ 2012 Date. 07 / 07 / 2012

To,

The e-tendering Tenderers

SUB:- Improvement to Riding Quality of Existing Carriage way in Km

161/570 to Km. 166/000 of Kalyan Ahmadmagar Pathardi Nanded

Nirmal Road N.H.222 in the State of Maharashtra

System Tender No.47

REF:- Pre bid meeting held in the office Chief Engineer, National Highway

(P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs.

Please find enclosed herewith CSD of the pre bid meeting held in the office of the

Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on 29/06/2012 in

pursuant to the clause 7.3 of Volume I of the bidding document for the above mentioned

work.

1. The CSD issued herewith shall be part of the bidding document & the

bidders are requested to submit the CSD on line along with the bidding

document.

2. No any other changes in terms & condition of Bid document except that are

mentioned in CSD

3. The Bidders are requested to submit their offer considering the CSD and that

offers shall be unconditional. The conditional offers are liable for rejection.

D.A.- CCoommmmoonn SSeett OOff DDeevviiaattiioonn

Executive Engineer

National Highway Division No. IX

Nashik

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc

COMMON SET OF DEVIATION (UPDATED 10.7.2012)

Name of Work. :- Improvement to Riding Quality of Existing Carriageway in Km.161/570 to Km.166/000 of Kalyan Ahmednagar

Pathardi Nanded Nirmal Road N.H.222 in the State of Maharashtra. (System Tender No. 47)

Sr

No

NIT

Page

No.

Clause

/Condition/I

tem/Line

No.

NIT Provisions Read as

1 Vol.II

Page

No.3

Section –I

Details of

works

Time Stipulated for Completion :- Nine (9) Calendar Months

which will include the monsoon period, if any.

Time Stipulated for Completion :- Thirteen (13) Calendar

Months which will include the monsoon period, if any.

2 Vol.II

Page

No.4

Tender

Notification

under e-

Procuremen(I

st Call)

Column No.7

Period of Completion :- Nine calendar months including

mons0on.

Period of Completion :- Thirteen (13) calendar months

including monsoon.

3 Vol.II

Page

No.6

General

Information

of Contract

Sr.No.8

Time stipulated for :- Nine (9) Calendar Months form the

date of written order to start work including monsoon period.

Thirteen (13) Calendar Months form the date of written order

to start work including monsoon period.

4 Vol.II

Page

No.7

Notice

inviting

tender

Sr.No.3

Time Limit for Completion of work :- Nine (9) months

including monsoon.

Time Limit for Completion of work :- Thirteen (13) months

including monsoon.

5 Vol.II

Page

No.9

Check List of accompaniments with the tender

Sr.No.4

Earnest money in the form of term Deposit Receipt for a period of

one year issued by Scheduled bank in the name of the Executive

Engineer, National Highway Division No 3, Thane from the last

date of receipt of tender or Certificate for Exemption for Earnest

Money if applicable.

Earnest money in the form of term Deposit Receipt for a period of

one year issued by Scheduled bank in the name of the Executive

Engineer, National Highway Division No.9, Nashik from the last

date of receipt of tender or Certificate for Exemption for Earnest

Money if applicable.

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc

-2-

Sr

N

o

NIT

Page

No.

Clause

/Condition/

Item/Line

No.

NIT Provisions Read as

6 Vol.II

Page

No.12

Section –II

Tender Data

Clause

No.2.1.4

Sr.No.2,3,8

&10

Sr. No.

Particulars of Machinery Quantity

2 Dozer 2 Nos.

3 Front End loader 1 No.

8 Water Tankar 3 Nos.

10 Tandom Roller 1 No.

Sr. No.

Particulars of Machinery Quantity

2 Excavator 1 No.

3 Front End loader 1 No.

8 Water Tankar 1No.

10 Tandom Roller --.

7 Vol.II

Page

No.14

Section –III

Contract

Data

Sr.No.2(f)

f)Time allowed for the work from date of written order to

commence :- Nine (9) Calendar Months Including Monsson.

f)Time allowed for the work from date of written order to

commence :- Thirteen (13) Calendar Months Including

Monsson.

Vol.II

Page

No.15

Section –III

Contract

Data

Sr.No.3

Levy of Compensation:

Milestone (Part duration with

respect to period of

completion)

Cumulative

physical

target to be

achieved

If not

achieved the

compensation

payable per

day

Milestone No. No. Months

form the date

of work order

I 3 1% Rs.5000.00

II 9 100% Rs.10000.00

Levy of Compensation:

Milestone (Part duration with

respect to period of

completion)

Cumulative

physical

target to be

achieved

If not

achieved the

compensation

payable per

day

Milestone No. No. Months

form the date

of work order

I 2 Months 1% Rs.5000.00

II 6 Months 60% Rs.10000.00

III 13 Months 100% Rs.15000.00

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc

9 Vol.II

Page

No.15

Section –III

Contract

Data

Sr.No.6

PPrriiccee Variation Clause :

1) Labour Component : N.A.

2) Material Component other than Bitumen and cement : N.A.

3) POL Component : N.A.

4) Bitumen Component : N.A.

5) HYSD & Mild Steel Component : N.A.

6) Cement Component : N.A.

Consumer Price Index (New Series ) for Industrial workers for

Mumbai center.

Average price of H. S. D. for Mumbai Center.

Star Rates for

1. Bitumen VG30 : Rs N.A.

2. Cement : Rs. N.A.

3. Steel : Rs. N.A.

PPrriiccee Variation Clause :

1) Labour Component : 6 %

2) Material Component other than Bitumen and cement : 25%

3) POL Component : 6%

4) Bitumen Component : 63%

5) HYSD & Mild Steel Component : ActualVo

6) Cement Component : Actual

7) C.I. & D.I Pipe Component : ActualIII.

Consumer Price Index (New Series ) for Industrial workers

for Mumbai center.

Average price of H. S. D. for Mumbai Center.

Star Rates for

1. Bitumen VG30 : Rs 45877 / M.T.

2. Bitumen VG10 : Rs. 44847 / M.T.

10 Vol.II

Page

No.21

Section IV Memorandu

m

(d)

d. Give Schedule (where

necessary) of dates by which

various items are to be

completed.

Time allowed for the work

from date of written order to

commence Nine (9) calendar

Months including Monsoon

d. Give Schedule (where

necessary) of dates by

which various items are to

be completed.

Time allowed for the

work from date of written

order to commence

Thirteen (13) calendar

Months including

Monsoon

12 Vol.II

Page

No.

Section XII

Drawing

BAR CHART The Modified Barchart is enclosed herewith as Annexture-A

13 16 Section III

Contract

Data

Sr.No.10

Sr.No. Section No. Particulars

10 24.1

Section I F

Performance Security

i) Performance

Security for

Mobilization of Plant

Rs.15.00 Lakh

Sr.No. Section No. Particulars

10 24.1

Section I F

Performance Security

i) Performance

Security for

Mobilization of Plant

5.00 Lakh

O.C. Approved by C.E.

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-161.570 to 166.100.doc

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc

(UPDATED 10.7.2012)

Office of the Executive Engineer,National Highway Division No. IX, Nashik.

Phone No: - 0253-2573270 Email:[email protected]

No. NH-IX/AB/Tender-2/ 592/ 2012 Date. 07 / 07 / 2012

To,

The e-tendering Tenderers

SUB:- Improvement to Riding Quality of Existing Carriage way in

Km 218/500 to Km. 230/000 of Kalyan Ahmadmagar

Pathardi Nanded Nirmal Road N.H.222

in the State of Maharashtra

System Tender No.48

REF:- Pre bid meeting held in the office Chief Engineer, National

Highway (P.W.) Konkan Bhavan, Navi Mumbai on Dated

29/06/2012 at 14.00 hrs.

Please find enclosed herewith CSD of the pre bid meeting held in the office of the

Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on 29/06/2012 in

pursuant to the clause 7.3 of Volume I of the bidding document for the above mentioned

work.

1. The CSD issued herewith shall be part of the bidding document & the

bidders are requested to submit the CSD on line along with the bidding

document.

2. No any other changes in terms & condition of Bid document except that are

mentioned in CSD

3. The Bidders are requested to submit their offer considering the CSD and that

offers shall be unconditional. The conditional offers are liable for rejection.

D.A.- CCoommmmoonn SSeett OOff DDeevviiaattiioonn

Executive Engineer

National Highway Division No. IX

Nashik

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc

COMMON SET OF DEVIATION (UPDATED 10.7.2012)

Name of Work. :- “Improvement to Riding Quality of Existing Carriageway in Km.218//550 to Km. 230/000 of Kalyan Ahmednagar Pathardi

Nanded Nirmal Road N.H.222 in the State of Maharashtra” (System Tender No. 48)

Sr

No

NIT

Page

No.

Clause

/Condition/I

tem/Line

No.

NIT Provisions Read as

1 Vol.II

Page

No.3

Section –I

Details of

works

Time Stipulated for Completion :- Eleven (11) Calendar

Months which will include the monsoon period, if any.

Time Stipulated for Completion :- Thirteen (13) Calendar

Months which will include the monsoon period, if any.

2 Vol.II

Page

No.4

Tender

Notification

under e-

Procuremen(I

st Call)

Column No.7

Period of Completion :- EElleevveenn calendar months including

mons0on.

Period of Completion :- Thirteen (13) calendar months

including monsoon.

3 Vol.II

Page

No.6

General

Information

of Contract

Sr.No.8

Time stipulated for :- EElleevveenn ((1111))Calendar Months form the

date of written order to start work including monsoon period.

Thirteen (13) Calendar Months form the date of written order

to start work including monsoon period.

4 Vol.II

Page

No.7

Notice

inviting

tender

Sr.No.3

Time Limit for Completion of work :- EElleevveenn ((1111)) months

including monsoon.

Time Limit for Completion of work :- Thirteen (13) months

including monsoon.

5 Vol.II

Page

No.9

Check List of accompaniments with the tender

Sr.No.4

Earnest money in the form of term Deposit Receipt for a period of

one year issued by Scheduled bank in the name of the Executive

Engineer, National Highway Division No 3, Thane from the last

date of receipt of tender or Certificate for Exemption for Earnest

Money if applicable.

Earnest money in the form of term Deposit Receipt for a period of

one year issued by Scheduled bank in the name of the Executive

Engineer, National Highway Division No.9, Nashik from the last

date of receipt of tender or Certificate for Exemption for Earnest

Money if applicable.

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc

-2-

Sr

N

o

NIT

Page

No.

Clause

/Condition/

Item/Line

No.

NIT Provisions Read as

6 Vol.II

Page

No.12

Section –II

Tender Data

Clause

No.2.1.4

Sr.No.2,3,8

&10

Sr. No.

Particulars of Machinery Quantity

2 Dozer 2 Nos.

3 Front End loader 1 No.

8 Water Tankar 3 Nos.

10 Tandom Roller 1 No.

Sr. No.

Particulars of Machinery Quantity

2 Excavator 1 No.

3 Front End loader 1 No.

8 Water Tankar 1No.

10 Tandom Roller --.

7 Vol.II

Page

No.14

Section –III

Contract

Data

Sr.No.2(f)

f)Time allowed for the work from date of written order to

commence :- Eleven (11) Calendar Months Including Monsson.

f)Time allowed for the work from date of written order to

commence :- Thirteen (13) Calendar Months Including

Monsson.

8 Vol.II

Page

No.15

Section –III

Contract

Data

Sr.No.3

Levy of Compensation:

Milestone (Part duration with

respect to period of

completion)

Cumulative

physical

target to be

achieved

If not

achieved the

compensation

payable per

day

I 3 Months 1.36% Rs.5000.00

II 11 Months 100% Rs.10000.00

Levy of Compensation:

Milestone (Part duration with

respect to period of

completion)

Cumulative

physical

target to be

achieved

If not

achieved the

compensation

payable per

day

Milestone No. No. Months

form the date

of work order

I 2 Months 1.36% Rs.5000.00

II 6 Months 60% Rs.10000.00

III 13 Months 100% Rs.10000.00

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc

9 Vol.II

Page

No.15

Section –III

Contract Data

Sr.No.6

PPrriiccee Variation Clause :

1) Labour Component : N.A.

2) Material Component other than Bitumen and cement : N.A.

3) POL Component : N.A.

4) Bitumen Component : N.A.

5) HYSD & Mild Steel Component : N.A.

6) Cement Component : N.A.

Consumer Price Index (New Series ) for Industrial workers for Mumbai

center.

Average price of H. S. D. for Mumbai Center.

Star Rates for

1. Bitumen VG30 : Rs N.A.

2. Cement : Rs. N.A.

3. Steel : Rs. N.A.

PPrriiccee Variation Clause :

1) Labour Component : 6.03 %

2) Material Component other than Bitumen and cement : 21.94 %

3) POL Component : 3 .47%

4) Bitumen Component : 68.31 %

5) HYSD & Mild Steel Component : 0.19ActualVo

6) Cement Component : 0.06 Actual

Consumer Price Index (New Series ) for Industrial workers for

Mumbai center.

Average price of H. S. D. for Mumbai Center.

Star Rates for

1. Bitumen VG30 : Rs 45877/ M.T.

2. Bitumen VG10 : Rs. 44847 / M.T.

2. Cement : Rs. 4600 / M.T.

3. Steel : Rs. 45000 / M.T.

10 Vol.II

Page

No.21

Section IV Memorandu

m

(d)

d. Give Schedule (where

necessary) of dates by which

various items are to be

completed.

Time allowed for the work

from date of written order to

commence EElleevveenn ((1111))

calendar Months including

Monsoon

d. Give Schedule (where

necessary) of dates by

which various items are to

be completed.

Time allowed for the

work from date of written

order to commence

Thirteen (13) calendar

Months including

Monsoon

11 16 Section III

Contract

Data

Sr.No.10

Sr.No. Section No. Particulars

10 24.1

Section I F

Performance Security

i) Performance

Security for

Mobilization of Plant

Rs.25,00,000/-

Sr.No. Section No. Particulars

10 24.1

Section I F

Performance Security

i) Performance

Security for

Mobilization of Plant

5.00 Lakh

12 Vol.II

Page

No.

Section XII

Drawing

BAR CHART The Modified Barchart is enclosed herewith as Annexture-A

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-218.550 to 230.00.doc

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc

(UPDATED 10.7.2012)

Office of the Executive Engineer,National Highway Division No. IX, Nashik.

Phone No: - 0253-2573270 Email:[email protected]

No. NH-IX/AB/Tender-2/593/ 2012 Date. 07 / 07 / 2012

To,

The e-tendering Tenderers

SUB:- Improvement to Riding Quality of Existing Carriage way in Km

295/00 to Km. 303/100 of Kalyan Ahmadmagar Pathardi Nanded

Nirmal Road N.H.222 in the State of Maharashtra

System Tender No.49

REF:- Pre bid meeting held in the office Chief Engineer, National Highway

(P.W.) Konkan Bhavan, Navi Mumbai on Dated 29/06/2012 at 14.00 hrs.

Please find enclosed herewith CSD of the pre bid meeting held in the office of the

Chief Engineer, National Highway (P.W.) Konkan Bhavan, Navi Mumbai on 29/06/2012 in

pursuant to the clause 7.3 of Volume I of the bidding document for the above mentioned

work.

1. The CSD issued herewith shall be part of the bidding document & the

bidders are requested to submit the CSD on line along with the bidding

document.

2. No any other changes in terms & condition of Bid document except that are

mentioned in CSD

3. The Bidders are requested to submit their offer considering the CSD and that

offers shall be unconditional. The conditional offers are liable for rejection.

D.A.- CCoommmmoonn SSeett OOff DDeevviiaattiioonn

Executive Engineer

National Highway Division No. IX

Nashik

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc

COMMON SET OF DEVIATION (UPDATED 10.7.2012)

Name of Work. :- Improvement to Riding Quality to Kalyan Ahmednagar Pathardi Nanded Nirmal Road N.H.222 in Km. 295/000 to 303/100 in

the State of Maharashtra. (System Tender No. 49)

Sr

No

NIT

Page

No.

Clause

/Condition/I

tem/Line

No.

NIT Provisions Read as

1 Vol.II

Page

No.3

Section –I

Details of

works

Time Stipulated for Completion :- Eight (8) Calendar Months

which will include the monsoon period, if any.

Time Stipulated for Completion :- Thirteen (13) Calendar

Months which will include the monsoon period, if any.

2 Vol.II

Page

No.4

Tender

Notification

under e-

Procuremen(I

st Call)

Column No.7

Period of Completion :- EEiigghhtt calendar months including

mons0on.

Period of Completion :- Thirteen (13) calendar months

including monsoon.

3 Vol.II

Page

No.6

General

Information

of Contract

Sr.No.8

Time stipulated for :- EEiigghhtt ((88)) Calendar Months form the

date of written order to start work including monsoon period.

Thirteen (13) Calendar Months form the date of written order

to start work including monsoon period.

4 Vol.II

Page

No.7

Notice

inviting

tender

Sr.No.3

Time Limit for Completion of work :- EEiigghhtt ((88)) months

including monsoon.

Time Limit for Completion of work :- Thirteen (13) months

including monsoon.

5 Vol.II

Page

No.9

Check List of accompaniments with the tender

Sr.No.4

Earnest money in the form of term Deposit Receipt for a period of

one year issued by Scheduled bank in the name of the Executive

Engineer, National Highway Division No 3, Thane from the last

date of receipt of tender or Certificate for Exemption for Earnest

Money if applicable.

Earnest money in the form of term Deposit Receipt for a period of

one year issued by Scheduled bank in the name of the Executive

Engineer, National Highway Division No.9, Nashik from the last

date of receipt of tender or Certificate for Exemption for Earnest

Money if applicable.

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc

-2-

Sr

N

o

NIT

Page

No.

Clause

/Condition/

Item/Line

No.

NIT Provisions Read as

7 Vol.II

Page

No.15

Section –III

Contract

Data

Sr.No.2(e)

e)Time allowed for the work from date of written order to

commence :- Eight (8) Calendar Months Including Monsson.

e)Time allowed for the work from date of written order to

commence :- Thirteen (13) Calendar Months Including

Monsson.

8 Vol.II

Page

No.15

Section –III

Contract

Data

Sr.No.3

Levy of Compensation:

Milestone (Part duration with

respect to period of

completion)

Cumulative

physical

target to be

achieved

If not

achieved the

compensation

payable per

day

Milestone No. No. Months

form the date

of work order

I 4 61% Rs.1000.00

II 4 100% Rs.5000.00

Levy of Compensation:

Milestone (Part duration with

respect to period of

completion)

Cumulative

physical

target to be

achieved

If not

achieved the

compensation

payable per

day

Milestone No. No. Months

form the date

of work order

I 2 0.31% Rs.5000.00

II 7 40% Rs.10000.00

III 13 100% Rs.15000.00

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc

9 Vol.II

Page

No.16

Section –III

Contract

Data

Sr.No.6

PPrriiccee Variation Clause :

1) Labour Component : N.A.

2) Material Component other than Bitumen and cement : N.A.

3) POL Component : N.A.

4) Bitumen Component : N.A.

5) HYSD & Mild Steel Component : N.A.

6) Cement Component : N.A.

Consumer Price Index (New Series ) for Industrial workers for

Mumbai center.

Average price of H. S. D. for Mumbai Center.

Star Rates for

1. Bitumen VG30 : Rs N.A.

2. Bitumen VG10 : Rs N.A.

3. Cement : Rs. N.A.

4. Steel : Rs. N.A.

PPrriiccee Variation Clause :

1) Labour Component : 5%

2) Material Component other than Bitumen and cement : 9%

3) POL Component : 29%

4) Bitumen Component : 57%

5) HYSD & Mild Steel Component : ActualVo

6) Cement Component : Actual

7) C.I. & D.I Pipe Component : ActualIII.

Consumer Price Index (New Series ) for Industrial workers

for Mumbai center.

Average price of H. S. D. for Mumbai Center.

Star Rates for

1. Bitumen VG30 : Rs. 45877.00 / M.T.

2. Bitumen VG10 : Rs 44847.00 / M.T.

10 16 Section III

Contract

Data

Sr.No.10

Sr.No. Section No. Particulars

10 24.1

Section I F

Performance Security

i) Performance

Security for

Mobilization of Plant

20.00 Lakh

Sr.No. Section No. Particulars

10 24.1

Section I F

Performance Security

i) Performance

Security for

Mobilization of Plant

5.00 Lakh

11 Vol.II

Page

No.21

Section IV Memorandu

m

(d)

d. Give Schedule (where

necessary) of dates by which

various items are to be

completed.

Time allowed for the work

from date of written order to

commence Eight (8) calendar

Months including Monsoon

d. Give Schedule (where

necessary) of dates by

which various items are to

be completed.

Time allowed for the

work from date of written

order to commence

Thirteen (13) calendar

Months including

Monsoon

C:\Users\Mahadeo\Desktop\nashik\CSD- NH-222-295.00 to 303.100.doc

12 Vol.II

Page

No.

29

Section VIII

III 69 to 72 54 Price variation clause Deleted

Deleted

13 Vol.II

Page

No.

Section XII

Drawing

BAR CHART The Modified Barchart is enclosed herewith as Annexure-A

O.C. Approved by C.E.