Download - Tunnel Failure

Transcript
Page 1: Tunnel Failure

up to cto er

   

     

     

     

Catalogue of Notable Tunnel Failure Case Histories

( O b 2012)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

(up to October 2012)

Prepared by Mainland East Division Geotechnical Engineering Office

Civil Engineering and Development Department

Page 2: Tunnel Failure

ublic attention. Even for the cases re orted, usuall onl

p p y y

Foreword

This catalogue of notable tunnel failures is primarily based on published information. Both overseas and local cases involving collapse or excessive deformation of the ground are included. For contractual and other reasons, there are relatively few cases reported in technical publications, and those reported are usually of such scale or seriousness that they have received public attention. Even for the cases reported, usually only limited information is available. Apart from the cases included, readers can find other information on tunnel failure in the list of General References given at the end of this catalogue.

This catalogue is a live document that will be updated from time to time as further information becomes available.

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 3: Tunnel Failure

details. Clients and works a ents are advised to im lement

 

g p

Foreword

The main purpose of the catalogue is to disseminate information and promote awareness on tunnel failures which could pose a danger to life and property. The possible causes of the failures, the geotechnical problems and the lessons learnt, where these are known, are outlined in the catalogue. Readers should refer to the source reference documents quoted for details. Clients and works agents are advised to implement effective geotechnical risk management measures in the planning, investigation, design and construction of their tunnel projects.

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 4: Tunnel Failure

Division Workin Grou on Cavern and Tunnel En ineerin and

 

g p g g

Foreword

The first edition of the catalogue was issued in February 2007 and was put together by Mr W Lee, supervised by Mr K J Roberts. The second edition issued in March 2009 was prepared by Ms L Y Pau, supervised by Mr L P Ho. This third edition was prepared by Ms L Y Pau, supervised by Mr K S Chau. GEO staff, members of the Hong Kong Institution of Engineers Geotechnical Division Working Group on Cavern and Tunnel Engineering and other individuals have contributed to this Catalogue. All contributions are gratefully acknowledged.

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 5: Tunnel Failure

 

Foreword

If any information in this catalogue is found to be inaccurate or out-of-date, please contact the Chief Geotechnical Engineer/Mainland East of the Geotechnical Engineering Office, Civil Engineering and Development Department, 101 Princess Margaret Road, Ho Man Tin, Kowloon, Hong Kong.

N F Chan Chief Geotechnical Engineer/Mainland East

Geotechnical Engineering Office Civil Engineering and Development Department

October 2012

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 6: Tunnel Failure

. un c n ergroun , ermany,

         

6 M i h U d d G 1980

Tunnel Failures – List of Overseas Cases

1. Green Park, London, UK, 1964

2. Victoria Line Underground, London, UK, 1965

3. Southend-on-sea Sewage Tunnel, UK, 1966

4. Rørvikskaret Road Tunnel on Highway 19, Norway, 18 March 1970

5. Orange-fish Tunnel, South Africa, 1970

6. Munich Underground, Germany, 1980

7. Holmestrand Road Tunnel, Norway, 16 Dec. 1981

8. Gibei Railway Tunnel, Romania, 1985

9. Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989

10. Seoul Metro Line 5 - Phase 2, Korea, 17 Nov. 1991

11. Seoul Metro Line 5 - Phase 2, Korea, 27 Nov. 1991

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 7: Tunnel Failure

         

Tunnel Failures – List of Overseas Cases

12. Seoul Metro Line 5 - Phase 2, Korea, 11 Feb. 1992

13. Seoul Metro Line 5 - Phase 2, Korea, 7 Jan. 1993

14. Seoul Metro Line 5 - Phase 2, Korea, 1 Feb. 1993

15. Munich Underground, Germany, 27 Sept. 1994

16. Heathrow Express, UK, 21 Oct. 1994

17. Los Angeles Metro, USA, 22 June 1995

18. Motorway Tunnels, Austria, 1993 - 1995

19. Docklands Light Rail, UK, 23 Feb. 1998

20. Athens Metro, Greece, 1991-1998

21. Lærdal Road Tunnel on European Highway E 16, Norway, 15 June 1999

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 8: Tunnel Failure

27. Shanghai Metro, China, 2003

         

Tunnel Failures – List of Overseas Cases

22. Sewage Tunnel, Hull, UK, 1999

23. Taegu Metro, South Korea, 1 Jan. 2000

24. Channel Tunnel Rail Link, UK, Feb. 2003

25. Météor Metro Tunnel, France, 14 Feb. 2003

26. Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003

27. Shanghai Metro, China, 2003

28. Tunnel Failure, Japan, 2003

29. Guangzhou Metro Line 3, China, 1 April 2004

30. Singapore MRT, 20 April 2004

31. Kaoshiung Rapid Transit, Taiwan, 29 May 2004

32. Oslo Metro Tunnel, Norway, 17 June 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 9: Tunnel Failure

. , , .

aos ung ap rans t a wan ec

         

Tunnel Failures – List of Overseas Cases

33. Kaoshiung Rapid Transit, Taiwan, 10 Aug. 2004

34. Hsuehshan Tunnel, Taiwan, 1991-2004

35. Barcelona Metro, Spain, 27 Jan. 2005

36. Lausanne M2 Metro, Switzerland, 22 Feb. 2005

37. Lane Cove Tunnel, Australia, 2 Nov. 2005

38 K hi R id T i T i 4 D 2005 38. Kaoshiung Rapid Transit, Taiwan, 4 Dec. 2005

39. Nedre Romerike Water Treatment Plant Crude Water and Potable Water Tunnels, Norway, 2005

40. Hanekleiv Road Tunnel, Norway, 25 Dec. 2006

41. Stormwater Management and Road Tunnel (SMART), Malaysia, 2003 – 2006

42. Sao Paulo Metro Station, Brazil, 15 Jan. 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 10: Tunnel Failure

         

Tunnel Failures – List of Overseas Cases

43. Guangzhou Metro Line 5, China, 17 Jan. 2008

44. Langstaff Road Trunk Sewer, Canada, 2 May 2008

45. Circle Line 4 Tunnel, Singapore, 23 May 2008

46. Hangzhou Metro Tunnel, China, 15 Nov. 2008

47. Cologne North-South Metro Tram Line, German, 3 March 2009

48. Brightwater Tunnel, USA, 8 March 2009

49. Seattle’s Beacon Hill Light Rail, USA, July 2009

50. Cairo Metro Tunnel, Egypt, 3 Sept. 2009

51. Shenzhen Express Rail Link, 27 March 2011, 4 May 2011 and 10 May 2011

52. Hengqin Tunnel, Macau, 19 July 2012

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 11: Tunnel Failure

           

Tunnel Failures – List of Hong Kong Cases

1. MTR Modified Initial System, Prince Edward Station, Nathan Road, 12 Sept. 1977

2. MTR Island Line, 22 Hennessy Road, 1 Jan. 1983

3. MTR Island Line, Shing On Street, Shau Kei Wan, 23 July 1983

4. MTR Island Line, 140-168 Shau Kei Wan Road, 16 Dec. 1983

5. 5. Kowloon Southern Link Contract KDB 200, Canton Road, 21 Oct. Kowloon Southern Link Contract KDB 200, Canton Road, 21 Oct. 2006

6. Kowloon Southern Link Contract KDB 200, Salisbury Road, 3 June 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 12: Tunnel Failure

Overseas Cases   

   Overseas Cases

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 13: Tunnel Failure

       

Green Park, London, UK, 1964

• Background • Tunnel (Green Park to Victoria) driven through London Clay

using drum-digger shield

• The failure • Inflow of sand and gravel, burying most of the shield

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Clay & Takacs (1997)

Page 14: Tunnel Failure

         

• Possible cause of failure • The crown of the shield penetrated through the London Clay

layer into sand and gravel

• Source • Clay & Takacs (1997)

Green Park, London, UK, 1964

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Clay & Takacs (1997)

Page 15: Tunnel Failure

         

n ow o san an grave

Victoria Line Underground, London, UK, 1965

• Background • Tunnel (300m long and 3.7m internal diameter) driven through

London Clay using hand-shield and lined with cast-iron segments under a disused railway marshalling yard

• The failure •• IInflow of sand and gravel f d lfl d

Clay & Takacs (1997) Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 16: Tunnel Failure

         

• Possible cause of failure • The shield was ineffective in supporting the overlying ground

• Source • Clay & Takacs (1997)

Victoria Line Underground, London, UK, 1965

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 17: Tunnel Failure

       

Southend­on­Sea Sewage Tunnel, UK, 1966

• Background • Tunnel driven through London Clay (40m long and 1.35m in

diameter)

• The failure • Water inflow into the tunnel

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Clay & Takacs (1997)

Page 18: Tunnel Failure

       

• Possible cause of failure • The tunnel intersected the bottom of an abandoned 600mm

diameter well

• Source • Clay & Takacs (1997)

Southend­on­Sea Sewage Tunnel, UK, 1966

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Clay & Takacs (1997)

Page 19: Tunnel Failure

• The to of the shaft on the round surface

           

     

Rørvikskaret Road Tunnel on Highway 19, Norway, 18 March 1970

• Background • Road tunnel 726m long and 8m wide constructed by the drill-and-blast

method • The failure

• Tunnel face collapsed and a 100m high cave-in shaft from the tunnel up to the ground surface was created

• The top p of the shaft on the ground g surface had a dimension of about 25m x 50m

• Although soft material was hauled out from the tunnel during the spring in 1971, cave-in continued from the shaft until autumn 1972.

• The cave-in zone extended 30m along the tunnel and the total volume of material hauled out from the tunnel was about 75,000m3

Karlsrud (2010)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 20: Tunnel Failure

• Pro ramme dela ed for more than 3 ears

           

     

g y y

Rørvikskaret Road Tunnel on Highway 19, Norway, 18 March 1970

• Possible cause of failure • Preliminary investigation carried out without any drilling • Probe drilling was not performed during tunnelling • No stabilization measures to support a large swelling clay section

before blasting

• Consequences • Programme delayed for more than 3 years • Double the cost of the tunnel compared to the estimated cost

• Emergency and remedial measures • Installation of corrugated steel vault, steel tubes and 500mm thick

concrete lining was not successful • The cave-in ceased after filling of about 3,000m3 concrete into the

shaft to form a plug from the tunnel up to 10m above the crown and another 4,000m3 of sand and stone from the top of the shaft above the concrete plug

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 21: Tunnel Failure

ar sru

           

     

Rørvikskaret Road Tunnel on Highway 19, Norway, 18 March 1970

• Lessons learnt • The importance of the adequate ground investigation to identify if

weak ground is present and to provide measures to support the weak ground before tunnel excavation

• Source • K l d (2010) • Karlsrud (2010)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 22: Tunnel Failure

       

Orange­fish Tunnel, South Africa, 1970

• Background • Tunnel designed to carry irrigation water from the Orange River

(80km long and 5.3m in diameter, 1,200m above sea level) • Tunnelling using the rail-mounted drill and blast method and lined

with insitu concrete

• First failure – Heavy water inflow • Water inflow of about 55,000 litres/min into the tunnel at 14 bars • Entire 1.6km tunnel section flooded within 24 hours

• Possible cause of failure • The tunnel passed through a shallow anticline and intersected a

fissure, about 75mm wide, almost perpendicularly

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 23: Tunnel Failure

       

Orange­fish Tunnel, South Africa, 1970

• Second failure – Fire • Methane gas ignited by a blast • No explosion occurred as the gas did not reach the explosive

concentration • The fire burnt for about 6 month

• Possible cause of failure • Methane gas from a methane bearing fissure entered the tunnel

during excavation

• Source • Clay & Takacs (1997)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 24: Tunnel Failure

     

Munich Underground, Germany, 1980

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Construction Today (1994b)

Page 25: Tunnel Failure

     

Munich Underground, Germany, 1980

• Background • New Austrian Tunnelling Method (NATM) construction of twin 6m

diameter tunnels

• The failure • 10m wide, 14m deep sinkhole • 10m wide, 14m deep sinkhole

• Possible causes of failure • Local variation in geology with reduction in marl cover to 1-1.5m

and led to overstressing of the sprayed concrete temporary lining

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 26: Tunnel Failure

     

Munich Underground, Germany, 1980

• Consequences • Delay to works

• Remedial Measures • Void was backfilled with crushed rock and cement and pressure

grouted grouted

Source • Construction Today (1994b)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 27: Tunnel Failure

           

Holmestrand Road Tunnel, Norway, 16 Dec. 1981 • Background

• Road tunnel 1.78km long and 10m wide tunnel constructed by the drill­and-blast method

• The failure • A minor cave-in from the face and

partly from the crown occurred during the the process of moving the steel process of moving the steel formwork for cast concrete lining forward to the face

• Possible cause of failure • A weak fault zone was encountered • No spiling bolts ahead of the face to

support the weak ground

Karlsrud (2010)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 28: Tunnel Failure

combination with fibre reinforced

           

Holmestrand Road Tunnel, Norway, 16 Dec. 1981 • Consequences

• More time (5 hours extended to 25 hours) required for hauling out and concreting the foundation for the mould

• Lessons learnt • Spiling bolts ahead of the face in

combination with fibre reinforced sprayed concrete, rock bolts, and reinforced ribs of sprayed concrete are required at the fault zones with extremely poor rock mass quality

• Source • Karlsrud (2010)

Karlsrud (2010)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 29: Tunnel Failure

       

Gibei Railway Tunnel, Romania, 1985

• Background • Railway tunnel 2.21km long and 9m in diameter

• The failure • “Compact” fissured clay layer failed suddenly, allowing water

inflow >600 litres/min into the tunnel

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Clay & Takacs (1997)

Page 30: Tunnel Failure

       

• Possible cause of failure • The tunnel penetrated a lens of waterlogged fine-grained sand

just above the crown

• Source • Clay & Takacs (1997)

Gibei Railway Tunnel, Romania, 1985

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Clay & Takacs (1997)

Page 31: Tunnel Failure

   

       

Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989

• Background • Tunnel constructed by Tunnel Boring Machine (TBM)

• The failure • Fine soil flowed into the tunnel forming a hole in the road as the

TBM went through the rock into the soft ground

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Clay & Takacs (1997)

Page 32: Tunnel Failure

   

       

• Possible cause of failure • The tunnel intersected a hidden area of soft clay

• Source • Clay & Takacs (1997)

Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 33: Tunnel Failure

             

   

Seoul Metro Line 5 ­ Phase 2, Korea, 17 Nov. 1991

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Lee & Cho (2008)

Page 34: Tunnel Failure

,

             

   

Seoul Metro Line 5 ­ Phase 2, Korea, 17 Nov. 1991

• Background • Construction of Seoul Metro tunnel near Majang by drill and blast

method

• The failure • After blasting : daylight collapse up to ground surface involving • After blasting : daylight collapse up to ground surface, involving

the embankment of a river • 20m x 15m and 4m deep crater at the ground surface • Water from river flowed into the tunnel

• Possible cause of failure • Thin weathered rock cover • Inflow of soil and groundwater

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 35: Tunnel Failure

chemical grouting

           

   

Seoul Metro Line 5 ­ Phase 2, Korea, 17 Nov. 1991

• Consequences • Roads collapse and gas mains

fractured

• Remedial measures • Backfilling the crater with soil

followed by cement grouting and chemical grouting

• Lessons learnt • Insufficient ground investigation • Unexpected groundwater inflow • No tunnel face stability analysis • No consideration of blasting effects

closed to weathered zone with shallow cover

Lee & Cho (2008) Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 36: Tunnel Failure

           

   

• Source • Lee & Cho (2008) • Madrid (1996) • Shin et al (2006)

Seoul Metro Line 5 ­ Phase 2, Korea, 17 Nov. 1991

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 37: Tunnel Failure

             

   

Seoul Metro Line 5 ­ Phase 2, Korea, 27 Nov. 1991

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Lee & Cho (2008)

Page 38: Tunnel Failure

am as ng

             

   

10:40 : bl ti

Seoul Metro Line 5 ­ Phase 2, Korea, 27 Nov. 1991

• Background • Construction of Seoul Metro tunnel near Dangsan by drill and

blast method

• The failure • 27 November 1991

10:40am : blasting 4:00pm : rock falls at the tunnel face

10:00pm : soil and groundwater inflow into the tunnel

• 28 November 1991 3:20am : substantial daylight collapse up to ground surface forming a 25m diameter crater

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 39: Tunnel Failure

,

Seoul Metro Line 5 ­ Phase 2, Korea, 

27 Nov. 1991

• Possible cause of failure • Weathered granite at the face

and high permeability soil

• Consequences • Three buildings collapsed • Several water mains gas • Several water mains, gas

pipes and sewerage were broken

• Remedial measures • Backfilling the crater with soil

followed by cement grouting and chemical grouting

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region Lee & Cho (2008)

Page 40: Tunnel Failure

zone w s a ow cover

             

   

Seoul Metro Line 5 ­ Phase 2, Korea, 27 Nov. 1991

• Lessons learnt • Insufficient ground investigation • Unexpected groundwater inflow • No tunnel face stability analysis • No consideration of blasting effects closed to weathered

ith h ll zone with shallow cover

• Source • Lee & Cho (2008) • Madrid (1996) • Shin et al (2006)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 41: Tunnel Failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 11 Feb. 1992

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Lee & Cho (2008)

Page 42: Tunnel Failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 11 Feb. 1992

• Background • Construction of Seoul Metro tunnel near Youido by road header

• The failure • Significant inflow of groundwater • About 4.5 tonnes of soil flowed into tunnel • 38m wide x 6m deep crater at the ground surface

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 43: Tunnel Failure

o owe y cement grout ng an

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 11 Feb. 1992

• Possible cause of failure • Weathered granite at the tunnel

face and high permeability soil

• Remedial measures • Backfilling the crater with soil

f ll d b i dfollowed by cement grouting and chemical grouting

• Lessons learnt • Insufficient ground investigation • Unexpected groundwater inflow • No tunnel face stability analysis

Lee & Cho (2008) Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 44: Tunnel Failure

              

   

• Source • Lee & Cho (2008) • Madrid (1996) • Shin et al (2006)

Seoul Metro Line 5 ­ Phase 2, Korea, 11 Feb. 1992

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 45: Tunnel Failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 7 Jan. 1993

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Lee & Cho (2008)

Page 46: Tunnel Failure

• The failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 7 Jan. 1993

• Background • Construction of Seoul Metro tunnel near Yongdungpo by drill and

blast method

• The failure • Tunnel collapsed after removing spoil • Tunnel collapsed starting from the left side of the crown • 900m3 of loose material flowed into the tunnel and water inflow of

up to 300 litres/min recorded

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 47: Tunnel Failure

eme a measures

R di l

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 7 Jan. 1993

• Possible cause of failure • Weathered granite at the tunnel

face • High groundwater pressure

•• Remedial measures • Backfilling the crater with soil

followed by cement grouting and chemical grouting

Lee & Cho (2008) Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 48: Tunnel Failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 7 Jan. 1993

• Lessons learnt • Insufficient ground investigation • Unexpected groundwater inflow • No tunnel face stability analysis • No consideration of blasting effects closed to weathered zone

with shallow cover

• Source • Lee & Cho (2008) • Madrid (1996) • Shin et al (2006)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 49: Tunnel Failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 1 Feb. 1993

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Lee & Cho (2008)

Page 50: Tunnel Failure

• The failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 1 Feb. 1993

• Background • Construction of Seoul Metro tunnel near Anyangcheon by road

header

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure • Daylight collapse when weathered granite found at the tunnel

face • Groundwater flowed into the tunnel • 60m wide oval shaped area subsided

Page 51: Tunnel Failure

onsequences

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 1 Feb. 1993

• Possible cause of failure • Weathered granite and alluvium

at the tunnel face • High groundwater pressure

• C• Consequences • Six heavy plants buried

• Remedial measures • Backfilling the crater with soil

followed by cement grouting and chemical grouting

Lee & Cho (2008)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 52: Tunnel Failure

              

   

Seoul Metro Line 5 ­ Phase 2, Korea, 1 Feb. 1993

• Lessons learnt • Insufficient ground investigation • Unexpected groundwater inflow • No tunnel face stability analysis

• Source • Lee & Cho (2008) • Madrid (1996) • Shin et al (2006)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 53: Tunnel Failure

own

         

d

Munich Underground, Germany, 27 Sept. 1994

• Background • 7m diameter tunnel supported by

sprayed concrete lining • The tunnel was assumed to be

beneath a clay layer overlying water-bearing gravel and groundwater would not be drawn down

• The failure • Quick inflow of water and ground

materials • Large subsidence crater quickly

filled with groundwater

Construction Today (1994a) • 20m wide, 18.5m deep crater Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 54: Tunnel Failure

Consequences

         

Munich Underground, Germany, 27 Sept. 1994

• Possible causes of failure • Layer of marl separating groundwater bearing layers was

much thinner than originally assumed • Sand-infilled cracks in the marl layer acted as preferential

pathways for water

• Consequences • Bus fell into the crater • Three passengers killed • 30 people injured

Civil Engineering and Development Department Construction Today (1994a)

The Government of the Hong Kong Special Administrative Region

Page 55: Tunnel Failure

         

Munich Underground, Germany, 27 Sept. 1994

• Remedial measures • Bored-pile wall to form a shaft • Excavation inside the shaft for rescue • Tunnel driven again using compressed air

• Sources • Sources • Boos et al (2004) • Construction Today (1994a) • Ground Engineering (1994)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 56: Tunnel Failure

           

Heathrow Express Tunnel, UK, 21 Oct. 1994

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Ground Engineering (2008) ICE (1998b)

Page 57: Tunnel Failure

• The failure

           

Heathrow Express Tunnel, UK, 21 Oct. 1994

• Background • NATM in London Clay

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• 10m diameter crater formed

ICE (1998b)

Page 58: Tunnel Failure

• Differential settlement induced at ad acent buildin s

           

j g

Heathrow Express Tunnel, UK, 21 Oct. 1994

• Possible cause of failure • A series of design and management errors combined with

poor workmanship and quality control

• Consequences • Differential settlement induced at adjacent buildings • Services Terminal 4 halted for one month • Remedial measures caused chaos at Heathrow Airport • Recovery cost £150M (3 times original contract sum)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 59: Tunnel Failure

           

Heathrow Express Tunnel, UK, 21 Oct. 1994

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

0 to +0.5m

0 to -1m

-1 to -2m

-2 to -3m

> -3m

GROUND SURFACE CONTOURS LEGENDS

Central Terminal Area Settlement Contours

Page 60: Tunnel Failure

           

• Remedial measures • Backfilled with 13,000m3 concrete

Heathrow Express Tunnel, UK, 21 Oct. 1994

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 61: Tunnel Failure

           

However much en ineers are ressured to build uickl and

Heathrow Express Tunnel, UK, 21 Oct. 1994

• Lessons learnt • Measures to ensure safety must be planned • Do not lose sight of critical technical issues in the pursuit of time

and cost reduction • Whilst a number of factors contributed to the collapse, half of them

were matters of management • However much engineers are pressured to build quickly and • g p q y

cheaply, the industry will be judged by its own failures

• Sources • Ground Engineering (2000) • HSE (1996, 2000) • ICE (1998b, 1999)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 62: Tunnel Failure

           

1996 report 2000 report

Heathrow Express Tunnel, UK, 21 Oct. 1994

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 63: Tunnel Failure

e ow sur ace

           

b l f

Los Angeles Metro, USA, 22 June 1995

• Background • Re-mining/remedial works to

realign an existing TBM tunnel (6.7m diameter, 25m deep), which had been bored off line

• Hard siltstone overlain by alluvium with groundwater level 10-12m below surface

• The failure • 25m deep sinkhole caused by

collapse of south bore • Serious cracking observed in

temporary lining of north bore Civil Engineer International (1995)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 64: Tunnel Failure

onsequences

C

           

Los Angeles Metro, USA, 22 June 1995

• Possible causes of failure • Failure occurred during removal of segmental lining in tunnel

roof and relining of tunnel to correct the horizontal alignment • Unexpected ground conditions in the alluvium • Fractured water mains (unconfirmed)

•• Consequences • 30m length of a four lane road (Hollywood Boulevard) affected

leading to road closure • Collapsed 250mm water main possibly contributing to failure • Broken gas pipe • Evacuation of local residents

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 65: Tunnel Failure

           

Los Angeles Metro, USA, 22 June 1995

• Remedial measures • Steel rings installed in tunnel either side of the collapse • 3,300m3 of grout to fill void and stabilise area • Road resurfacing

• Source • Civil Engineer International (1995)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 66: Tunnel Failure

       

Motorway Tunnels, Austria, 1993 ­ 1995

• Background • Tunnel constructed in sandstone and shale with fault zones

by the drill & blast method • Tunnel divided into 4 sections, namely T1 – T4 • T1 - 376m long; T2 - 562m; T3 – 2,760m and T4 – 1,230m

• Failures at T4 in 1993 • About 130 overbreak incidents with total volume of 1,461m3,

maximum deformation of 120mm measured in the tunnel • 200m3 of loose material collapsed after a blast, resulting in

water inflow of up to 450 litres/min

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 67: Tunnel Failure

       

Motorway Tunnels, Austria, 1993 ­ 1995

• Two failures at T3 in 1995 • 650m3 of loose material flowed into the tunnel, water inflow of up

to 1,500 litres/min recorded • Radial movement of rib of about 300mm occurred and water

inflow of up to 1,500 litres/min recorded

• Source • Clay & Takacs (1997)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 68: Tunnel Failure

           

Docklands Light Rail, UK, 23 Feb. 1998

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

ICE (2004) ICE (1998a)

Page 69: Tunnel Failure

           

Docklands Light Rail, UK, 23 Feb. 1998

• Background • Tunnel constructed for Docklands Light Rail (diameter 5.2m) by

earth pressure balance TBM

• The failure • 22m wide and 7m deep crater formed in the grounds of George

Green School

ICE (1998a)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 70: Tunnel Failure

n ows up o m away ro en y e s ower o mu an

Wi d t 100 b k b th h f d d

           

Docklands Light Rail, UK, 23 Feb. 1998

• Possible causes of failure • Insufficient overburden above the tunnel • High pressure within tunnel causing blow out failure

• Consequence •• Windows up to 100m away broken by the shower of mud and

stones released

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 71: Tunnel Failure

           

• Lesson learnt • To require specific assessments / calculations to demonstrate

the adequacy of factor of safety against blow out failure

• Sources • ICE (1998a)

Docklands Light Rail, UK, 23 Feb. 1998

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• ICE (1998a) • ICE (2004)

Page 72: Tunnel Failure

     

Athens Metro, Greece, 1991­1998

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

IMS IMIA

Page 73: Tunnel Failure

rate ran in from 1.6m to 18m er da based on 18-hour- er-da

     

Athens Metro, Greece, 1991­1998

• Background • Construction of the Olympic Metro under a turnkey contract

(estimated cost about 2 billion ECUs) • Construction started in November 1991 and operation in 1998 • TBM (by Mitsubishi) used for construction of 11.7km long, 9.5m

diameter tunnels located at a depth of 15-20m (with penetration rate ranging from 1.6m to 18m per day based on 18g g p y -hour-perp -day y shift, depending on the ground conditions)

• Cut and cover, supported by soldier piles, struts and prestressed anchor tiebacks for 6.3km long tunnels and stations

• NATM for other short auxiliary tunnels and oval-shaped stations where existence of buried antiquities precluded open excavation

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 74: Tunnel Failure

e n ense y wea ere an g y ec on se zones o en an

     

Athens Metro, Greece, 1991­1998

• The failures • Roof collapses of appreciable size often occurred • Large and occasionally uncontrollable overbreaks for TBM

• Possible causes of failure • Ravelling of the ground seems to be due to insufficient strength in

th i t l th d d hi hl t t i d f Ath ithe intensely weathered and highly tectonised zones of Athenian schist (which is a flysch-type sediment consisting of thinly bedded clayey and calcareous sandstones with alterations and subjected to intense folding, thrusting, faulting and fracturing)

• Large muck openings of the TBM cutterhead which cannot adequately control muck-flow (the cutterhead operates in the open air, i.e. under atmospheric pressure)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 75: Tunnel Failure

     

Athens Metro, Greece, 1991­1998

• Consequence • Major delay in TBM tunnelling

• Remedial measures • Cavities caused by the TBM overbreaks was backfilled by grout

(which sometimes reached the ground surface)

• Source • IMIA • IMS • Kavvadas et al (1996) • Mihalis & Kavvadas (1999)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 76: Tunnel Failure

             

     

• Background • Road tunnel at 1,100m depth,

24.5km long and 9m wide constructed by the drill-and-blast method

Lærdal Road Tunnel on European Highway E 16, Norway, 15 June 1999

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure • A cave-in involving 17m length of

tunnel and extending up to about 11-12m above the crown

• The volume of the failed rock mass was estimated to be 1,200­1,500m3

The Lærdal Tunnel

Ch.11080

CAVE IN

DEBRIS

1200-1500m3

Karlsrud (2010)

Page 77: Tunnel Failure

             

     

Lærdal Road Tunnel on European Highway E 16, Norway, 15 June 1999

• Possible cause of failure • Poor communication : the driller did not inform the engineer about

abnormal drilling rate encountered

• Expansion of the swelling clay under high stress to water during drilling of the rock bolts

• The combination of the swelling of the clay and high stress produced a squeezing effect, which resulted in gradual weakening of the rock mass in the tunnel

• Consequences • The crew was evacuated in time and no one was hurt • About 10 days delay in the excavation works and cost increased for

the remedial works

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 78: Tunnel Failure

70

80

87 no

             

     

• Emergency and remedial measures

• Reinforced ribs of sprayed concrete in addition to layers of sprayed concrete and rock bolts were installed just behind the cave-in zone

Lærdal Road Tunnel on European Highway E 16, Norway, 15 June 1999

The Lærdal Tunnel Cave in zone

700 m3 concrete

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Rock material was hauled into the tunnel building up a barrier up to 2m below the crown and concrete was pumped through a steel pipe to fill the void above the debris

• Debris was gradually hauled out with step wise installation of rock anchors and sprayed fibre reinforced concrete

Fa

ce b

efo

re

cave

in

110

110

110

Debris

1200-1500 m3Concrete Debris hauled out

Ch

.

Karlsrud (2010)

Page 79: Tunnel Failure

• Swelling of clay in condition of high stress could provide a

             

     

Lærdal Road Tunnel on European Highway E 16, Norway, 15 June 1999

• Lessons learnt • The importance of good communication between the driller and the

engineer • Importance of having good understanding of the geological

conditions and their influence on the stability • Swelling of clay in condition of high stress could provide a

squeezing effect and result in weaking of the rock mass in a tunnel

• Source • Karlsrud (2010)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 80: Tunnel Failure

       

Sewage Tunnel, Hull, UK, 1999

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Boos et al (2004)

Page 81: Tunnel Failure

• Water and sand ingress

       

Sewage Tunnel, Hull, UK, 1999

• Background • Construction of a 10.5km long underground sewer by earth

pressure balance TBM (diameter 3.85m) supported by reinforced concrete segmental lining

• The failure • Water and sand ingress • Tunnel subsided by 1.2m causing serious subsidence at surface

• Possible cause of failure • Fluctuation of groundwater level caused by tidal effects resulting in

vertical movement of the tunnel tube causing opening of joints

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 82: Tunnel Failure

• Reconstruction of tunnel using sprayed concrete

       

Sewage Tunnel, Hull, UK, 1999

• Consequences • Damage to buildings, roads and utility lines • TBM had to be abandoned

• Emergency and remedial measures • Ground freezing • Reconstruction of tunnel using sprayed concrete

• Source • Boos et al (2004)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 83: Tunnel Failure

           

Taegu Metro, South Korea, 1 Jan. 2000

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Boos et al (2004)

Page 84: Tunnel Failure

           

Taegu Metro, South Korea, 1 Jan. 2000

• Background • Construction of underground Taegu Metro

• The failure • Failure of diaphragm wall • Excavation pit caved in • Excavation pit caved in

• Possible causes of failure • Rapid fluctuation of groundwater level caused movement of

unidentified gravel and sand strata • Additional loading on diaphragm wall was not considered in design

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 85: Tunnel Failure

• xcavat on p t ac e

E i i b kfill d

           

Taegu Metro, South Korea, 1 Jan. 2000

• Consequences • Bus buried and bus driver seriously injured • Three passengers killed • Neighbouring buildings suffered considerable damage

• Remedial measures • Excavation pit backfilled • Subsoil grouted and diaphragm wall strengthened

• Source • Boos et al (2004)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 86: Tunnel Failure

           

Channel Tunnel Rail Link, UK, Feb. 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

ICE (2003)

Page 87: Tunnel Failure

orme n e groun e n a row o

           

t

Channel Tunnel Rail Link, UK, Feb. 2003

• Background • Tunnelling using TBM (diameter 8.2m) • Boring at a depth of 21m

• The failure • 10m diameter and 20m deep void

f d i h d b hi dformed in the ground behind a row of f houses

• Possible cause of failure • The vibration from the TBM may have

caused the nearby wells (30m deep and 1.8m diameter) to collapse

ICE (2003) Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 88: Tunnel Failure

           

• Consequence • Three uncharted wells collapsed

• Remedial measures • The voids were backfilled with grout

Channel Tunnel Rail Link, UK, Feb. 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source • ICE (2003)

Page 89: Tunnel Failure

           

Météor Metro Tunnel, France, 14 Feb. 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Dubois & Rat (2003)

Page 90: Tunnel Failure

         

Météor Metro Tunnel, France, 14 Feb. 2003

• Background • Construction of Météor

Metro Tunnel in Paris

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure • About 3,000m3 of

sedimentary deposits collapsed underneath a school, occupying an area of 400m2 on plan

Dubois & Rat (2003)

Page 91: Tunnel Failure

• The school had to be closed for a ear affectin 900 students

           

y g

Météor Metro Tunnel, France, 14 Feb. 2003

• Possible cause of failure • Not known

• Consequences • No casualty • The school had to be closed for a year affecting 900 students

• Source • Dubois & Rat (2003)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 92: Tunnel Failure

           

Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003

• Background • Three major failures and many minor failures occurred at a road

tunnel during in service

• The failure • First failure occurred on 28 December 2003: about 20m3 of crushed

and weathered rock involving with clay, which came down from the and weathered rock involving with clay, which came down from the crown went through the frost insulated water shielding vault and down to the carriageway

• Second failure involved about 3m3 of heavily weathered rock, which came down from the springline and fell down to the invert

• Third failure involved 2-3m3 of completely weathered rock, which fell down from the crown and rested on top of the water shielding vault

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 93: Tunnel Failure

Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Third failure

First failure

Karlsrud (2010)

Page 94: Tunnel Failure

• Possible cause of failure• The humidity behind the vault constructed for frost insulated

water shielding was high and the high content of swelling clay inthe weathered rock started sucking water and expandedgradually over a long period of time

• Consequences

Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Consequences• Closure of the tunnel for more than 3 months for extensive

repairs and upgrading of the tunnel support

• Emergency and remedial measures• Complete removal of the vault before installing additional rock

support including fiber reinforced shotcrete, rock bolts andreinforced ribs of sprayed concrete

Page 95: Tunnel Failure

• Lessons learnt• The importance of proper geological mapping and rock mass

classification• The need to identify swelling minerals and the potential of

deterioration of strength in weathered rock• The importance of adequate support design for long-term

Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The importance of adequate support design for long-termstability in weathered rock

• Source• Karlsrud (2010)

Page 96: Tunnel Failure

Shanghai Metro, China, 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Boos et al (2004)

Page 97: Tunnel Failure

Shanghai Metro, China, 2003

• Background• Expansion of the Shanghai Metro (上海地鉄) Line 4 crossing

beneath the Huangpu River (黃埔江)• Two parallel tunnel tubes constructed by earth pressure balance

TBM

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• Failure occurred during construction of a cross passage• Massive ingress of water and material at the face at a depth of 35m• Several metres ground subsidence

Page 98: Tunnel Failure

• Possible cause of failure • Failure of ground freezing unit

• Consequences• High rise office buildings seriously damaged• Flood protection dyke on the river badly damaged

Shanghai Metro, China, 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source • Boos et al (2004)

Page 99: Tunnel Failure

Tunnel Failure in Japan, 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Takahashi (2010)

Page 100: Tunnel Failure

• The failure• Ground collapse of an avalanche type containing cobbles, gravels

and water took place at the point 900m away from the tunnel portal• A large crater was observed at the ground surface about 130m

above the tunnel

Tunnel Failure in Japan, 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative RegionTakahashi (2010)

Page 101: Tunnel Failure

• Possible cause of failure• Existence of high groundwater

pressure• Decrease in cover of the mud-

stone layer• Water path created by the

investigation drillhole

Tunnel Failure in Japan, 2003

Filling with foam concrete

Grout

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Consequence• Programme delayed for about 2

years

• Emergency and remedial measures• Filling the cave-in area by foam

concrete• Grouting under the collapse area• Boring for drainage from the tunnel

Takahashi (2010)

Page 102: Tunnel Failure

• Lessons learnt• The importance of adequate ground investigation before

tunnelling• The importance of investigations and observations during

construction for adopting appropriate support measures

• Source

Tunnel Failure in Japan, 2003

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Takahashi (2010)

Page 103: Tunnel Failure

Guangzhou Metro Line 3, China, 1 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

ChinaDaily (2004)

Page 104: Tunnel Failure

Guangzhou Metro Line 3, China, 1 April 2004

• Background• Construction of a 58.5km long underground metro in which

45.6km is a single-tube shield TBM

• The failure• Failure of a diaphragm wall

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Failure of a diaphragm wall

• Possible cause of failure• Rapid fluctuation of groundwater level due to the heavy rainfall• Complicated geology including a layer of swelling soil

Page 105: Tunnel Failure

• Consequences• A three-storey building collapsed and sunk into the ground• Collapse of nearby underground water mains

• Remedial measures• Backfilled with crushed rock and cement

Guangzhou Metro Line 3, China, 1 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• ChinaDaily (2004) • Soufun (2004) • Longhoo (2004)

Page 106: Tunnel Failure

Singapore MRT, 20 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Government of Singapore (2005)

Page 107: Tunnel Failure

Singapore MRT, 20 April 2004

• Background• An open cut tunnel excavated for Singapore MRT’s new Circle Line • Design and build• Excavated trench of 15m wide and 33m deep mainly in marine clay

with some fluvial clay supported by 0.8-1.0m thick diaphragm wall which is 35-45m deep without rock socket

• Steel struts: 4-5m horizontal and 3m vertical spacing

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Steel struts: 4-5m horizontal and 3m vertical spacing• Bottom-up construction • Jet grouted base slabs

• Layer 1-1.5m thick at 28.5m below ground• Layer 2-3m thick at 33.5m below ground (Layer 2 not yet

constructed when collapse occurred)

Page 108: Tunnel Failure

• The failure• 9th level of struts being installed when

collapse took place• Unusual cracking and groaning noises heard

early in the morning (6 hours)• Loud cracking noise heard in the afternoon, 15

minutes before collapse

Singapore MRT, 20 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

minutes before collapse• Collapse plan area was 100m by 130m• Settlement up to 15m• Diaphragm walls displaced• Steel struts mangled

Government of Singapore (2005)

Page 109: Tunnel Failure

• Possible causes of failure• Under-design of the strut-waler connection in the strutting system• Incorrect use of Finite Element Method• No proper design reviews• Disregard of different warnings, for example, excessive wall

deflections and surging inclinometer readings

Singapore MRT, 20 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

deflections and surging inclinometer readings• Poor construction quality• Ineffective instrumentation and monitoring system• Failure to implement risk management

Page 110: Tunnel Failure

• Consequences • Part of Nicoll Highway, Singapore’s major east-west harbour-front

road, destroyed• Four workers killed• Several others injured • 15,000 people and 700 businesses affected

Singapore MRT, 20 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• 15,000 people and 700 businesses affected• Three offices and retail towers at risk from further ground movement• Damage of a gas service line, resulting in an explosion and fire• A storm drain damaged

Page 111: Tunnel Failure

• Remedial measures• Rescue and backfilling• Structurally disconnected the Merdeka Bridge• All contracts of the Circle Line put on hold• All contracts to carry out checks and review of design and

construction of temporary works• All Professional Engineers to confirm in writing the adequacy of

Singapore MRT, 20 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• All Professional Engineers to confirm in writing the adequacy of their designs

• All designs to be independently checked by the Building & Construction Authority

Page 112: Tunnel Failure

• Lessons learnt• This is a need for robust design, risk management, design review

and independent checking, purposeful back analysis, an effective instrumentation, monitoring and interpretation regime, an effective system of management of uncertainties and quality during construction, corporate competencies and safety management

• The safety of temporary works is as important as that of

Singapore MRT, 20 April 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

permanent works and should be designed according to established codes and checked by competent persons

• Main Source• Government of Singapore (2005)

Page 113: Tunnel Failure

Kaohsiung Rapid Transit , Taiwan, 29 May 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Lee & Ishihara (2010)

Page 114: Tunnel Failure

• Background• Chemical Churning Piles (CCP) of

350mm diameter installed as guide wallsfor the diaphragm wall construction

• Soil improvement works by the use ofSuper Jet Grouting (SJG) method at thereception area for break-out operations

• The diaphragm wall panels were first

Kaohsiung Rapid Transit , Taiwan, 29 May 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The diaphragm wall panels were firstcored through by chain saw according tothe face-shape of the shield tunnelmachine and manual power tool wasused to disassemble the reinforcedconcrete residual inside the coring holes

• EPB Tunnel Boring Machine 500mmaway from the wall face awaiting forbreak-out and invert leakage started

Lee & Ishihara (2010)

Page 115: Tunnel Failure

• The failure• Sinkhole of about 10m in diameter formed at the ground surface• Ground settlement influence zone ranging from 40m to 50m in

diameter with maximum settlement from 500mm to 1,500mm.• Several rings of tunnel segmental linings were damaged

Kaohsiung Rapid Transit , Taiwan, 29 May 2004

Settled Area of Ground Surface

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region Lee & Ishihara (2010)

Chemical Churning Pile (CCP)

Soil Improvement Zone

Diaphragm Wall

CCP

Possible Collapse Zone

Soil Improvement Zone

Leakage spot

Tunnel Boring Machine

Path of Leakage

Page 116: Tunnel Failure

Kaohsiung Rapid Transit , Taiwan, 29 May 2004

• Possible causes of failure • Progressive development of unexpected cracks inside the soil

improvement zone resulting in groundwater leakages in the reception area as a result of piping and/or hydraulic fracturing

• Leakage paths at the interfaces between Chemical Churning Pile (CCP) and the diaphragm wall, CCP and Super Jet Grout (JSG) materials, or inside the lower portion of the JSG body

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

(JSG) materials, or inside the lower portion of the JSG body

• Chloride assault and deterioration of CCP, which were installed two years before the wall breaking process, had significant effects on the integrity and water tightness at the interfaces

• The highly sensitive and erodible soil dispersed around the SJG might have been disturbed due to the application of highly pressured water jet in the grouting process

Page 117: Tunnel Failure

Kaohsiung Rapid Transit , Taiwan, 29 May 2004

• Possible causes of failure • Mechanical and/or vibration disturbances occurred during the wall

breaking process leading to serious cracks and fissure development inside the deteriorated CCP and defective SJG blocks

• Unfavourable sub-surface conditions which consisted of silty sands and sandy silts with water contents almost reaching their liquid limits

• Consequences

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Consequences • Adjacent buildings were damaged

Lee & Ishihara (2010)

Page 118: Tunnel Failure

Kaohsiung Rapid Transit , Taiwan, 29 May 2004

• Emergency and remedial measures• Stabilizing the ground by piling-up

sand bags in front of the tunnelface to reduce leakage, backfillingthe sinkhole and grouting thetunnel crown and invert

• Advancing the TBM further toreduce the gap between the D-wall

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

reduce the gap between the D-walland the tunnel

• Installation of steel frames toreinforce the damaged ringsegments

• Source• Lee & Ishihara (2010)

Lee & Ishihara (2010)

Page 119: Tunnel Failure

• Background• Metro line tunnel 1.3km long and 7m wide connecting with an old tunnel

Oslo Metro Tunnel, Norway, 17 June 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Karlsrud (2010)

Planned concrete wall

Cave in area

Page 120: Tunnel Failure

Oslo Metro Tunnel, Norway, 17 June 2004

• The failure• At the junction where the two tunnels met in an acute angle, tunnel

cave-in after removal of most part of the rock pillar between thetunnels

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Karlsrud (2010)

m iljo\d iv\2000\ah-1.pp t

Removed pillar

New tunnel Old tunnel

Span 18-20m after cave-in

Page 121: Tunnel Failure

• Possible cause of failure• Unfavourable direction of the bedding planes in relation to the

geometry and span of the tunnels• Over excavation of the rock pillar and the removal of the

remaining rock pillar and old concrete wall before the plannedconcrete pillar was constructed

• Consequence• Programme delayed for about 3 months

Oslo Metro Tunnel, Norway, 17 June 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Programme delayed for about 3 months• Cost implication: extra cost of the remedial works

• Emergency and remedial measures• Filling up the whole opening by concrete above the fallen debris• Installation of 10m long cable anchors together with permanent

support of 200mm thick lining of reinforced sprayed concrete,reinforced ribs of sprayed concrete and additional 6m long rockbolts

Page 122: Tunnel Failure

• Lessons learnt• The importance of adequate ground investigation• The need to follow the sequence of rock support installation in

accordance with the design plans during construction

• Source

Oslo Metro Tunnel, Norway, 17 June 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Karlsrud (2010)

Page 123: Tunnel Failure

Kaohsiung Rapid Transit, Taiwan, 10 Aug. 2004

• Background• Construction of the Kaohsiung Rapid

Transit Blue & Orange Lines in Kaohsiung City

• The failures

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• First collapse on 29 May 2004 underneath a street

• Second collapse in mid June 2004• Third collapse on 13 July 2004 with

formation of a large sinkhole• Fourth collapse on 10 Aug 2004

Taiwan Info (2004)

Page 124: Tunnel Failure

• Possible cause of failure• Possible adverse ground and groundwater conditions

• Consequences• First collapse - Several buildings affected and 100 people

evacuated • Third collapse - Three residential buildings evacuated and

Kaohsiung Rapid Transit, Taiwan, 10 Aug. 2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Third collapse - Three residential buildings evacuated and significant disruption to water/electricity supply

• Fourth collapse - No casualty, one building affected and part of the works suspended

• Source• Taiwan Info (2004)

Page 125: Tunnel Failure

Hsuehshan Tunnel, Taiwan, 1991-2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

TANEEB (2005)

TANEEB (2005)

Page 126: Tunnel Failure

Hsuehshan Tunnel, Taiwan, 1991-2004

• Background• Construction of 12.9km long and 4.8m diameter Hsuehshan

Tunnel in Taiwan (雪山隧道) • Works commenced in 1991 and completed in 2004• Comprised 2 main tunnels (East & Westbound) and a pilot tunnel• Eastbound by TBM method (July 1993 to Sept. 2004)• Westbound by TBM method (July 1993 to April 2004)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Westbound by TBM method (July 1993 to April 2004)• Pilot tunnel by drill & blast method (July 1991 to Oct. 2003)

Westbound Eastbound

Pilot TunnelTANEEB (2005)

Page 127: Tunnel Failure

• The failures• Eastbound

• 28 collapses occurred• Westbound

• TBM badly damaged due to tunnel collapse and groundwater inflow of 45,000 litres/min into the tunnel

• Pilot Tunnel

Hsuehshan Tunnel, Taiwan, 1991-2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Pilot Tunnel• 8 collapses occurred

• Possible causes of failure• Unexpected difficult geology with fractured rock and massive

inflows of water• 6 major faults found along the tunnel alignment

Page 128: Tunnel Failure

• Consequences• Eastbound

• Failure in May 1993 affected 56 buildings and 73 families• Westbound

• 11 men died• Pilot Tunnel

• 13 stoppages

Hsuehshan Tunnel, Taiwan, 1991-2004

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• 13 stoppages

• Source• TANEEB (2005)

Page 129: Tunnel Failure

Barcelona Metro, Spain, 27 Jan. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

European Foundations (2005)

Page 130: Tunnel Failure

Barcelona Metro, Spain, 27 Jan. 2005

• Background• Tunnel for Barcelona Line Five Metro Extension• Tunnelling using NATM

• The failure• 30m wide and 32m deep crater formed

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• 30m wide and 32m deep crater formed

• Possible cause of failure• A “hidden” vertical fault located 1m behind the sprayed concrete

lining

Page 131: Tunnel Failure

• Consequences• 2 five-storey buildings and a smaller one demolished• More than 50 families made homeless

• Remedial measures• The void was backfilled with grout of about 2,000m3

Barcelona Metro, Spain, 27 Jan. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The void was backfilled with grout of about 2,000m3

• Source• European Foundations (2005)

Page 132: Tunnel Failure

Lausanne M2 Metro, Switzerland, 22 Feb. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Tunnels & Tunnelling (2005)

Page 133: Tunnel Failure

Lausanne M2 Metro, Switzerland, 22 Feb. 2005

• Background• Tunnel (6km long, approximately 10m wide x 7m high) for

Lausanne Metro M2 Project (cost US$472M) in Switzerland• Tunnelling using an Eickhoff ET 380-L roadheader

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Collapse in area of soft ground (lake deposits)• 50m3 of material displaced into the tunnel at a depth of 12m,

leading to a crater at the surface

• Possible cause of failure• Tunnel driven through a pocket in the glacial moraine, causing

sudden inflow of groundwater

Page 134: Tunnel Failure

• Consequences• People in two buildings, a supermarket and a food outlet in

commercial district evacuated when their cellars collapsed• No injuries reported

• Remedial measures• A curtain of 11 piles constructed ahead of the collapsed face with

Lausanne M2 Metro, Switzerland, 22 Feb. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• A curtain of 11 piles constructed ahead of the collapsed face with grouting to strengthen the ground and limit further flow of material into the tunnel

• The void was backfilled with 800m3 of glass-sand (recycled glass)

• Source• Tunnels & Tunnelling (2005)

Page 135: Tunnel Failure

Lane Cove Tunnel, Australia, 2 Nov. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 136: Tunnel Failure

Lane Cove Tunnel, Australia, 2 Nov. 2005

• Background• Twin NATM tunnels (7m high, 8.1 wide and 3.6km long)

constructed under Lane Cove Tunnel Project in Sydney

• The failure• Collapse occurred during breakout for a ventilation tunnel from

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Collapse occurred during breakout for a ventilation tunnel from the running tunnel

• A 10m by 10m, 25m deep crater formed in the ground between a 3-storey high residential building and a highway exit ramp

Page 137: Tunnel Failure

• Possible causes of failure• Possible “rock slippage”• Ground investigation did not identify dyke at the tunnel

intersection• Under designed rock bolts due to increased effective span at

intersection of adit and tunnel

Lane Cove Tunnel, Australia, 2 Nov. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Consequences• A 3-storey building partially collapsed and 47 residents

evacuated• A water main burst• Citybound road closed

Page 138: Tunnel Failure

• Remedial measures• The void was backfilled with

1,400m3 of concrete• Continual monitoring

• Sources

Lane Cove Tunnel, Australia, 2 Nov. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Sources• Golder (2005)• Ground Engineering (2005)• Ground Engineering (2006a)• Ground Engineering (2006b)• ICE (2006)• NNN (2005)• SMH (2005)

ICE (2006)

Page 139: Tunnel Failure

Kaohsiung Rapid Transit, Taiwan, 4 Dec. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

TT (2005)

Page 140: Tunnel Failure

Kaohsiung Rapid Transit, Taiwan, 4 Dec. 2005

• Background• Construction of Kaohsiung Rapid Transit (KRT) Orange Line at

the junction of Chungcheng Road and Tashun Road in Kaohsiung City

• The failure• Failure occurred during excavation of an underground sump pit at

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Failure occurred during excavation of an underground sump pit at a cross passage (33m below ground) underneath an existing reservoir

• A 30m by 20m, 4m deep trench initially formed on 4 Dec. 2005 and was collapsed to form a 50m by 30m, 10m deep crater at the road surface

• This was the 10th reported failure of the KRT project• Another crater (10m diameter, 7m deep) formed at another

location on 10 Dec. 2005

Page 141: Tunnel Failure

• Possible cause of failure• Massive water seepage from a reservoir

Kaohsiung Rapid Transit, Taiwan, 4 Dec. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 142: Tunnel Failure

• Consequences• Chungcheng Road (a major trunk road) closed for a week• The nearby Linkang railway line temporarily suspended• A 100m long section of tunnels and utilities damaged• Cracks found at 20 nearby residential buildings

Kaohsiung Rapid Transit, Taiwan, 4 Dec. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Remedial measures• The crater was backfilled with about 2,800m3 of soil/rock and

concrete 20 hours after the accident• The damaged sections of the KRT tunnels needed to be re-

constructed• Cost of the remedial measures estimated to be up to NT$500M

(US$15M) excluding reconstruction of the damaged sections of the KRT tunnels

Page 143: Tunnel Failure

• Sources• TVB News (2005)• TT (2005)• SP (2005)• ST (2005)• Sun (2005)• WWP (2005)

Kaohsiung Rapid Transit, Taiwan, 4 Dec. 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• WWP (2005)• OD (2005)• TKP (2005)• MP (2005)

TVB News (2005)

Page 144: Tunnel Failure

• Background• The tunnel works were completed in

1980. Two tunnels of 3m width forcrude water and potable watersupply were constructed inPrecambrian highly metamorphicgneisses

Nedre Romerike Water Treatment Plant, Crude

Water and Potable Water Tunnels, Norway, 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

gneisses• In some areas, the gneiss is highly

weathered and is partly transformedto clay

Karlsrud (2010)

Page 145: Tunnel Failure

• The failure• The failure was progressive for more than 25 years resulting in

blockage of the crude water tunnel• A major failure occurred in the crude water tunnel in winter 2005 and

the weathered rock failed• Two major progressive failures occurred in 2007 and about 200m3 and

30-40m3 rocks fell each time

Nedre Romerike Water Treatment Plant, Crude

Water and Potable Water Tunnels, Norway, 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

30-40m3 rocks fell each time

Section A-A

Karlsrud (2010)

Open joint which released a large block

Page 146: Tunnel Failure

• Possible cause of failure• Lack of mapping of weakness zones containing swelling clay

resulting in insufficient rock support

• The humidity in the water tunnel probably causing a gradualexpansion of the swelling clay which resulted in detachment of the

Nedre Romerike Water Treatment Plant, Crude

Water and Potable Water Tunnels, Norway, 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

expansion of the swelling clay which resulted in detachment of therock

• Consequences• About 150, 000 people affected by disruption in water supply

Page 147: Tunnel Failure

• Emergency and remedial measures

• Due to the limited access in the crude water tunnel, only manuallyreplacement and redistribution of the debris downstream from thecave-in areas could be carried out by divers when the water levelwas lowered

Lessons learnt

Nedre Romerike Water Treatment Plant, Crude

Water and Potable Water Tunnels, Norway, 2005

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Lessons learnt• The importance of proper rock mass classification, detailed

mapping of weakness zones and weathered rock, andimplementation of adequate rock support

• Source• Karlsrud (2010)

Page 148: Tunnel Failure

• Background• The tunnel was supported with a

combination of rock bolts and steelfiber reinforced concrete

• The failure• A section of tunnel caved in10-11

years after excavation

Hanekleiv Road Tunnel, Norway, 25 December

2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

years after excavation

• Possible cause of failure • Unfavourable geometry with joints

almost parallel to the tunnel axis.• The rock bolts installed mainly

parallel to the rock joints and with limited influence on the stability

Karlsrud (2010)

Page 149: Tunnel Failure

• Consequences• About 200m3 of debris fell down from the crown and the tunnel

was closed for about 6.5 months

• Emergency and remedial measures• Casting concrete lining and installing about 4,000 rock bolts

Hanekleiv Road Tunnel, Norway, 25 December

2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Lessons learnt• Lack of qualified engineering geologist at the site to carry out

mapping and design during the tunnel construction

• Source• Karlsrud (2010)

Page 150: Tunnel Failure

Stormwater Management and Road Tunnel

(SMART), Malaysia, 2003 - 2006

Limestone

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

SMART

Siow, M. T. (2006)

Page 151: Tunnel Failure

Stormwater Management and Road Tunnel

(SMART), Malaysia, 2003 - 2006

• Background• 9.7km long and 13.26m diameter tunnel driven through karst

formation by slurry shield TBM

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• 37 incidents within 8 km of tunnel excavation

• Possible cause of failure• Adverse geology and karst conditions

Page 152: Tunnel Failure

Stormwater Management and Road Tunnel

(SMART), Malaysia, 2003 - 2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Siow, M. T. (2006)

Page 153: Tunnel Failure

Stormwater Management and Road Tunnel

(SMART), Malaysia, 2003 - 2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

McFeat-Smith (2008)

Page 154: Tunnel Failure

• Source• Siow, M. T. (2006)• McFeat-Smith (2008)

Stormwater Management and Road Tunnel

(SMART), Malaysia, 2003 - 2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 155: Tunnel Failure

Sao Paulo Metro Station, Brazil,

15 Jan. 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Gulp (2007)

Page 156: Tunnel Failure

Sao Paulo Metro Station, Brazil,

15 Jan. 2007

• Background• New Austrian Tunnelling Method (NATM) was used to excavate a

18.5m diameter 45m long section station tunnel• The tunnel failure occurred close to a junction with a 40m

diameter, 40m deep access shaft

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• Collapse of the station tunnel and partial damage to the access

shaft• The rate of settlement at the tunnel crown increased rapidly and

reached 15mm to 20mm two to three days before the failure

Page 157: Tunnel Failure

• Possible cause of failure• Failed to account for the geology of the site; fractured rock

located over the excavation • The lack of sufficient supports in the roof and side walls of the

excavation

• Consequences

Sao Paulo Metro Station, Brazil,

15 Jan. 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Consequences• Several vehicles dropped into the 30m-deep hole• Seven persons killed

• Remedial measures• Stabilized the section of tunnel with extensive reinforcement• A system of anchors extending 32m into the soil was put in place

and the excavation through the section was performed after pre-grouting

Page 158: Tunnel Failure

• Source• ICE (2008)• Gulp (2007)

Sao Paulo Metro Station, Brazil,

15 Jan. 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 159: Tunnel Failure

Guangzhou Metro Line 5, China,

17 Jan. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Sina (2008a)

AD (2008)

Page 160: Tunnel Failure

Guangzhou Metro Line 5, China,

17 Jan. 2008

• Background• Construction of a cross passage between two tunnel boring

machine tunnels

• The failure• Collapse of the cross passage tunnel

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Collapse of the cross passage tunnel

• Possible cause of failure• Groundwater flowed into the tunnel

• Consequences• Cave-in at the road, about 100m2 on plan• No injury

Page 161: Tunnel Failure

• Remedial measures• Crater backfilled with concrete

• Source• AD (2008a)• Sina (2008a, 2008b)

Guangzhou Metro Line 5, China,

17 Jan. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Sina (2008a, 2008b)

Page 162: Tunnel Failure

Langstaff Road Trunk Sewer, Toronto, Canada

2 May 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Wallis, P (2009) Discharge through the screw conveyor of the EPBM

Page 163: Tunnel Failure

• Background• Tunnelling by EPBM for the construction of the sewer tunnel

• The failure• About 1,800 m3 of liquefied mud flowed into the tunnel over a 48-

hour period through the tail brushes causing the tunnel and the TBM to sink by more than 3m and collapse

Langstaff Road Trunk Sewer, Toronto, Canada

2 May 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

TBM to sink by more than 3m and collapse• A deep sinkhole formed at the ground surface

• Possible causes of failure • Damaged wire brushes of the tailseal of the EPBM were the

catalyst for initiating the whole sequence of the failure events • Highly saturated very fine sands and silts under 1.5 bars of

groundwater pressure

Page 164: Tunnel Failure

• Consequences• The road above the excavated area closed• Major delay to the project • The TBM was buried

• Emergency and remedial measures• Filling the sinkhole with unshrinkable fill (low strength concrete)

Langstaff Road Trunk Sewer, Toronto, Canada

2 May 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Filling the sinkhole with unshrinkable fill (low strength concrete)• Areas of continuing subsidence were stabilized with sand infill• Bulkhead was built about 300m behind the TBM to control the

infow• Water main repaired and road repaved

• Source• Wallis, P (2009)• Wallis, S (2008)

Page 165: Tunnel Failure

Circle Line 4 Tunnel, Singapore, 23 May 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Property Highlights of Singapore (2008)

Property Highlights of Singapore (2008)

Page 166: Tunnel Failure

Circle Line 4 Tunnel, Singapore, 23 May 2008

• Background• Construction of Circle Line 4

tunnel by 6m diameter slurry mixshield TBM

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• Cave-in at Holland Road

approximately 8m diameter x 3m deep

• Possible cause of failure• Loose ground

Property Highlights of Singapore (2008)

Page 167: Tunnel Failure

• Consequences• Temporary suspension of water supply

• Remedial measures• Crater backfilled with concrete

Circle Line 4 Tunnel, Singapore, 23 May 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Property Highlights of Singapore (2008)

Page 168: Tunnel Failure

Hangzhou Metro Tunnel, China, 15 Nov. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

AD (2008b)

Page 169: Tunnel Failure

Hangzhou Metro Tunnel, China, 15 Nov. 2008

• Background• Construction of Hangzhou Metro

• The Failure• Failure of a series of continuous walls of 800mm thick

constructed by cut-and-cover method forming a 21m wide x 16m deep excavated area

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

deep excavated area

• Consequences• A 75m long section of road collapsed and 11 vehicles fell into the

16m deep excavation• A 600mm diameter water main was broken • Water from the nearby river flowed into the collapsed area

Page 170: Tunnel Failure

Hangzhou Metro Tunnel, China, 15 Nov. 2008

• Consequences• Three 3-storey buildings seriously damaged and needed to be

demolished• Two 110kV cables were damaged • 8 persons died, 13 persons missing (as of 19 Nov. 2008) and 11

persons injured

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

persons injured

Page 171: Tunnel Failure

Hangzhou Metro Tunnel, China, 15 Nov. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region CNS (2008)

CNS (2008)

CNS (2008)

Page 172: Tunnel Failure

Hangzhou Metro Tunnel, China, 15 Nov. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

XINHUANET (2008)

XINHUANET (2008)

XINHUANET (2008)

Page 173: Tunnel Failure

Hangzhou Metro Tunnel, China, 15 Nov. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

XINHUANET (2008)

XINHUANET (2008)

Page 174: Tunnel Failure

• Source• AD (2008b)• Beijing Review (2008) • CNS (2008)• NCE (2008)

Hangzhou Metro Tunnel, China, 15 Nov. 2008

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• XINHUANET (2008)

Page 175: Tunnel Failure

Cologne North-South Metro Tram Line,

Germany, 3 March 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Wallis, S (2009)

Page 176: Tunnel Failure

• Background• Construction of a shaft using diaphragm walls

• The failure• Collapse of the diaphragm walls

• Possible causes of failure

Cologne North-South Metro Tram Line,

Germany, 3 March 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Possible causes of failure • ‘Boiling’ of the shaft’s invert under high pressures, loss of ground

due to inflow of groundwater, and creating a void outside the diaphragm walls into which the archive building collapsed

• Protective measures such as compensation grouting not carried out for protection of the buildings adjacent to the excavation

Page 177: Tunnel Failure

• Consequences• Collapse of the city’s historical archive building • Partial collapse of two apartment buildings• Evacuation of local residents (80 families in 10 buildings)• Two people killed

• Source

Cologne North-South Metro Tram Line,

Germany, 3 March 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Wallis, S (2009)

Wallis, S (2009)

Page 178: Tunnel Failure

Brightwater Tunnel, Seattle, U. S. A.,

8 March 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Wallis, P (2009a)

Page 179: Tunnel Failure

• Background• Tunnelling by Mixshield slurry TBM

• The Failure• 4.5m x 9m sinkhole formed at a driveway of a house

• Possible cause of failure • The inexperience TBM operator with the closed slurry system

Brightwater Tunnel, Seattle, U. S. A.,

8 March 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The inexperience TBM operator with the closed slurry system making it difficult to judge the amount of material being excavated during a shove

• The presence of a large boulder in the face that stalled penetration without slowing extraction of material and caused over excavation

• The high artesian water pressure and its influence on the excavation cycle

Page 180: Tunnel Failure

• Consequences• The driveway of a house damaged

• Emergency and remedial measures• Filling the sinkhole with crushed rock and sand

• Source

Brightwater Tunnel, Seattle, U. S. A.,

8 March 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Wallis, P (2009a)

Page 181: Tunnel Failure

Seattle’s Beacon Hill Light Rail, U. S. A.,

July 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Wallis, P (2009b)

Page 182: Tunnel Failure

• Background• Tunnelling by EPBM

• The failure• A 6.4m deep sinkhole formed at the ground surface• Six other large voids were found 6m to 18m below the ground

surface and behind the segmental lining of the bored TBM running tunnels

Seattle’s Beacon Hill Light Rail, U. S. A.,

July 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

tunnels

• Possible cause of failure • Over excavation when the EPBM hit pockets of sand in the stable

clay stratum

Page 183: Tunnel Failure

• Consequences• Sinkhole in the front yard of a house near its foundation

• Remedial measures• Filling the voids with 200 to 400 cubic yards of controlled density fill • Compaction grouting beneath the voids and the top of the running

Seattle’s Beacon Hill Light Rail, U. S. A.,

July 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Compaction grouting beneath the voids and the top of the running tunnels

• Source• Wallis, P (2009b)

Page 184: Tunnel Failure

Cairo Metro Tunnel, Egypt, 3 Sept. 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Wallis, S (2009a)

Page 185: Tunnel Failure

• Background• Tunnelling by 9.4m diameter Mixshield slurry TBM

• First failure• A segment fallen out of a ring subsequently forming a sinkhole on

the ground surface

• Second failure

Cairo Metro Tunnel, Egypt, 3 Sept. 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Second failure• Second ground collapse occurred after the pouring of concrete to

attempt to arrest the first collapse

• Possible cause of failure • First failure - a segment of the recently installed ring just leaving

the tail shield fell and allowed water and soil to flow to the tunnel, filling the interior of the TBM and the tunnel.

Page 186: Tunnel Failure

• Possible cause of failure • Second failure – More than 1,000 m3 of concrete was used to fill

the first sinkhole. The weight of the concrete acting on soft ground under a high groundwater table caused a second groundcollapse

Cairo Metro Tunnel, Egypt, 3 Sept. 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Consequences• TBM buried• A parked car slid into the 15m-20m diameter x 20m deep

sinkhole• Evacuation of local residents (80 families in 10 buildings)

Page 187: Tunnel Failure

• Remedial measures• First failure – Backfilled the sinkhole with concrete • Second failure – Injection of chemical grout, vertically and on

inclines, to strengthen the soil around the TBM and the tunnel to support the recovery excavation to uncover the TBM

• Source

Cairo Metro Tunnel, Egypt, 3 Sept. 2009

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Wallis, S (2009a)

Page 188: Tunnel Failure

Shenzhen Express Rail Link, China, 27 March

2011, 4 May 2011 and 10 May 2011

• Background• Tunnelling by TBM at about

22m to 26m below ground • Several ground failures

occurred in Xiameilin, Futian District (福田區上梅林)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

OD (2011)

Page 189: Tunnel Failure

Shenzhen Express Rail Link, China, 27

March 2011, 4 May 2011 and 10 May 2011• First failure (World Journal (2011))

• A sinkhole of about 7m diameter and 10m deep was formed at a football pitch on 27 March 2011

• The sinkhole was full of muddy water and air bubbles

• Consequence• Evacuation of nearby residents

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Evacuation of nearby residents

• Possible cause of failure• Unexpected change in sub-surface

materials encountered, from slight decomposed rock to completely decomposed rock

• Remedial Measures• Backfill of the sinkhole with concrete

World Journal (2011)

Page 190: Tunnel Failure

Shenzhen Express Rail Link, China, 27 March

2011, 4 May 2011 and 10 May 2011

• Second failure (21CN (2011))• A sinkhole of about 10m in diameter was formed near the

location of the first failure on 4 May 2011

• Possible cause of failure

• Heavy rainfall and the ground at the location of the previous failure had not been fully stabilized

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Third failure (TKP (2011))• A sinkhole of about 7m deep was formed at the ground surface

during the changing of cutter discs on 10 May 2011

• Possible cause of failure• Loose fill layers with high water infiltration • Existence of a sub-layer drainage channel

Page 191: Tunnel Failure

Shenzhen Express Rail Link, China, 27 March

2011, 4 May 2011 and 10 May 2011• Fourth failure ((SD(2011))

• A sinkhole of about 1.5m in diameter and 7m deep formed atfootball pitch where previous three ground collapses occurredon 18 May 2011

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

SD (2011)

Page 192: Tunnel Failure

Shenzhen Express Rail Link, China, 27 March

2011, 4 May 2011 and 10 May 2011

• Fifth failure (21CN (2011))• A sinkhole of about 5m deep in plan area of 100m2 was formed

on a road on 30 October 2011

• Possible causes of failure

• Existence of soft and hard lens of soil above the tunnel

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Existence of soft and hard lens of soil above the tunnel

• Leakage of compressed air

• Remedial Measures• Backfill of the sinkhole with soil

Page 193: Tunnel Failure

Shenzhen Express Rail Link, China, 27 March

2011, 4 May 2011 and 10 May 2011

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

2home (2011)

Page 194: Tunnel Failure

Shenzhen Express Rail Link, China, 27 March

2011, 4 May 2011 and 10 May 2011

• Source• 2home (2011)• 21CN (2011)• OD (2011)• SD (2011)• TKP (2011)

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• TKP (2011)• World Journal (2011)

Page 195: Tunnel Failure

Hengqin Tunnel, Macau, 19 July 2012

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

MD (2012)

Page 196: Tunnel Failure

• Background• Four-lane 1.57km long road tunnel constructed by the cut-and-

cover method

• Failure• The lateral support wall collapsed resulting in caving of the

Hengqin Tunnel, Macau, 19 July 2012

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The lateral support wall collapsed resulting in caving of the surrounding ground surface

• Possible cause of failure • Existence of a weak geological structure in the sub-surface • Rising of groundwater levels due to heavy rainfall causing the weak

soil between the interlayer to slip • Failure of the construction of support structures to keep pace with

the excavation

Page 197: Tunnel Failure

• Possible cause of failure • Weak ground with high groundwater levels increasing pressure

acting on the foundation pit pile

• Consequences

Hengqin Tunnel, Macau, 19 July 2012

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Five heavy machines buried• Programme delayed

Page 198: Tunnel Failure

• Source• MD (2012)• MDT (2012) • OD (2012)

Hengqin Tunnel, Macau, 19 July 2012

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 199: Tunnel Failure

Hong Kong Cases

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Hong Kong Cases

Page 200: Tunnel Failure

MTR Modified Initial System, Prince Edward

Station, Nathan Road, 12 Sept. 1977

• Background• A running tunnel (5m in diameter) being constructed from Prince

Edward Station by the drill and blast method• Ground above the tunnel strengthened

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• A wall section of the running tunnel under Nathan Road

collapsed• The subsidence did not affect the road surface

Page 201: Tunnel Failure

• Possible causes of failure• Gap existed between the ground treatment above the station

tunnel and that above the running tunnel allowing the soil to flow into the tunnel

MTR Modified Initial System, Prince Edward

Station, Nathan Road, 12 Sept. 1977

Nathan RoadWater table

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Station Tunnel RunningTunnel

Annular GroundTreatment

Annular GroundTreatment

after Clay & Takas (1997)

Page 202: Tunnel Failure

• Consequences• Nathan Road between Argyle Street and Arran Street closed as

a safety measure• Three buildings (Nos. 745, 745A and 745B Nathan Road)

involving 100 people evacuated• Closure Order issued for nearby shops and a petrol station

MTR Modified Initial System, Prince Edward

Station, Nathan Road, 12 Sept. 1977

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Source• Clay & Takacs (1997)• SCMP (1977)

Page 203: Tunnel Failure

MTR Island Line, 22 Hennessy Road, 1 Jan. 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 204: Tunnel Failure

MTR Island Line, 22 Hennessy Road, 1 Jan. 1983

• Background • Tunnelling from Admiralty to Causeway Bay for MTR Island Line

using the drill and blast method• Tunnel formed by the drill and blast method

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• Water-bearing fill flowed into the tunnel, opening a hole at the

road above• 1,500m3 of material flowed into the tunnel creating a void of an

area of 100m2 and 30m deep beneath the road surface

Page 205: Tunnel Failure

• Possible cause of failure• Misinterpretation of the geology by the Contractor• Blasting went too far, resulting in the tunnel penetrating the

rock into soft ground

MTR Island Line, 22 Hennessy Road, 1 Jan. 1983

Hennessy RoadWater

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Soft Ground

after Clay & Takas (1997)

Shield Chamber

Rock

Water table

Page 206: Tunnel Failure

• Consequences• Cracks found in the granite masonry of the outside wall of a

building at 22 Hennessy Road• At least 21 timber piles beneath an adjacent building of 22

Hennessy Road exposed• More than 150 people in 18-22 Hennessy Road evacuated

MTR Island Line, 22 Hennessy Road, 1 Jan. 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• More than 150 people in 18-22 Hennessy Road evacuated• The building at 18-20 Hennessy Road reopened 3 hours after

the incident and the building at 22 Hennessy Road 6 days later

Page 207: Tunnel Failure

• Remedial measures• The void was backfilled by grout• The floor slab of the building at 22

Hennessy Road pushed up by the grouting works by 50-75mm

MTR Island Line, 22 Hennessy Road, 1 Jan. 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Sources• Clay & Takacs (1997)• SCMP (1983)

SCMP (1983)

Page 208: Tunnel Failure

MTR Island Line, Shing On Street,

Shau Kei Wan, 23 July 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

MP (1983a)

Page 209: Tunnel Failure

MTR Island Line, Shing On Street,

Shau Kei Wan, 23 July 1983

• Background • Tunnelling from Tai Koo Station to Sai Wan Ho Station for

MTR Island Line

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• 13m x 1m void formed

Page 210: Tunnel Failure

• Consequences• Section of Shau Kei Wan Road closed• Building at 122-124 Shau Kei Wan Road settled more than

100mm and tilting observed• More than 80 families (400 people) evacuated & a woman injured• Water main damaged due to the settlement

MTR Island Line, Shing On Street,

Shau Kei Wan, 23 July 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Water main damaged due to the settlement• Water and gas supplies stopped

• Source• MP (1983a)

Page 211: Tunnel Failure

MTR Island Line, 140-168 Shau Kei Wan Road

16 Dec. 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

MP (1983a)

Page 212: Tunnel Failure

MTR Island Line, 140-168 Shau Kei Wan Road

16 Dec. 1983

• Background• Construction of Sai Wan Ho Station for MTR Island Line

• The failure• More than 40mm of ground settlement• About 150m3 of soil flowed into the tunnel leaving a void

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• About 150m3 of soil flowed into the tunnel leaving a void between Shau Kei Wan Road and the tunnel

Page 213: Tunnel Failure

• Consequences• Section of Shau Kei Wan Road closed• Water supply stopped

• Source• MP (1983b)

MTR Island Line, 140-168 Shau Kei Wan Road

16 Dec. 1983

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• MP (1983b)

Page 214: Tunnel Failure

Kowloon Southern Link Contract KDB 200,

Canton Road, 21 Oct. 2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

GEO File Information

Page 215: Tunnel Failure

Kowloon Southern Link Contract KDB 200,

Canton Road, 21 Oct. 2006

• Background• Twin railway tunnels between Jordan Road and East Tsim Sha

Tsui Station constructed by a slurry TBM• Incident of ground loss occurred at TBM launch area

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• 3m(W) x 3.5m(L) x 3m(D) sinkhole formed reaching the ground

surface

• Possible cause of failure• Slurry leakage and loss of slurry support pressure

Page 216: Tunnel Failure

• Consequences • Crater formed at the ground surface closed to a busy road and a

gas main

• Remedial measures

Kowloon Southern Link Contract KDB 200,

Canton Road, 21 Oct. 2006

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Remedial measures• Backfilling of the sinkhole with stockpile materials and sub-base

materials

• Source• GEO File Information

Page 217: Tunnel Failure

Kowloon Southern Link Contract KDB 200,

Salisbury Road, 3 June 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 218: Tunnel Failure

Kowloon Southern Link Contract KDB 200,

Salisbury Road, 3 June 2007

• Background• Twin railway tunnels between Jordan Road and East Tsim Sha

Tsui Station constructed by a slurry TBM

• The failure

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• The failure• 2m x 3m sinkhole reaching the ground surface

• Possible cause of failure• Sudden air pressure loss through the interface between

CDG/HDG and overlying marine sand during a compressed air intervention, resulting in loss of face support and subsequent formation of sinkhole

Page 219: Tunnel Failure

• Consequences• Crater formed at the ground surface, with associated settlement• Temporary closure of a busy road lane• A low pressure gas main and a 1200 mm stormwater drain were

affected

Kowloon Southern Link Contract KDB 200,

Salisbury Road, 3 June 2007

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

• Remedial measures• Backfilling of sinkhole with granular fill

• Source• GEO File Information

Page 220: Tunnel Failure

References

2home (2011). <www.2home.com.cn/article/article_4190.html> (31 October 2011).

21cn (2011). <http://house.21cn.com/collect/2011/10/31/9615710.shtml> (31 October 2011).

AD (2008a). 珠江橋口塌半邊馬路. Apple Daily Newspaper. 19 January 2008, Hong Kong, pp A22.

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

AD (2008b). 杭州地鐵地盤塌陷增至2死19傷<http://www.appleactionews.com/site/art_main.php?&iss_id=20081116&sec_id=10793096&art_id=11853290&dis_type=ss&media_id=1>.

Beijing Review website (2008). Death Toll Could Reach 21 in Tunnel Collapse. <http://www.bjreview.com.cn/headline/txt/2008-11/19/content_165283.htm> (19 Nov 2008).

Page 221: Tunnel Failure

References

Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner, H., Schmid, G., & Wannick, H. (2004). Underground Transportation Systems, Chances and Risks from the Re-insurer’s Point of View.Munich Re Group, Germany, pp 58-62. <http://www.munichre.com/> (31 Jan. 2007).

China Daily (2004). 100 homeless after metro site collapse. <http://www.chinadaily.com.cn/english/doc/2004-04/02/content_320246.htm> (2 April 2004).

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

04/02/content_320246.htm> (2 April 2004).

Civil Engineer International (1995). Tunnel lining removal prompts LA Metro cave in. Institution of Civil Engineers, July Issue, p10.

CNS (2008). <http://www.chinanews.com/>.

Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected – Flood, fire overbreak, inrush, collapse. Proceedings of the International Conference on Tunnelling Under Difficult Ground and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

Page 222: Tunnel Failure

Construction Today (1994a). Police probe repeat Munich tunnel breach. Construction Today, October Issue, pp 4-5.

Construction Today (1994b). Unstable ground triggers Munich tunnel collapse. Construction Today, October Issue, p 5.

Dubois, P. & Rat, M. (2003). Effondrement sur le chantier "Météor“. Conseil Général des Ponts et Chaussées, France, 22p. <http://www2.equipement.gouv.fr/actualites/Rapports/Meteor.pdf>

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

<http://www2.equipement.gouv.fr/actualites/Rapports/Meteor.pdf> (31 Jan. 2007).

European Foundations (2005). Tighter NATM rules follow Barcelona failure. European Foundations, Spring Issue, No. 26, p 3.

GEO File Information. GEO File Reference: GCME 3/5/7989/05, KSL Southern Link – C/No. KDB200, West Kln Station & Ancillary Bldg & Tunnel.

Page 223: Tunnel Failure

Golder (2005). Causes of Subsidence, 2 November 2005, Lane Cove Tunnel Project. Sydney NSW, 52p.

Government of Singapore (2005). Report of the Committee of Inquiry into the Incident at the MRT Circle Line Worksite That Led to the Collapse of Nicoll Highway on 20 April 2004. Government of Singapore, Land Transport Authority. <http://www.lta.gov.sg/home/index_home_nicoll.htm> (31 Jan.

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

<http://www.lta.gov.sg/home/index_home_nicoll.htm> (31 Jan. 2007).

Ground Engineering (1994). London NATM controversy. Ground Engineering, November Issue, p 6.

Ground Engineering (2000). Catalogue of disaster. Ground Engineering, August Issue, pp 10-11.

Ground Engineering (2005). Australian tunnel collapse raises doubts over NATM. Ground Engineering, December Issue, p 6.

Page 224: Tunnel Failure

Ground Engineering (2006a). Sydney tunnel collapse triggered by under-designed rock bolts. Ground Engineering, February Issue, p 4.

Ground Engineering (2006b). Rock bolts used instead of steel girders may have contributed to Lane Cove collapse. Ground Engineering, May Issue, p 4.

Gulp (2007). Desenvolvimento e diversão. <http://gulp.com.br/imagem/acidente-no-metro-de-sao-paulo> (17

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

<http://gulp.com.br/imagem/acidente-no-metro-de-sao-paulo> (17 January 2007).

HSE (1996). Safety of New Austrian Tunnelling Method (NATM) Tunnels. Health & Safety Executive, UK, 86p.

HSE (2000). The Collapse of NATM Tunnels at Heathrow Airport. Health & Safety Executive, UK, 116p.

ICE (1998a). Bulkhead location blamed for DLR blast. New Civil Engineer, Institution of Civil Engineers, February Issue, pp 3-4.

Page 225: Tunnel Failure

ICE (1998b). HSE signs up QC Carlisle for HEX prosecution. New Civil Engineer, Institution of Civil Engineers, March Issue, pp 4-5.

ICE (1999). Heathrow Express court cases kicks off. New Civil Engineer, Institution of Civil Engineers, January Issue, p 6.

ICE (2003). Ground failure linked to well collapses. New Civil Engineer, Institution of Civil Engineers, February Issue, pp 6-7.

ICE (2004). Docklands tunnel blowout down to “elementary error”, says

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

judge. New Civil Engineer, Institution of Civil Engineers, January Issue, pp 8-9.

ICE (2006). Australian tunnel collapse raises new NATM doubts. New Civil Engineer, Institution of Civil Engineers, January Issue, pp 6-7.

ICE (2008). Heart of darkness, New Civil Engineer, Institution of Civil Engineers, September Issue, pp 14-15.

IMIA. <http://www.imia.com>.

Page 226: Tunnel Failure

IMS. <http://www.imstunnel.com/index2.htm>.

Karlsrud Kjell (2010). Technical Note : Experience with tunnel failures in Norwegian tunnels. The Government of the Hong Kong Civil Engineering and Development Department. (Unpublished).

Kavvadas, M., Hewison, L.R., Laskaratos, P.G., Seferoglou, C. & Michalis, I. (1996). Experiences from the construction of the Athens Metro. Proceedings of International Symposium on the

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Metro. Proceedings of International Symposium on the Geotechnical Aspects of Underground Construction in Soft Ground, City University, London, April.

Lee, I. M. & Cho, G. C. (2008). Underground construction in decomposed residual soils (presentation slides). The 6th

International Symposium on Geotechnical Aspects of Underground Construction in Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.

Page 227: Tunnel Failure

Lee, W. F. & Ishihara, K. (2011) Forensic diagnosis of a shield tunnel failure. Engineering Structures. Volume 32, Issue 7, July 2010, Pages 1830-1837.

Longhoo (2004). 廣州地鐵3號線工地塌方﹐附近居民樓傾斜.<http://www.longhoo.net/big5/longhoo/news/civil/node107/userobject1ai172577.html> (2 April 2004).

Madrid (1996). Informe sobre el NATM del Health & Safety Executive,

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. <http://www.madrid.org/metro/infonatm.html> (1996).

McFeat-Smith, I. M. (2008). Personal communications. GEO File Reference: GCME 6/8/6-1, Newspaper Articles for Tunnels/Media Reports.

MD (2012). 橫琴澳大塌河隧. Macao Daily, 21 July 2012, Macau.

Page 228: Tunnel Failure

MDT (2012). Report : four causes account for Hengqin tunnel collapsed. Macau Daily Times. 14 August, 2012.

Mihalis, I. & Kavvadas, M. (1999). Ground movements caused by TBM tunnelling in the Athens Metro Project. Proceedings of International Symposium on the Geotechnical Aspects of Underground Construction in Soft Ground, Japan, July, pp 229-234.

MP (1983a). 筲箕灣路陷傳真. Ming Pao Newspaper. 24 July 1983,

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

MP (1983a). 筲箕灣路陷傳真. Ming Pao Newspaper. 24 July 1983, Hong Kong.

MP (1983b). 西灣河站塌泥墜道情況已穩定. Ming Pao Newspaper. 17 Dec. 1983, Hong Kong.

NNN (2005). National Nine News. 2 Nov. 2005, Australia.

OD (2011). 深圳屋苑地陷居民逃命. Oriental Daily, 29 March, 2011, Hong Kong.

Page 229: Tunnel Failure

OD (2005). 高捷洞陷. Oriental Daily. 7 Dec. 2005, Hong Kong.

OD (2012). 橫琴澳大新校區隧道坍塌. Oriental Daily, 21 July, 2012, Hong Kong.

Property Highlights of Singapore (2008). <http://propertyhighlights.blogspot.com/2008/05/circle-line-work-causes-cave-in-off.html> (25 May 2008).

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

SCMP (1977). MTR tunnel collapses. South China Morning Post. 13 Sept. 1977, Hong Kong.

SCMP (1983). MTR tunnelling may be to blame. South China Morning Post. 2 Jan. 1983, Hong Kong.

SD (2011). Fourth land collapse in Xiameilin. Shenzhen Daily, 20 May 2011, Shenzhen.

Page 230: Tunnel Failure

Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5. Tunnel and Underground Space Techonology, Issue no. 21, pp 296-297.

Sina (2008a). <http://news.sina.com/ch/phoenixtv/102-101-101-102/2008-01-17/15232606535.html> (17 Jan 2008).

Sina (2008b). <http://news.sina.com.hk/cgi-

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Sina (2008b). <http://news.sina.com.hk/cgi-bin/nw/show.cgi/9/1/1/613096/> (18 Jan 2008).

Siow, M. T. (2006). Geotechnical aspects of the SMART tunnel. International Conference and Exhibition on Trenchless Technology and Tunnelling, 7-9 March 2006, Malaysia.

SMH (2005). The Sydney Morning Herald. 2 Nov. 2005, Australia.

Soufun (2004).追踪报道::::广州地铁3333号线工地塌方险情受控. <http://news.gz.soufun.com/2004-04-04/259585.htm> (4 April 2004).

Page 231: Tunnel Failure

SP (2005). Sing Pao Newspaper. 6 Dec. 2005, Hong Kong.

ST (2005). Sing Tao Newspaper. 6 Dec. 2005, Hong Kong.

Sun (2005). Sun Newspaper. 6 Dec. 2005, Hong Kong.

TANEEB (2005). Hsuehshan Tunnel. Taiwan Area National Expressway Engineering Bureau (台灣國工局), Taiwan. <http://egip.taneeb.gov.tw> (31 Jan. 2007).

Taiwan Info (2004). Nouvel incident sur le chantier du métro de

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Taiwan Info (2004). Nouvel incident sur le chantier du métro de Kaohsiung. Taiwan. <http://taiwaninfo.nat.gov.tw/Societe/1092119498.html> (31 Jan. 2007).

Takahashi, Hiroshi (2010). Huge collapse leading to ground surface caving in 130m earth thickness.

TT (2005). Cave-in at KRTC site snarls up Kaohsiung traffic. Taipei Times. 5 Dec. 2005, Taiwan.

Page 232: Tunnel Failure

TKP (2005). Ta Kung Pao Newspaper. 7 Dec. 2005, Hong Kong.

TKP (2011). 深圳一小區三次地陷 居民撤離. Ta Kung Pao Newspaper, 11 May 2011, Shenzhen .

TVB News (2005). TVB News. 4 Dec. 2005, Taiwan.

Tunnels & Tunnelling (2005). Lausanne Metro Tunnel collapse. Tunnels & Tunnelling International, April Issue, p 6.

References

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Tunnels & Tunnelling International, April Issue, p 6.

Wallis, P. (2009). EPBM recovery reveals the unexpected. TunnelTalk. <http://www.tunneltalk.com/YorkSewer-Aug-09-TBM-recovery-reveals-the-unexpected.php> (August 2009).

Wallis, P. (2009a). Sinkhole bothers Brightwater. TunnelTalk. <http://www.tunneltalk.com/Brightwater-Mar09-Brightwater-sinkhole.php> (March 2009).

Page 233: Tunnel Failure

References

Wallis, P. (2009b). Beacon Hill celebration and investigation. TunnelTalk.<http://www.tunneltalk.com/BeaconHill-Jul09-Celebration-and-Investigation.php> (July 2009).

Wallis, S. (2008). Buried EPBM recovery in Toronto. TunnelTalk<http://www.tunneltalk.com/Buried-EPBM-recovery-in-Toronto.php>(August 2008).

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Wallis, S. (2009). Köln - speculation and anger in aftermath. TunnelTalk.<http://tunneltalk.com/Cologne-collapse-Mar09-Deadly-collapse-in-Cologne.php> (March 2009).

Wallis, S. (2009a). Cairo Metro tunnel collapse. TunnelTalk. http://www.tunneltalk.com/Cairo-Metro-Sep09-tunnel-collapse.php>(September 2009).

Page 234: Tunnel Failure

References

World Journal (2011). 高鐵惹禍? 深圳地陷 驚現10米深坑<http://www.worldjournal.com/view/full_news/12536326/article-

%E9%AB%98%E9%90%B5%E6%83%B9%E7%A6%8D%EF%BC%9F-%E6%B7%B1%E5%9C%B3%E5%9C%B0%E9%99%B7-%E9%A9%9A%E7%8F%BE10%E7%B1%B3%E6%B7%B1%E5%9D%91?instance=news_pics> (29 March 2011).

WWP (2005). Wen Wei Po Newspaper. 6 Dec. 2005, Hong Kong.

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

XINHUANET. <http://www.xinhuanet.com/> (4 April 2004).

Page 235: Tunnel Failure

General References

Brand, E.W. (1996c). Bibliography on Settlements Caused by Tunnelling to March 1996 (GEO Report No. 51). Geotechnical Engineering Office, Hong Kong, 70 p.

Health and Safety Executive (HSE) 1996. Safety of New Austrian Tunnelling Method (NATM) Tunnels, A review of sprayed concrete tunnels with particular reference to London Clay, (HSE) Books, Sudbury, 80 p.

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Sudbury, 80 p.

Jacobs J. D. (1975). Some tunnel failures and what they have taught. Hazards in Tunnelling and on Falsework, Institution of Civil Engineers, London, pp 37-46.

Moh, Z.C. & Hwang, R.N. (2007). Lessons learned from recent MRT construction failures in Asia Pacific. Journal of the Southeast Asian Geotechnical Society, December 2009, pp 121-137.

cases already included in the catalogue?

Page 236: Tunnel Failure

General References

Seidenfub, T. (2006). Masters Degree in Foundation Engineering and Tunnelling: Collapse in Tunnelling. Stuttgart University of Applied Sciences, Germany, 194 p. (Note: 109 numbers of failures of all types of tunnels). <http://www.ita-aites.org/cms/fileadmin/filemounts/general/pdf/ItaAssociation/ProductAndPublication/Thesis/ThesisSeidenfuss.pdf>some the failure cases already included in the catalogue?

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Page 237: Tunnel Failure

End

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

Civil Engineering and Development Department

The Government of the Hong Kong Special Administrative Region

End