• Jan03 Session #22– Complete TRD, Selection Criteria Doc, and Downselect Procedure Doc

• Mar03 Session #23– Proposals should be heard, criteria doc amended as needed

• May03 Session #24– Second round of proposals heard – We should spend part of this session discussing proposals presented, answering technical

questions/concerns (i.e. put the diehard engineers in a room and let them verbally duke it out).

– Spend time on conference calls discussing proposals to let everyone get comfortable (before and after this session).

– Criteria doc amended as needed

• Jul03 Session #25– Final round of presentations. Voting must occur here --start drafting process.

• Sep03 Session #26– proposals for draft improvements should be entertained at this time (i.e. now that we know

the realm of the game, let the games begin)

• Nov03 Session #27– complete drafting process…seek approval to go to WG Letter Ballot

Page 2: TG3a Project Timeline

January 2003

Robert F. Heile, AppairentSlide 2

doc.: IEEE 802.15-03/056r0

Submission

TG3a Timeline

2003

J J A S O N D J F M A M J J DJ F M A M A S O N

Downselect

2002

CFA

D

PAR