CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement

L.I.CL.I.CL.I.CL.I.C

Planning Departement

Package No. : D0469

Planned Progress % Actual Progress % Variance % Ahead/Behind

Concrete 97% 95.03% -2.24% Behind

Residential Tower N4 100.00% 99.02% -1% Behind

Residential Tower N3 100.00% 98.94% -1% Behind

Residential Tower N2 100.00% 98.91% -1% Behind

Residential Tower N1 100% 98.90% -1% Behind

Residential Tower S3 100.00% 97.77% -2% Behind

Residential Tower S2 100% 98.91% -1% Behind

Residential Tower S1 100.00% 97.82% -2% Behind

Hotel Tower H1 100% 99.10% -1% Behind

Hotel Tower H2 100.00% 98.66% -1% Behind

Parking 89.13% 84.45% -5% Behind

Club House 100% 80% -20% Behind

Swimming Pool 8.33% 0% -8% Behind

Planned Progress % Actual Progress % Variance % Ahead/Behind

Concrete 97% 95.03% -2.24% Behind

Residentials 100% 98.61% -1% Behind

Hotel 100% 98.92% -1% Behind

Parking 89.13% 84.45% -5% Behind

Club House 100% 80% -20% Behind

Swimming Pool 8.33% 0% -8% Behind

Type Of WorkCurrent Month (Up to 26January2008)

Data Date :

26January 08 Progress Of Concrete Works

Anantara Palm Jumeirah and Tiara Residences

Type Of WorkCurrent Month (Up to 26January2008)