CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement
L.I.CL.I.CL.I.CL.I.C
Planning Departement
Package No. : D0469
Planned Progress % Actual Progress % Variance % Ahead/Behind
Concrete 97% 95.03% -2.24% Behind
Residential Tower N4 100.00% 99.02% -1% Behind
Residential Tower N3 100.00% 98.94% -1% Behind
Residential Tower N2 100.00% 98.91% -1% Behind
Residential Tower N1 100% 98.90% -1% Behind
Residential Tower S3 100.00% 97.77% -2% Behind
Residential Tower S2 100% 98.91% -1% Behind
Residential Tower S1 100.00% 97.82% -2% Behind
Hotel Tower H1 100% 99.10% -1% Behind
Hotel Tower H2 100.00% 98.66% -1% Behind
Parking 89.13% 84.45% -5% Behind
Club House 100% 80% -20% Behind
Swimming Pool 8.33% 0% -8% Behind
Planned Progress % Actual Progress % Variance % Ahead/Behind
Concrete 97% 95.03% -2.24% Behind
Residentials 100% 98.61% -1% Behind
Hotel 100% 98.92% -1% Behind
Parking 89.13% 84.45% -5% Behind
Club House 100% 80% -20% Behind
Swimming Pool 8.33% 0% -8% Behind
Type Of WorkCurrent Month (Up to 26January2008)
Data Date :
26January 08 Progress Of Concrete Works
Anantara Palm Jumeirah and Tiara Residences
Type Of WorkCurrent Month (Up to 26January2008)