Download - Progress Of Elevators Per Floors

Transcript
Page 1: Progress Of Elevators Per Floors

CLIENT: Zabeel Investement L.I.C

Planning Departement

Package No. : D0469

Early Planned Start Early Planned Finish

Tower N4

Elevators Installation 19-Aug-07 15-Mar-08 76% 11% Behind

Tower N3

Elevators Installation 17-Sep-07 14-Apr-08 62% 11% Behind

Tower N2

Elevators Installation 25-Sep-07 21-Apr-08 58% 11% Behind

Tower N1

Elevators Installation 13-Oct-07 05-Apr-08 60% 11% Behind

Tower S1

Elevators Installation 25-Aug-07 14-Feb-08 88% 11% Behind

Tower S2

Elevators Installation 18-Sep-07 11-Mar-08 74% 11% Behind

Tower S3

Elevators Installation 11-Aug-07 06-Mar-08 80% 11% Behind

Hotel H1

Elevators Installation 21-Aug-07 18-Mar-08 75% 0% Behind

Hotel H2

Elevators Installation 28-Aug-07 25-Mar-08 72% 0% Behind

Month : 26January 2008

Early Planned Progress Of Elevators

WorksActual Progress Of Elevators Works

Elevators Performance

Progress Status

Anantara Palm Jumeirah and Tiara Residences

Progress Of Elevators Works

Early Planned Dates Of Elevators Works