• A leading, Bulgarian based, private company
• Engineering, Procurement, Construction and Project Management company
• Founded in 1999 by team of leading engineers experienced in the field of hydrometallurgy and especially in Uranium recovery
• Primarily focused on the mining resources and recycling sectors
• Directed especially to base and precious metals
Consultation, Process Engineering, Design, Procurement, Construction and Management of Projects
Leaching, Ion Exchange, Solvent Extraction and Electrowinning Plants
Hydrometallurgical Treatment of Waste Materials from Mining Industry and Metallurgy
Reclamation of Contaminated Grounds and Waters
Engineering Services in the Mining, Metallurgy and Chemical industries
Copper recovery by Ion exchange, solvent extraction and electrowinning
(Combined L/IX/SX/EW process )
Excellent, without any preconditioning, for processing of:
Pregnant leach solutions (PLS) even with low quality Decommissioning of spent copper heaps and
dumps. Acid mine drainage /AMD/. Other industrial streams. Environmentally friendly technology approach
Copper Cathodes Production via Leaching/IonExchange/Solvent Extraction and Electrowinning
Location – Bulgaria, Old copper oxidized dump Capacity - 1000 t/y copper cathodes LME Grade A Services Completed -Scoping Study, Pre-
Feasibility Study, Feasibility Study, Metallurgical Testwork, Detailed Engineering, Equipment Supply, Construction, Commissioning, Start up , Plant operating and maintenance personnel training, Management.
Developped for copper containing industrial wastes treatment.
Copper recovery from Acid Mine Drainage Location-Bulgaria, Reclaimed East Dump-Assarel
mine Producing PLS with 15 gpl copper Capacity -220 t/y by copper Planned extention for capacity up to 1800 t/y by
copper Used IONTIX unit technology. Services Completed -Testwork,Detailed engineering,
Equipment Supply, Construction, Commissioning, Start up , Plant operating and maintenance personnel training
Fulfilled “under key”
Copper recovery from old copper dump and new oxide copper heap
Copper Cathodes Production via Leaching, Ion Exchange, Solvent Extraction and Electrowinning
Location-Republic of Macedonia, Bucim copper mine
Project Capacity - 2400 t/y copper cathodes LME Grade A
Services-Metallurgical Testwork, Detailed engineering, Equipment Supply, Construction, Commissioning, Start up , Plant operating and maintenance personnel training
Fulfilled “under key”
Aktogai Copper Project Copper Cathodes Production via Leaching/Ion
Exchange/Solvent Extraction and Electrowinning Location-Kazakhstan, Aktogai Copper Project Capacity - 10000 t/y coper cathodes LME grade A Services Completed- Scoping Study, Pre-Feasibility Study,
Feasibility Study, Metallurgical Testwork, Bacsik Engineering
Kounrad Old Dumps Project Copper Cathodes Production via Leaching/Ion
Exchange/Solvent Extraction and Electrowinning Location-Kazakhstan, Kounrad copper open pit mine Capacity -5000 t/y copper cathodes LME Grade A Services Completed-Scoping Study,Pre-Feasibility Study,
Feasibility Study, Metallurgical Testwork, Basik Engineering
Assarel L/IX/SX/EW Copper Project Copper Cathodes Production via Leaching/Ion
Exchange/Solvent Extraction and Electrowinning Location-Bulgaria, Assarel open pit copper mine
West dump Capacity -2000 t/y copper cathodes LME Grade A Services Completed - Scoping Study, Pre-
Feasibility Study, Feasibility Study, Metallurgical Testwork
Feasibility Study - “Hydrometallurgical treatment of flotation tailings from oxide ore, Zhezkazgan”, Kazakhstan
Test work , Technical regulation, Design and Technical Solutions ”Hydrometallurgical treatment of Sulfide ores from Zhezkazgan mine”, Kazakhstan
Location- in the industrial area of town of Devnya, adjacent to the Varna – Sofia railway line.
Bordered on three sides by “Agropolychim” JSC
Site area - 8686,17 m2
Scheduled for operation in the end of 2014
Plant for treatment of hazardous wastes Devnya
Developed by IONTECH Hydrometallurgical technology for leaching,
ionexchange and electrolytic processes, can be used for reducing the amount of metal wastes
The metals of interest are copper (Cu), zinc (Zn) and lead (Pb).
Further development for Ni, Au and Ag
Patents BG 63734 B1 – Method for reclamation of multi-lift heaps and dumps BG 63733 B1 – Method for underground leaching of formation of
polymetalic impermeable ore layers with horizontal and inclined occurrence, separated by barren or slightly mineralized zones
BG 65932 B1 – Method for selective copper recovery from copper-containing waters and solutions for high grade cathode copper production
BG 1242 U1 – Installation for processing and recycling of industrial wastes from non-ferrous metallurgy, containing mainly copper, zinc, lead, nickel and precious metals
Patent Applications Rеg.№109782/21.12.2006 – Method and installation for selective
extraction of metal cations from weakly acidic to weakly basic solutions
Rеg.№ 110301/ 5.01.2009 -Method for selective copper and zinc recovery from process solutions for production of high grade electrolytic products
CONTACT US
IONTECH 2000 JSC
Bulgaria, 1113 Sofia 20, Frederik Jolio Kyuri str. Tel.: +359 2 8164431 Fax: +359 2 8164461 E-mail [email protected]@[email protected] [email protected]
www.ionteching.com www.ionteching.com
IONTECH www.ionteching.com www.ionteching.com Bulgaria, 1113 Sofia, 20, Frederik Jolio Kyuri str., Tel.: +359 2 8164431, Fax: +359 2 8164461 e-mail: [email protected] [email protected] [email protected] [email protected]