Pea Ridge Street Overlay ProgramJuly 2 - November 9, 2010
\
DECCO Asphalt Paving of Rogers was low bidderfrom four companies that submitted on bids June 2nd.
Seven Valleys Construction was low bidder on thedrainage structure on N Davis & McCulloch, bids
were let June 10th.
Greer St was let to bid on August 12th . Wood Stwas added to the list by use of Force Account prices
but was not an impact street.
The plans and specifications were developed in-house and executed using impact fees for funding.
Each department of the Pubic Works did theirrespective share of the work in preparation and
execution of the improvements.
8/7/2019 Pea Ridge Overlay Program
2/58
Purpose of Work
Improve structural capacity & safety Correct roadway drainage problems Improve geometries by widening where possible Resection roadways with more crown Clean ditches for overall drainage improvement Establish smoother ride
8/7/2019 Pea Ridge Overlay Program
3/58
Street Selection
Streets were selected from the impacted list of the
associated subdivision. The selection was based on
the present serviceability rating (PCR) and
projected future traffic. A typical value of six tripsper day per lot was used for estimating the future
traffic.
Most of the streets selected were very marginal in
structural serviceability and were deteriorating at arapid rate. The treatment selected would not be
considered as an ultimate up-grade but would be a
significant improvement over the existing condition.
8/7/2019 Pea Ridge Overlay Program
4/58
Program Cost
Seven Valleys Drainage Structures $68,434.50 DECCO June 12th Paving 187,387.00 DECCO Aug `12th Greer St 52,554.00Wood Street (Force Account) 11,848.00
Total cost of program $320,223.50
8/7/2019 Pea Ridge Overlay Program
5/58
30-inch CMP to be replaced with DBL 27-inch RCP
8/7/2019 Pea Ridge Overlay Program
6/58
Drainage Restrictions on McCulloch
8/7/2019 Pea Ridge Overlay Program
7/58
Protecting an existing sewer line
8/7/2019 Pea Ridge Overlay Program
8/58
8/7/2019 Pea Ridge Overlay Program
9/58
Replacing a 36 CMP with DBL 27 RCP
8/7/2019 Pea Ridge Overlay Program
10/58
8/7/2019 Pea Ridge Overlay Program
11/58
Cross Drainage Improvement on McCulloch
8/7/2019 Pea Ridge Overlay Program
12/58
Replacing 60 CMP with 5x10x80 RC Box Culvert on N Davis
8/7/2019 Pea Ridge Overlay Program
13/58
8/7/2019 Pea Ridge Overlay Program
14/58
A bit of history uncovered
8/7/2019 Pea Ridge Overlay Program
15/58
Previous improvements are exposed here
8/7/2019 Pea Ridge Overlay Program
16/58
8/7/2019 Pea Ridge Overlay Program
17/58
8/7/2019 Pea Ridge Overlay Program
18/58
Intercepting the gas line on the West end of the
culvert resulted in a 0.7 ft. elev. change on that
end of the box requiring a revised the drainageplan.
8/7/2019 Pea Ridge Overlay Program
19/58
Raised Elev. 0.7 ft.
8/7/2019 Pea Ridge Overlay Program
20/58
Raising MH 22.5 inches to match street elevation
8/7/2019 Pea Ridge Overlay Program
21/58
Constructing drop-inlet in top of box
8/7/2019 Pea Ridge Overlay Program
22/58
Compacting the Fill
8/7/2019 Pea Ridge Overlay Program
23/58
Finished Ditch LineFinished Ditch Line
8/7/2019 Pea Ridge Overlay Program
24/58
8/7/2019 Pea Ridge Overlay Program
25/58
Patching & Ditch Cleaning on Carr St.
8/7/2019 Pea Ridge Overlay Program
26/58
8/7/2019 Pea Ridge Overlay Program
27/58
Replacing CMP Culvert on Carr
8/7/2019 Pea Ridge Overlay Program
28/58
Drainage issue at E Patton and N Davis
8/7/2019 Pea Ridge Overlay Program
29/58
8/7/2019 Pea Ridge Overlay Program
30/58
Construction of drainage swale @ E Patton & Davis St.
8/7/2019 Pea Ridge Overlay Program
31/58
Drainage Swale
E Patton widened from 19/20 to to 22 ft.
8/7/2019 Pea Ridge Overlay Program
32/58
Drainage Issue at Carr & W Patton
8/7/2019 Pea Ridge Overlay Program
33/58
8/7/2019 Pea Ridge Overlay Program
34/58
8/7/2019 Pea Ridge Overlay Program
35/58
Drainage swale
8/7/2019 Pea Ridge Overlay Program
36/58
Curb recovering on Carr St.
8/7/2019 Pea Ridge Overlay Program
37/58
Paving on Carr St..
8/7/2019 Pea Ridge Overlay Program
38/58
West Harris
8/7/2019 Pea Ridge Overlay Program
39/58
Removing Existing Material on Greer
8/7/2019 Pea Ridge Overlay Program
40/58
Reworking Subgrade on Greer
8/7/2019 Pea Ridge Overlay Program
41/58
Using Sheep Foot Roller on Subgrade
8/7/2019 Pea Ridge Overlay Program
42/58
Shaping Subgrade
8/7/2019 Pea Ridge Overlay Program
43/58
Final Dressing Subgrade
8/7/2019 Pea Ridge Overlay Program
44/58
Placing Class-7 Base
8/7/2019 Pea Ridge Overlay Program
45/58
Finishing Class-7 Base Material On Greer
8/7/2019 Pea Ridge Overlay Program
46/58
Greer St. completed
8/7/2019 Pea Ridge Overlay Program
47/58
Removing & Replacing Distress Area on N Davis
8/7/2019 Pea Ridge Overlay Program
48/58
Sequence of work
#1 Tack coat#2 Scab layer
#3 Followed by overlay
8/7/2019 Pea Ridge Overlay Program
49/58
McCulloch widened from 19/20 to 22 ft
8/7/2019 Pea Ridge Overlay Program
50/58
Paving on N Davis St.
8/7/2019 Pea Ridge Overlay Program
51/58
Completed north approach to new culvert
8/7/2019 Pea Ridge Overlay Program
52/58
Paving South approach to Culvert
8/7/2019 Pea Ridge Overlay Program
53/58
Culvert area completed on N Davis
8/7/2019 Pea Ridge Overlay Program
54/58
Paving Wood St.
8/7/2019 Pea Ridge Overlay Program
55/58
Paving completed on Wood St.
8/7/2019 Pea Ridge Overlay Program
56/58
N Davis St. completed
8/7/2019 Pea Ridge Overlay Program
57/58
Turning Radii were increased on
narrowstreets where possible
8/7/2019 Pea Ridge Overlay Program
58/58
Many thanks to the traveling public of
Pea Ridge for your patience shown to our
construction crews while doing this work.
No doubt this construction caused some
inconvenience, but we really didn
t receiveany complaints from the public. On behalf
of the City crews and Contractors we
thank you for your support during this busy
time.M. J. Hensley P.E.
Project Engineer