    Pea Ridge Street Overlay ProgramJuly 2 - November 9, 2010

    \

    DECCO Asphalt Paving of Rogers was low bidderfrom four companies that submitted on bids June 2nd.

    Seven Valleys Construction was low bidder on thedrainage structure on N Davis & McCulloch, bids

    were let June 10th.

    Greer St was let to bid on August 12th . Wood Stwas added to the list by use of Force Account prices

    but was not an impact street.

    The plans and specifications were developed in-house and executed using impact fees for funding.

    Each department of the Pubic Works did theirrespective share of the work in preparation and

    execution of the improvements.

  • 8/7/2019 Pea Ridge Overlay Program

    2/58

    Purpose of Work

    Improve structural capacity & safety Correct roadway drainage problems Improve geometries by widening where possible Resection roadways with more crown Clean ditches for overall drainage improvement Establish smoother ride

  • 8/7/2019 Pea Ridge Overlay Program

    3/58

    Street Selection

    Streets were selected from the impacted list of the

    associated subdivision. The selection was based on

    the present serviceability rating (PCR) and

    projected future traffic. A typical value of six tripsper day per lot was used for estimating the future

    traffic.

    Most of the streets selected were very marginal in

    structural serviceability and were deteriorating at arapid rate. The treatment selected would not be

    considered as an ultimate up-grade but would be a

    significant improvement over the existing condition.

  • 8/7/2019 Pea Ridge Overlay Program

    4/58

    Program Cost

    Seven Valleys Drainage Structures $68,434.50 DECCO June 12th Paving 187,387.00 DECCO Aug `12th Greer St 52,554.00Wood Street (Force Account) 11,848.00

    Total cost of program $320,223.50

  • 8/7/2019 Pea Ridge Overlay Program

    5/58

    30-inch CMP to be replaced with DBL 27-inch RCP

  • 8/7/2019 Pea Ridge Overlay Program

    6/58

    Drainage Restrictions on McCulloch

  • 8/7/2019 Pea Ridge Overlay Program

    7/58

    Protecting an existing sewer line

  • 8/7/2019 Pea Ridge Overlay Program

    8/58

  • 8/7/2019 Pea Ridge Overlay Program

    9/58

    Replacing a 36 CMP with DBL 27 RCP

  • 8/7/2019 Pea Ridge Overlay Program

    10/58

  • 8/7/2019 Pea Ridge Overlay Program

    11/58

    Cross Drainage Improvement on McCulloch

  • 8/7/2019 Pea Ridge Overlay Program

    12/58

    Replacing 60 CMP with 5x10x80 RC Box Culvert on N Davis

  • 8/7/2019 Pea Ridge Overlay Program

    13/58

  • 8/7/2019 Pea Ridge Overlay Program

    14/58

    A bit of history uncovered

  • 8/7/2019 Pea Ridge Overlay Program

    15/58

    Previous improvements are exposed here

  • 8/7/2019 Pea Ridge Overlay Program

    16/58

  • 8/7/2019 Pea Ridge Overlay Program

    17/58

  • 8/7/2019 Pea Ridge Overlay Program

    18/58

    Intercepting the gas line on the West end of the

    culvert resulted in a 0.7 ft. elev. change on that

    end of the box requiring a revised the drainageplan.

  • 8/7/2019 Pea Ridge Overlay Program

    19/58

    Raised Elev. 0.7 ft.

  • 8/7/2019 Pea Ridge Overlay Program

    20/58

    Raising MH 22.5 inches to match street elevation

  • 8/7/2019 Pea Ridge Overlay Program

    21/58

    Constructing drop-inlet in top of box

  • 8/7/2019 Pea Ridge Overlay Program

    22/58

    Compacting the Fill

  • 8/7/2019 Pea Ridge Overlay Program

    23/58

    Finished Ditch LineFinished Ditch Line

  • 8/7/2019 Pea Ridge Overlay Program

    24/58

  • 8/7/2019 Pea Ridge Overlay Program

    25/58

    Patching & Ditch Cleaning on Carr St.

  • 8/7/2019 Pea Ridge Overlay Program

    26/58

  • 8/7/2019 Pea Ridge Overlay Program

    27/58

    Replacing CMP Culvert on Carr

  • 8/7/2019 Pea Ridge Overlay Program

    28/58

    Drainage issue at E Patton and N Davis

  • 8/7/2019 Pea Ridge Overlay Program

    29/58

  • 8/7/2019 Pea Ridge Overlay Program

    30/58

    Construction of drainage swale @ E Patton & Davis St.

  • 8/7/2019 Pea Ridge Overlay Program

    31/58

    Drainage Swale

    E Patton widened from 19/20 to to 22 ft.

  • 8/7/2019 Pea Ridge Overlay Program

    32/58

    Drainage Issue at Carr & W Patton

  • 8/7/2019 Pea Ridge Overlay Program

    33/58

  • 8/7/2019 Pea Ridge Overlay Program

    34/58

  • 8/7/2019 Pea Ridge Overlay Program

    35/58

    Drainage swale

  • 8/7/2019 Pea Ridge Overlay Program

    36/58

    Curb recovering on Carr St.

  • 8/7/2019 Pea Ridge Overlay Program

    37/58

    Paving on Carr St..

  • 8/7/2019 Pea Ridge Overlay Program

    38/58

    West Harris

  • 8/7/2019 Pea Ridge Overlay Program

    39/58

    Removing Existing Material on Greer

  • 8/7/2019 Pea Ridge Overlay Program

    40/58

    Reworking Subgrade on Greer

  • 8/7/2019 Pea Ridge Overlay Program

    41/58

    Using Sheep Foot Roller on Subgrade

  • 8/7/2019 Pea Ridge Overlay Program

    42/58

    Shaping Subgrade

  • 8/7/2019 Pea Ridge Overlay Program

    43/58

    Final Dressing Subgrade

  • 8/7/2019 Pea Ridge Overlay Program

    44/58

    Placing Class-7 Base

  • 8/7/2019 Pea Ridge Overlay Program

    45/58

    Finishing Class-7 Base Material On Greer

  • 8/7/2019 Pea Ridge Overlay Program

    46/58

    Greer St. completed

  • 8/7/2019 Pea Ridge Overlay Program

    47/58

    Removing & Replacing Distress Area on N Davis

  • 8/7/2019 Pea Ridge Overlay Program

    48/58

    Sequence of work

    #1 Tack coat#2 Scab layer

    #3 Followed by overlay

  • 8/7/2019 Pea Ridge Overlay Program

    49/58

    McCulloch widened from 19/20 to 22 ft

  • 8/7/2019 Pea Ridge Overlay Program

    50/58

    Paving on N Davis St.

  • 8/7/2019 Pea Ridge Overlay Program

    51/58

    Completed north approach to new culvert

  • 8/7/2019 Pea Ridge Overlay Program

    52/58

    Paving South approach to Culvert

  • 8/7/2019 Pea Ridge Overlay Program

    53/58

    Culvert area completed on N Davis

  • 8/7/2019 Pea Ridge Overlay Program

    54/58

    Paving Wood St.

  • 8/7/2019 Pea Ridge Overlay Program

    55/58

    Paving completed on Wood St.

  • 8/7/2019 Pea Ridge Overlay Program

    56/58

    N Davis St. completed

  • 8/7/2019 Pea Ridge Overlay Program

    57/58

    Turning Radii were increased on

    narrowstreets where possible

  • 8/7/2019 Pea Ridge Overlay Program

    58/58

    Many thanks to the traveling public of

    Pea Ridge for your patience shown to our

    construction crews while doing this work.

    No doubt this construction caused some

    inconvenience, but we really didn

    t receiveany complaints from the public. On behalf

    of the City crews and Contractors we

    thank you for your support during this busy

    time.M. J. Hensley P.E.

    Project Engineer