Semi-Annual Evaluation Report S1/2015
E G E C Q a t a r
1 1 0 D - R i n g R o a d , D o h a , Q A T A R
( + 9 7 4 ) 4 4 6 4 3 1 3 5 / 4 4 3 6 3 6 9 0
Prepared by Osama Shawky May 2015
EGEC Qatar | Semi-Annual Evaluation Report 1
Contents
1. Executive Summary ....................................................................................................................... 3
2. Terms of Reference ....................................................................................................................... 4
2.1. Preface ................................................................................................................................... 4
2.2. Why are we evaluating? ........................................................................................................ 5
2.3. What are we evaluating? ....................................................................................................... 5
2.4. How are we evaluating? ........................................................................................................ 6
2.4.1. Activity-Based Costing .................................................................................................... 7
2.4.2. Employee Performance Evaluation ................................................................................ 9
2.5. How will the evaluation be managed? ................................................................................ 10
3. Findings and Recommendations ................................................................................................. 11
3.1. Using Attributes while defining Spaces in Master-planning ............................................ 11
3.2. Use DIESEL Expressions for Attributes and Dynamic Blocks ............................................... 12
3.3. Use BatchInEditor for batch processing of drawings .......................................................... 13
3.4. Revitology experts affirm that Revit is the future ........................................................ 14
3.5. GSAS Green Compliance is no more an option ................................................................ 16
3.6. Providing ELEC Loads for equipment to ELEC department ................................................. 17
3.7. As-Built drawings ................................................................................................................. 18
3.8. Documentation & LOG files ................................................................................................. 19
3.9. Interpersonal skills ............................................................................................................... 20
3.10. Becoming Part of the Research Community .................................................................... 20
4. Sample Project Evaluation (Qetaifan Islands) ............................................................................. 21
4.1. Background to the Project ................................................................................................... 21
4.2. Scope of Works .................................................................................................................... 21
4.3. Project Main Objective ........................................................................................................ 21
4.4. Critical Success Factors ........................................................................................................ 22
4.5. Outputs ................................................................................................................................ 22
4.6. Resources Management ...................................................................................................... 22
4.7. Evaluation ............................................................................................................................ 22
5. Status of Current Projects (HVAC Department) .......................................................................... 23
EGEC Qatar | Semi-Annual Evaluation Report 2
List of Figures
Figure 1: Evaluation and Control Process ............................................................................................ 6
Figure 2: Sample WBS (Qetaifan Islands) ............................................................................................. 8
Figure 3: Sample Evaluation Form (Revit: Links, Imports and Groups) ........................................... 10
Figure 4: Exporting Fields data to EXCEL ............................................................................................ 11
Figure 5: Using DIESEL expressions in AutoCAD ................................................................................ 12
Figure 6: BatchInEditor Plugin for AutoCAD ...................................................................................... 13
Figure 7: Revit model proposed for the generator room in Al-Jassimeya project .......................... 15
Figure 8: GSAS Calculators ................................................................................................................. 16
Figure 9: ELEC Loads of Mechanical Equipment using unprintable layers ........................................ 17
Figure 10: Sample As-Built drawing for a Chiller plant ...................................................................... 18
Figure 11: Sample Folder Hierarchy of inputs (Qetaifan Islands Project) .......................................... 19
Figure 12: Planned vs extended working days in Qetaifan Islands .................................................... 21
EGEC Qatar | Semi-Annual Evaluation Report 3
1. Executive Summary
This report provides an analysis and evaluation of the current and prospective progress of
activities performed in the first and second quarters of 2015. The outcome is to find a
strategic fit between external opportunities and internal strengths while working around
external threats and internal weaknesses. This is achieved by uncovering deficiencies
experienced, and directing the team towards tools that will help improving and
developing some important skills.
The main goal is to focus on improving the competitive position of our companys services
within the consulting industry. It can be said that the essence of the strategy formulation
is mainly divided into:
Functional strategy: the approach a department (functional area) takes to achieve
corporate and business unit objectives and strategies by maximizing resource
productivity. It is concerned with developing and nurturing a distinctive
competence to provide a company or business unit with a competitive advantage.
Corporate strategy: Through a series of coordinating devices, a company transfers
skills and capabilities developed in one unit to other units that need such
resources. In this way, it attempts to obtain synergy among numerous business
units so that the corporate whole is greater than the sum of its individual business
unit parts.
The intent is to issue this evaluation report on a biannual basis, to ensure success of our
mission.
EGEC Qatar | Semi-Annual Evaluation Report 4
2. Terms of Reference
2.1. Preface
In this section, aspects of the evaluation process will be defined. The process is composed
from four basic elements:
Environmental scanning is the monitoring, evaluating, and disseminating of
information from the external and internal environments to key people within the
corporation. Its purpose is to identify strategic factorsthose external and
internal elements that will determine the future of the corporation.
Strategy formulation is the development of long-range plans for the effective
management of environmental opportunities and threats, in light of corporate
strengths and weaknesses. It includes defining the corporate mission, specifying
achievable objectives, developing strategies, and setting policy guidelines.
Strategy implementation is a process by which strategies and policies are put into
action through the development of programs, budgets, and procedures. This
process might involve changes within the overall culture, structure, and/or
management system of the organization.
Evaluation and control is a process in which corporate activities and performance
results are monitored so that actual performance can be compared with desired
performance. Managers at all levels use the resulting information to take
corrective action and resolve problems.
Environmental Scanning Strategy
Formulation Strategy
Implementation Evaluation and
Control
EGEC Qatar | Semi-Annual Evaluation Report 5
2.2. Why are we evaluating?
The aim of the evaluation is to analyze the activities performed throughout the different
stages of the projects so as to identify the tedious, repetitive & time-consuming activities
that has to be properly setup so as to speed-up the workflow. A variety of tools and
techniques once introduced will make the workflow runs faster. Examples are not limited
to the list hereafter:
Eliminating Human Error by automating most of the activities.
Limiting Human Intervention and reducing the time consumed by the activities.
Introducing the concept of Intelligent Dynamic Update to cope effectively with
projects changes.
2.3. What are we evaluating?
The following factors are being evaluated:
Automational: elimination of human intervention and achievement of more
efficient structuring of processes.
Informational: capturing of process information for purposes of analyzing and
better understanding.
Sequential: transformation of sequential processes to parallel in order to
achieve cycle-time reductions.
Tracking: monitoring the status of executing processes and objects on which the
processes operate
Analytical : analysis of information and decision making
Geographical: allowing the organizations to effectively overcome geographical
boundaries
Integrative: improvement of process performance promoting the coordination
between different tasks and processes also thanks to common database and
information exchange.
Intellectual: capturing and distribution of employee expertise
Dis-intermediating: increasing efficiency by eliminating human intermediaries in
relatively structured tasks.
EGEC Qatar | Semi-Annual Evaluation Report 6
2.4. How are we evaluating?
By means of monitoring activities to identify the strengths and challenges of each, an
organization can assess the quality (maturity level) of its activities. The evaluation and
control process ensures that a company is achieving what it set out to accomplish. It
compares performance with desired results and provides the feedback necessary for
management to evaluate results and take corrective action, as needed. This process can
be viewed as a five-step feedback model:
1. Determine what to measure: The processes and results must be capable of being
measured in a reasonably objective and consistent manner. The focus should be on
the most significant elements in a processthe ones that account for the highest
proportion of expense or the greatest number of problems.
2. Establish standards of performance: Standards used to measure performance are
detailed expressions of strategic objectives. They are measures of acceptable
performance results. Each standard usually includes a tolerance range, which defines
acceptable deviations.
3. Measure actual performance: Measurements must be made at predetermined times.
4. Compare actual performance with the standard: If actual performance results are
within the desired tolerance range, the measurement process stops here.
Figure 1: Evaluation and Control Process
EGEC Qatar | Semi-Annual Evaluation Report 7
2.4.1. Activity-Based Costing
Activity-based costing (ABC) is a recently developed method for allocating indirect and
fixed costs to activities going into a product. This method is thus very useful in doing a
value-chain analysis of a firms activities for making outsourcing decisions.
A work breakdown structure lets project managers plan their activity based costing more
efficiently through properly defining the following items:
Scope: One of the key functions of the project management is to define the scope
of the project. The challenge is to make sure that everything within the project
scope is completed without carrying out any extra work. The WBS helps define
scope by listing individual tasks that make up the project. The project team
completes all the listed tasks but no additional work.
Tasks: The main purpose of a WBS is to reduce complicated activities to a
collection of tasks. This is important for the project manager because he can
oversee the tasks more effectively than the complex activities. Tasks must be
measurable and independent, with clearly defined limits. All the project work
must be included in one of the tasks and the tasks must not include any non-
project work.
Schedule: Because the WBS tasks have clearly defined limits, the project
management can determine how advanced the project is by checking which of the
tasks are finished. Even within each task, the project management can check for
percent completion because each task is measurable.
Responsibility: An important part of project management is to assign
responsibility for the work. With a WBS, the project management assigns
responsibility for each of the tasks. The task manager is responsible for completing
the full scope of the project on time, within the budget and with all of its planned
functionality intact.
EGEC Qatar | Semi-Annual Evaluation Report 8
Figure 2: Sample WBS (Qetaifan Islands)
As shown in the figure mentioned here-above, each activity has a specific duration,
starting date, ending date, with specific requirements for the activity to be done, as well
as set of deliverables that has to be submitted by the end of each activity (either
internally between disciplines, or externally to the client). Once the actual man-hours are
compared against the planned (scheduled) man-hours, the bleed in resources can be
identified, and corrective actions are undertaken.
18-J
an
19-J
an
20-J
an
21-J
an
22-J
an
23-J
an
24-J
an
25-J
an
26-J
an
27-J
an
28-J
an
29-J
an
30-J
an
31-J
an
1-Fe
b
2-Fe
b
3-Fe
b
4-Fe
b
5-Fe
b
6-Fe
b
7-Fe
b
8-Fe
b
9-Fe
b
10-F
eb
11-F
eb
12-F
eb
13-F
eb
14-F
eb
1.1 Review of Project Scope of Works x
1.2 Project Drawings (Layouts, Elevations, Sections ) x
1.3 Internal Loads Parameters (People, Lighting, ) x
1.4 Construction Parameters (Roofs, Walls, ) x
1.5 Review of Project Requirements (GSAS, QCDD, ) x
2.1 Define and Schedule Project Activities x
2.2 Define Project List of Deliverables and Submission Dates x
2.3 Define Project Responsibility Matrix for each Activity x
3.1 Preparation of Block Load Calculations
3.2 Preparation of Design Basis Report x x
3.3 Request for Space/Shaft Requirements GV1 GV2 WF1 WF2
3.4 Review of Space/Shaft Requirements GV1 GV2 WF1 WF2
3.5 Provide ELEC Loads to ELEC Department GV1 GV2 WF1 WF2
3.6 Provide Drainage Locations to P&FF Department GV1 GV2 WF1 WF2
4.1 Preparation of Single-Line Layouts
4.2 Preparation of Air & Water Risers GV1 GV2 WF1 WF2
4.3 Preparation of Schedule of Equipment GV1 GV2 WF1 WF2
5.1 Preparation of Detailed-Design Layouts
5.2 Update of Air & Water Risers GV1 GV2 WF1 WF2
5.3 Update of Schedule of Equipment GV1 GV2 WF1 WF2
5.4 Preparation of Typical Details Drawings GV1 GV2 WF1 WF2
GV1 GV2 GV4WF1
GV4WF1GV2GV1
Detailed Design
GV1
Schematic Design
Preliminary Design
GV2 WF1 GV4
Structuring Work Breakdown
Gathing Project Data
Week 01 Week 02 Week 03 Week 04
Work Breakdown Structure
EGEC Qatar | Semi-Annual Evaluation Report 9
2.4.2. Employee Performance Evaluation
Good modern personal development and evaluation extend beyond the obvious skills and
knowledge required for the job or organization or qualification. Effective personal
development must also consider: individual potential (natural abilities often hidden or
suppressed); individual learning styles; and whole person development (life skills, in other
words).
For effective training and learning evaluation, the principal questions should be:
To what extent were the identified training needs objectives achieved by the
program?
To what extent were the learners' objectives achieved?
What specifically did the learners learn or be usefully reminded of?
What commitment have the learners made about the learning they are going to
implement on their return to work?
And back at work,
How successful were the trainees in implementing their action plans?
To what extent were they supported in this by their line managers?
To what extent has the action listed above achieved a Return on Investment (ROI)
for the organization, either in terms of identified objectives satisfaction or, where
possible, a monetary assessment.
EGEC Qatar | Semi-Annual Evaluation Report 10
Topics
Score
Before Course
Q1 2015
Q2 2015
Q3 2015
Q4 2015
Links, Imports, and Groups
1. Linking AutoCAD DWG files
2. Creating topography from a DWG link
3. Understanding CAD inserts
4. Import tips
5. Create a group
6. Mirroring groups to create a layout
7. Creating Revit links
8. Rotating and aligning a Revit link
9. Establishing shared coordinates
10. Managing links
11. Understanding file formats
TOTAL
Figure 3: Sample Evaluation Form (Revit: Links, Imports and Groups)
The figure shown here-above is a sample from learning topics related to Revit. Each time
an employee is assigned to a new task, the features of this task should be properly
defined so as to have way for measuring development of skills.
2.5. How will the evaluation be managed?
The conclusion for new/corrective actions has to be discussed with all the departments, a
key person will be assigned responsible to assure that these actions are adopted and
properly applied. These actions will be evaluated quarterly, and will be subject to
continuous improvement until we reach a satisfactory level of workflow.
EGEC Qatar | Semi-Annual Evaluation Report 11
3. Findings and Recommendations
3.1. Using Attributes while defining Spaces in Master-planning
A CAD drawing can be used to export data to another file (such as Microsoft) for others to
use. By using attributes rather than simple text fields, very useful information can be
exported
Taking ASHGHAL Custom Training Center and Warehouses project as an example, it is
required to prepare a block load calculation. By means of using attributes in the earliest
stages of the project (Master-planning): Spaces names, descriptions and areas will be
exported to spread sheets in which the design criteria will be applied for each space, thus
a very close load estimation can be obtained rather than using rules of thumb. This will
have its impact on the level of details in the design basis report which is assumed to be
the first contact with the client. In addition, the gap between preliminary & detailed
stages will be gapped.
This recommendation should be addressed to our Arch. Department.
Figure 4: Exporting Fields data to EXCEL
EGEC Qatar | Semi-Annual Evaluation Report 12
3.2. Use DIESEL Expressions for Attributes and Dynamic Blocks
Make intelligent drawings by using AutoCAD Fields. Fields are used to add intelligence to
the drawings. Drawings can be customized with title-blocks, blocks, tables, plot stamps,
email links, web page links and much more. When you use Fields, the text information in
the drawing stays current reducing errors and aiding in drawing consistency.
Taking Qetaifan Islands project as an example, the client requested to change the file-
naming format after issuing more than 600 DWGs. Using DIESEL expressions, the
manipulation of this enormous amount of drawings will be much easier by setting the
attribute in only one drawing, then calling for a batch processor to apply the
modifications for all drawings.
Figure 5: Using DIESEL expressions in AutoCAD
This recommendation should be addressed to our CAD department.
The figure shown here above is an example of a file-naming structure composed of 10
fields, of which 8 fields have to be updated for each submitted drawing. If each field
consumes 5 seconds to be updated, then for a submission of 500 drawings, the saved
time is:
500 drawings X 8 fields / drawing X 5 seconds / field
= 20,000 seconds
5 hrs 33 mins
EGEC Qatar | Semi-Annual Evaluation Report 13
3.3. Use BatchInEditor for batch processing of drawings
BatchInEditor is a program that takes AutoCAD batch process to a new level with
powerful built-in commands and an easy to use interface. You can run multiple
commands on selected drawings or selected layouts, Import/Export of drawing list and
commands list and check drawing version. Key Features:
1. Easy to use Interface and Automated batch process.
2. Run multiple built-in commands , lisp and scripts commands on selected
drawings/Layouts
3. Run multiple plot task on layouts and Model by assigning multiple page setup (PDF,
DWF, PLT, image format and to printer).
4. Drawing version check could be done instantly by loading drawings in the Bacth
process.
5. Drawing version change only could be done by setting drawing version (2000 to 2013)
with no commands added.
6. Import/Export of Drawing list and commands list.
7. Supports Windows 32/64 bit AutoCAD 2012 to 2015 and Verticals
Figure 6: BatchInEditor Plugin for AutoCAD
This recommendation should be addressed to our CAD department.
EGEC Qatar | Semi-Annual Evaluation Report 14
3.4. Revitology experts affirm that Revit is the future
Building Information Modeling or BIM is a process and it is already having an enormous
impact on the construction and infrastructure industry. The very face of Qatar will change
over the next decade as work on the countrys various mega projects is undertaken and
completed, while further advancements will be made as the vision for 2030 is realized.
The nature and size of the projects means that Qatar has turned to Building Information
Modelling (BIM) facilitate its building ambitious schedule.
From Dohas Metro System to the numerous sporting stadiums, BIM will enable project
teams of architects, engineers, building and infrastructure owners and construction firms
to use 3D digital models to collaborate and support building projects throughout their
lifecycle - from design and documentation to building and field support - ensuring that
projects are delivered to the required specifications on schedule and within budget.
In recent years, a series of high profile success stories in the Middle East has meant that
BIM is now being viewed as a critical factor in the design, planning and construction
stages of todays complex and ambitious architecture projects. It can also have a very
positive effect on the whole lifecycle of a building. Future BIM Implementation Qatar is
the essential platform in 2015 for all those involved in the architecture, design,
construction, engineering, consulting, building and infrastructure industry in Qatar and
the GCC to stay up-to-date on how this software and technology is facilitating future cities
in the region.
QP Mosques project will be our launching base for Revitology; it is requested to prepare
6 Revit models for 6 different plots (mosque + imam house). We proposed to prepare
one model as a sample; development of this sample will be developed in the form of a
small workshop, so as to assist our design team getting familiar with BIM modeling. Our
next step will be to develop the remaining 5 plots in parallel using the first plot as a guide
(template).
This recommendation should be addressed to our Engineering and CAD departments.
EGEC Qatar | Semi-Annual Evaluation Report 15
Figure 7: Revit model proposed for the generator room in Al-Jassimeya project
EGEC Qatar | Semi-Annual Evaluation Report 16
3.5. GSAS Green Compliance is no more an option
Green building is no longer an option it is an obligation to secure the environment for
generations to come, according to the co-founder of a sustainable engineering
consultancy. Green building regulations and certification are driving the performance of
buildings in the UAE and the MENA region to the next level.
Qatars revamped its QSAS green building rating system. Re-launched under a new name,
the Global Sustainability Assessment System (GSAS) is muscling in as Middle East- North
Africas green standard.
Public works authority Ashghal is the first governmental institution to fully adopt GSAS.
Established by Emiri Decree in 2004, Ashghal has oversight of all state buildings and
infrastructure projects in Qatar. All new government buildings including mosques, schools
and hospitals approved as of 2012 must adhere to these green specifications.
Ashghal Custom Training Center and Warehouses project will be our launching base so as
to prepare for GSAS certification rather than outsources the task. The project has been
defined as four different typologies which are:
Commercial
Mosque
Light industry
Hotel
The project has to achieve a 3 stars certification which is quite challenging.
Figure 8: GSAS Calculators
EGEC Qatar | Semi-Annual Evaluation Report 17
3.6. Providing ELEC Loads for equipment to ELEC department
It has been brought to our attention that the activity of providing the electrical loads of
mechanical equipment has not been properly defined, resulting in too much frustration,
especially after getting approval from KAHRAMAA. This has been encountered in many of
the projects. The proposed scheme is to:
Prepare a library of mechanical equipment. The electrical loads will be mentioned
along with the unit name size and capacity.
This library will be used in the preliminary design stage while the mechanical
department is allocating spaces/shafts for MEP services.
The ELEC loads will always be available on the mechanical drawings throughout
the development of mechanical design. The ELEC loads will use a separate
AutoCAD layer which will be set as unprintable.
In case the design has to be updated/modified, Equipment affected by this deign
change will be clouded with a Revision-cloud (Rev-01, Rev-02 etc.) so as to help
the ELEC department to focus only on the modified equipment rather than going
through all the plan. Again, the Revision-cloud will use an unprintable AutoCAD
layer, with each revision having a separate layer.
By default the ELEC department is collecting the Electrical demand from all departments,
and locating equipment on his drawings. A preliminary coordination for equipment is
performed, and in case of clashing between equipment from different disciplines, the
clash is addressed so as location of equipment is rectified.
Figure 9: ELEC Loads of Mechanical Equipment using unprintable layers
EGEC Qatar | Semi-Annual Evaluation Report 18
3.7. As-Built drawings
As built drawings are important since they are a record from which future system changes
and/or additions can be designed. Future renovation projects will be more efficient and
less disruptive if the as built documents can be depended upon for critical information
such as pipe and duct routing and sizing, terminal unit locations, control system sensor
locations, etc.
Few of the current projects in hand are renovation projects (MMUP, Domasco, QDB,
etc.). The design team has been disappointed with the accuracy, completeness, and
timeliness of as built drawings they have received. The client also was disappointed
because either he is receiving unworkable set of drawings, or the submission has been
delayed to accommodate these design conditions.
In case this task will be outsources, a specialized surveyor has to be assigned to the task,
and our engineers should very the deliverables on site, otherwise, EGEC design team will
inherit the deficiencies encountered in these drawings.
Figure 10: Sample As-Built drawing for a Chiller plant
EGEC Qatar | Semi-Annual Evaluation Report 19
3.8. Documentation & LOG files
Proper documentation procedures have to be followed by the Project Coordinator:
LOG files should be instantly recording activities of receiving new inputs, and
submission of new deliverables.
New inputs should be located on the server, even if is a simple drawing, and not to
be sent to individuals by email.
Folder name has to specify the date of the input, the description and the sender.
The input folder write permission is only granted to the Project Coordinator.
The Project coordinator has the responsibility of updating the XREFs as per the
new input, and notifying the MEP team so as to update their works accordingly.
Folders Hierarchy should be the same for all projects, so as to facilitate the hand-
over process, and for ease of information tracking.
Contacts of Key persons (Client, Contractor, etc.) have to be documented along
with Project information.
Handover procedure should be clearly defined, and controlled.
Figure 11: Sample Folder Hierarchy of inputs (Qetaifan Islands Project)
EGEC Qatar | Semi-Annual Evaluation Report 20
3.9. Interpersonal skills
Personal development is a lifelong process. Its a way for people to assess their skills and
qualities, consider their aims in life and set goals in order to realize and maximize their
potential.
The CAD draftsmen are identified to nee for improvement pertaining to one's level of
personal quality. Video Training materials will be provided to them covering basics,
drawing techniques as well as advanced techniques. For those of them who didnt
encounter real MEP works in their experience, site visits should be scheduled so as they
get familiar with the systems as well as the equipment. It is also suggested that they
should attend the as-build exercise, with the plan to rely on them in the future for
carrying this task out.
3.10. Becoming Part of the Research Community
Publishing your ideas is important for several reasons: it gives you a source of feedback
from people who read your papers; it establishes you as a member of the research
community; and it forces you to clarify your ideas and to fit them in the context of the
current state of research in your field.
Breaking into the research community requires attending conferences, meeting
established researchers, and making ourselves known. Just going to conferences and
standing in the corner isn't enough. Especially if we are not normally outgoing
participants, we have to make a conscious effort to meet and build relationships with
other researchers. Presenting papers is a good way to do this, since people will often
approach us to discuss our presentation.
If someone expresses an interest in our work, we follow up! Send them e-mail talking
about new ideas or asking questions; send them drafts of papers; ask them for drafts of
their papers and send them comments. Maintain the relationships we form via e-mail,
and by re-establishing contact at each workshop or conference we attend. If we work at
it, and use our initial acquaintances to meet new people, we will find that our network
grows rapidly.
EGEC Qatar | Semi-Annual Evaluation Report 21
4. Sample Project Evaluation (Qetaifan Islands)
4.1. Background to the Project
Owner: LREDC (Lusail Real Estate Development Company,)
Tender Complete Title: Design Consultancy & Pre-Contract Quantity Surveying
Services for Qetaifan Islands Villas and Apartment Blocks
Total Plot Area: Approx. 370,000 m2
Land Use: Luxury Villas (Waterfront and Garden & Middle Villa) and
Luxury Apartment Blocks
Total Built Area: Approx. 218,000 m2
4.2. Scope of Works
Prepare the necessary Design Drawings (excluding SPECS, BOQ, tender documents and
bid analysis) for the MEP works, defined as follows:
2 types of Waterfront villa
2 types of Garden & Middle villa
1 types of Apartment Block
Follow up to obtain the related authorities permits (DC1, DC2, and QCDD).
4.3. Project Main Objective
The objective was to prepare and submit the MEP design in 28 days, the design for the
villas was completed and submitted in 114 days.
Figure 12: Planned vs extended working days in Qetaifan Islands
25%
75%
Project Duration
Planned
Extension
EGEC Qatar | Semi-Annual Evaluation Report 22
4.4. Critical Success Factors
The assigned team exhibits flexibility & commitment, sharing willingly all the information,
knowledge and experience. In such a dynamic and face-pace project, the team has
successfully issued ~40 official submissions (Around one submission each three days). All
of the above mentioned submissions met their submission dates.
4.5. Outputs
More than 600 MEP design drawings are issues for Qetaifan Islands project.
4.6. Resources Management
The project consumed 400% the planned man-hours due to the following main reasons:
Architectural drawings were not frozen, and they were continuously subjected to
modifications.
MEP requirements Space/Shafts were not considered in the Architectural design
and it took so much time so as to be implemented.
Information such as interior design, false ceiling layouts, landscape, kitchens,
laundries were not provided in the early stages of the project.
Technical specifications were not part of the scope, but according to top
management instructions, we added the specifications to our scope.
4.7. Evaluation
Projects in which Architectural design is carried out by others, MEP requirements should
be addressed clearly at the early stages of the project so as to avoid bleeding unnecessary
man-hours.
EGEC Qatar | Semi-Annual Evaluation Report 23
5. Status of Current Projects (HVAC Department)
Task Action (By)
??? :: Al-Bustan (The Avenue Office building)
The tie in points has changed and the external MEP
needs to be redesigned to accommodate that change.
We are requested to study, evaluate, and submit request
for variation.
Changes will not affect the HVAC design (-)
157 :: Ali Al-Kuwari Villa extension
Architecture and MEP design review & obtain the
required municipal approvals in order to obtain the
required modified final building permit.
For MEP, As-built drawings from client are not received.
MEP review shall be carried out after
receiving necessary documents (-)
002 :: Al-Jassimeya Tower
Provide new proposal (along with calculations) for the
generator room, and the pump room, to cover the
comments received from Qatar Civil Defense.
Action plan for remaining site activities has to be
prepared. Facility management personnel as well as
client representative have to attend any future hand-over
inspections.
Proposal has been provided (along with a
Revit model for the generator room). The
proposals got approved from QCDD (-)
Action plan shall be carried out by site team
(-)
097 :: Al-Khoor Park
Review and implement the clients comments on
preliminary design package.
Awaiting Detailed design to be reviewed
(Wael Hassan)
159 :: Al-Muraikhi Private Villa
Provide requirements to be taken into consideration in
preliminary stage.
Provided on 19-Apr-2015 (Wael Hassan)
139 :: AWQAF Design & Supervision at Meshireb
Update MEP design and provide BOQ. Provided on 4-Mar-2015 (Abdullah ElAwady)
??? :: Barar Nursery
Proceed with the FF, FA & ACMV No action required from HVAC team (-)
EGEC Qatar | Semi-Annual Evaluation Report 24
Task Action (By)
145 :: Barwa Office
Submit MEP design to QCDD for approval. Design got approved by QCDD on 25-Feb-
2015 (Abdullah Abo-ElAta)
143 :: Bus Station
Update MEP design and provide BOQ. Provided on 26-Feb-2015 (Abdullah ElAwady)
163 :: Coast Guard
Update MEP design. Provided on 5-May-2015 (Abdullah ElAwady
& Wael Hassan)
162 :: Al-Sadd Building (Saeed ElKhayreen)
Review design drawings and prepare assessment report Provided on 9-May-2015 (Osama A.Shawky)
156 :: DOMASCO's Workshop St.10
Review as-build drawings provided by Concord. Reviewed on 3-May-2015 (Osama A.Shawky)
003 :: ECQ D16
Review and implement the clients comments on design
package
Reviewed and submitted on 29-Apr-2015
(Osama A.Shawky)
117 :: H-Compound
Update the HVAC package as per QCDD comments, and
provide CFD analysis for car park ventilation.
Request for CFD analysis has been sent on
25-Feb-2015. Awaiting results (Osama
A.Shawky)
??? :: Lekhweya Car Parking
Provide preliminary BOQ and cost estimate Submitted on 9-May-2015 (Osama A.Shawky)
128 :: MMUP
Update design package as per site modifications Submitted on 4-May-2015 (Wael Hassan)
079 :: MOFA
Review design package prior to submitting to client Reviewed and submitted on 9-May-2015
(Wael Hassan)
EGEC Qatar | Semi-Annual Evaluation Report 25
Task Action (By)
129 :: MOI
Review and implement the clients comments on design
package
Reviewed and submitted on 30-Apr-2015
(Wael Hassan)
??? :: Pearl Grand Cinemas Building
Provide load calculations Submitted on 29-Mar-2015 (Wael Hassan)
118 :: PHCC
Obtain QCDD approvals Design got approved by QCDD on 3-May-
2015 (Wael Hassan & Ahmed Hamied)
161 :: PWA 5 Mosques
Prepare and submit the Design Basis Report Submitted internally on 25-Apr-2015 (Osama
A.Shawky)
150 :: PWA Custom Training Center & Warehouses
Update the Design Basis Report as per the clients
comments.
Schedule a meeting for Dr. Sameh Nada to meet with
Eng. Bibi Malik
Start in the preliminary design & space allocation
Awaiting the results from the meeting of Dr.
Sameh with Eng. Bibi Malik (Osama
A.Shawky)
Preliminary design will start starting Sunday
24th of May (Ahmed Abdullah)
144 :: QDB
154 :: Qetaifan Islands
Submit tender packages for GV1, GV2, GV3.
Submit tender packages for WF1, WF2, WF3.
Reply to all Queries sent by the contractor.
Cover all comments received from the client.
All deliverables are submitted, and we are
awaiting the Architectural Package of the
apartment buildings so as to proceed with
the MEP design (Osama A.Shawky & Others)
EGEC Qatar | Semi-Annual Evaluation Report 26
Task Action (By)
134 :: QP Mosques
Review and update Sample drawings.
Update Layers request.
Submit General Details drawings.
Submit HVAC calculations for all plots.
Submit preliminary design for all plots.
Submit Tag-Numbers request
Submitted on 5-May (Ahmed Abd-ElHamied)
Submitted on 5-May (Ahmed Abd-ElHamied)
Submitted on 29-Apr (Wael Hassan)
Submitted on 23-Apr (Wael Hassan)
Submitted on 15-May (Wael Hassan)
Pending
115 :: Sleil Store
Obtain QCDD approvals for ACMV. Design got approved by QCDD on 1-Jan-2015
(Abdullah Abo-ElAta)
149 :: Khalifa South Commercial Building
Prepare and submit HVAC tender pakage. BOQ has to be prepared and submitted
(Abdullah Abo-ElAta)
142 :: Valentino
Prepare and submit HVAC tender package. Submitted on 1-Jan-2015
(Abdullah Abo-ElAta)