Bud Blancher Trail August 17, 2012
Background
• 2009 Eatonville Trails Plan • Bud Blancher and Koch Family Donation:
$500,000 • RCO Grant: $700,000 award requiring a
$702,000 match • Eatonville required to come up with matching
funds including in kind contributions totaling $202,000
• Total Project Cost: $1,402,000
Bud Blancher Trail Location
Phase 1: Volunteer Project
Phase 1: Volunteer Project
Phase 2: To Be Bid
Phase 2: Little Mashel Bank Stabilization and Enhancement
Phase 2: Little Mashel Bank Stabilization and Enhancement
Phase 2: Mashel River Bridge
• Use existing abutments
• Remove old bridge pier from center of river
• Install prefabricated bridge to minimize disturbance
Phase 2: Mashel River Bridge
Trail Section
Project Schedule • Volunteer Project Phase 1 – September 8, 2012 • Complete Design on Phase 2 – October 2012 • Phase 2 Permitting – In progress – Complete by
May 2013 • Bid Phase 2 Project – January 2013 • Phase 2 construction start date – June 2013