Bud Blancher Trail Construction, Eatonville 2012

13
Bud Blancher Trail August 17, 2012

description

Presentation given by Nick Bond, Town Planner of Eatonville

Transcript of Bud Blancher Trail Construction, Eatonville 2012

Page 1: Bud Blancher Trail Construction, Eatonville 2012

Bud Blancher Trail August 17, 2012

Page 2: Bud Blancher Trail Construction, Eatonville 2012

Background

•  2009 Eatonville Trails Plan •  Bud Blancher and Koch Family Donation:

$500,000 •  RCO Grant: $700,000 award requiring a

$702,000 match •  Eatonville required to come up with matching

funds including in kind contributions totaling $202,000

•  Total Project Cost: $1,402,000

Page 3: Bud Blancher Trail Construction, Eatonville 2012

Bud Blancher Trail Location

Page 4: Bud Blancher Trail Construction, Eatonville 2012

Phase 1: Volunteer Project

Page 5: Bud Blancher Trail Construction, Eatonville 2012

Phase 1: Volunteer Project

Page 6: Bud Blancher Trail Construction, Eatonville 2012

Phase 2: To Be Bid

Page 7: Bud Blancher Trail Construction, Eatonville 2012

Phase 2: Little Mashel Bank Stabilization and Enhancement

Page 8: Bud Blancher Trail Construction, Eatonville 2012

Phase 2: Little Mashel Bank Stabilization and Enhancement

Page 9: Bud Blancher Trail Construction, Eatonville 2012

Phase 2: Mashel River Bridge

•  Use existing abutments

•  Remove old bridge pier from center of river

•  Install prefabricated bridge to minimize disturbance

Page 10: Bud Blancher Trail Construction, Eatonville 2012

Phase 2: Mashel River Bridge

Page 11: Bud Blancher Trail Construction, Eatonville 2012

Trail Section

Page 12: Bud Blancher Trail Construction, Eatonville 2012
Page 13: Bud Blancher Trail Construction, Eatonville 2012

Project Schedule •  Volunteer Project Phase 1 – September 8, 2012 •  Complete Design on Phase 2 – October 2012 •  Phase 2 Permitting – In progress – Complete by

May 2013 •  Bid Phase 2 Project – January 2013 •  Phase 2 construction start date – June 2013