2016 UNDERWATER
BRIDGE INSPECTION REPORT
BRIDGE #
DISTRICT: COUNTY: CITY/TOWNSHIP:
Date of Inspection:
Equipment Used:
Inspected By:
Report Written By:
Report Reviewed By:
Final Report Date:
18501
CSAH 16 over PINE RIVER
District 3 Crow Wing Cross Lake
06/06/2016
Life Jacket, Boat, Probing Rod, Non-destructive TestingEquipment - waders
Stromberg, Dan
Dan Stromberg
County Highway AgencyOwner:
MinnesotaSTATE:
UNDERWATER SUMMARY 3
UNDERWATER INSPECTION 4
UNDERWATER INSPECTION PROCEDURES 6
STRUCTURE INVENTORY 7
ELEMENTS 8
PHOTOGRAPHS 11
BRIDGE 18501 UNDERWATER INSPECTION DRAWINGS2016
14
TABLE OF CONTENTS
PAGE NUMBER
Contractor:
(A) Reinspect the submerged substructure units at the normal maximum recommended (NBIS) interval of sixty (60) months.
Collins Engineers, Inc.
9687Contractor Job Number:
RECOMMENDATIONS
REPORT SUMMARY
UNDERWATER INSPECTION
The substructure units inspected below water at Bridge No. 18501, Piers 1, 2, and 3, were found to be in good condition with coating failure and minor related corrosion on the piles below the waterline covering 15% to 20% of their surface area. All piles also have 100% coverage of zebra mussels from 2 feet below the waterline to the channel bottom. The channel bottom around the substructure units appeared stable with no significant scour or debris accumulations and no notable changes since the last inspection.
(A) The channel bottom around Piers 1 and 3 consisted of riprap up to 3 feet in diameter allowing no probe rod penetration.
(B) The channel bottom around Pier 2 consisted of gravel, sand, and 4 to 12 inch diameter cobbles allowing no probe rod penetration.
(C) The piles exhibited coating failure and related minor surface corrosion on 15% to 20% of their surface area below the waterline. Additionally, all piles exhibited a layer of aquatic growth from the waterline to 2 feet below the waterline.
(D) All piles exhibited a 1 inch thick layer of zebra mussels from 2 feet below the waterline to the channel bottom.
INSPECTION FINDINGS
Page 3 of 15
The top of the pile cap at the north end of Pier 2.Water Level Reference:
WATERLINE DATUM
Waterline Elevation (feet):
The waterline was located approximately 9.7 feet below the reference.Description:
90.3 feet
4.
Piers 1, 2, and 3Substructure(s) Inspected:
SUBSTRUCTURE INSPECTION DATA
General Shape:
8.0 feetMaximum Water Depth at Substructure(s) Inspected (feet):
Piers 1, 2, and 3 consist of a single line of eight steel pipe piles supporting a reinforced concrete cap. Each abutment is a pile supported reinforced concrete abutment with a concrete slope wall.
Code:Item 62: Culvert:
7
Y 48 06/2016Code:Item 92B: Underwater Inspection:
Code:
(Minnesota specific codes are used for 92B and 113)
NBIS CODING INFORMATION5.
Item 60: Substructure:
Item 61: Channel and Channel Protection:
7Code:
District 3District:
CSAH 16
County:
The superstructure consists of four spans of multiple concrete beams. The superstructure is supported by two reinforced concrete abutments and three steel pipe pile bent piers. The piers are numbered 1 through 3 starting from the south end of the bridge.
Bridge Description:
018 - Crow Wing
Facility Carried:
BRIDGE DATA1.
UNDERWATER INSPECTION
Bridge #:
PINE RIVERFeature Intersected:
18501
Underwater Visibility (feet):
Overcast, 62°FWeather Conditions:
5.0 feet
3.
NegligibleWaterway Velocity (ft/sec):
06/06/2016
Professional Engineer/Team Leader:
INSPECTION DATA2.
Daniel G. Stromberg
Date of Underwater Inspection:
Daniel G. StrombergInspection Diver:
Page 4 of 15
885 Scour 1 EA 1
STRUCTURAL ELEMENT CONDITION RATING
Conditions
6.
I
Bridge is scour critical because abutment or pier foundation is rated as unstable due to observed scour at bridge site.
Item 113: Scour Critical Bridge: Code:
No (Mark your selection with an X)Yes X
225
CS3 CS4
Steel or CIP Piling 2424 EA
CS2ELEM # Unit CS1Element Description Quantity
Page 5 of 15
The routine underwater inspection of Bridge 18501 (CSAH 16 over Pine River) was completed on June 6, 2016. The underwater inspection was conducted from shore. The inspection was conducted by a team consisting of a Professional Engineer Diver with a valid MnDOT Team Leader certification, a backup diver and dive tender. The inspection utilized commercial dive equipment and techniques (SSA and/or SCUBA) in accordance with OSHA regulations. Channel bottom profiles were taken along the upstream and downstream faces of the bridge and around the periphery of substructure units to determine the presence, location and area of scour.The bridge elements inspected consisted of three piers. According to the bridge inventory, Piers 1, 2, and 3 are founded on steel pipe piles supporting a reinforced concrete cap. Inspection procedures followed FHWA guidance and the MnDOT Bridge and Structure Inspection Program Manual with channel bottom probing to search for foundations. The maximum routine underwater inspection frequency is recommended to remain at 60 months based on those findings and risk factors. Also, inspection procedures should continue to follow the above approach and standard guidance with 100% Level I and 10% Level II intensity efforts.
INSPECTION PROCEDURES
UNDERWATER INSPECTION
Page 6 of 15
Spec. Feat.Pier Foundation (Material/Type)
8 - CIPCantilever ID
+ W A T E R W A Y +Number of Spans Historic Status
4 - PILE BENT
Underwater 60Culvert Type 3 - FTG PILE
Pinned Asbly.
06/06/2016
Barrel Length
124.3 ft. Navigation Control
Waterway Opening (sf.) 1320Structure Length
ft. Year Painted
0 - No nav. control on waterwayDeck Width (Out-to-Out) 43.6
+ P A I N T +
APPR: 0 TOTAL:5 - Not eligible
MAIN: 4
Main Span Length 31.1 ft.Drainage Area (sq. mi.)
B R I D G E D A T A +Main Span Detail
1 - MEETS STANDARDS+ M I S C.
Appr. Span Type Structure Flared
GR Termini 1 - MEETS STANDARDS
Appr. Guardrail
Main Span Type 5 - Prestress or Precast Median Width On Bridge
ft. Bridge Railing 1 - MEETS STANDARDS
1 - MEETS STANDARDS
Main Span Design 21 - Quad Tee
ft. GR Transition
Skew 0
Y/N Freq Date
Abutment Foundation (Material/Type)
1 - CONC Frac. Critical
D E P T H I N S P. +Appr. Span Design
0 - No flare+ I N
Appr. Span Detail Field Conn. ID
Parallel Structure N - No parallel structure
Pier Protection
0 - Not Required
Rating Date 04/14/00165005 sq. ft. Traffic
ft. 50B. Rt 0.00Sidewalk Width 50A. Lt 0.00
Roadway Area (Curb-to-Curb)
Posted Load 0 - Not Required
PostingStructure Area (Out-to-Out) 5419 sq. ft.
DBL:VEH: SEMI:
Rt 22 ARail Type Lt 22 C 1 - No Restriction
1 - No Restriction
B 1 - No Restriction
N - Not Applicable Overweight Permit CodesCurb Height Lt
ft. Horizontal 1 - Object Markers
0.00 ft. Vertical0.00 ft. Rt
0Wear Surf Install Year
sq. ft. Nav. Vert. Lift Bridge Clear. (ft.)
I - LOW RISK YearPrimer Type MN Scour Code
Painted Area
Unsound Paint % Nav. Clr. (ft.)
1 - Not required
Deck Material 1 - Concrete Cast-in-Place 0.0Wear Surf Type 6 - Bituminous
Vert. 0.0 Horiz.
S I G N S +Operating Rating 2 - HS TRUCK
0 - None + B R I D G E
Inventory Rating 2 - HS TRUCK 27.60
45.60Deck Rebars Install Year 1991
Deck Rebars
Finish TypeWear Course/Fill Depth 0.33 ft.
0 - None
Design Load 9 - HS 25 (OR GREATER)
+ C A P A C I T Y R A T I N G S +Deck Membrane
46 ° 41
Inspector Name Stromberg, Dan
Latitude Control Section (TH Only) Status' 2.16 ''
2 - 2-way traffic
Routine Inspection Frequency 24
Sect., Twp., Range
1.2 MI S OF JCT CSAH 66 Level of Service 1 - MAINLINE
- 27W Roadway Type17 - 137N
Detour Length 4.0 mi.R A T I N G S +
Custodian 02 - County Highway Agency
Owner 02 - County Highway AgencyDeck 5 Unsound
Deck %
C O N D I T I O N° 7 '
A - Open
Longitude 94 012+00.150 + N B I 36.18 '' Reference Point
Crew
+ I N S P E C T I O N +
Agency Br. No. 58
District 03
Bridge Match ID (TIS) 0 Userkey
CSAH 16 over PINE RIVER
Minnesota Structure Inventory Report
Bridge ID: 18501
+ G E N E R A L + + R O A D W A Y +
Date: 08/04/2016
Sufficiency Rating 98.3Roadway Name or Description
16
City Cross Lake
Routine Inspection Date 11/05/2014
Desc. Loc.
Township CSAH 16
Number
NRoadway O/U Key Route On StructureMaint. Area Structurally Deficient
NRoute Sys 04 - CSAHCounty 018 - Crow Wing Functionally Obsolete
Lanes
Waterway Adequacy 9Max. Vert. Clear.
ft.Legislative District 04Bft.Potential ABC 2 - N/A ft.
ft.On - Off System Roadway Width 40.30 ft.
Vertical Clearance ft.1 - ON
Underclearances N
Service On 1 - Highway Appr. Surface Width+ S A F E T Y F E A T U R E S +
5 - Waterway Bridge Roadway Width 40.3
40.0 ft.
Service Under
ft.
ft. Approach Alignment 8Horizontal Clear.
ft.
ft.+ S T R U C T U R E + Lateral Clearance
HCADT ADTT7
Year Built 1963
MN Year Reconstructed 1991 Functional Class
%Channel 7
Substructure
0Superstructure 7
ON 2 UNDER
2419 YEAR 2008BMU Agreement ADT
Structure Evaluation 7If Divided
D I M E N S I O N S +Bridge Plan Location 3 - COUNTY
9/1/1991Deck Geometry 6
NB-EB SB-WBDate Opened to Traffic
+ R D W Y
FHWA Year Reconstructed
MN Temporary Status
07 - Rural - Major CollectorCulvert N
A P P R A I S A L R A T I N G S ++ N B I
Page 7 of 15
County:
City:
Township:
Township:Section: Range:
Span Type:
NBI Deck: Super: Sub: Chan: Culv:
Appraisal Ratings - Approach: Waterway:
Required Bridge Signs - Load Posting:
Horizntal:
Traffic:
Vertical:
MN Scour Code:
Open, Posted, Closed:
Location:
Route:
Control Section:
Local Agency Bridge Nbr.:
Ref. Pt.:
Maint. Area:
Length:
Deck Width:
Rdwy. Area/ Pct. Unsnd:
Paint Area/ Pct. Unsnd:
Culvert:
Crow Wing
Cross Lake
137N17 27W
5 - Prestressed Concrete 2 -Stringer/Multi-beam or Girder
5 7 7 7 N
8 9
0 - Not Required
1 - Object Markers
0 - Not Required
N - Not Applicable
I - LOW RISK
1.2 MI S OF JCT CSAH 66
04 - CSAH 16 012+00.150
124.3
43.6
5005 sq. ft. / %
sq. ft. / %
N/A
A - Open
ft.
ft.
Postings:List:
MINNESOTA BRIDGE INSPECTION REPORT
09/23/2016
Inspector: CO Bridge
BRIDGE 18501 CSAH 16 OVER PINE RIVER
Unofficial Structurally Deficient N
NUnofficial Functionally Obsolete
Unofficial Sufficiency Rating 98.3
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4REPORT TYPE
Prestressed Concrete Top Flange 08/04/2016 5419 SF 5419 0 0 015 Underwater
5419 SF 5419 0 0 0Migrated Values
Notes: [2016] Migrator assumed CS1.
510 - Wearing Surfaces 5005 SF 3754 0 1251 0
Notes: Bituminous Overlay Notes: 11/05/14: The bituminous surface continues to deteriorate w/ small pot holes scattered across the entiredeck in isolated locations. The most prevalent being in the wheel paths and there are potholes 1' to 2' in diameter over the piers. The crackshave been rubber sealed. Cracks in the diving lanes in the bituminous overlay averaging 3' square. Longitudinal cracks over the tee beamseams in the diving lanes. In places the cracks have widened to the point that they are small potholes. There is efflorescence over the piersbetween the beams and at the poured in place diaphragms.11/02/12: The bituminous surface continues to deteriorate w/ small pot holes scattered across the entire deck in isolated locations. The mostprevalent being in the wheel paths. The cracks have been rubber sealed. Cracks in the diving lanes in the bituminous overlay averaging 3'square. Longitudinal cracks over the tee beam seams in the diving lanes. In places the cracks have widened to the point that they are smallpotholes.11/03/10: Bituminous surface is deteriorating w/ impending potholes. All cracks need to be sealed. Cracks in the diving lanes in thebituminous overlay averaging 3' square. Longitudinal cracks over the tee beam seams in the diving lanes. In places the cracks have widenedto the point that they are small potholes.10/13/08: Sealed cracks in the diving lanes in the bituminous overlay averaging 3' square. Longitudinal cracks over the tee beam seams in thediving lanes.10/19/06: Some cracks in bit overlay over the Tee seams, otherwise random in nature and minor.
Underwater 08/04/2016
5005 SF 3754 0 1251 0Migrated Values
Prestressed Concrete OpenGirder/Beam
08/04/2016 4474 LF 0 4474 0 0109 Underwater
4474 LF 0 4474 0 0Migrated Values
Notes: [2016] Migrator estimated the quantity of the quad tees. Verify the quantity by multiplying the number of vertical beams by the decklength.11/05/14: Water is leaking through the deck at the edges of the quad tees throughout the bridge. There is rust staining through out between thebeams and some visible spall in isolated locations beneath the welded plates between the beams.11/02/12: Water is leaking through the deck at the edges of the quad tees throughout the bridge, w/ rust staining at the seams.10/13/08: Some water is leaking through the deck at the seams of the quad tee through out.10/19/06: Some water coming through the seam in the middle of the W span.
Reinforced Concrete Abutment 08/04/2016 132 LF 132 0 0 0215 Underwater
132 LF 132 0 0 0Migrated Values
Notes: [2016] Migrator added 40 LF to abutment quantity to account for wingwalls (CS1:40 CS2:0 CS3:0 CS4:0).11/05/14: Isolated cracking in the abutment and rust staining from water leaking over the bridge seat. There is a crack in the west abutment atapproximately the center of the structure.
Page 8 of 15
Steel Pile 08/04/2016 24 EA 0 24 0 0225 Underwater
24 EA 0 24 0 0Migrated Values
Notes: 11/05/14: Freckled rust above the waterline in isolated locations w/ 10% coating failure. From under water inspection, the piles exhibiteda coating failure covering 15% to 20% of the surface area below the waterline. Associated w/ the coating loss was minor surface corrosion andrust nodules.11/02/12: Above the waterline the total surface area of the piles are showing a coating failure of 5% or less w/ minor surface rust.09/09/12: From under water inspection, the piles exhibited a coating failure covering 15% to 20% of the surface area below the waterline.Associated w/ the coating loss was minor surface corrosion and rust nodules.10/13/08: Some loose paint on all of the piling at the water line w/ some minor surface rust.
515 - Steel Protective Coating 999 SF 999 0 0 0
Notes: [2016] Migrator assumed CS1 and a quantity of 999 SF.
Underwater 08/04/2016
999 SF 999 0 0 0Migrated Values
Reinforced Concrete Pier Cap 08/04/2016 131 LF 131 0 0 0234 Underwater
131 LF 131 0 0 0Migrated Values
Notes: 10/05/14: Rust staining is present from in isolated locations. There is a vertical crack in the west pier above pile #5 visible from the eastside of the pier cap.
Reinforced Concrete Bridge Railing 08/04/2016 249 LF 249 0 0 0331 Underwater
249 LF 249 0 0 0Migrated Values
Notes: 11/03/10: Painted summer 2010.
Critical Deficiencies or Safety Hazards 08/04/2016 1 EA 1 0 0 0800 Underwater
1 EA 1 0 0 0Migrated Values
Notes: No critical structural deficiencies or serious safety hazards are present on this structure.
Bituminous Approach Roadway 08/04/2016 2 EA 0 2 0 0822 Underwater
2 EA 0 2 0 0Migrated Values
Notes: 11/05/14 - 11/02/12: There is some settlement in the approach spans creating some traffic impact to the bridge.10/13/08: W approach has been dura-patched. E Approach has some settlement occurring at the deck transition.10/19/06: E Approach has some settlement occurring at the deck transition.
Concrete Shear Cracking 08/04/2016 1 EA 1 0 0 0883 Underwater
1 EA 1 0 0 0Migrated Values
Notes: Use this element to monitor the presence of shear cracking on concrete elements. Pay particular attention to the concrete pier caps.
Scour 08/04/2016 1 EA 1 0 0 0885 Underwater
1 EA 1 0 0 0Migrated Values
Other Bridge Signing 08/04/2016 1 EA 1 0 0 0891 Underwater
1 EA 1 0 0 0Migrated Values
Notes: 11/05/14: The "Minimum Wake" signing is faded and should be replace.
Slopes & Slope Protection 08/04/2016 1 EA 0 1 0 0892 Underwater
1 EA 0 1 0 0Migrated Values
Notes: 11/05/14 - 10/13/08: 25% of rip rap is missing on the west abutment slope. No significant changes.10/19/06: 25% of rip rap is missing on the west abutment slope.
Guardrail 08/04/2016 1 EA 0 1 0 0893 Underwater
1 EA 0 1 0 0Migrated Values
Notes: 11/05/14: The bridge transition and guardrail at the NE corner has been hit effecting about 75' of rail. Rail is still functional at this time.11/03/10: Missing nut has been replaced, guardrail is good condition and function.10/13/08: Missing nut on 4th post from SW end.10/19/06: Missing nut on 4th post from SW end.
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 18501 CSAH 16 OVER PINE RIVER
REPORT TYPE
Page 9 of 15
Deck & Approach Drainage 08/04/2016 1 EA 1 0 0 0894 Underwater
1 EA 1 0 0 0Migrated Values
Protected Species 08/04/2016 1 EA 1 0 0 0900 Underwater
1 EA 1 0 0 0Migrated Values
Notes: Use this element to track the presence of protected species living on this structure.
General Notes:
Inspector's Signature Reviewer's Signature
Inventory Notes:
11/05/14: Some visible spalling in isolated locations beneath the welded plates between the beams. Some efflorescenceappearing below the "T" beam joins over the piers and at the diaphragms.11/05/14 - 11/02/12: Was able to inspect w/ a boat and walk beneath the approach spans to see elements. Under waterinspection was done fall 2012. There is rust staining between the beams.11/03/10: Was able to inspect w/ a boat but unable to get to the center pier today, water is high, flowing fast, and strong. Noscour is suspect. Was able to wade to the outside piers and see the center span.10/13/08: Was able to inspect w/ a boat and walk under the bridge and see all above water elements. Need to remove smalltrees and brush from around the abutments. Utilities have finished the installation of the new conduit and appears to beproperly anchored as per their proposed permit plan.10/19/06: Was able to inspect with a boat. Need to remove small trees and brush from under the abutments. No Structuralproblems apparent. Utilities are digging at the NW & NE corners of the bridge and have hung a new conduit on the N bridgerailing. Someone also has drilled plastic anchors into the railing and installed eyebolts to hang banners from the bridge.11-01-2004: SLOPE PROTECTION AT ABUTMENTS HAS BEEN VANDALIZED, TO SOME EXTENT, BY REMOVAL OFSOME OF THE ROCKS OF THE SLOPE PROTECTION.09/16/1999: CRACKING OF BITUMINOUS OVERLAY HAS NOT WORSENED.06/06/2016 Underwater Inspection - Collins Engineers
58. Deck NBI:
36A. Brdg Railings NBI:
36B. Transitions NBI:
36C. Appr Guardrail NBI:
36D. Appr GuardrailTerminal NBI:
59. Superstructure NBI:
60. Substructure NBI:
61. Channel NBI:
62. Culvert NBI:
71. Waterway Adeq NBI:
72. Appr RoadwayAlignment NBI:
11/05/14: The bituminous surface continues to deteriorate w/ small pot holes scattered across the entire deck in isolatedlocations. The most prevalent being in the wheel paths and there are potholes 1' to 2' in diameter over the piers. The crackshave been rubber sealed. Cracks in the diving lanes in the bituminous overlay averaging 3' square. Longitudinal cracks overthe tee beam seams in the diving lanes. In places the cracks have widened to the point that they are small potholes. There isefflorescence over the piers between the beams and at the poured in place diaphragms. There is rust staining and somevisible spall in isolated locations beneath the welded plates between the beams.
11/05/14: There is rust staining and some visible spall in isolated locations beneath the welded plates between the beams.
11/05/14: Isolated cracking in the abutment and rust staining from water leaking over the bridge seat. There is a crack in thewest abutment at approximately the center of the structure.
11/05/14: 25% of the rip-rap is missing from the west revetment slope.
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 18501 CSAH 16 OVER PINE RIVER
REPORT TYPE
Page 10 of 15
Photo 1 - North Fascia, Looking Southeast
Photo 2 - South Fascia, Looking Northeast
Pictures
Page 11 of 15
Pictures
Photo 3 - Pier 1, Looking Southeast
Photo 4 - Pier 2, Looking Southwest
Page 12 of 15
Pictures
Photo 5 - Pier 3, Looking Southwest
Page 13 of 15
N
SOUNDING PLAN
UNDERWATER BRIDGE INSPECTION
DEPARTMENT OF TRANSPORTATION
MINNESOTA
INSPECTION AND SOUNDING PLANTYPICAL END VIEW OF PIERS
Shoreline (Typ.)
West Abutment Pier 1 Pier 2 East Abutment Legend
30'-6•" 30'-6•"31'-1" 31'-1"
Pier 3
Flo
w
DISTRICT 3, CROW WING COUNTY
OVER THE PINE RIVER (CROSS LAKE/RUSH LAKE)
STRUCTURE NO. 18501
1
3
2
3 3
1
123 North Wacker Drive
Suite 300
Chicago, Il. 60606
(312) 704-9300
www.collinsengr.com
-5.2
-5.2
Notes:
location.
All soundings based on 2016 waterline
Concrete Pile
Steel Pipe, Cast-in-place
-3.3-7.5-6.5-7.0-6.0
-4.5
-3.9-7.3-7.3-7.0-4.6
-5.1 -7.0 -7.5 -7.4 -4.4
-3.8
-5.6 -8.2 -6.9 -7.9 -4.2
DRAWN BY: BMS
CHECKED BY: DGS
Sounding Depth (6/6/16)
Sounding Depth (9/9/12)
-3.0
N.A.
-8.0
-7.4
-8.0
N.A.
-1.5
-3.7
-4.5
N.A.
substructure units.
4. Soundings were taken parallel to the bridge at mid point intervals between the
in feet.
3. Soundings indicate the water depth at the time of inspection and are measured
was 90.3.
of 100.0 was assumed. Based on the assumed reference the waterline elevation
Since insufficient bridge elevation information was available, a reference elevation
approximately 9.7 feet below the top of the pile cap at the north end of Pier 2.
2. At the time of inspection on June 6, 2016, the waterline was located
1. Piers 1, 2, and 3 were inspected underwater.
GENERAL NOTES:
CODE: 968718501
DATE: JUNE 6, 2016
SCALE: NTS
FIGURE NO.: 1
(Cross Lake/
Rush Lake)
Pin
e
River
with
Riprap
Bank
Concrete Slo
pe
wall
with
Riprap
Bank
Concrete Slo
pe
wall
N
Plan
waterline to the channel bottom.
All piles exhibited a 1 inch thick layer of zebra mussels from 2 feet below the 4
growth from the waterline to 2 feet below the waterline.
surface area below the waterline. Additionally, all piles exhibited a layer of aquatic
The piles exhibited coating failure and related minor corrosion on 15% to 20% of their 3
cobbles allowing no probe rod penetration.
The channel bottom around Pier 2 consisted of gravel, sand, and 4 to 12 inch diameter2
allowing no probe rod penetration.
1 The channel bottom around Piers 1 and 3 consisted of riprap up to 3 feet in diameter
INSPECTION NOTES:
Page 14 of 15
UNDERWATER BRIDGE INSPECTION
DEPARTMENT OF TRANSPORTATION
MINNESOTA
FASCIA PROFILES
Refer to Figure 1 for General Notes.
Note:
NORTH AND SOUTH
30'-6•" 30'-6•"31'-1" 31'-1"
100.0
80.0
100.0
80.0
~ W. Abut. ~ Pier 1 ~ Pier 2 ~ Pier 3 ~ E. Abut.
NORTH FASCIA PROFILE
SOUTH FASCIA PROFILE
30'-6•" 30'-6•"31'-1" 31'-1"
100.0
80.0
100.0
80.0
~ W. Abut. ~ Pier 1 ~ Pier 2 ~ Pier 3 ~ E. Abut.
Shoreline Shoreline
Shoreline Shoreline
DISTRICT 3, CROW WING COUNTY
OVER THE PINE RIVER (CROSS LAKE/RUSH LAKE)
STRUCTURE NO. 18501
123 North Wacker Drive
Suite 300
Chicago, Il. 60606
(312) 704-9300
www.collinsengr.com
W.L. El. 90.3
W.L. El. 90.3
DRAWN BY: BMS
CHECKED BY: DGS
on 9/9/12
Channel Bottom
CODE: 968718501
on 6/6/16
Channel Bottom
on 6/6/16
Channel Bottom
DATE: JUNE 6, 2016
SCALE: 1/16" =1'
FIGURE NO.: 2
60.0 60.0
60.0 60.0
adsfasdf
on 9/9/12
Channel Bottom
Page 15 of 15