free wysiwyg wiki
Deliverables List
Contents
[hide]
1 Process Deliverables List
2 P&ID Stage Process Deliverables
2.1 IFR - Issued for Review (Pre-FEED Stage)
2.2 IFA - Issued for Approval (FEED Stage)
2.3 IFH - Issued for HAZOP (FEED Stage)
2.4 IFD - Issued for Design (Used for Class III Estimate - bids back from vendors/ PO's
issued)
2.5 IFC - Issued For Construction (Class III Estimate will be refined by trends/DCNs
issued to this point)
2.5.1 Documents to check or update
2.5.2 Calculations to complete and sign by checker
2.6 Re-IFC - Re-Issued For Construction (Post Construction / Commisioning)
[edit] Process Deliverables List
A process deliverables list should have the following columns:
Priority - This is to assign priorities to those responsible
Plant Area - The area of responsibility of the process lead.
Subject Name -
Action Description -
Responsible Engineer - Lists one person that is primarily responsible for that deliverable
Checker Engineer - List one person that is primarily responsible for checking that deliverable
Forecase Date - Date from the project overall schedule from PM.
Scheduled Date - The date that the responsible engineer and checker are required to complete
the deliverable.
Completed Date
Original Manhours - From the project overall schedule from PM
Forecast Manhours - The time that the responsible engineer and checking engineer can use to
complete deliverable.
Submitted For Review - Date when the calculation is submitted to checking
Review Completed - When the calculation is fully signed off by all and filed
Comments - Insert here any needs and risks to not complete the deliverable & if the deliverable
is "in progress" or "pending information - x".
[edit] P&ID Stage Process Deliverables
Note 1: Issuing HOLDS: This is an outline of all of the deliverables which must be completed in order to
support the P&ID issue. If any of these supporting documents have not been done then it is preferable
to put the information related to this deliverable on HOLD on the P&IDs to indicate that this information
has not been confirmed for this issue.
Note 2: Use personal master copy of P&IDs and Line List. Updated stick file with changes as soon as they
are approved through change management (it is worthwhile to have a clean, blank copy to make copies
from as well). A review meeting with Area Leads should be performed weekly or bi-weekly to discuss
major changes and update the P&IDs. This allows everyone to be prompted to communicate their
changes to the P&IDs before the last day prior to freezing them for the next issue.
Note 3: When using smart P&IDs or Line List, an electronic copy of each must be sent to the data base
manager for update to keep current.
[edit] IFR - Issued for Review (Pre-FEED Stage)
IFA Simulation
IFA PFDs (Process Flow Diagrams)
IFA Material Balances
IFA Design Basis
IFA Equipment List
[edit] IFA - Issued for Approval (FEED Stage)
Incorporate all IFR input from previous reviews
IFD Simulation
IFD PFD
IFD Material Balances / Water Balances
IFD Specifications
IFD Material Diagram
IFD Operating/Design Temperature/Pressure Diagram
IFD Design Basis
IFA Tank Sizing Summary
IFA Vessel Sizing Calculations
IFA Chemical Injection Summary
IFA Utilities Balances (FG, IA/UA, Steam, Vapour Recovery, Glycol)
IFA Pump and Compressor Hydraulics based on plot plan
IFA PSV, vendor PSV and PVSV hydraulics based on plot plan
IFA Line Sizing Summary
IFA System & Tank Transient Analysis
IFA Instrument Sizing Calculations
IFA SP Item Preliminary Sizing Calc Sheets
RFQ Data Sheets issued to mechanical from process
IFA design basis for future connections
IFA MSDS documents
IFA Line List (issued with IFA P&IDs)
IFA Control Philosophies
IFA Shutdown Keys
IFA Tie-in List
IFA Car Sealed Valves List
[edit] IFH - Issued for HAZOP (FEED Stage)
Incorporate all IFA input from previous reviews.
Update all IFA P&ID documents with comments and re-issue IFD or IFA.
Perform own pre-HAZOP review by lead or area lead for HAZOP questions.
Create Project Change Notices (PCNs) or Design Change Notices (DCNs) for fundamental design
basis changes.
IFH Line List (Issued with IFH P&IDs)
[edit] IFD - Issued for Design (Used for Class III Estimate - bids back from vendors/ PO's issued)
IFD Simulation Stick File
IFD PFD Stick File
IFD Material Balances / Water Balances Stick File
IFD Specifications Stick File
IFD Material Diagram Stick File
IFD Operating/Design Temperature/Pressure Diagram Stick File
IFD Design Basis Stick File
Incorporate all DCNs, Trends, Client Queries - see the Change Management Log.
Incorporate all client comments - see the Client Comments Log.
Incorporate all input from HAZOP review - Check HAZOP binder complete and signed off by
client.
RFPs for all equipment signed off and sent to vendor - (HOLD all pieces without RFP signed-off &
sent to vendor & based on IFD calculation).
IFD Tank Sizing Summary
IFD Vessel Sizing Calculations
IFD Chemical Injection Summary
IFD Utilities Balances (FG, IA/UA, Steam, Vapour Recovery, Glycol)
IFD Pump and Compressor Hydraulics based on preliminary/stress isometrics/piping study
model
IFD PSV, vendor PSV and PVSV based on preliminary/stress isometrics/piping study model with
client sign-off
IFD PSV Relief Summary with client sign-off.
IFD Line Sizing Summary - based on pump/compressor/PSV hydraulic calcs or separate line sizing
calculations.
IFD System & Tank Transient Analysis
IFD Instrument Sizing Calculations based on preliminary isometrics/piping study model with
client sign-off.
IFD SP Item Preliminary Sizing Calc Sheets
RFP Data Sheets issued to mechanical from process
RFQ SP Item Data Sheets issued to mechanical from process
RFP Instrument Data Sheets issued to instrumentation from process
IFD design basis for future connections
IFD MSDS documents collected with corrosion/material considerations.
IFD Line List (issued with IFD P&IDs)
IFD Control Philosophies
IFD Shutdown Keys
10% study model review & comments
IFA Operating Manual
[edit] IFC - Issued For Construction (Class III Estimate will be refined by trends/DCNs issued to this
point)
[edit] Documents to check or update
Check existing revisions of the same drawings for which drawing to issue - update drawing list.
Vendor Information & Drawings recieved matches all of the following (note that this is vendor
information that has been recieved from the vendor regardless of the code of the drawings that
have gone back) - keep a copy of all of the checked drawings in Process Refs Folder (scan).
IFD Simulation Stick File Updated
IFD PFD Stick File Updated
IFD Material Balances / Water Balances Stick File Updated
IFD Specifications Stick File Updated
IFD Material Diagram Stick File Updated
IFD Operating/Design Temperature/Pressure Diagram Stick File Updated
IFD Design Basis Stick File Updated
Incorporate all DCNs, Trends, Client Queries - see the Change Management Log.
Incorporate all client comments - see the Client Comments Log.
Incorporate all input from HAZOP review - Check HAZOP binder complete and signed off by
client.
HAZOP binder complete, signed by process and signed by client - create HAZOP binder with
recommendations section, parking lot section, HAZOP details and resolutions sections.
RFPs for all equipment signed off and sent to vendor - (HOLD all pieces without RFP signed-off &
sent to vendor & based on IFD calculation). - keep checked drawing (as basis) electronically in
the Process Refs folder by tag# along with other correspondance.
RFP Data Sheets issued to mechanical from process - keep copy (scan) sent to mechanical in
Process Refs folder as basis of P&IDs.
RFP Instrument Data Sheets issued to instrumentation from process - keep copy (hard copy in a
binder) by tag# sent to mechanical in Process Refs folder as basis of P&IDs (scan whole thing
when done).
RFQ SP Item Data Sheets issued to mechanical from process - keep copy (scan) sent to
mechanical in Process Refs folder as basis of P&IDs.
IFD design basis for future connections
IFD MSDS documents collected with corrosion/material considerations.
IFC Line List (issued with IFC P&IDs)
IFD Control Philosophies & SDK/Control Philosophy Review comments incorporated - stored in a
section of the control philosophy/SDK binder/folder.
IFD Shutdown Key & SDK/Control Philosophy Review Meeting comments incorporated - stored
in a section of the control philosophy/SDK binder/folder.
IFD Tie-in List
Issued for Demolition Drawings issued.
IFC Tie-in P&IDs issued prior to IFC issue.
IFD Car Sealed Valves List
30% model review comments
IFD Operating Manual
[edit] Calculations to complete and sign by checker
Keep Calculation Log - contains file number/location, calc. number, revision and revision date, status (ie.
"In progress (initials of responsibility)" or "With checking (initials)"), due date (matches deliverables list).
IFC Tank Sizing Summary complete and signed as checked
IFC Vessel Sizing Calculations complete and signed as checked
IFC Chemical Injection Summary complete and signed as checked
IFC Utilities Balances (FG, IA/UA, Steam, Vapour Recovery, Glycol) complete and signed as
checked
IFC Pump and Compressor Hydraulics based on final isometrics/piping model, pump sales or
test curve complete and signed as checked
IFC PSV, vendor PSV and PVSV based on final isometrics/piping model and vendor
informaiton/drawings with client sign-off
IFC PSV Relief Summary with client sign-off.
IFC Line Sizing Summary - based on pump/compressor/PSV hydraulic calcs or separate line sizing
calculations complete and signed as checked.
IFC System & Tank Transient Analysis complete and signed as checked
IFC Instrument Sizing Calculations based on final isometrics/piping model; complete and signed
as checked.
IFD SP Item Final Sizing Calc Sheets complete and signed as checked
[edit] Re-IFC - Re-Issued For Construction (Post Construction / Commisioning)
IFC Operating Manual
As-Built Data Sheets (Equipment, Packages, Instrumentation, SP-Items) signed by process and
sent to mechanical/instrumentation.
Data Books (Equipment, Packages, Instrumentation, SP-Items) signed-off by process.
Re-Issue all other documents, calculations, etc. that have changed
Top Related