    Deliverables List

    Contents

    [hide]

    1 Process Deliverables List

    2 P&ID Stage Process Deliverables

    2.1 IFR - Issued for Review (Pre-FEED Stage)

    2.2 IFA - Issued for Approval (FEED Stage)

    2.3 IFH - Issued for HAZOP (FEED Stage)

    2.4 IFD - Issued for Design (Used for Class III Estimate - bids back from vendors/ PO's

    issued)

    2.5 IFC - Issued For Construction (Class III Estimate will be refined by trends/DCNs

    issued to this point)

    2.5.1 Documents to check or update

    2.5.2 Calculations to complete and sign by checker

    2.6 Re-IFC - Re-Issued For Construction (Post Construction / Commisioning)

    [edit] Process Deliverables List

    A process deliverables list should have the following columns:

    Priority - This is to assign priorities to those responsible

    Plant Area - The area of responsibility of the process lead.

    Subject Name -

    Action Description -

    Responsible Engineer - Lists one person that is primarily responsible for that deliverable

    Checker Engineer - List one person that is primarily responsible for checking that deliverable

    Forecase Date - Date from the project overall schedule from PM.

  • Scheduled Date - The date that the responsible engineer and checker are required to complete

    the deliverable.

    Completed Date

    Original Manhours - From the project overall schedule from PM

    Forecast Manhours - The time that the responsible engineer and checking engineer can use to

    complete deliverable.

    Submitted For Review - Date when the calculation is submitted to checking

    Review Completed - When the calculation is fully signed off by all and filed

    Comments - Insert here any needs and risks to not complete the deliverable & if the deliverable

    is "in progress" or "pending information - x".

    [edit] P&ID Stage Process Deliverables

    Note 1: Issuing HOLDS: This is an outline of all of the deliverables which must be completed in order to

    support the P&ID issue. If any of these supporting documents have not been done then it is preferable

    to put the information related to this deliverable on HOLD on the P&IDs to indicate that this information

    has not been confirmed for this issue.

    Note 2: Use personal master copy of P&IDs and Line List. Updated stick file with changes as soon as they

    are approved through change management (it is worthwhile to have a clean, blank copy to make copies

    from as well). A review meeting with Area Leads should be performed weekly or bi-weekly to discuss

    major changes and update the P&IDs. This allows everyone to be prompted to communicate their

    changes to the P&IDs before the last day prior to freezing them for the next issue.

    Note 3: When using smart P&IDs or Line List, an electronic copy of each must be sent to the data base

    manager for update to keep current.

    [edit] IFR - Issued for Review (Pre-FEED Stage)

    IFA Simulation

    IFA PFDs (Process Flow Diagrams)

    IFA Material Balances

    IFA Design Basis

    IFA Equipment List

    [edit] IFA - Issued for Approval (FEED Stage)

    Incorporate all IFR input from previous reviews

  • IFD Simulation

    IFD PFD

    IFD Material Balances / Water Balances

    IFD Specifications

    IFD Material Diagram

    IFD Operating/Design Temperature/Pressure Diagram

    IFD Design Basis

    IFA Tank Sizing Summary

    IFA Vessel Sizing Calculations

    IFA Chemical Injection Summary

    IFA Utilities Balances (FG, IA/UA, Steam, Vapour Recovery, Glycol)

    IFA Pump and Compressor Hydraulics based on plot plan

    IFA PSV, vendor PSV and PVSV hydraulics based on plot plan

    IFA Line Sizing Summary

    IFA System & Tank Transient Analysis

    IFA Instrument Sizing Calculations

    IFA SP Item Preliminary Sizing Calc Sheets

    RFQ Data Sheets issued to mechanical from process

    IFA design basis for future connections

    IFA MSDS documents

    IFA Line List (issued with IFA P&IDs)

    IFA Control Philosophies

    IFA Shutdown Keys

    IFA Tie-in List

    IFA Car Sealed Valves List

  • [edit] IFH - Issued for HAZOP (FEED Stage)

    Incorporate all IFA input from previous reviews.

    Update all IFA P&ID documents with comments and re-issue IFD or IFA.

    Perform own pre-HAZOP review by lead or area lead for HAZOP questions.

    Create Project Change Notices (PCNs) or Design Change Notices (DCNs) for fundamental design

    basis changes.

    IFH Line List (Issued with IFH P&IDs)

    [edit] IFD - Issued for Design (Used for Class III Estimate - bids back from vendors/ PO's issued)

    IFD Simulation Stick File

    IFD PFD Stick File

    IFD Material Balances / Water Balances Stick File

    IFD Specifications Stick File

    IFD Material Diagram Stick File

    IFD Operating/Design Temperature/Pressure Diagram Stick File

    IFD Design Basis Stick File

    Incorporate all DCNs, Trends, Client Queries - see the Change Management Log.

    Incorporate all client comments - see the Client Comments Log.

    Incorporate all input from HAZOP review - Check HAZOP binder complete and signed off by

    client.

    RFPs for all equipment signed off and sent to vendor - (HOLD all pieces without RFP signed-off &

    sent to vendor & based on IFD calculation).

    IFD Tank Sizing Summary

    IFD Vessel Sizing Calculations

    IFD Chemical Injection Summary

    IFD Utilities Balances (FG, IA/UA, Steam, Vapour Recovery, Glycol)

    IFD Pump and Compressor Hydraulics based on preliminary/stress isometrics/piping study

    model

  • IFD PSV, vendor PSV and PVSV based on preliminary/stress isometrics/piping study model with

    client sign-off

    IFD PSV Relief Summary with client sign-off.

    IFD Line Sizing Summary - based on pump/compressor/PSV hydraulic calcs or separate line sizing

    calculations.

    IFD System & Tank Transient Analysis

    IFD Instrument Sizing Calculations based on preliminary isometrics/piping study model with

    client sign-off.

    IFD SP Item Preliminary Sizing Calc Sheets

    RFP Data Sheets issued to mechanical from process

    RFQ SP Item Data Sheets issued to mechanical from process

    RFP Instrument Data Sheets issued to instrumentation from process

    IFD design basis for future connections

    IFD MSDS documents collected with corrosion/material considerations.

    IFD Line List (issued with IFD P&IDs)

    IFD Control Philosophies

    IFD Shutdown Keys

    10% study model review & comments

    IFA Operating Manual

    [edit] IFC - Issued For Construction (Class III Estimate will be refined by trends/DCNs issued to this

    point)

    [edit] Documents to check or update

    Check existing revisions of the same drawings for which drawing to issue - update drawing list.

    Vendor Information & Drawings recieved matches all of the following (note that this is vendor

    information that has been recieved from the vendor regardless of the code of the drawings that

    have gone back) - keep a copy of all of the checked drawings in Process Refs Folder (scan).

    IFD Simulation Stick File Updated

    IFD PFD Stick File Updated

  • IFD Material Balances / Water Balances Stick File Updated

    IFD Specifications Stick File Updated

    IFD Material Diagram Stick File Updated

    IFD Operating/Design Temperature/Pressure Diagram Stick File Updated

    IFD Design Basis Stick File Updated

    Incorporate all DCNs, Trends, Client Queries - see the Change Management Log.

    Incorporate all client comments - see the Client Comments Log.

    Incorporate all input from HAZOP review - Check HAZOP binder complete and signed off by

    client.

    HAZOP binder complete, signed by process and signed by client - create HAZOP binder with

    recommendations section, parking lot section, HAZOP details and resolutions sections.

    RFPs for all equipment signed off and sent to vendor - (HOLD all pieces without RFP signed-off &

    sent to vendor & based on IFD calculation). - keep checked drawing (as basis) electronically in

    the Process Refs folder by tag# along with other correspondance.

    RFP Data Sheets issued to mechanical from process - keep copy (scan) sent to mechanical in

    Process Refs folder as basis of P&IDs.

    RFP Instrument Data Sheets issued to instrumentation from process - keep copy (hard copy in a

    binder) by tag# sent to mechanical in Process Refs folder as basis of P&IDs (scan whole thing

    when done).

    RFQ SP Item Data Sheets issued to mechanical from process - keep copy (scan) sent to

    mechanical in Process Refs folder as basis of P&IDs.

    IFD design basis for future connections

    IFD MSDS documents collected with corrosion/material considerations.

    IFC Line List (issued with IFC P&IDs)

    IFD Control Philosophies & SDK/Control Philosophy Review comments incorporated - stored in a

    section of the control philosophy/SDK binder/folder.

    IFD Shutdown Key & SDK/Control Philosophy Review Meeting comments incorporated - stored

    in a section of the control philosophy/SDK binder/folder.

    IFD Tie-in List

  • Issued for Demolition Drawings issued.

    IFC Tie-in P&IDs issued prior to IFC issue.

    IFD Car Sealed Valves List

    30% model review comments

    IFD Operating Manual

    [edit] Calculations to complete and sign by checker

    Keep Calculation Log - contains file number/location, calc. number, revision and revision date, status (ie.

    "In progress (initials of responsibility)" or "With checking (initials)"), due date (matches deliverables list).

    IFC Tank Sizing Summary complete and signed as checked

    IFC Vessel Sizing Calculations complete and signed as checked

    IFC Chemical Injection Summary complete and signed as checked

    IFC Utilities Balances (FG, IA/UA, Steam, Vapour Recovery, Glycol) complete and signed as

    checked

    IFC Pump and Compressor Hydraulics based on final isometrics/piping model, pump sales or

    test curve complete and signed as checked

    IFC PSV, vendor PSV and PVSV based on final isometrics/piping model and vendor

    informaiton/drawings with client sign-off

    IFC PSV Relief Summary with client sign-off.

    IFC Line Sizing Summary - based on pump/compressor/PSV hydraulic calcs or separate line sizing

    calculations complete and signed as checked.

    IFC System & Tank Transient Analysis complete and signed as checked

    IFC Instrument Sizing Calculations based on final isometrics/piping model; complete and signed

    as checked.

    IFD SP Item Final Sizing Calc Sheets complete and signed as checked

    [edit] Re-IFC - Re-Issued For Construction (Post Construction / Commisioning)

    IFC Operating Manual

    As-Built Data Sheets (Equipment, Packages, Instrumentation, SP-Items) signed by process and

    sent to mechanical/instrumentation.

  • Data Books (Equipment, Packages, Instrumentation, SP-Items) signed-off by process.

    Re-Issue all other documents, calculations, etc. that have changed