ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

15
ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT

Transcript of ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

Page 1: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

ZEKERİYA ERKANTÜRK TELEKOM OPERATION

DEPARTMENT

Page 2: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

CHANGES ?

Page 3: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

CHANGES BEFORE AFTER

Topology Central Distrubuted

Media copper Fiber

Power Not needed Needed

Air-conditioning Not needed Needed

Eqt. Quantity As needed (x) High (20 to 30 X *)

* : For TT Case

Change details

Page 4: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

CHANGES BEFORE AFTER

Service types Limited Multiple

Complexity Low High

Operation Easy Diffucult

Human Resources-Headcount Qualification

Low High

Change details

Page 5: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

• Depending on the type of area, income level, topology and conditions of competition, FTTH, FTTB or FTTC solutions are implemented.

FTTC

Secondary Cable(copper)≤ 250 mt

FTTB

F/O

F/O

F/O

F/O

F/O

F/OFTTH

•CENTRAL OFFICE TO STREET CABINET THROUGH FIBER CABLE•STREET CABINET TO THE CUSTOMER THROUGH SECONDARY(COPPER) CABLE (MAX:250 mt)

•FIBER REACHES THE BOUNDARY OF THE BUILDING, SUCH AS THE BASEMENT IN A MULTI-DWELLING UNIT, WITH THE FINAL CONNECTION TO THE INDIVIDUAL LIVING SPACE BY CAT-6 (COPPER CABLE)

• FIBER REACHES THE BOUNDARY OF LIVING SPACE

SPLITTER

ONT

FIBER BUILT-IN CABLING

CAT-6 BUILT-IN CABLING

FTTH Selected greenfield areas, industrialized areas

FTTB Existing customers, business areas, high income residences, etc.

FTTC Locations where rapid transformation is required and use of local cable is feasible

Deployment Model

Page 6: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

Cabinet Types Application PSTN Ports DSL Ports Total Power consumption(w)

Battery- Back up time(hrs)

Type A FTTC 1472 896 2368 1000 6-8

Type B FTTC 960 216 1176 500 6-10

Type C FTTC 960 768 1728 700 7-10

Type D FTTC 192 72 264 100 8-12

Type E FTTB 64 48 112 70 3-6

Type F FTTB 24 24 30 1,5 - 3

FTTX SPECIFICATIONS

Page 7: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-EARTHQUAKE

Scenerio 1 : Earthquake on large FTTX deployed area

Assumptions

Main Telecom buildings are not damagedAC Mains is off Aftershocks are expecting Collapsed or Destroyed;

BuildingsTelecom İnfrastructure (Ducts, Pipes, Cables, Equipments …)

High amount of incoming voice and Data traffic towards Disaster area Goverment agenciesRelief agenciesPress agencies………

Page 8: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-EARTHQUAKE

RESULTS

Telecom infrastructure destroyed and out of service

There is no way to quickly recover infrastructure and provide service other than Mobile capabilities.

Page 9: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

EFFECT OF EARTQUAKE

Page 10: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

EFFECT OF EARTQUAKE

Page 11: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-EARTHQUAKE

Scenerio 2 : Earthquake on large FTTX deployed area

Main Telecom buildings are not damagedAC Mains is off Aftershocks are expectingSome buildings collapsed destroyed others undamagedTelecom infrastructure (Ducts, Pipes, Cables, Equipments …) partially destroyed in some areas but still big portion un damagedHigh amount of incoming voice and Data traffic towards

Disaster area Goverment agenciesRelief agenciesPress agencies………

Page 12: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-EARTHQUAKE

RESULTS

Telecom infrastructure destroyed and out of service in some areasBig Part of Network in good condition and works

But still there is risk to loose all services

Since Mains off, Fuel is running out, Battery back up times are exceeding

How we can maintain services ?

Page 13: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-EARTHQUAKE

Page 14: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-FLOODING

Page 15: ZEKERİYA ERKAN TÜRK TELEKOM OPERATION DEPARTMENT.

DISASTER-EARTHQUAKE

Fiber cables more sensible pressure than copper cables

Ring or mesh topoloji critical for FTTC cabinets

Power shortage is very criticalSpare FTTX equipment or boards and

batteriesFireMore network people to diagnose problems

and put equipments in service