Transcript of Www.ribaplanofwork.com RIBA Plan of Work 2013. The RIBA Plan of Work 2013: an overview John Orrell...
www.ribaplanofwork.com
RIBA Plan ofWork 2013
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
John Orrell
DLA Design - Group Board Director
Immediate past Chair RIBA Yorkshire
RIBA Core Review Group P o W
Member BIM4FM and BSI FM Committee
FAME Conference
27th June 2014
Merchant Adventurers Hall
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
1. What are the key benefits?
2. Why now?
3. How was it developed?
4. What is new?
5. What does itmean for users?
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
Design process diagram by Eva Jiricna – a Plan of Work?
www.ribaplanofwork.com
What is the RIBA Plan of Work 2013?
“The RIBA Plan of Work 2013 organises the process of briefing, designing, constructing, maintaining, operating and using building projects into eight Work Stages”
• It is not a schedule of services document
• It is not intended to be contractual
… but it does set the scene
www.ribaplanofwork.com
Landscape relating to the Plan of Work
• Complexcontract cartography
• Constantly changing
www.ribaplanofwork.com
RIBA Plan of Work 2013: Key benefits
• Fit for purpose for the construction industry in the 21st century to help deliver capital and operational efficiencies, carbon reductions and better briefing and outcomes
• More efficient design processes
• Suitable for all size and type of project
• Suitable for all procurement routes
• For use by the whole project team
• Simple
• Adaptable
• Online tool
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
1. What are the key benefits?
2. Why now?
3. How was it developed?
4. What is new?
5. What does it meanfor users?
www.ribaplanofwork.com
The RIBA Plan of Work 2013: BIM Overlay May 2012
www.ribaplanofwork.com
The RIBA Plan of Work 2013: BIM Overlay May 2012
www.ribaplanofwork.com
RIBA Plan of Work: History
501967 revised
1973 revised
1998 revised
2007 revised
2013 new plan
1963Plan of Work for Design Team Operations
www.ribaplanofwork.com
1963
www.ribaplanofwork.com
RIBA Plan of Work: The Original
www.ribaplanofwork.com
RIBA Outline Plan of Work 2007STRENGTHS
• Simplicity
• Stages A – D clearly understoodWEAKNESSES
• Simplicity
• Stages E and F loosely defined
• Traditional procurement bias
• Planning not embedded
• Soft landings/whole life cycleemphasis not included
• Performance specified work not covered
www.ribaplanofwork.com
RIBA Plan of Work: Why make changes?
To reflect the increasingly complex constructionlandscape including:
• UK Government Construction Strategy
• Changing procurement processes
• Need for earlier collaboration and project team assembly
• Importance of client briefing
• Importance of handover and post occupancy work
• Increasing use of information management including BIM
• Complexity of design stages including specialistsubcontractor design
• approach to town planning
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
1. What are the key benefits?
2. Why now?
3. How was it developed?
4. What is new?
5. What does it meanfor users?
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
Continuing dialogue with construction
industry
BIMOverlay
RIBAmembers
consultation
GreenOverlay
CPD & furtherIndustry
Engagement
May Aug Oct
2012 2013 2014Feb 21 May
UK Government Digital Plan
of Work
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
1. What are the key benefits?
2. Why now?
3. How was it developed?
4. What is new?
5. What does it meanfor users?
www.ribaplanofwork.com
RIBA Plan of Work 2013: core components
• Eight Stages & Eight Task Bars
• Simplicity retained, Flexibility added
• Maps to Government’s Digital Plan of Work
• New topics included
• Defined terms & project strategies
www.ribaplanofwork.com
RIBA Plan of Work 2013: Eight Task Bars
Each task baris either:
Eigh
t Tas
k Ba
rs • Fixed or• Variable or • Switchable
www.ribaplanofwork.com
RIBA Plan of Work 2013 includes:
• Procurement options
• Design Responsibility
• Planning Application options
• Design Team to Project Team
• Whole Life / Sustainability
• Intelligent Briefing / Project Outcomes
• Soft Landings / Project Handover
• Information Exchanges
• Health & Safety
www.ribaplanofwork.com
RIBA Plan of Work 2013: Mapping
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 0 Core Objectives
Identify client’sBusiness Case andStrategic Brief andother core project requirements.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 1 Core Objectives
Develop Project Objectives including Quality Objectives and Project Outcomes, Sustainability Aspirations, Project Budget, other parameters or constraints and develop Initial Project Brief. Undertake Feasibility Studies and review of Site Information.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 1 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 1 Core Objectives
Point Cloud
Laser Scanner
Built-in Camera
Existing Building
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 1 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 1 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 1 Core Objectives
512 Trees in 33 minutes
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 2 Core Objectives
Prepare Concept Design, including outline proposals for structural design, building services systems, outline specifications and preliminary Cost Information along with relevant Project Strategies in accordance with Design Programme. Agree alterations to brief and issue Final Project Brief.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 2 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 2 Core ObjectivesOp1: Detached Op2: Semi-Detached Op3: Terrace Op4: Block
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 3 Core Objectives
Prepare Developed Design, including coordinated and updated proposals for structural design, building services systems, outline specifications, Cost Information and Project Strategies in accordance with Design Programme.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 3 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 3 Core Objectives
Architectural
Structural
MEP
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 3 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 3 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 4 Core Objectives
Prepare Technical Design in accordance with Design Responsibility Matrix and Project Strategies to include all architectural, structural and building services information, specialist subcontractor design and specifications, in accordance with Design Programme.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 4 Core Objectives
Example highlighting the insulated wall panel quantities in both model and schedule
Auto take off from 3D (Vico).
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 4 Core Objectives
Generate all steelwork quantities from the Engineer’s Revit structural model. Westok beams highlighted.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 4 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 4 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
Offsite manufacturing and onsite Constructionin accordance with Construction Programme and resolution of Design Queries from site asthey arise.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
Un-coordinated Services
Optimised Design? Building Fresh Air!
Main Feature Bridge link– Slender?
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 5 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 6 Core Objectives
Handover of buildingand conclusion of Building Contract.Inspection of defects as they are rectified.Production of certification required by the Building Contract.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 6 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 6 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 6 Core Objectives
www.ribaplanofwork.com
RIBA Plan of Work 2013: Stage 7 Core Objectives
Undertake In Use servicesin accordance with Schedule of Services.Acknowledges the potential benefits of harnessing the project design information to assist with the successful operation and use of a building.Post Occupancy Evaluation – back to the new Stage 0.
www.ribaplanofwork.com
RIBA Plan of Work 2013: Procurement Task Bar
www.ribaplanofwork.com
RIBA Plan of Work 2013: Procurement Options available when generating a practice or project specific Plan of Work
www.ribaplanofwork.com
RIBA Plan of Work 2013: Programme Task Bar
www.ribaplanofwork.com
RIBA Plan of Work 2013: Programme Options available when generatinga practice or project specific Plan of Work
www.ribaplanofwork.com
RIBA Plan of Work 2013: (Town) Planning Task Bar
www.ribaplanofwork.com
RIBA Plan of Work 2013: Planning Options available when generatinga practice or project specific Plan of Work
www.ribaplanofwork.com
RIBA Plan of Work 2013: The template
www.ribaplanofwork.com
The RIBA Plan of Work 2013: an overview
1. What are the key benefits?
2. Why now?
3. How was it developed?
4. What is new?
5. What does it meanfor users?
www.ribaplanofwork.com
RIBA Plan of Work 2013: how to use it
• Online tool
• www.ribaplanofwork.com
• Customise a practice, or project, specific RIBAPlan of Work 2013
• Free to use
• Available now Practice Project
Template
www.ribaplanofwork.com
RIBA Plan of Work 2013: Building a continuous cycle of improvement
• Start at the end
• Defining outcomes
• Making early decisionson handover strategy
• Using post occupancy evaluation
• Learning from completed projects
• Additional servicesprovided in Stages0 and 7
www.ribaplanofwork.com
RIBA Plan of Work 2013: Supporting publications
• RIBA Plan of Work 2013 Overview - free publication including: - Glossary of terms- Frequently Asked Questions- Hard copy & pdf available via www.ribaplanofwork.com
• Guide to using the RIBA Plan of Work 2013
• Assembling the Collaborative Project Team
• RIBA Job Book
• RIBA Agreements: alternative schedules of services
• Other documents will continue to be updated
• See www.ribabookshops.com/plan-of-workfor more information & offers
www.ribaplanofwork.com
RIBA Plan of Work 2013: What does it mean for users?
• Fit for purpose for the construction industry in the 21st century to help deliver capital and operational efficiencies, carbon reductions and better briefing
• More efficient design processes
• Suitable for all size and type of project
• Suitable for all procurement routes
• For use by the whole project team
• Simple
• Adaptable
• Online tool
www.ribaplanofwork.com
RIBA Plan of Work 2013: Online Tool
www.ribaplanofwork.com
Thank you for listeningAny questions?