Www.energy.gov/EM 1 Decontamination, Deactivation, and Demolition David S. Rhodes Acquisition...
-
Upload
maleah-rollin -
Category
Documents
-
view
220 -
download
0
Transcript of Www.energy.gov/EM 1 Decontamination, Deactivation, and Demolition David S. Rhodes Acquisition...
www.energy.gov/EM 1
Decontamination, Deactivation, and Demolition
David S. RhodesAcquisition Integrated Project Team Chair
Environmental Management Los Alamos Field Office
March 3, 2015
www.energy.gov/EM 2
Framework for DD&D
Decontamination and Deactivation• Some Technical Area (TA) 21 facilities have been adequately surveyed to allow
demolition debris disposal, while building 257 requires some decontamination and equipment removal
• TA-54 Material disposal Areas –L and –G facilities are in use and decontamination and deactivation needs cannot currently be assessed
Demolition• None of the facilities have reuse potential• All of the facilities have to be removed to allow remediation of subsurface
contaminants or solid waste management units • DD&D is not specifically addressed in Compliance Order on Consent with the
State of New Mexico, however, remediation of sites around and beneath facilities are in Consent Order
• Most facility demolition will fall under DOE’s radiological regulatory authority instead of the State of New Mexico’s hazardous waste regulatory authority
www.energy.gov/EM 3
Three Distinct Areas
Technical Area 21• Small items in-progress such as Warehouse and Sanitary Waste Water Facility• Radiological Liquid Waste Facility
o Basements with tanks insideo Structure collapsing (roof had to be repaired to keep rain out)
• DP West Slabs and contaminated soils beneatho Through slab characterization needed of soilso Soils sampling to depth outside foundation
• Buried waste lines between remaining facilitieso ARRA project did very similar scope three years ago
• Timing is generally open-ended with no long-term programmatic linkageso Timing is determined on available funding and priority relative to other worko Window of opportunity is FY2016 through FY2019
www.energy.gov/EM 4
TA-21 View of Facilities
www.energy.gov/EM 5
Three Distinct Areas
TA-54 MDA-L• Five facilities with slabs and substantial structures• Equipment slabs, carports, and laydown areas• MDA-L area is covered by asphalt
o Well and borehole heads located within the covered area are accessed through man-hole type ports
• Facilities and asphalt are not at consistent elevations with more than a 30-ft change over 400-ft length
• Timing for MDA-L demolition is flexibleo Timing is determined on available funding and priority relative to other worko Wait for completion of soil-vapor extraction, yet not impact operations at MDA-G
www.energy.gov/EM 6
MDA-L Facilities
www.energy.gov/EM 7
Three Distinct Areas
TA-54 MDA-G• Several hard-walled facilities• Dozen steel-framed and fabric-covered domes on concrete slabs
o Several domes have TRU waste processing lines within them• Ancillary support structures• Concrete RCRA pads that are regulated units• Issues
o Current TRU operations utilize the facilitieso RCRA Closures must be coordinated with all permittees (including NNSA)
EM contractors will remove materials from RCRA pads before closure and demolish the pads after closure
EM contractors will integrate/coordinate planning and execution of closureso Timing of demolition requires a high-degree of coordination and phasing as MDA-G
TRU operations complete – no earlier than FY2022 and likely complete by FY2032
www.energy.gov/EM 8
MDA-G Aerial View of FacilitiesMDA-G Aerial View of Facilities
www.energy.gov/EM 9
Dome 231 Box Line & Dome 375 Permacon