WSUProjectCharter-v10

download WSUProjectCharter-v10

of 30

Transcript of WSUProjectCharter-v10

  • 8/3/2019 WSUProjectCharter-v10

    1/30

    Washington State University

    Student Information Systems Project

    Project Charter

    Revised: November 22, 2010

  • 8/3/2019 WSUProjectCharter-v10

    2/30

    Table of Contents

    Version Control ............................................................................................................................................. 1

    Foundation and Background ......................................................................................................................... 2

    Executive Statement ................................................................................................................................. 2

    Accreditation and Leadership Statement ................................................................................................. 2

    Problem Statement ................................................................................................................................... 2

    Purpose of the Project Charter ................................................................................................................. 4

    Project Vision ............................................................................................................................................ 4

    Mission ...................................................................................................................................................... 4

    Goals, Critical Success Factors and Success Criteria ................................................................................. 4Project Scope ................................................................................................................................................ 7

    In Scope Items ........................................................................................................................................... 7

    Out of Scope Items .................................................................................................................................... 8

    Approach ....................................................................................................................................................... 8

    Project Sequence ...................................................................................................................................... 8

    Customizations ........................................................................................................................................ 10

    Conversion ................................................................................................................................................ 9

    Testing ....................................................................................................................................................... 9

    Training ................................................................................................................................................... 12

    Reporting ................................................................................................................................................ 10

    Security ................................................................................................................................................... 11

    End User Acceptance .............................................................................................................................. 11

    Staffing Approach and the Use of External Resources ........................................................................... 12

    Project Management and Control .......................................................................................................... 16

    Timeline....................................................................................................................................................... 17Summary of Key Milestones ................................................................................................................... 17

    Project Structure ......................................................................................................................................... 18

    Organization Chart .................................................................................................................................. 18

    Roles and Responsibilities ....................................................................................................................... 19

    Other Teams............................................................................................................................................ 24

  • 8/3/2019 WSUProjectCharter-v10

    3/30

    Team Operations and Guiding Principles ................................................................................................ 24

    Project Management and Control .............................................................................................................. 21

    Project Plan Maintenance ....................................................................................................................... 21

    Project Meetings ..................................................................................................................................... 25

    Project Reporting .................................................................................................................................... 22

    Project Budget Management .................................................................................................................. 23

    Issue Management .................................................................................................................................. 27

    Decision-Making and Issue Escalation Process ....................................................................................... 24

    Change Control Management ................................................................................................................. 28

    Documentation Management ................................................................................................................ 29

    Communications ......................................................................................................................................... 30

    Required Outreach and Operational Readiness ......................................................................................... 31

    Post-Implementation .................................................................................................................................. 32

  • 8/3/2019 WSUProjectCharter-v10

    4/30

    P a g e | 1

    Version Control

    Document Title: Washington State University SIS Project Charter

    Authors: Tori Byington, Chair, SIS Steering CommitteeMichael Corwin, SIS Project Technical Manager

    Matt Skinner, Director, Operating Budgets

    Cathy Fulkerson, Director, Institutional Research

    Betsy Davidson, Solution Architect, Oracle Consulting

    Sally Texter, Assistant Vice President, Student Affairs and Enrollment

    Ken Vreeland, Special Assistant to Provost and Executive Vice President

    Mark DeMaio, WSU SIS Project Manager

    Revision History:

    Date Revision By Page(s)

    July 2010 Initial charter written Management team All

    Sept 30, 2010 Content merge Ivy Wang All

    November 4,

    2010

    Mark DeMaio revisions and

    consolidation of comments

    Mark DeMaio All

    November 10,

    2010

    Mark DeMaio and Tori Byington edits

    and revisions

    Mark DeMaio All

    November 22,

    2010

    Mark DeMaio: All Steering Committee

    input. Version 1.0 complete

    SIS Steering

    Committee, JuliaPomerenk, Mark

    DeMaio

    All

    December 2,

    2010

    Kate Esselbach edit document layout

    and presentation

    Kate Esselbach All

    February 9,

    2011

    Casey Hanson and Kate Esselbach edit

    document layout and presentation

    Casey Hanson, Kate

    Esselbach

    All

  • 8/3/2019 WSUProjectCharter-v10

    5/30

    P a g e | 2

    Foundation and Background

    Executive Statement:Everyone who works at this university or at any technology-driven institution understands how

    much we rely on our information systems. Unfortunately, WSUs IT infrastructure is increasingly

    unreliable, made up of obsolete systems that were not originally designed for the multiple tasks theynow perform. That they continue to work at all is a tribute to employees who have specialized

    knowledge of the unique fixes that are frequently required.

    Clearly, a world-class research university cannot long stand on such a shaky IT foundation. In fact, in

    the generally glowing accreditation report filed by the Northwest Commission on Colleges and

    Universities about our university this summer, one recommendation read: The Committee recommends

    that Washington State University provide contemporary information management systems that will

    address the needs of the future for its student, academic and management support requirements.

    The committee echoed the findings of Gartner, Inc., the consulting firm brought in by WSU to examine

    our information systems in light of our funding requests. The current applications do not provide the

    necessary agility to meet changing business and academic requirements in a rapidly growing andevolving environment such as WSU is experiencing today,the report found.

    Students and their parents are frustrated by breakdowns in our systems for registration, payments and

    financial aid. Just this fall, our registration software failed in the days leading up to the first day of

    classes. The situation was resolved, thanks to an intensive round-the-clock effort by our programming

    team. However, it was yet another clear sign that we can no longer delay solutions. Excerpt from: Dr.

    Elson Floyd, Perspectives, November 9, 2009

    Accreditation and Leadership StatementThe Northwest Commission on Colleges and Universities (NWCCU) 2009 Evaluation Committee

    recommendation that Washington State University provide contemporary enterprise information

    management systems that will address the needs of the future for its student, academic andmanagement support requirements did not come as a surprise. Over the course of preparing the 2009

    Self-Study report, information technology and an aging legacy system were identified as one of four

    cross-cutting challenges impacting the university as a whole and serving as a serious impediment to

    progress for almost every area of the university. Our internal assessment, and that of the Evaluation

    Committee, was reaffirmed in May 2009 in a report provided by a nationally recognized professional

    consultant. Responding to this challenge has been and continues to be a high priority of the University.

    The Student Information System project is a key component to the Universitys overall effort to enhance

    WSUs ability to deliver improved and expanded information technology services to the University

    community.

    Problem Statement

    The forces pushing the WSU student information replacement project forward are particularly strong atthis time. These are the primary business drivers:

    Risk of non-compliance Risk of system failure Improved integration and system capabilities Opportunity for a vastly improved business intelligence program University, college and program accreditation needs

  • 8/3/2019 WSUProjectCharter-v10

    6/30

    P a g e | 3

    These business drivers push WSU forward from a risk and compliance standpoint and/or pull WSU

    forward from an opportunity standpoint. While the administrative systems generally do not deal directly

    with the strategic initiatives of the University, they play key supporting roles in fulfilling the Universitys

    mission.

    Risk of Non-Compliance

    The lack of a robust electronic workflow process across integrated University systems jeopardizes WSUsability to exercise adequate internal controls in the current systems and in meeting complex regulatory

    requirements. In general, WSU systems are characterized by relatively weak internal controls and are

    thus vulnerable.

    Risk of System Failure

    The current student systems put WSU at significant risk. The myWSU Portal has failed at key times over

    the past several years severely impacting the ability of faculty, staff and students to prepare for the

    beginning of both fall and spring terms. The current 30 year-old student systems are unique to WSU and

    supported by only two or three technical staff members, some nearing retirement. In general, the

    availability of qualified staff to support administrative systems is extremely limited, and there is no

    vendor support available for the current application software.

    Improved Integration and System Capabilities

    Historically WSU has worked around many limitations in current systems, but is unable to do much more

    without addressing the fundamental underlying systems. There are long lists of system improvements

    that WSU needs, but is unable to implement due to the inflexibility of current systems. Over the past

    few years WSU has, for the most part, only developed and implemented systems to keep current with

    regulatory requirements. WSU is not in a position to react quickly to market needs and pressures with

    current student systems. On the other hand, there is a tremendous opportunity to improve the

    capabilities of our systems and allow for greater economies of scale. With the implementation of

    PeopleSoft we will be able to sunset many existing peripheral systems while taking advantage of the

    economies of scale of an expanded, flexible and integrated system. Improved system capabilities will

    not only allow WSU to address long-standing known shortcomings, but will also put us in a position to

    react quickly to unforeseen emerging needs.

    Opportunity for Vastly Improved Business Intelligence

    The business intelligence (BI) portion of the project will primarily focus on university business processes

    and the needs of data consumers at the institution. More broadly, this change in data management will

    allow data consumers to ask new types of questions that previously went unanswered. By structuring

    data from a University perspective based on consistency of common data and hierarchies, we will make

    a leap forward in reporting, predictive analytics and data modeling.

    In order for our BI program to be successful the implementation team will ensure data conversion and

    data warehousing are consistent with the needs of current and future organizational goals. The BI

    functional teams efforts will encompass data conversion and cleansing, data warehousing, data

    consistency and data consumption. For reporting, a set number of general dashboards and reports willbe made available at implementation time. Extensive training of the basic BI tools will be offered in the

    initial phase. In a later phase tools for data analysis will be added to support analytics.

  • 8/3/2019 WSUProjectCharter-v10

    7/30

    P a g e | 4

    University, College and Program Accreditation Needs

    The risk to the university was documented in both internal and external reviews including a

    recommendation from the Northwest Commission on Colleges and Universities (NWCCU) based upon

    their Evaluation Teams visit in 2009. While the universitys accreditation was reaffirmed, the

    Commission identified the need for contemporary enterprise information management systems as a

    challenge the university needed to address.

    Purpose of the Project CharterThe Project Charter is the primary operating document defining the goals, objectives, strategies, scope,

    organization and standards for the SIS project (The Project). It anticipates the reality of very large

    projects and defines processes for constructively dealing with project issues and decisions and defines

    the mechanisms for project control.

    Project VisionOnce implemented, this student information system will positively impact virtually everyone associated

    with the University: students, their families, faculty and staff. The new system will increase data

    accuracy, make student information management more secure, effective, convenient and accessible,

    and begin to coordinate information across the system to simplify student access to Universityresources.

    MissionWashington State University demonstrates its commitment to WSU students, faculty, staff and the State

    of Washington by planning, resourcing and implementing on time and within budget a robust, modern,

    integrated, standards-based, sustainable and vendor-supported Student Information Systems (SIS). The

    new SIS will improve service, accountability, work-flow, end-user reporting and provide access to

    reliable, timely, accurate and insightful information for recruiting prospective students, managing the

    needs of current students as well as the related needs of faculty and for institutional decision-making

    and resource planning.

    Goals, Critical Success Factors and Success CriteriaBecause a new student information system is a significant investment for the institution, the successful

    implementation will need to meet or exceed a number of goals. These goals or Pillars of Success will

    be used in conjunction with critical success factors to guide project decision making which optimizes the

    likelihood of meeting the success criteria as defined by system users for each functional area.

    Goals

    Complete the project on time and within budget. Provide a system that substantially improves service to students, faculty, staff and other

    users.

    Provide a system that supports institutional initiatives. Provide reliable and valid student and academic program data in one integrated University

    system of record that allows for the flexibility to meet specific university and academic unit

    strategic decision-making needs and ensure that data quality continues to improve.

    Implement a stable, integrated, upgrade-compatible system with minimal total cost ofownership.

    Position WSUs administrative applications to support significant growth and expansion. Implement a reliable, secure and scalable technical infrastructure.

  • 8/3/2019 WSUProjectCharter-v10

    8/30

    P a g e | 5

    Critical Success Factors

    Critical success factors are conditions and resources that must be present in order for the project to

    succeed.

    Acknowledge that people are the most important critical success factor. For success, it isessential that we:

    o Place the right people in the right roles at the right time across the breadth andlength of the project;

    o Provide strong support by senior management;o Use skilled participants;o Keep employees and students informed; ando Foster broad participation and representation.o Give department personnel a good understanding of how their departments and

    roles will change as early as possible in the project so that people can assimilate to

    the changes more effectively. The organizational design effort will be a sensitive

    topic for end users.

    Agree that the PeopleSoft student business processes are reasonably close to best practices.Therefore, it is reasonable to start with a vanilla approach to the implementation and

    adapt our business processes to minimize complexity and optimize the delivered capabilitiesof our system. Project participants will be able and willing to think out of the box, across

    departmental lines, and with an eye always toward the good of the institution.

    Ensure that the overall SIS project is viewed as a university owned project and not ownedby individual departmental silos.

    Manage scope in a disciplined but not rigid manner. Scope changes can occur if its best forthe institution, but they must be explicitly identified, assessed and approved.

    Structure and discipline governance process to a high extent with clear decision rights. Theproject leaderships decisions and processes will be biased towards action, accountability,

    candor and support for the greater good of the institution.

    Expect that we will not get the system and process design perfectly right the first time.Therefore, we will use an iterative design approach to implementation throughout theproject.

    Agree that end users must be trained in regards to business processes in addition to theirrole within the business processes so that they can play a key role in achieving the intended

    business outcomes.

    Assume that the project will be able to proceed in the face of overall budget reductions. Inpart this has to do with protecting the project budget. But more importantly the project will

    not take place in a vacuum, as many participants, and all those affected by the project, are

    being affected by budget reductions.

    Success Criteria

    WSU functional areas have defined the following as measurements of success for the SIS project. As the

    project progresses, the project team will monitor activities and deliverables to ensure that these criteriaare met.

    Campus Community

    A single source for associates and biographical/demographical data. Ability to create and maintain checklists for students, streamlining student notification of

    information needed for admissions and other areas.

    Ability to create communications, either by batch or manually, as needed by any area fortheir needs.

  • 8/3/2019 WSUProjectCharter-v10

    9/30

    P a g e | 6

    Admissions

    A seamless transition from the current legacy AIS system to PeopleSoft Campus Solutions inwhich staff from graduate and undergraduate admissions will be trained and able to process

    applications without confusion.

    Ability to proceed through all steps of application processing via automated processeswherever possible while retaining the ability to rush or manually process when needed for

    individual cases.

    Ability of departmental users to easily access accurate data for their day-to-day operationswhich will cut down on manual intervention.

    Ability to track applicants by the appropriate offices through all stages (applicant, admitted,confirmed) for both graduate and undergraduate, in order to accurately project

    matriculation.

    Logical manner for work to flow through the system. Well-defined and flexible business processes (easy to change when necessary) that are

    easily documented (with documentation tools that are common across modules), and

    trainable (with interfaces that are intuitive for users and training materials that are easy to

    maintain).

    Easy access for users/departments to data for their day-to-day operations instead of liststhat are fed to them by The Graduate School. This will cut down on manual intervention

    and communication from Graduate School to departments and to students.

    Student Financial Aid

    Meeting all target deadlines and ensuring that data across the PeopleSoft Campus Solutionsenvironment is accurate and accessible.

    Successful load of FAFSA/Scholarship applications, packaging aid and delivery of funds tostudent accounts while staying compliant with state and federal regulations all without

    adversely impacting students.

    Student Finance

    Precise tuition calculation. Successful coordination of aid release in conjunction with Financial Aid. Appropriate and accurate posting of all payments to Student Accounts. Accurate aid disbursement/refunds to students on the first day of school.

    Student Records-Graduate

    Smooth transition from one registration system to the next with student completing theirpriority registration with full class loads, by priority group.

    Effective drop/add period beginning the week prior to classes and extending two weeks intothe term, with students able to complete their changes in a timely manner.

    Planned and effective use of class lists and grading by faculty before, during and at theconclusion of the 2012 fall semester.

    Ability to track special population of students (example: Fulbright and InternationalAgreements) in the Campus Solutions system rather than in shadow systems and paper files.

    Ability to track and communicate with students on Graduate leave or Continuous DoctoralStatus without staff intervention.

  • 8/3/2019 WSUProjectCharter-v10

    10/30

    P a g e | 7

    Advising

    Ability for students and their advisors to create programs of study. Ability for offices or students to run a degree audit to check their status and progress

    towards a degree.

    Ability to track departmental degree requirements and faculty committee eligibility.

    Ability to easily schedule student exams. Ability to process deficient students easily along with holds to prevent registration until

    reinstatement occurs.

    Improved reliability of the system and true accuracy of reported data.Reporting

    Adoption of a tool for easy access to all components of the enterprise student system froma single source with planned integration and/or linkages to data outside the SIS (Housing,

    Human Resources, Research, Finance, Alumni, WSU Foundation, etc.).

    Secure self-service access to data and information for a broad base of users in appropriateforms that meet diverse needs.

    Ability to conduct deeper analysis and data mining, turning data into information.Project Scope

    In Scope Items:WSU is replacing parts of its major administrative systems: Student, Student Warehouse, and the

    myWSU Portal. This will affect many support and peripheral systems as well. We are replacing WSU

    student systems with PeopleSoft Version 9.0. The new PeopleSoft student system will be integrated

    with the existing WSU business systems (Human Resources, Payroll, and Financials). The new system

    replaces functionality currently found in our student administrative systems, which is comprised of

    modules in AIS, RONet, Financial Aid and the Graduate Schools systems.

    Along with replacing the core administrative systems, a substantial investment is being made in

    Business Intelligence. These efforts are being made to both adapt to changing administrative systemsand to greatly expand the availability of business information to managers and executives. New BI tools

    will replace the current ITS housed data warehouse and Business Objects, the primary tool used to

    access that data. Also in scope is the replacement of the current Undergraduate Admissions data mart

    and the Graduate School reporting data base.

    The following list identifies what is currently in scope for the SIS project:

    PeopleSoft Portal PeopleSoft Campus Solutions

    o Academic Advising (including DARS replacement)o Student Self-Serviceo Admissionso Campus Communityo Student Financialso Financial Aido Student Records

    PeopleSoft Data Warehouse (EPM and OBIEE toolsets) PeopleSoft Campus Solutions Fusion Intelligence OBIEE Integration of current SAN located on SharePoint

  • 8/3/2019 WSUProjectCharter-v10

    11/30

    P a g e | 8

    Depending on project progress, performance to budget and business needs, the steering committee

    may add additional items to scope. As this occurs, the additional items will be added as in scope to this

    charter through the projects scope change process.

    Out of Scope Items

    On a regular basis the project team and the steering committee will review project scope. Currently, thefollowing items are deemed out of scope:

    Human Resources systems and processes Finance systems and processes Research systems and processes Campus Recruiting and recruiting business processes. Recruiting data will be fed from

    legacy recruiting systems to Campus Solutions via an interface.

    Campus Solutions Grade BookDepending on project progress, performance to budget and business needs, the steering committee

    may deem additional items out of scope. As this occurs, the additional items will be added as out of

    scope to this charter through the projects scope change process.

    Approach

    Project SequenceThe SIS project will use a phased implementation approach that delivers new and improved functionality

    in time to support the normal WSU academic calendar. The SIS project will aggressively seek to

    minimize customizations to the delivered software. Appropriate project processes have been defined

    to enforce this practice.

    CustomizationsTo help minimize customizations the WSU SIS project will:

    Communicate clearly about vanilla implementations. The SIS project view is that soundbusiness processes are embedded in the software and that WSU will look to adopt those

    processes rather than changing the delivered software. We will question why we do things

    the way we do. Is it really a best practice or is it because our legacy systems have limited

    how we could do it? Many WSU business processes were built around antiquated systems

    and limitations of current systems. Whats the worst thing that could happen if we change

    it?

    Be open to possibilities and doing things differently. Be open to new ways of naming andtalking about things. Be open to self-service, automation and consistency. Explore and take

    advantage of the full functionality. How can we better serve students? How can we better

    serve departments?

    Along with delivering systems that WSU is in great need of, this approach also serves to manage cost.

    The SIS project team will work very hard to meet target dates. Aggressive timelines require rapid

    decision-making, and the project will work in this fashion. Processes are set up to support

    knowledgeable and empowered decision-making. These processes are documented in the Project

    Management Plan document. Proven methodologies will be employed. The SIS project will also

    implement strong control mechanisms to effectively manage budget, issues, changes, etc. This includes

    outside audit oversight by JB Harris Consulting, the selected Quality Assurance vendor, which will

    perform monthly review of project status, plans and budgets.

  • 8/3/2019 WSUProjectCharter-v10

    12/30

    P a g e | 9

    ConversionData conversion is the process of migrating high-value information from our legacy transaction systems

    into the new PeopleSoft system. This is done for both operational and analytic purposes. There are

    mature best practices and technologies available to minimize the cost of performing this work.

    Conversion will be performed by creating data extracts from the mainframe legacy system, AIS. These

    extracts will then be loaded to a series of staging tables through the SQL loader tool. The OracleComponent Interface tool will be used to then load data to the appropriate Campus Solutions data

    tables.

    TestingThe strategy for testing SIS is to employ all the aspects as listed below when they are applicable and

    when they are possible. For example, a performance test is valuable when there is a concern about

    volume processing and/or a critical need for response time. A usability test is valuable when the

    experience of users will help us either in the design of the user interface or in the design of user training

    and help-desk tools and materials. A parallel test is extremely valuable when possible. Transcript

    production is an excellent example. The testing strategy varies from one initiative to another and is

    incorporated into the implementation strategy and then the project plan for that initiative.Test Plan

    Before testing begins, a test plan is created. A typical test plan documents input values for the test,

    procedures used to perform the testing and the expected output values or results. Test plans range from

    very simple to very complex, usually in relation to the complexity of software processes which are to be

    test. For instance, testing whether a new user prompt is added to a screen may not require a test plan at

    all, while testing a complicated process may require documenting many varied input scenarios and the

    corresponding expected results and outputs for each case. During the testing, the test plan is updated to

    log test activities, results and variances with what was originally expected.

    Unit Test

    A unit test typically focuses on a minimal component, module or narrow activity. The unit test validates

    that the specific module functions correctly. In relation to new or modified code, the unit test is oftenperformed by the developer.

    Integration Test

    Integration testing follows a business process through a series of components, modules and activities to

    ensure that a function performed by the system works as designed from end to end. The purpose of

    integration testing is to reveal issues arising along the process chain, even though the individual

    modules execute correctly. Performing integration testing is usually the domain of business analysts or

    their equivalent that are well versed in the system functionality.

    System Test

    System testing takes, as its input, all of the "integrated" components that have successfully passed

    integration testing. System testing is a more limited type of testing; it seeks to detect defects both

    within the "inter-assemblages" and also within the system as a whole.

    Parallel Test

    Parallel testing compares the output between two different systems performing similar processes on the

    same input data. In cases where the output is not identical, the causes of the differences are researched

    and explained.

  • 8/3/2019 WSUProjectCharter-v10

    13/30

    P a g e | 10

    Acceptance Test

    Acceptance testing usually occurs in cases which require a sign-off in order for the coding or

    functionality to be considered complete. If the acceptance testing proves successful, the code or

    functionality is considered ready for production, and no further changes are required or allowed.

    Performance Test

    Performance testing attempts to put a system under a heavy load (such as a large number of concurrentusers or complex batch processing). The performance test shows whether measures such as system

    response time are acceptable.

    Usability Test

    Usability testing seeks to discover whether the user interface is intuitive or at least easy to use.

    Usability testing is often administered in a controlled environment in which sample end users are

    monitored and asked for feedback on their experience.

    TrainingTraining is a critical activity to ensure successful user adoption of the new applications system as well as

    to meet the success criteria of the project. The user community of SIS is large and is spread out among

    multiple locations and campuses. The SIS project will utilize a Train the Trainer strategy that providesdetailed application and business process training to a select group of power users throughout the

    various departments and locations. These power users in turn will train other employees within the

    various departments. The power users then can function as user support during the post go-live

    period. This maximizes the effectiveness of training and minimizes the cost of classroom training and

    materials. Training will be made available to end users via PeopleSoft on-line functionality (User

    Productivity Kit).

    For training to be effective, it should be delivered on a just in time basis in order to maximize

    information retention and allow task repetition to reinforce learning.

    A detailed training strategy and plan will be developed as part of the project execution process.

    ReportingReports to support day-to-day business processes will be delivered along with each Campus Solutions

    module. These reports are referred to as Operational and Transaction Reports. The development of

    reporting requirements, report layouts and data elements will be accomplished by the functional teams

    with input and participation from the appropriate University department. The technology team will code

    and build these reports and will aid in testing and implementation. The appropriate functional and

    technical project team members will work together to build and test these reports as part of the SIS

    implementation.

    In addition, cross-functional reporting requirements will be defined by the reporting team and will

    ensure that all University wide reporting requirements will be met. A fit /gap analysis will be performed

    to identify any cross-functional issues and to set direction for analytical and business intelligence reports

    to be defined later. These will be then prioritized by each functional area, based on business needs.

    As an overall strategy, the execution and running of reports needs to have a minimal effect on Campus

    Solutions processing and user response time. Where practicable, reporting should be supported by the

    EPM and OBIEE toolset. PS Query and other Campus Solutions tools will be used when necessary and

    will contain well defined security to ensure minimal impact to production processing and system access.

    A detailed reporting strategy document will be created as part of the project execution process.

  • 8/3/2019 WSUProjectCharter-v10

    14/30

    P a g e | 11

    SecurityWith the implementation of the new student system, WSU will implement a system that is FERPA

    compliant and gives users access to only the student records that they should be able to see. PeopleSoft

    security can be set at two different functional levels simultaneously. An individual users security access

    privileges are controlled by the resulting interacting combinations of these settings for that user.

    Page (Screen) AccessA user can be granted one of the following access modes to Campus Solutions:

    No Accessthe user can neither see nor interact with the application. Further, if no accessis granted to any of the pages associated with a menu choice, then that menu choice is not

    shown to the user.

    View-Only (also referred to as Display-Only) the user can see the data on the page butcannot change it. (Note that link controls on the page may or may not be active depending

    on the page design and coding.)

    Update/Displaythe user can see and change data on the page if no effective dating isinvolved. If the data is effective-dated then the user can only change current-dated and

    future-dated data, not historic data.

    Correctionthe user can see and change all data on the page, effective-dated or not.Administering Security

    In order to ease the burden of redefining security for each individual user, standard groupings of

    security objects are typically defined.

    Sets of pages and the corresponding page access modes are grouped into permission lists.Additionally, any page or set of pages can appear in multiple permission lists with the same

    or different access modes. Also, a permission list is often used as a convenient way to hold a

    given row-level security definition.

    In turn, permission lists can be grouped in a variety of ways and assigned to a role.Additionally, multiple roles may make use of the same permission list in combination with

    other permission lists.

    Effective security administration leverages the power of roles and permission lists byassigning users with similar requirements to the appropriate set or combinations of roles.

    Security access for an individual is defined by that individuals assigned roles which are in

    turn defined by the roles permission lists which are in turn composed of sets of pages, the

    access modes of those pages, and the assigned row-level security.

    End User AcceptanceThe overall strategy for end user acceptance starts early in the project and extends through Help Desk

    support after go-live. These are some of the key components:

    Support by executive management

    End users know at all times that executive management fully supports the SIS project and understands

    the difficulties of adapting to these new administrative systems.

    Involvement by middle management

    Middle management is informed of project progress and involved in project issues and decisions

    through vehicles such as the Steering Committee and Core Project Team.

    Involvement by university technical leaders

    Similar to the above, university technical leaders are informed of project progress and involved in

    project issues through vehicles such as the Technical Integration Group.

  • 8/3/2019 WSUProjectCharter-v10

    15/30

    P a g e | 12

    Project communications

    Through multiple vehicles (including open forums and web pages), described elsewhere in the Project

    Charter, end users have access to information about project progress, issues, target dates, etc. (Please

    refer to the projects communication plan.)

    Hands-on exposure

    End users have opportunities to see the system in action in a demonstration environment.

    Training

    Training specific to end users and specific to the WSU environment is developed and delivered to end

    users by the SIS project team. End user training will also be made available to end users via PeopleSoft

    on-line functionality (User Productivity Kit).

    Testing

    To the extent possible, the project team will recruit end users to participate in tests, in order to provide

    early exposure and to receive early feedback on any end user acceptance issues.

    Support

    Support for end users will be provided by the same organizational unit that is responsible for training.

    This will provide a seamless training and support environment that will extend into the future. Thisconsistency will avoid the issues of inconsistent facts and language.

    Staffing Approach and the Use of External ResourcesThe SIS project is too large and too complex for WSU to undertake on its own. Thus, outside consultants

    will play key roles on the project and will serve as well as sources for the additional temporary labor that

    is needed. The SIS project will employ consultants for their specific expertise and advice and will work to

    maximize knowledge transfer.

    There will also be a great impact on colleges/departments due to changes in business processes,

    including shifts in responsibility for data entry and the forms and formats of the information available.

    Based on experience, this impact is best addressed by overall project communications, appropriate

    involvement in the project, and in particular by adequate training provided by knowledgeable trainers.

  • 8/3/2019 WSUProjectCharter-v10

    16/30

    P a g e | 13

    Project Management and ControlIn developing a project management and control framework, WSU benefits from the experience of

    other leading research-intensive institutions that have successfully implemented the PeopleSoft Student

    Information System. WSU will aggressively seek to employ proven leading practices and core values that

    will guide us in the management of the overall project.

    1. Demonstrate consistent and visible support for project by executive management.2. Continuously communicate implementation information to university community.3. Re-engineer business processes to conform to industry standards built into the software, to

    avoid software customization.

    4. Drive implementation schedule with specific milestones.5. Develop business intelligence and reporting strategies early in the project. Data conversion is

    addressed early, not late, in the life cycle. In addition, operational and transaction reporting are

    to be delivered at the time of go-live for each module.

    6. Employ experienced consultants for expertise and support of core functional team. Consultantsenable WSU to make decisions, and WSU drives the project, so that at the end of

    implementation WSU will be self-sufficient.

    7. Maximize knowledge transfer from consultants to WSU staff.8. Establish project teams representing all functional areas, weighing functional more than

    technical. Functional process and needs are core to the project.

    9. Assign the project management team and core team members full-time on the project; reassignnormal job duties.

    10.Empower the project team to make decisions.11.Track and reallocate project budget in a timely manner.12.Create a dedicated work environment for the project team.13.Promote positive work environment, with actions to reward, praise and celebrate project

    successes and value fun at work.

    14.Monitor organizations need and readiness to adapt on a continual basis.15.

    Build prototypes early and often. Build, test and demonstrate frequently.

    Processes and procedures to implement these practices are outlined and maintained in the Project

    Management Plan document.

  • 8/3/2019 WSUProjectCharter-v10

    17/30

    P a g e | 14

    Timeline

    Summary of Key Milestones

    MILESTONE TARGETDATE

    Start SIS Implementation Project July 2010 Academic Structure Defined November 2010 Campus Community Defined June 2011 Student Bio/Demo Data Converted June 2011 Course Catalog/Schedule Converted September 2011 ISIRs Loaded January 2012 Enrollment History Converted March 2012 Ready for Live Student Pre-Registration March 2012 Student Financials Balances Converted August 2012 Financial Aid Awarded/Packaged August 2012 Ready to Post Grades November 2012 Calculate Tuition/Accept Payments June 2012 Business Intelligence/OBIEE and EPM Fully Functional June 2012

  • 8/3/2019 WSUProjectCharter-v10

    18/30

    P a g e | 15

    Project Structure

    Organization ChartThe organization chart below illustrates the SIS project organization.

  • 8/3/2019 WSUProjectCharter-v10

    19/30

    P a g e | 16

    Roles and ResponsibilitiesThe table below defines the various roles and responsibilities of project leaders and team members of

    the SIS project:

    Role Responsibilities Decision Authority Example

    Executive Committee

    Overall

    Act as champions for the project Make decisions that affect the University

    as a whole or those that cannot be

    resolved by the Steering Committee

    Steering Committee

    Executive Leadership

    Define project success criteria Advise project management in resolution

    of escalated issues. (See definition of

    issues under Decision-Making and Issue

    Escalation Process.)

    Seek input from SIS Policy Committee onfundmental academic policy issues

    Review and approve modifications thataffect University policy, project duration

    and budget

    Foster executive support and buy-in Assess value accomplished for the

    investment

    Attend weekly State of Project SteeringCommittee Meeting

    Changes to implementationdate

    Major scope or approachchanges with impact to cost

    Policy Committee

    Recommendations and Oversight

    Review project progress regularly Make policy change recommendations as

    requested by Steering Committee

    Project Management

    Team:

    Tori Byington

    Mark DeMaio

    Mike Corwin

    John Hansen

    Project Direction

    Review progress and work products Prioritize; decide scope boundaries for

    potential customizations

    Manage organizational change Determine what risk mitigation strategies

    to adopt

    Review and approve options to resolveissues, problems and scope changes to be

    brought to the SIS Steering Committee

    Monitor that staffing is maintained;participate as appropriate in candidate

    selection

    Provide weekly updates to MicrosoftProject plan

    Provide operational oversight over corefunctionality

    Prioritization of scope changerequests

    Risk mitigations to adopt Approval of issues to escalate

    to SIS Steering Committee

    Resolve any project teamissues that cannot be resolved

    by the project team members

    Overall

  • 8/3/2019 WSUProjectCharter-v10

    20/30

    P a g e | 17

    Role Responsibilities Decision Authority Example

    WSU Steering

    Committee

    Chairperson

    Tori Byington

    Assume responsibility for the successfulcompletion of the SIS project

    Maintain oversight and enforceaccountablity for the project team

    Co-chair of Policy Committee Lead and coordinate issues escalated from

    the core project team

    Assist with graduate school functionality

    Provide guidance andleadership regarding

    academic policy and issue

    escalation

    Oversee and provide guidanceto project management team

    members

    WSU Project

    Manager:

    Mark DeMaio

    Overall

    Assume responsibility for execution ofproject plan and the successful completion

    of the SIS project

    Manage and revise project workplan withinputs from Oracle Project Manager and

    WSU Technical Manager, BI and Change

    Management teams

    Review and approve time in SIS timetracking Oversee and direct Oracle Project

    Manager

    Facilitate the development of projectstrategy documents and project

    organizational items

    Create weekly project progress statusreports

    Assist with facilitatation of the weeklySteering Committee Meeting

    Facilitate the resoultion of project issuesand problems as appropriate

    Provide monthly progress reports toIndependent QA consultants

    Assist with conversion planning effort andstrategy

    Contract Management

    Review contracts, identify exposures andmanage contract changes or additions

    Monitor contract compliance Scrutinize expenses Escalate vendor issues to accomplish

    resolution

    Risk Management

    Manage risk tracking, mitigation strategiesrecommended, mitigation strategies

    adopted, responsible party, status,

    probability and impact

    Monitor impacts to critical path based on

    Oversee planning activities Maintain project work plan

  • 8/3/2019 WSUProjectCharter-v10

    21/30

    P a g e | 18

    Role Responsibilities Decision Authority Example

    updated project schedules from Oracle

    Consulting Project Manager and WSU

    Technical Manager

    Participate in all quality checkpoints Recommend risk mitigation strategiesIndependent Oversight

    Provide independent project managementopinions to the State of Washington

    Provide independent project review,assessment, and advice to the CIO

    Assume other duties as appropriate anddefined by the Vice President and Chief

    Information Officer

    Oracle Project

    Manager:

    John Hansen

    Overall

    Manage and lead all Campus Solutionsfunctional activities

    Provide oversight and management toOracle consultants

    Provide Campus Soluitions subject matterexpertise

    Create and manage detailed projectschedule for Campus Solutions

    implementation tasks and provide project

    plan updates to WSU Project Manager

    Provide progress reports to WSU ProjectManager

    Budget

    Create and manage vendor detailedbudget

    Calculate burn rate throughout phases Reconcile to actuals from financeContract Management

    Review contracts, identify exposures andmanage contract changes or additions

    Monitor contract compliance Scrutinize expenses Escalate client issues to Oracle

    Management when required to accomplish

    resolutionRisk Management

    Assist with risk tracking, mitigationstrategies recommended, mitigation

    strategies adopted, responsible party,

    status, probability and impact

    Monitor impacts to critical path based on

    Lead configuration activites

  • 8/3/2019 WSUProjectCharter-v10

    22/30

    P a g e | 19

    Role Responsibilities Decision Authority Example

    updated project schedules from Oracle

    Consulting Team Project Managers

    Participate in all quality checkpoints Assist in creating risk mitigation strategiesProject Administration Monitor appropriate framework in place

    for project results

    Detailed Task Management

    Assign tasks and monitor completion Update completed Microsoft Projects Identify at-risk, late tasks Provide preliminary status compilation to

    Program Director weekly

    Identify and monitor critical path Review team work products (primary) Manage day-to-day staff resources Assign and maintain adequate resource

    levels and appropriate allocations

    Manage issues tracking (date,responsibility, status)

    WSU Technical

    Manager:

    Mike Corwin

    Overall

    Assume responsibility for all developmentactivities, including all aspects of the

    lifecycle

    Create and manage detailed projectschedule for techncial implementation

    tasks and provide project plan updates to

    WSU Project Manager Develop conversion strategy and plan Provide leadership and management to

    WSU technical staff

    Identify and staff technical roles tosuccessfully deliver required functionality

    Act as WSU client manager for all Oracletechnical services and Oracle On-Demand

    Provide leadership to ensure successfulimplementation of WSU environments,

    when necessary

    Detailed Task Management Assign tasks and monitor completion Update completed technical activities in

    Microsoft Project

    Identify at-risk, late tasks Provide preliminary status compilation to

    Project Manager weekly

    Identify and monitor critical path

  • 8/3/2019 WSUProjectCharter-v10

    23/30

    P a g e | 20

    Role Responsibilities Decision Authority Example

    Review team work products (primary) Manage day-to-day staff resources Assign and maintain adequate resource

    levels and appropriate allocations

    Manage issues tracking (date,responsibility, status)

    Program

    Coordinator:

    Ivy Wang

    Responsible for coordinating projectlogistics including space, onboarding,

    supplies, etc. Also acts as Administrative

    Assistant to Project Management Team

    Meeting scheduling Document preparation

    SIS Budget

    Administrator:

    Dawn Barnard

    Reports to the CIO Assumes responsibility for managing all

    aspects of project finances, including the

    project budget. Responsible for project

    time tracking. Also responsible for

    administration of all consultant contracts

    Monthly budget report Approval of all consultant

    requests

    Washington State

    Treasury/COP

    Liaison:

    Barry Johnston

    Advises CIO on project financial mattersthat relate to the WSU and to the StateTreasury Office

    Responsible for all communications withthe Washington State Treasury Office

    regarding project funding

    Responsible for regular reports andexpenditure submissions to the Treasury

    Office

    Responsible for coordinating long termCertificate of Participation documentation

    and payments

    Washington State

    University Budget

    Liaison:

    Matt Skinner

    Advises CIO on project financial andbudgetary matters that relate to WSU and

    to the Office of Financial Management

    Advises the project team on studentfinancials as it relates to the Universitys

    budget and budget process

    Other Teams Student User Team is a group of selected students that will participate in focus groups,

    testing, review, etc. The Integration Group, chaired by the Director of UISS, consists of

    technical leaders within the project and within the university IT community. The integration

    group is responsible for ensuring that project functional decisions are aligned with technical

    directions. The group works with the University community to develop technical integration

    standards and ensures non-ERP systems can integrate with PeopleSoft.

    SIS Communications Committee will be responsible for and will coordinate all campus andUniversity wide communications pertaining to the SIS project.

  • 8/3/2019 WSUProjectCharter-v10

    24/30

    P a g e | 21

    Team Operations and Guiding Principles

    SIS implementations bring together a group of talented individuals to bring about significant University

    transformation and improvement. While WSU can and should expect a very positive and successful

    project, implementations can also be a challenge. The SIS project will seek to balance the needs of team

    member work and personal time. The project will promote trust, accountability, openness and will

    provide mechanisms for conflict resolution.

    Project Management and Control

    Project Plan MaintenanceThe overall SIS Project Plan is a consolidation and integration of the project plans for the individual

    initiatives. Project plans will be created and maintained in Microsoft Project for these initiatives:

    Campus Solutions Portal Business Intelligence

    The Oracle Project Manager is responsible for maintaining the project plans, with oversight and

    direction from the WSU Project Manager. This responsibility may be partially delegated to consultants

    and/or to a WSU Project Administrator, but the Project Manager is responsible for the integrity of the

    plan as a whole, including integration across projects and with other initiatives. Maintenance activities

    include marking of completed tasks, reassignment of tasks, redefinition of tasks, etc. Since project plans

    contain greater detail for near-term tasks than for longer-term tasks, a part of the regular maintenance

    of project plans is the decomposition of upcoming activities into tasks.

    The ideal task, from a size standpoint, is what one person can accomplish in a week. That level of detail

    is normally expected to be present for the upcoming three months.

    With regard to the SIS project plan the SIS project team will work with the WSU Project Manager and

    Oracle Project Manager to plan the work and work the plan. At the beginning of each week, the Oracle

    Project Manager will ensure that each team member knows and understands the work that is expected

    to be worked on and completed during the week.

    The Oracle Project Manager will complete updates to the project plan(s) each and every Friday. Project

    plans will be done in Microsoft project, will be versioned, and will be kept on the SIS project SharePoint

    site.

  • 8/3/2019 WSUProjectCharter-v10

    25/30

    P a g e | 22

    Project Meetings

    Continual communication across the project organization is essential and will often include meetings.

    However, it is essential that meeting time be designed to maximize productivity and efficiency. Thus,

    the standard SIS meeting protocol is:

    There is a designated chair. There is an agenda that includes expected participants and topics to be discussed. Meeting notes are kept, typically by supplementing the agenda with key decisions made

    and/or follow-up items and assignments indicated.

    Necessary documents are available either as pre-printed materials or as electronicallydisplayed materials.

    Meetings are conducted in such a way to maximize the productivity of the group timeinvestment.

    Team will strive for full participation in meetings. Team members that are unable to attend a meeting should be prepared to accept the

    decisions reached during the meeting.

    The standard SIS meeting schedule includes:

    Executive Committee typically every 3 months Steering Committee weekly or as needed SIS Policy Committee monthly or as required/requested by the Steering Committee. Senior Project staff weekly Steering/Project Coordination Committee weekly SIS Project Management Meeting weekly Project Management weekly Quality Assurance monthly Functional Teams daily or as required

    The core functional team working sessions are held as needed. A general project pattern is to meet

    daily as a group in the morning and to work as individuals or smaller groups in the afternoon, but this is

    at the discretion of the Project Manager.

    Project ReportingProject status reports will occur weekly and monthly.Weekly Status

    Each Oracle consultant will provide a weekly status report to the WSU Project Manager and the Oracle

    Project Manager. The Oracle consultant will work with their WSU counterparts to produce the status

    report. The status report will detail the work in progress, accomplishments, issues, risks, hours and all

    information necessary to allow the Oracle Project Manager to update the Microsoft project plan. All

    status reports will be posted to the project SharePoint site and be visible to the core project team.The WSU Project Manager will provide a weekly report that summarizes project status, progress against

    milestones, steering committee action items, and risk summary and resource issues. In addition, the

    WSU Project Manager will provide an overall project assessment of work in progress, accomplishments,

    issues, risks and hours.

    The functional coordinators and technical lead will report status to the Project Director and Project

    Manager (and to each other) at the weekly Core Management Team meeting.

  • 8/3/2019 WSUProjectCharter-v10

    26/30

    P a g e | 23

    Monthly Status and Quality Assurance

    The WSU Project Manager and SIS Budget Administrator will ensure that an updated project plan,

    budget summary issues log, and risk log are available on SharePoint for examination by the Independent

    Quality Assurance Consultants by the 5th

    business day of each month.

    Project Budget ManagementBudget management is critical to determining project status and making timely project decisions. The

    SIS Budget Administator, in close collaboration with the WSU Project Manager, is responsible for

    tracking actual expenses to date, actively forecasting of total project costs, and administering project

    contracts. Responsiblities include:

    Create and manage detailed budget Review/approve invoices/record in spreadsheets Calculate burn rate throughout phases Reconcile to actuals from finance Review contracts, identify exposures and manage contract changes or additions Monitor contract compliance

    Scrutinize expensesThe budget management process is supported by the SIS Budget Administrator, with representation

    from the Office of Business and Finance and the University Office of Budget and Planning.

    The SIS Budget Administrator and WSU Project Manager are responsible for tracking time spent on the

    SIS project. Core team members and consultants will submit a weekly timesheet showing time spent by

    initiative and by activity. This is an important tool for project management. It allows monitoring of

    resources as actually delivered to the project, as well as a tracking of what is required to complete

    activities. This timesheet is separate from, and has a different business purpose than, timesheets

    submitted for payroll purposes. The SIS Budget Administrator and WSU Project Manager will meet

    monthly to review and track fiscal/project progress, to resolve open issues, and to discuss upcoming

    planned expenditures.

    The SIS Budget Administrator is responsible for the processing of all project-related invoices. This

    includes contractor/consultant invoices with reconciliation against project timesheets. The Project

    Manager has authority to initiate spending requests in accordance with established project budgets.

    The SIS Budget Administrator will provide second-level review and set appropriate accounting codes on

    the transactions.

    Issue ManagementIssues will arise throughout the life of the project. An issue is any condition or situation which, if not

    addressed, threatens the project from a time, cost or result standpoint.

    When an issue is identified it is logged, in the SIS Project Issues Log, located in the SIS Project SharePoint

    site. The log of outstanding issues is reviewed as a standing item on project team meeting agendas.

    Standard protocol for issue creation includes:

    Assign a unique ID Name the issue Describe the issue, including its potential impact Assign a priority (Critical, High, Medium, Low) Assign the person responsible for resolution Set the initial status (Open)

  • 8/3/2019 WSUProjectCharter-v10

    27/30

    P a g e | 24

    The protocol for issue review includes

    Update status, record key decisions and next steps Determine the current status (Open, Closed, Hold)

    Once an issue is opened it remains on the log until closed. One way to close an issue is to resolve it by

    taking action or making a decision. Another is to determine that in fact it isnt an issue; no action or

    decision is required. A third way is to turn it into a task on the project plan. All issues will be tracked via

    the SIS SharePoint Issues List.

    Issue logs are maintained at multiple levels on the project and managed as follows:

    The SIS Steering Committee Chair The WSU Project Manager The Oracle Project Manager The Functional Lead (for an individual project within a given initiative)

    Decision-Making and Issue Escalation ProcessIssues will arise over the course of the project. An issue is any condition or situation which, if left

    unresolved, threatens the project from a time, cost or result standpoint . Quick and appropriateresolution of issues is critical.

    Each of the core project teams are empowered to identify and develop recommended resolutions to

    project issues. Some issues, those that affect University policy, project scope, project schedule and the

    budget, will require escalation and resolution by the Project Management Team, the Steering

    Committee or the Policy Committee. If an issue requires escalation, it will be assigned a PMT status

    and will be reviewed by the Project Management Team weekly. In the event that a weekly turnaround

    is not sufficient to complete an activity on time, the issue owner can escalate the issue to the WSU

    Project Manager immediately. The Project Management Team will either accept the resolution or, if

    required, assign it to the Steering Committee for approval. Items escalated to the Steering Committee

    will be reviewed weekly.

    Change Control ManagementOne of the more difficult aspects of a large project is change. Change is a fact, and it needs to be

    managed in a controlled way. The process should be quick when the request is straightforward and

    inexpensive and very considered when the request is more complex and/or more expensive.

    The change control process has these steps:

    1. Propose

    Anyone may propose a change informally in the course of the project. These proposals are normal

    what-if discussions. A formal request for change, however, must go through the WSU functional lead.

    If the functional lead concurs, a System Change Request (SCR) is initiated. If the functional lead does not

    concur, an issue will be opened, and the issue process used to resolve the disagreement.

    The System Change Request (SCR) includes:

    Initiative

    Requestor

    Date

    Description

    Expected benefit

    Attachments as necessary

  • 8/3/2019 WSUProjectCharter-v10

    28/30

    P a g e | 25

    2. Log System Change Request

    The System Change Request (SCR) is presented to and discussed with the Project Manager. If the Project

    Manager agrees with the judgment of the functional leads, then the Project Manager assigns an ID to

    the SCR, and logs it in the System Change Request Log. This log is maintained for the overall SIS project.

    3. Assess System Change RequestThe requested change is analyzed to determine what would be involved if this request were approved.

    What modules/dialogs/tables/etc. would be affected? What more specifically would be the benefit?

    What would be the cost to the project? Assessment of benefit and cost is done on a lifetime

    benefit/cost basis. For example, a customization to PeopleSoft will need to be revisited every time a

    new PeopleSoft release is installed. In the case of more complex requests this analysis can itself be a

    considerable amount of work. As a result of this work the original SCR is modified, so that it now

    includes:

    SCR ID

    Initiative

    Requestor

    Date submitted

    Analyst

    Date analyzed

    Description (revised if necessary)

    Affected components

    Expected benefit (revised if necessary)

    Expected cost (time and dollars)

    4. Review System Change Request

    All SCRs are reviewed by the Change Request Group (Oracle Project Manager, Technical Lead,

    Undergraduate Liaison, Graduate Liaison, the Independent Project Manager, WSU Project Manager, and

    the SIS Steering Committee Chair). The Change Request Group then decides whether or not to approve

    the modification.

    Documentation ManagementSIS documentation is managed as a shared resource. In most cases project documents are created and

    distributed exclusively in electronic form. Documents fall under revision control once issued, so that all

    users know which version is current. Documents are clearly marked as to version, and an indication of

    what has changed is communicated when the version is released. Document authors are widely

    dispersed across the project. All project documents will be kept on the SIS project SharePoint site.

    CommunicationsThis role is responsible for all communications between the project and the University community, and

    as necessary. Communications is viewed as a two-way process. Project information must be delivered to

    the right constituencies using the right language and via the right channels. In turn, issues and concernsfrom the various university constituencies must be aggressively solicited and interpreted back into the

    project so that appropriate actions can be taken.

    The project will define and employ branding and other marketing methods to ensure that individual SIS

    communications are perceived as part of a larger cohesive whole, with connotations that reflect the

    vision and goals of the project.

  • 8/3/2019 WSUProjectCharter-v10

    29/30

    P a g e | 26

    The SIS project will use multiple channels for communication including:

    SharePoint Website Discussion forums

    Newsletters Emails Personal Letters Open forums Participation in standing meetings of extant leadership groups Participation in ad hoc meetings as appropriate Monthly meetings with urban campuses

    Other project units have significant responsibility for project communications. These include:

    Steering Committee Core Project Team Outreach and Liaison Team Integration Group Business Intelligence Advisory Council Technical Council

    Required Outreach and Operational ReadinessEven though WSUs student administrative offices are primarily responsible for implementing our new

    Student Information System, this system will serve the entire University for many years. In order to get

    the most out of it, we need all WSU personnel and students to learn about it, become familiar with it,

    think creatively about how they can use it, test its functionality, and to be ready to use it when it goes

    live.

    Monthly meetings will be held that are open to the entire University, including a Student Information

    Systems Liaison Group (representatives from all colleges, academic-support areas, campuses, and

    student groups) with the SIS Steering Committee Chair, WSU Project Manager, Consulting Project

    Manager, Content Area Leads, to talk about:

    Current implementation activities What we are learning about how Oracle works What we are changing in our business processes and what is seamlessly being implemented What issues have arisen and what decisions have been made about them and why (Whats

    not a good fit? Why is what we do not a best practice? What is the best practice?)

    What campuses, colleges, academic-support areas are concerned about (their own currentprocesses and what will be included or not) and what they may be interested in learning

    more about (new functionality pertaining to them)Agendas will be established ahead of time, and minutes will be kept of the meetings. Using agendas,

    liaisons can communicate details to their constituents and those impacted will be invited to participate

    in upcoming meeting. Using meeting minutes, members of the University community can learn the

    needed details of the discussion.

    Liaisons will be responsible for monitoring project progress via the website, attending monthly

    meetings, communicating back to their constituents about the project and representing (or ensuring

    representation of) their constituents specific needs and interests to the project.

  • 8/3/2019 WSUProjectCharter-v10

    30/30

    Once we have a module in place for testing, liaisons will be responsible for identifying the appropriate

    personnel in their areas to go through the training and then for ensuring that they actively participate

    during the testing phase of implementation. They will also be responsible for ensuring that the results

    of module testing are communicated back to the project personnel.

    At least quarterly, the SIS Project Manager will provide the Liaison Group and the WSU public a

    demonstration of Oracle functionality showing how it works and how its being set up for WSU to use.This will give people a feel for it before the modules are ready for trained personnel in the academic and

    academic-support areas to test them. That way they can get excited about it and anticipate how it

    might interface with what they do right now or how it might work very differently. This may generate

    creative thinking about business process change and may also prevent anyone from seeing any major

    surprises about the product once it is ready for testing.

    Post-ImplementationThe project budget includes consideration for the definition; setup and initial operation of the ongoing

    systems after the implementation go live events have been achieved. It is expected that a new

    organization will emerge with responsibility for ongoing governance, development, maintenance,

    operation, training, etc. for all the initiatives that are part of the SIS project. The organizational structureof this sustainability function is not known, but it is assumed that it will arise and evolve organically

    out of the implementation project structure and activities. It is also expected that some number of

    project participants will not in fact return to their home departments, but will be part of this new

    organization. In general this issue will not be further addressed until the go live events have occurred.