WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

6
WRWSA Water Supply Plan Update Progress Report – (February-March 2013) > Project Tasks 1. Water Demand Estimates 2. Availability of Ground- and Surface Water 3. Conservation and Reclaimed Water Strategies 4. Water Supply Project Options 5. Water Supply Project Configurations 6. Facility Integration Plan 7. Governance 8. Facilitation of Technical Advisory Committee

description

Project Tasks Water Demand Estimates Availability of Ground- and Surface Water Conservation and Reclaimed Water Strategies Water Supply Project Options Water Supply Project Configurations Facility Integration Plan Governance Facilitation of Technical Advisory Committee. - PowerPoint PPT Presentation

Transcript of WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

Page 1: WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

WRWSA Water Supply Plan UpdateProgress Report – (February-March 2013)

> Project Tasks1. Water Demand Estimates

2. Availability of Ground- and Surface Water

3. Conservation and Reclaimed Water Strategies

4. Water Supply Project Options

5. Water Supply Project Configurations

6. Facility Integration Plan

7. Governance

8. Facilitation of Technical Advisory Committee

Page 2: WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

WRWSA Water Supply Plan UpdateProgress Report – (February-March 2013)

> Project Tasks1. Water Demand Estimates

2. Availability of Ground- and Surface Water

3. Conservation and Reclaimed Water Strategies

4. Water Supply Project Options

5. Water Supply Project Configurations

6. Facility Integration Plan

7. Governance

8. Facilitation of Technical Advisory Committee

Page 3: WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

WRWSA Water Supply Plan UpdateProgress Report – (February-March 2013)

> Project Tasks1. Water Demand Estimates> Met with representatives of SWFWMD and SJRWMD to coordinate

demand projections methodologies> Worked with Districts to acquire all data necessary to complete

projections> Completed summary of tables and graphs for TAC review> Completed entire Chapter for insertion into report

Page 4: WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

WRWSA Water Supply Plan UpdateProgress Report – (February-March 2013)

> Project Tasks2. Availability of Ground- and Surface Water> Met with staff from the Districts to determine how they will use regional

groundwater models during the next year to evaluate groundwater availability.

> Determined that the Districts will provide Cardno with the regional model to determine impacts of proposed wellfields on water resources and MFL waterbodies.

Page 5: WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

WRWSA Water Supply Plan UpdateProgress Report – (February-March 2013)

> Project Tasks3. Conservation and Reclaimed Water Strategies> Evaluated Florida’s EZ Guide Water Conservation Model and

determined which data would be required to run the model to evaluate conservation potential for each utility

> Obtained comprehensive reclaimed water data from the SWFWMD to begin the process of projecting the quantity of reclaimed water that will be available to offset demand through 2035.

Page 6: WRWSA Water Supply Plan Update Progress Report – (February-March 2013)

WRWSA Water Supply Plan UpdateProgress Report – (February-March 2013)

> Project Tasks8. Facilitation of Technical Advisory Committee> Constituted the membership of the TAC> Determined how the meetings will be structured, dates of meetings,

and discussion topics.> Scheduled first meeting for April 24th.