WEEKLY PROGRESS UPDATE · 2019-12-20 · WEEKLY PROGRESS UPDATE DECEMBER 20TH, 2019. Progress...

3
WEEKLY PROGRESS UPDATE DECEMBER 20 TH , 2019

Transcript of WEEKLY PROGRESS UPDATE · 2019-12-20 · WEEKLY PROGRESS UPDATE DECEMBER 20TH, 2019. Progress...

Page 1: WEEKLY PROGRESS UPDATE · 2019-12-20 · WEEKLY PROGRESS UPDATE DECEMBER 20TH, 2019. Progress Photos Exterior Metal Stud Wall Installation Metal Roof Installation. PROGRESS UPDATE

WEEKLY PROGRESS UPDATE

DECEMBER 20 TH, 2019

Page 2: WEEKLY PROGRESS UPDATE · 2019-12-20 · WEEKLY PROGRESS UPDATE DECEMBER 20TH, 2019. Progress Photos Exterior Metal Stud Wall Installation Metal Roof Installation. PROGRESS UPDATE

Progress Photos

Exterior Metal Stud Wall Installation

Metal Roof Installation

Page 3: WEEKLY PROGRESS UPDATE · 2019-12-20 · WEEKLY PROGRESS UPDATE DECEMBER 20TH, 2019. Progress Photos Exterior Metal Stud Wall Installation Metal Roof Installation. PROGRESS UPDATE

PROGRESS UPDATE 12.20.2019

• INSTALLATION OF METAL ROOF AND ROOF INSULATION – ONGOING

• INSTALLATION OF EXTERIOR METAL STUD WALLS - STARTED

• NEXT WEEK: COMPLETE METAL ROOF INSTALLATION, CONTINUE EXTERIOR METAL STUD WALL INSTALLATION.

• TOTAL WORK DAYS LOST DUE TO WEATHER – 4 DAYS• TOTAL WORK DAYS LOST DUE TO INSPECTION DELAYS – 0 DAYS