Wp mp-update-camp pendleton.-april_25_2013
-
Upload
san-diego-county-water-authority -
Category
Technology
-
view
166 -
download
0
Transcript of Wp mp-update-camp pendleton.-april_25_2013
Report on Evaluation of Proposed Camp Pendleton
Seawater Desalination Project
Water Planning Committee
APRIL 25, 2013
Cesar Lopez Senior Water Resources Specialist
Presentation Outline
Background Report on latest planning and technical
studies Off-Shore Technical Studies Site Development Evaluations Product Water Conveyance Analyses
Preliminary Cost Estimates
2
Proposed Desalination Project
• 50 - 150 mgd seawater RO Project
• Phased implementation
• Unique, large coastal site at top of Aqueduct system
• 2 potential sites approved by the Base for further study
• Unlike Carlsbad, project would require new seawater intake and discharge facilities
3
Potential Project Benefits to Camp Pendleton
• RELIABILITY – Drought-proof water supply located on the base
• WATER QUALITY – High quality product water – Potential blending opportunity
• OCEAN OUTFALL – Potential for dual-use outfall for treated wastewater and concentrate
from desalination plant
4
Project Background
• Conceptual feasibility study completed
• Board added additional technical and environmental studies to CIP in 2009
• Planning MOU between SDCWA and MCBCP executed in 2010 established framework for cooperation during performance of studies
• Consultant contracts executed in 2011 for: • Technical Studies – Issues and impacts of offshore facilities • Site Development Evaluations – Plant and onshore infrastructure • Product Water Conveyance System Analyses
5
Technical Studies Objectives
Intakes: • Determine viability of subsurface intake
• Permitting agencies will require evaluation of alternative intake methods
• Considered to have least impact to marine life
• Locate and configure open ocean intake • Can be designed to minimize marine impacts
Brine Discharge:
• Locate and configure discharge system
• Minimize marine impacts
6
Technical Studies - Geologic / Hydrogeologic Investigations
• Conducted Geophysical Survey using seismic reflection
• Drilled exploratory boreholes
• Constructed test well and pump tested offshore aquifer
• Built Groundwater Model
Key Findings: • Large sub-seafloor ancient river channel
• Potential favorable geology to support large subsurface intake system
7
Technical Studies - Marine Environment Investigations
• Physical Oceanography – Ocean currents – Wave pressure
• Water Quality Monitoring and Sampling
– Temperature – Salinity – Boron / Bromide – Etc.
• Marine Biology Monitoring and Sampling – Ichthyoplankton (larvae) – Phytoplankton (algae) – Demersal Species (fish) – Infauna Invertebrate (sea-floor habitants)
Key Findings: • Typical marine environment –
nothing unusual • No fatal flaws to siting open
ocean intake and discharge 8
• Ancient river channel provides favorable geology for developing a sub-surface intake
• Open ocean intakes are feasible with low and manageable marine environment impacts
• Potential lower cost
• Oceanographic conditions (i.e. ocean currents, wave action) and marine habitat in project area are favorable for siting a brine discharge diffuser system at approx. 40 ft. depth
• Geotechnical conditions are suitable for soft-ground tunnel construction
Technical Studies – Key Conclusions
9
10
11
Site Development Evaluations Objectives
• Analyze site access, traffic flow, space availability and security • Determine optimal and reliable treatment processes for project
• For maximum utilization, consider producing “untreated” water
• Determine power requirements, supply source and transmission
• Screened Open Ocean
• Subsurface
Prepare water for desalination process
• Conventional or membrane process
• Desalination Process
• Re-hardening • Disinfection
Residual
• Treated Water System • Untreated Water System
Pre-treatment
Intake System
Reverse Osmosis
Post Treatment
Key Treatment Process Design Elements
12
MCTSSA Site Rendering
13
SRTTP Site Rendering
14
• Both sites are viable for construction and operation
• SRTTP Site offers the best site access
• “Untreated” water production possible • Maximum plant utilization • Eliminates any potential overlap with treatment plant production • Increased cost of “re-treatment” • Cost savings likely due to reduced chemical requirements and potential
elimination of second pass RO
• Phase 1 (50 mgd) project can be supported by existing power supply infrastructure.
• Future phases would require new power supply infrastructure ($91 - $164 million)
Site Evaluations – Key Conclusions
15
Product Water Conveyance Analyses
• 19 – 21 miles 72 inch diameter pipeline
16
Product Water Conveyance Key Conclusions
• The southern alignment provides the best opportunity for efficient integration into the Water Authority Aqueduct system
• Shorter alignment • Best alignment for both untreated and treated water integration • least direct impact to MCBCP
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
Elev
atio
n (ft
)
Length (ft)
Pipeline Reach
HGL of Pipeline 4EL 1242
150 MGD – EL 1300100 MGD – EL 127250 MGD – EL 1254
2A 2B 2C 2D 2E 2F 2G
Proposed Forebay and Pump StationEL 650Proposed Desalination
Facilities and Pump StationEL 60
150 MGD – EL 892100 MGD – EL 767
50 MGD – EL 686
Ground Profile
17
Capital Cost Summary
50 mgd Initial Phase
Plant Site
Seawater Intake
Desalination Plant
Brine Discharge
Conveyance System
Total
MCTSSA $218 - $360 $670 - $698 $184 $328 $1,428 - $1,542
SRTTP $241 - $369 $636 - $663 $207 $317 $1,429 - $1,529
Based on supply integration into the untreated system. Costs include oversizing buried project components for the 150 mgd ultimate capacity.
Costs in million $
18
Cost Estimate Summary
Plant Production Capacity 50 mgd 150 mgd
Capital Costs (million$) Desalination Plant 1,110 – 1,260 2,320 – 2,900 Conveyance 317 – 328 350 – 360 Annual O&M Costs (million$) 61 - 70 174 - 200
Total Unit Cost ($ per AF) 2,750 - 3,100 2,070 - 2,450
19
Questions?
20