Wp mp-update-camp pendleton.-april_25_2013

20
Report on Evaluation of Proposed Camp Pendleton Seawater Desalination Project Water Planning Committee APRIL 25, 2013 Cesar Lopez Senior Water Resources Specialist

Transcript of Wp mp-update-camp pendleton.-april_25_2013

Page 1: Wp   mp-update-camp pendleton.-april_25_2013

Report on Evaluation of Proposed Camp Pendleton

Seawater Desalination Project

Water Planning Committee

APRIL 25, 2013

Cesar Lopez Senior Water Resources Specialist

Page 2: Wp   mp-update-camp pendleton.-april_25_2013

Presentation Outline

Background Report on latest planning and technical

studies Off-Shore Technical Studies Site Development Evaluations Product Water Conveyance Analyses

Preliminary Cost Estimates

2

Page 3: Wp   mp-update-camp pendleton.-april_25_2013

Proposed Desalination Project

• 50 - 150 mgd seawater RO Project

• Phased implementation

• Unique, large coastal site at top of Aqueduct system

• 2 potential sites approved by the Base for further study

• Unlike Carlsbad, project would require new seawater intake and discharge facilities

3

Page 4: Wp   mp-update-camp pendleton.-april_25_2013

Potential Project Benefits to Camp Pendleton

• RELIABILITY – Drought-proof water supply located on the base

• WATER QUALITY – High quality product water – Potential blending opportunity

• OCEAN OUTFALL – Potential for dual-use outfall for treated wastewater and concentrate

from desalination plant

4

Page 5: Wp   mp-update-camp pendleton.-april_25_2013

Project Background

• Conceptual feasibility study completed

• Board added additional technical and environmental studies to CIP in 2009

• Planning MOU between SDCWA and MCBCP executed in 2010 established framework for cooperation during performance of studies

• Consultant contracts executed in 2011 for: • Technical Studies – Issues and impacts of offshore facilities • Site Development Evaluations – Plant and onshore infrastructure • Product Water Conveyance System Analyses

5

Page 6: Wp   mp-update-camp pendleton.-april_25_2013

Technical Studies Objectives

Intakes: • Determine viability of subsurface intake

• Permitting agencies will require evaluation of alternative intake methods

• Considered to have least impact to marine life

• Locate and configure open ocean intake • Can be designed to minimize marine impacts

Brine Discharge:

• Locate and configure discharge system

• Minimize marine impacts

6

Page 7: Wp   mp-update-camp pendleton.-april_25_2013

Technical Studies - Geologic / Hydrogeologic Investigations

• Conducted Geophysical Survey using seismic reflection

• Drilled exploratory boreholes

• Constructed test well and pump tested offshore aquifer

• Built Groundwater Model

Key Findings: • Large sub-seafloor ancient river channel

• Potential favorable geology to support large subsurface intake system

7

Page 8: Wp   mp-update-camp pendleton.-april_25_2013

Technical Studies - Marine Environment Investigations

• Physical Oceanography – Ocean currents – Wave pressure

• Water Quality Monitoring and Sampling

– Temperature – Salinity – Boron / Bromide – Etc.

• Marine Biology Monitoring and Sampling – Ichthyoplankton (larvae) – Phytoplankton (algae) – Demersal Species (fish) – Infauna Invertebrate (sea-floor habitants)

Key Findings: • Typical marine environment –

nothing unusual • No fatal flaws to siting open

ocean intake and discharge 8

Page 9: Wp   mp-update-camp pendleton.-april_25_2013

• Ancient river channel provides favorable geology for developing a sub-surface intake

• Open ocean intakes are feasible with low and manageable marine environment impacts

• Potential lower cost

• Oceanographic conditions (i.e. ocean currents, wave action) and marine habitat in project area are favorable for siting a brine discharge diffuser system at approx. 40 ft. depth

• Geotechnical conditions are suitable for soft-ground tunnel construction

Technical Studies – Key Conclusions

9

Page 10: Wp   mp-update-camp pendleton.-april_25_2013

10

Page 11: Wp   mp-update-camp pendleton.-april_25_2013

11

Page 12: Wp   mp-update-camp pendleton.-april_25_2013

Site Development Evaluations Objectives

• Analyze site access, traffic flow, space availability and security • Determine optimal and reliable treatment processes for project

• For maximum utilization, consider producing “untreated” water

• Determine power requirements, supply source and transmission

• Screened Open Ocean

• Subsurface

Prepare water for desalination process

• Conventional or membrane process

• Desalination Process

• Re-hardening • Disinfection

Residual

• Treated Water System • Untreated Water System

Pre-treatment

Intake System

Reverse Osmosis

Post Treatment

Key Treatment Process Design Elements

12

Page 13: Wp   mp-update-camp pendleton.-april_25_2013

MCTSSA Site Rendering

13

Page 14: Wp   mp-update-camp pendleton.-april_25_2013

SRTTP Site Rendering

14

Page 15: Wp   mp-update-camp pendleton.-april_25_2013

• Both sites are viable for construction and operation

• SRTTP Site offers the best site access

• “Untreated” water production possible • Maximum plant utilization • Eliminates any potential overlap with treatment plant production • Increased cost of “re-treatment” • Cost savings likely due to reduced chemical requirements and potential

elimination of second pass RO

• Phase 1 (50 mgd) project can be supported by existing power supply infrastructure.

• Future phases would require new power supply infrastructure ($91 - $164 million)

Site Evaluations – Key Conclusions

15

Page 16: Wp   mp-update-camp pendleton.-april_25_2013

Product Water Conveyance Analyses

• 19 – 21 miles 72 inch diameter pipeline

16

Page 17: Wp   mp-update-camp pendleton.-april_25_2013

Product Water Conveyance Key Conclusions

• The southern alignment provides the best opportunity for efficient integration into the Water Authority Aqueduct system

• Shorter alignment • Best alignment for both untreated and treated water integration • least direct impact to MCBCP

0

100

200

300

400

500

600

700

800

900

1000

1100

1200

1300

1400

Elev

atio

n (ft

)

Length (ft)

Pipeline Reach

HGL of Pipeline 4EL 1242

150 MGD – EL 1300100 MGD – EL 127250 MGD – EL 1254

2A 2B 2C 2D 2E 2F 2G

Proposed Forebay and Pump StationEL 650Proposed Desalination

Facilities and Pump StationEL 60

150 MGD – EL 892100 MGD – EL 767

50 MGD – EL 686

Ground Profile

17

Page 18: Wp   mp-update-camp pendleton.-april_25_2013

Capital Cost Summary

50 mgd Initial Phase

Plant Site

Seawater Intake

Desalination Plant

Brine Discharge

Conveyance System

Total

MCTSSA $218 - $360 $670 - $698 $184 $328 $1,428 - $1,542

SRTTP $241 - $369 $636 - $663 $207 $317 $1,429 - $1,529

Based on supply integration into the untreated system. Costs include oversizing buried project components for the 150 mgd ultimate capacity.

Costs in million $

18

Page 19: Wp   mp-update-camp pendleton.-april_25_2013

Cost Estimate Summary

Plant Production Capacity 50 mgd 150 mgd

Capital Costs (million$) Desalination Plant 1,110 – 1,260 2,320 – 2,900 Conveyance 317 – 328 350 – 360 Annual O&M Costs (million$) 61 - 70 174 - 200

Total Unit Cost ($ per AF) 2,750 - 3,100 2,070 - 2,450

19

Page 20: Wp   mp-update-camp pendleton.-april_25_2013

Questions?

20