WP 2012-10 Bored Tunnels

download WP 2012-10 Bored Tunnels

of 4

Transcript of WP 2012-10 Bored Tunnels

  • 7/30/2019 WP 2012-10 Bored Tunnels

    1/4

    Bored tunnels are some o the

    most demanding and challenging

    projects a waterprooer will ever

    work on.Unlike tunnels close to the surace,

    which are usually constructed using

    cut-and-cover techniques, bored or

    mined tunnels are constructed deep

    below grade, where sometimes just

    getting to the worksite is a major ordeal.

    Additionally, the pressures, depths, and

    lack o repair options inherent in this

    type o work make doing the job right

    even more critical than usual.

    Because o these challenges, boredtunnels are usually economical only

    when other construction methodssuch

    as cut-and-covercant be used, usually

    because the jobsite is too deep. Its not

    unusual or bored tunnels to reach 160

    eet below the surace. At those depths,

    the tunnel is almost always carved

    through solid bedrock. In other cases,

    bored tunnels are preerred because the

    surace cannot be disturbed.

    Basic tunneling methods are airly

    standard. First, the tunnel is excavated

    using heavy equipment, drill-and-blast

    mining techniques, gigantic tunnelboring machines (BMs) or some

    combination o the above. I needed, soil

    nails and rock bolts are then installed

    to strengthen and stabilize the newly

    exposed ace. Also, nearly every bored

    tunnel receives a layer o shotcrete that

    serves the same purpose.

    Most o the popular waterproong

    methods take advantage o this shotcrete

    layer to simpliy the waterproong

    process. Once this is in place, workerscan install any drainage and/or

    waterproong membranes. Finally, a

    grid o reinorcing steel is set up, and a

    nal tunnel lining is cast. Tis lining is

    usually either another layer o shotcrete

    or a traditional concrete mix thats cast-

    in-place using sliporms.

    While each jobsite is unique and

    each project requires a customized

    waterproong system, these systems can

    be categorized into just a ew basic types.

    Crystalline Systems

    Perhaps the least complex methodis to incorporate a crystalline admixture

    into the shotcrete so that the concrete

    itsel becomes waterproo and sel

    sealing. In past decades, the product

    was usually applied as a powder or a

    liquid aer-the-act. Recently though,

    a better method has been developed.

    (For more on crystalline admixtures, see

    Understanding Integral Waterproofng in

    the Spring 2010 issue.)

    Ann Martucci, a marketing executive

    Waterproofng Techniques

    For Bored Tunnels

    PhotoCourtesyICSPenetron

    Bored tunnels, suchas this Pacifc Coast

    Highway tunnel nearDevils Slide, Caliornia,

    can be a challengeor waterprooers.

    Typically, the stakes arehigh, the jobsite remote,

    and project size isenormous.

    24 WATERPROOF!

    https://na8.salesforce.com/0038000000TzftQ?srPos=0&srKp=003https://na8.salesforce.com/0038000000TzftQ?srPos=0&srKp=003
  • 7/30/2019 WP 2012-10 Bored Tunnels

    2/4

  • 7/30/2019 WP 2012-10 Bored Tunnels

    3/4

    on the Devils Slide tunnel, construction

    ollowed the typical pattern. Workers

    installed a double mat o rebar to match

    the areas seismic requirements. A rail-

    mounted slip-orm was used to cast the

    nal tunnel lining.

    CECO has recently developed a

    series o PVC membranes specically

    or bored tunnels. Te CoreFlex 60

    integrates a 60-mil thermoplastic

    membrane with DuPont's Elvaloy-

    KEE (Keytone Ethylene Ester) to seal

    any leaks that develop. Its reportedly

    the only thermoplastic membrane

    composite with this reactive, sel-sealing

    perormance eature.

    Te company also makes 80- 100-

    and 120-mil membranes without the sel

    sealing liners.

    Te tunneling industry really

    preers these durable PVC membranesbecause o the longer service lie, reports

    Stacy Byrd, National Products Manager

    at CECO.

    Drainage and WaterstopsMany tunnel designsespecially

    deep tunnel designsallow or a certain

    amount o leakage.

    Designers typically shy away rom

    speciying drain sheets, as pressures

    deep within the earth are extreme, andthey dont want anything compressible

    in the design. Still, some sort o drainage

    is needed to reduce hydrostatic pressure

    on the waterproong system. Engineers

    typically turn to a system o waterstops,

    drain pipes, and sump pumps.

    Te goal is to direct the fow o water

    to the drain lines or discharge as quickly

    as possible.

    I a PVC membrane is used,

    thermoplastic waterstops are standard,

    as they can be welded to the membrane.

    PVC waterstopsfexible, impermeable

    barriersare installed vertically at

    regular intervals to limit the distance

    water can migrate behind the membrane.

    Byrd reports that theyre typically

    installed every 30 eet or so, dividing

    the tunnel into drainage sections o

    no more than a thousand square eet.

    Tese waterstops are dierent rom the

    conventional cold-joint waterstops used

    in regular concrete work. Tey have

    a dierent prole, and are so sti that

    they cant easily be rolled. Tey typically

    arrive at the jobsite in long straight

    sections with separate actory-abricated

    connections.

    Te preerred solution or drain

    lines is surprisingly mundane: the

    standard perorated-pipe-in-gravelevery waterproong contractor is

    amiliar with. On the 25-mile Channel

    unnel connecting England to France,

    the perorated pipe was laid in the gravel

    ballast under the rails.

    I possible, the pipes are run to

    daylight and drained by gravity. On the

    Channel unnel and other deep tunnels,

    a standard sump pump setup is used.

    Polyurethane GroutSystemsLike every type o project, bored

    tunnels have an Achilles Heel. Cold

    joints, expansion joints, and connections

    to other tunnelssuch as ventilation

    shas or cross passagesare prone to

    leakage and require extra care.

    One popular method or secondary

    waterproong or remedial repair is

    polyurethane grout. Teyre especially

    useul when access shas or other

    penetrations create geometric shapes

    that are too awkward or sheet goods to

    seal adequately. Tis grout is usually

    injected as a liquid resin that reacts with

    water to orm a watertight, permanent

    seal.

    Grace Construction Products

    markets a sheet membrane that comes

    with a grid o polyurethane grout

    injection ports pre-installed. Aer the

    nal tunnel lining is installed, the grout

    can be injected at any location to ensure

    a watertight bond.

    CECOs line o thermoplastic

    membranes can also be installed with

    integral grout tubes.

    Additional ConsiderationsWaterproong is critical in deep

    tunnel applications because the stakesare so high. Maintenance or repair

    work typically would cause a serious

    interruption in service, so the job has to

    be done right. A ailed waterproong

    job, though, is not only inconvenient,

    but dangerous. In a mountain highway

    tunnel, or instance, any water or ice

    buildup is a serious saety hazard.

    Peter DAntonio, who oversees

    tunnel sales or Sika Sarnal, notes,

    Proper waterproong o tunnels isone o the most cost-eective ways to

    increase the useul lie o these structures

    and enhance saety. Water seeping into

    a structure endangers the building

    materials through the reeze-thaw

    cycle, with water reezing inside cracks

    and causing them to enlarge. Further,

    preventing water rom reezing on road

    suraces increases saety. n

    P h o

    t o C o u r t e s y X y p e x

    The 25-mile-long Channel Tunnel, connecting England and France,used more than 500 tons o joint waterproofng.

    26 WATERPROOF!

  • 7/30/2019 WP 2012-10 Bored Tunnels

    4/4