Workshop on ICTAD/SBD2 & FIDIC 1999 (C) Contract
Transcript of Workshop on ICTAD/SBD2 & FIDIC 1999 (C) Contract
CONSTRUCTION INDUSTRY DEVELOPMENT AUTHORITY
CENTER FOR HOUSING PLANNING AND BUILDING
TVEC Registration - Reg. No. P01/0545
Workshop on ICTAD/SBD2 & FIDIC 1999 (C) Contract
MINISTRY OF HOUSING AND CONSTRUCTION
To Whom : Engineers, Quantity Surveyors, Architects, Accountants, Auditors, Project Managers, Design Officers, Contractors, Technical Officers & Technical Staff of stakeholders.
Contents :
Dates :
15th , 22nd May & 05thJune 2018 Time : 9.00 am - 16.00 pm
Course Fee :
Rs. 15,000/= (Including Course Materials & Meals)
Payments :
Cheque Payment : The Cheque should be drawn in favour of “Chairman, Construction Industry Development Authority”
Direct payment to the bank, A/C 77454975 - BOC Independent Square Please send a copy of deposited slip by Fax or E-Mail
Venue : Centre for Housing Planning & Building (CHPB) No.33, Parliament Road, Pelawatta, Battaramulla.
Medium : English with Sinhala Explanation
Resource Person
: Mr. Tilak Kolonne B Sc,Dip Arb, Dip(Adj)*, FIQSSL
Consultant, Mediator, Adjudicator/ DB Member, Arbitrator
A valuable certificate of participation will be awarded by CIDA Mandatory CCD Points for CIDA registered contractors : 10 Points (per person subject to a maximum of 50)
For further details : T P : 011-2787661 / 011-3069270 Fax : 011-2785629 E - Mail : [email protected] Web : www.cida.ik FB : cida chpb
Introduction to FIDIC (and ICTAD Contracts) Contract interpretation (Sub-
Clause 1.2) Rules of interpretation and
the legal background Letter writing Priority of documents (Sub-
Clause 1.5) The Employer (Clause 2) The Engineer (Clause 3)
The Contractor (Sub-Clauses 4.1, 4.3, 4.10 – 4.12) (Design liability, Design-Build,
liability for “fit-for-purpose”) Right of access, commence-
ment, appointments etc Delayed Drawings or Instruc-
tions (Sub-Clause 1.9)
Time, extension of time, com-pletion (Clause 8) Employer’s Taking Over
(Clause 10) Defects Liability (Clause 11)
Financial Procedures (Clauses 12, 13 and 14) Employer’s Claims (Sub-Clause
2.5) Claims, Disputes and Arbitra-
tion (Clause 20) (Notices; Claims in Contract,
Tort, Restitution; loss, damag-es, remoteness)
Assignment (Sub-Clause 7)
Subcontracting (Sub-Clauses 4.4, 4.5 and Clause 5) Free-Issue Material (Sub-
Clause 4.20) Tests on Completion (Clause
9) Tests After Completion
(Clause 12 of P&DB/EPC) Termination by Employer
(Clause 15) Suspension and Termination
by Contractor (Clause 16) Risks and Responsibility
(Clause 17) Force Majeure (Clause 19)