Work Method Statements for Reed Select
description
Transcript of Work Method Statements for Reed Select
![Page 1: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/1.jpg)
REEDS ELECTRICAL SERVICES PTY LTD
WORK METHOD STATEMENTS
As these Work Method Statements may be used on building sites, the Risk Levels are as defined in the Principal Contractors Safety Alliance “Subby Pack” as follows:
Class 1, High Risk: Does the hazard have the potential to kill or permanently disable you?
Class 2, Medium Risk: Does the hazard have the potential to cause serious injury or illness which would temporarily disable you?
Class 3, Low Risk: Does the hazard have the potential to cause a minor injury which would not disable you?
![Page 2: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/2.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement CONDUIT INSTALLATION, PLACED PRIOR TO POURING CONCRETE WMS No 001 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By : Matt Reed
Project: All Sites Applicable Section Project Manager:
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check layout and mark out.
2. Install disposable lids fro conduit boxes to timber
3. Lay conduit and accessories.
4. Tie down conduit.
Tripping and exposed nails.
Cuts and abrasions.
Chemical glues.
Cuts and abrasions
3
3
3
3
Ensure areas in particular walkways are clear (1.5)
Use suitable gloves (3.4)
Refer to MSDS and follow safe work practices set out therein
Use suitable gloves (3.4)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 3: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/3.jpg)
WORK METHOD STATEMENT : CONDUIT INSTALLATION, PRIOR TO CONCRETE POUR WMS No. 001. Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Hand tools to be checked daily.
Read and Signed by All Employees on Site:
![Page 4: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/4.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement CONDUIT INSTALLATION IN THE GROUND WMS No 002 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1.Check area for other services and confirm locations of any gas lines, power cables, telephone cables, water or sewer lines and tree roots.
2. Check layout and mark out
3.Excavate trenches
4.Lay conduit
5. Restore ground to client’s specifications
Sun exposureTripping
Tripping
Manual handling
Falling in trenches
Trench collapse
Services damage
Fire and explosionPersonal injuryElectric shockConfined spaces
Manual handingTripping
23
3
2
3
3
3
3312
23
Use skin protection (3.4)Ensure are is clear (1.5)Ensure location of other services is confirmed and appropriate access permits obtained.
Ensure area is clear (1.5) . Wear safety footwear (3.4)
Implement manual handling risk control procedures (1.7)
Ensure trenches are as even and flat as practical (5.3)Barricade work areaProvide shoring, benches or battering in accordance with WorkCover requirements (5.2)Provide warning lights if necessary overnight
Comply WorkCover requirements (5.2)Implement risk management procedures (1.7)Confirm any existing installations are dead.Follow Standard Working Procedures (3.6)
Implement manual handling risk control procedures (1.7)Ensure area is clear (1.5)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 5: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/5.jpg)
WORK METHOD STATEMENT: CONDUIT INSTALLATION IN GROUND WMS No. 002. Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice under the supervision of a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3.No previous experience required. Barricades to be used as appropriate
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Engineering details to include depth of trenches in accordance with AS 3000 and client’s specifications.
Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Hand tools for trenching, barricades, warning lights. Hand tools and ladders to be checked daily. Batteries for warning lights.
Read and Signed by All Employees on Site:
![Page 6: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/6.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement CONDUIT INSTALLATION IN WALLS AND CEILINGS WMS No 003 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check layout and mark out
2. Check equipment is tagged
3. Secure fixings and supports
Tripping and exposed nails.
Electric Shock
Debris and noise from drilling
Struck by falling objects
Falling
3
1
3
2
2
Ensure area in particular walkways are clear (1.5)Wear safety footwear (3.4)
Use only correctly tagged equipment (4.2)
Use minimum drilling speed consistent with effective work.Use goggles fro eye protection, suitable respirator and hearing protection (3.4)Ensure drill bits are sharpUse ladders in accordance with WMS 006 (5.3)Use fall protection where appropriate (3.5)
Wear safety helmet (3.4)Restrict trafficMobile scaffolds locked (5.4)Use ladders in accordance with WMS 006 (5.3)EWP Certificate
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 7: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/7.jpg)
WORK METHOD STATEMENT: CONDUIT INSTALLATION IN WALLS AND CEILINGS WMS No. 003. Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3.EWP Certificate 3. EWP training if using EWP.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Installation to comply with AS 3000 and clients specifications. Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable tools, ladders, EWP Hand tools and ladders to be checked daily. EWP in accordance with manufacturers recommendations.
Read and Signed by All Employees on Site:
![Page 8: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/8.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement CABLE AND LADDER TRAY INSTALLATION WMS No 004 Page 1of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check layout and mark out
2. Secure fixings and supports using correct size bolts and fixings
3. Cut ladders or trays to fit using drop saw or 100mm angle grinder
4. Secure ladders or trays to support
5. Remove sharp edges and protruding fixings
Tripping and exposed nails
Debris and noise from drilling
Noise, eye injuries, cuts and abrasions
Cuts and abrasion from sharp edges
Working at heights, falls
Manual handling
Burns and fires from cutting and welding
3
2
2
2
2
2
2
Ensure are a in particular walkways are clear (1.5)Wear safety footwear (3.4)
Use minimum drilling speed consistent with effective work.Use PI respirator if appropriate(3.4)Use appropriate eye protection (3.4)Ensure drill bits and sharp.
Ensure workpiece is clamped. Use eye and hearing protection Use gloves (3.4)
Use ladders in accordance with WMS 006 (5.3)Use fall protection where appropriate (3.5) Use gloves (3.4)
Use ladders in accordance with WMS 006 (5.3)Use fall protection where appropriate (5.3)
Follow manual handling risk control procedures (1.7)
Follow Hot Work procedures (4.6)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 9: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/9.jpg)
WORK METHOD STATEMENT: CABLE AND LADDER TRAY INSTALLATION WMS No. 004 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. No previous experience required. 3. EWP Training if using EWP.
4. EWP Certificate
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications. Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable drill, welder, ladders, EWP, grinder, drop saw. Hand tools to be checked daily.
Read and Signed by All Employees on Site:
![Page 10: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/10.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement WORKING IN RISERS WMS No 005 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check location to drawing and reference to specification layout and mark out.
2. Check for access to riser and have clear working are
3. Check for confined spaces
4. Check for adequate lighting
5. Protect al openings to risers
6. Install warning signs
Tripping and exposed nails
Falling, falling objects
Restricted working space
Work restrictions
Falling
Objects falling
3
2
2
3
2
2
Ensure area in particular walkways are clear (1.5)Wear safety footwear (3.4)
Wear safety helmets with chin straps (3.4)Use fall protection as appropriate (3.5)Provide training and use entry permit when appropriate
Implement Confined Space Procedure if necessary
Use supplementary lighting if necessary
Builder to provide protection
Using appropriate sign eg,“DANGER MEN WORKING ABOVE”
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 11: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/11.jpg)
WORK METHOD STATEMENT: WORKING IN RISERS WMS No. 005 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3.Confined space training. 3. Confined space training if applicable
4. No previous experience required. .
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable tools. Hand tools to be checked daily.
Read and Signed by All Employees on Site:
![Page 12: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/12.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement USING PORTABLE LADDERS WMS No 006 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Select appropriate ladder with regard to compliance with the relevant part of AS 1892 and the work to be done.
2 Inspect the ladder for condition.
3. Position ladder to ensure stability.
Electric shock
Falling
Falling
1
2
2
Metal or wire reinforced ladders shall not be used for any electrical work (5.3)
Inspect ladders. Do not use damaged ladders. (5.3)
Position ladders a minimum of 1 metre from edges of slabs or floors.Increase this distance as working heights increases.Straight or extension ladders to be secured at top and bottom.Ladders needs to extend 1 metre above landing level and to be long enough to work at least 1 metre from the top (5.3)Angle of ladder should be nominally 1in 4 (5.3)Always face the ladder.When ascending or descending a ladder keep two hands and one foot on the ladder. (5.3)Fall protection to be used when working above 1.8m (5.3)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 13: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/13.jpg)
WORK METHOD STATEMENT: USING PORTABLE LADDERS WMS No. 006 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Ladders complying with the relevant part of AS 1892. Ladders to be checked daily.
Read and Signed by All Employees on Site:
![Page 14: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/14.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLING LIGHT FITTINGS WMS No 007 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check layout and mark out.
2. Receive lights on site and confirm correct numbers and types
3. Confirm cabling requirements.
4. Install light fitting base or bracket and terminate cabling or plug into lighting socket.
5. Complete the fitting of any other parts.
6. Confirm fitting is secure and installed to specifications.
7. Clear area and remove isolation danger tags
Tripping and exposed nails
Struck by falling objectsManual handling
Electric shock
Electric shock Falling
Falling
Falling
Hand injuries
3
2
2
1
12
2
2
3
Ensure area in particular walkways are clear (1.5)Wear safety foot wear
Keep lifting area clear of people. (4.9)
Implement manual handling risk control procedures(1.7)
Test and confirm cables before commencing work. Isolate and fit danger tags as appropriate (3.1, 3.2)
Ensure power tools and leads are tagged (4.2)Use ladders or platforms appropriately (5.3)
Use ladder or platform appropriately. (5.3)
Use ladder or platform appropriately. (5.3)
Use gloves. (3.4)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
*To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 15: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/15.jpg)
WORK METHOD STATEMENT: INSTALLING LIGHT FITTINGS WMS No. 007 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. No previous experience required. 3. EWP Training if using EWP.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications. Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable drill, leads and ladders. Hand tools and ladders to be checked daily.
Read and Signed by All Employees on Site:
![Page 16: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/16.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF SWITCHBOARDS WMS No 008 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Confirm installation specifications.
2. Prepare installation area and confirm adequate space including door swing for maintenance.
3. Arrange for crane or other mechanical handling equipment if needed.
4. Receive switchboard on site including test certificates.
5. Transfer switchboards to installation location
6. Mark out location ensuring coordination with other services.
7. Install switchboard to manufacture’s and client’s specifications.
8. Commission switchboard
9. Clean area
N/A
Hand injuries, tripping and exposed nail
N/A
Falling objectsManual handling
Falling objectsManual HandlingN/A
Manual handling
Electric shock, explosion
Hand injuries
N/A
3
N/A
22
22
2
1
3
N/A
Ensure Area in particular walkways are clear (1.5)Wear safety footwear (3.4)Use suitable gloves (3.4)
N/A
Keep lifting area clear of people (4.9)Implement manual handling risk control procedures (1.7)
Use mechanical handling equipment (4.9)Implement manual handling risk control procedures (1.7)N/A
Implement manual handling risk control procedures (1.7)
Carry out pre-commission test and isolation procedures (6.3,6.4)
Use suitable gloves (3.4)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 17: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/17.jpg)
WORK METHOD STATEMENT : INSTALLATION OF SWITCHBOARDS WMS No. 008 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to complete work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals Codes of Practice, Legislation
AS3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Portable drills, ladders, appropriate mechanical handling equipment.
Maintenance Checks: Mechanical handling equipment to be check in accordance with Statutory and manufacturer’s requirements.
Hand tools and ladders to be checked daily.
Read and Signed by All Employees on Site:
![Page 18: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/18.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF PYROTENAX (MIMS) CABLE WMS No 009 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check location to drawing and specification layout and mark out
2. Confirm cable specification and condition.
3. Confirm cable supports on conduits have been installed to specifications.
4. Install rollers on other protection to client’s specifications.
5. Install cable stands to client’s specifications.
6. Install cable manually with rope or winch as appropriate to client’s specification.
7. Cut any excess cable and seal exposed ends to manufacturer’s recommendations
8. Locate/dress cable to fix in position to client’s specification.
Tripping and exposed nails
N/A
Falls
Falls
Manual handling
Manual handling
Hand injuries
Falls
3
N/A
2
2
2
2
3
2
Ensure area is clear (1.5)Wear safety footwear (3.4)
N/A
Refer to WMS 004, cable and ladder tray installation
Use ladders in accordance with WMS 006 (5.3)Use fall protection as appropriate (3.5)
Implement manual handling risk control procedures (1.7)
Implement manual handling risk control procedures (1.7)
Use suitable gloves (3.4)Use toll in accordance with manufacturer’s instruction
Use ladders in accordance with WMS 006 (5.3)Use fall protection as appropriate (3.5)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 19: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/19.jpg)
WORK METHOD STATEMENT: INSTALLATION OF PYROTENAX (MIMS) CABLE WMS No. 009 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Manufacture’s recommended tools. Maintenance Checks:
Hand tools to be checked daily.
Read and Signed by All Employees on Site:
![Page 20: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/20.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF LIGHTING LOOMS WMS No 010 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check drawings to confirm loom locations and specifications.
2. Receive cable and sockets bases on site and confirm correct types, sizes and numbers.
3. Construct lighting looms to client’s specifications.
4. Label each loom with distribution board and circuit number.
5. Install looms to client’s specifications.
6. Confirm socket locations and fixings to client’s specification
7. Install circuit feeds and switch wires to client’s specifications.
8. Clean area.
N/A
Struck by falling objectManual handling
Hand injuries
N/A
Electric shockFalls
Falls
Electric shockFalls
Hand injuries
N/A
32
3
N/A
12
2
12
3
N/A
Keep lifting area clear of people (4.9)Implement manual handling risk control procedures (1.7)
Use tool appropriately
N/A
Use only correctly tagged equipment (4.2)Use ladders in accordance with WMS 006 (5.3)
Use ladders in accordance with WMS006 (5.3)
Use only correctly tagged equipment (4.2)Use ladders in accordance with WMS 006 (5.3)
Wear suitable gloves (3.4)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 21: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/21.jpg)
WORK METHOD STATEMENT: INSTALLATION OF LIGHTING LOOMS WMS No. 010. Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Portable tools, ladders Maintenance Checks:
Hand tools and ladders to be checked daily.
Read and Signed by All Employees on Site:
![Page 22: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/22.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF CABLE SUPPORTS WMS No 011 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check location to drawing and specifications
2. Receive cable supports on site confirming correct type, size and number
3. Mark out route of cable supports to specifications confirming clearance of other services
4. Install supports to client’s specifications supporting as necessary and using correct size bolts.
5. Confirm tightness of fixings
6. Install cable supports
7. Clean area
Tripping and exposed nails
Struck by falling objectsManual handling
Falling
Electric shockFalling
Falling
Struck by falling objectsFalling
Hand injuries
3
22
2
12
2
22
3
Ensure area is clear (1.5)Wear safety footwear (3.4)
Keep lifting area clear of people (4.9)Implement manual handling risk control procedures (1.7)
Use ladders in accordance with WMS 006 (5.3)Use fall protection as appropriate (3.5)
Ensure power tools and leads are tagged (4.2)Use ladders in accordance with WMS 006 (5.2)
Use ladders in accordance with WMS 006 (5.2)
Keep lifting area clear of people (4.7)Use ladders in accordance with WMS 006(5.3)Use fall protection as appropriate (3.5)
Use suitable gloves
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 23: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/23.jpg)
WORK METHOD STATEMENT: INSTALLATION OF CABLE SUPPORTS WMS No. 011. Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. EWP Certificate 3. EWP Certificate if using EWP.
4. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable drill, ladders, EWP Hand tools to be checked daily. EWP in accordance with manufacture’s recommendations.
Read and Signed by All Employees on Site:
![Page 24: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/24.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF MAINS WMS No 012 Page 1 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Liase with Supply Authority to coordinate to supply.
2. Obtain Supply Authority Certificates and check drawings.
3. Coordinate shutdowns with client.
4. Receive mains on site.
5. Shut down and install DANGER Tags.
6. Remove existing mains terminations if applicable.
7. Install mains to specifications.
8. Terminate new mains to specifications.
N/A
N/A
N/A
Falling objectsManual handling
Electric shock
Electric shock
Electric shock
Electric shock
N/A
N/A
N/A
22
1
1
1
1
N/A
N/A
N/A
Keep lifting area clear of people (4.7)Implement manual handling risk control procedures (1.7)
Confirm DEAD before commencing work (6.1)
Confirm DEAD before commencing work (6.1)
Confirm DEAD before commencing work (6.1)
Confirm DEAD before commencing work (6.1)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide fro Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 25: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/25.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF MAINS WMS No 012 Page 2 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
9. Confirm installation to drawings and specifications
and ensure connections are tight.
10. Clean area.
11. Test installation.
12. Liase with Supply Authority for inspection and test.
13. Remove DANGER Tags.
14. Energise supply.
15. Install signs or labels as required.
Electric shock
Hand injuries
Electric shock
N/A
N/A
Electric shock
Hand injuries
1
3
1
N/A
N/A
1
3
Confirm DEAD and identify cables before commencing work (6.1)
Wear suitable gloves (3.4)
Confirm DEAD and identify cables before commencing work (6.1)
N/A
N/A
Follow Standard Working procedures. (Chapter 6)
Use tools appropriately (5.6)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide fro Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 26: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/26.jpg)
WORK METHOD STATEMENT: INSTALLATION OF MAINS WMS No. 012 Page 3 of 3
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. EWP Certificate
4. No previous experience required.
3. EWP training if using EWP.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Installation to comply with AS 3000 and clients specifications. Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable tools, ladders, EWP Hand tools and ladders to be checked daily. EWP in accordance with manufacturers recommendations.
Read and Signed by All Employees on Site:
![Page 27: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/27.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF SWITCHBOARD CONNECTIONS WMS No 013 Page 1 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Confirm switchboard meets and has been installed to specifications
2. Confirm cables to be connected meet specifications and all cables have been installed. Check any specific requirements have been met.
3. Group cables together as they enter switchboard and fix with cable ties.
4. Separate cables into groups of like destination. Seal or plug any unused cable entries.
5. Mark each conductor prior to removing any secondary insulation.
6. Group conductors of like destinations and fix into a loom system
7. Align and terminate each conductor into its correct location.
N/A
N/A
Hand injuries
Electric shock
N/A
Hand injuries
Electric shock
N/A
N/A
3
1
N/A
3
1
N/A
N/A
Use suitable gloves (3.4)
Confirm DEAD before commencing work (6.1)
N/A
Use suitable gloves (3.4)
Confirm DEAD before commencing work (6.1)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 28: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/28.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF SWITCHBOARD CONNECTIONS WMS No 013 Page 2 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
8. Check and tighten all terminations and connections.
9. Confirm installations meet specifications.
10. Install labels, signs or markings as required.
11. Clean switchboard.
12. Confirm all circuits have been completed and DANGER TAG any incomplete circuits.
13. Test and commission switchboard using relevant procedures. Confirm phase rotation of all 3 phase equipment.
14. Complete records.
Electric shock
N/A
N/A
Hand injuries
N/A
Electric shock
N/A
1
N/A
N/A
3
N/A
1
N/A
Confirm DEAD before commencing work (6..1)
N/A
N/A
Use suitable gloves (3.4)
N/A
Follow safe work practices (6.3)
N/A
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 29: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/29.jpg)
WORK METHOD STATEMENT: INSTALLATION OF SWITCHBOARD CONNECTIONS WMS No. 013 Page 3 of 3
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. No previous experience required. 3. EWP Training if using EWP.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications. Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Portable drill, leads and ladders. Hand tools and ladders to be checked daily.
Read and Signed by All Employees on Site:
![Page 30: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/30.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF NEW WORK IN EXISTING SWITCHBOARDS WMS No 014 Page 1 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check drawings and specifications.
2. Arrange isolation of section of, or complete switchboard with client.
3. Isolate section of, or complete switchboard, install insulating barriers.
4. Fit DANGER TAGS to isolation devices.
5. Test that work area has been safely isolated.
6. Complete installations to client’s specification.
7. Check and tighten all terminations and connections.
N/A
N/A
Electric shock
N/A
Electric shock
Electric shock
Electric shock
N/A
N/A
1
N/A
1
1
1
N/A
N/A
Confirm DEAD before commencing work (6.1)Follow Standard Working Procedures (Chapter 6)
N/A
Confirm DEAD before commencing work (6.1)Follow Standard Working Procedures (Chapter 6)
Test and identify cables before commencing work (6.1)
Confirm DEAD before commencing work (6.1)Follow Standard Working Procedures (Chapter 6)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 31: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/31.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF NEW WORK IN EXISTING SWITCHBOARDS WMS No 014 Page 2 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
8. Confirm installation to client’s specifications.
9. Fit DANGER TAGS to any incomplete work.
10. Install labels, signs or markings as required.
11. Clean work area.
12. Test and commission new installation following relevant procedures. Confirm phase rotation of all 3 phase equipment.
13. Complete records.
N/A
N/A
N/A
Hand injuries
Electric shock
N/A
N/A
N/A
N/A
3
1
N/A
N/A
N/A
N/A
Wear suitable gloves (3.4)
Follow Standard Working Procedures (Chapters 2 and 6]
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 32: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/32.jpg)
WORK METHOD STATEMENT : INSTALLATION OF NEW WORK IN EXISTING SWITCHBOARDS WMS No. 014 Page 3 of 3
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to complete work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2 Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. EWP Certificate 3. EWP training if using EWP.
4. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Installation to comply with AS3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Portable tools, ladders, EWP Maintenance Checks: hand tools and ladders to be checked daily. EWP in accordance with manufacturer recommendations.
Read and Signed by All Employees on Site:
![Page 33: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/33.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF SUBMAINS WMS No 015 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check location to drawings and specification layout and mark out
2. Plan installation so as to work towards the main switchboard.
3. Confirm cable specifications and condition.
4. Install cable to client’s specifications.
5. Terminate sub mains to specifications. 6. Clean area
7. Test installation
8. Remove DANGER TAGS
9. Energise main switchboard.
10. Install signs or labels are required.
Tripping and exposed nails
Electric shock
N/A
Falls
Manual handlingElectric shock
Electric shock
Hand injuries
Electric shock
N/A
Electric shock
Hand injuries
3
1
N/A
2
21
1
3
1
N/A
1
3
Ensure area is clear (1.5)Wear safety foot wear (3.4)
Connections to the main switchboard to be made ONLY when it is CONFIRMED DEAD (6.1)
N/A
Use ladders in accordance with WMS 006 (5.3)Use fall protection as appropriate (3.5)Implement manual handling risk control procedures (1.7)Ensure that no bare conductors can contact any live parts.Effectively insulate both ends of all cables near any live parts.Restrain the ends of all cables near any live parts.
Isolate main switchboard and install DANGER TAGS.CONFIRMED DEAD before making any connections (6.1)Use suitable gloves (3.4)
CONFIRMED DEAD and identify cables before commencing work (6.1)N/A
Follow Standard Working Procedures (Chapter 6)
Use tools appropriately (5.6)
Wear suitable gloves (3.4)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
![Page 34: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/34.jpg)
* To be read in conjunction with NECA Safety Guide fro Electrical Industry Employees 2001 (Clause No.) where applicable
WORK METHOD STATEMENT : INSTALLATION OF SUBMAINS WMS No. 015 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. EWP Certificate.
4. No previous experience required. 3. EWP training if using EWP.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Portable drills, ladders, appropriate mechanical handling equipment. Maintenance Checks: Mechanical handling equipment to be checked in accordance with Statutory and manufacturer’s requirements.
Hand tools and ladders to be checked daily. EWP in accordance with manufacture's recommendations.
Read and Signed by All Employees on Site:
![Page 35: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/35.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLATION OF POWER AND LIGHT CABLING WMS No 016 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check location to drawings and specification layout and mark out
2. Plan installation so as to work towards the main switchboard.
3. Confirm cable specifications and condition.
4. Install cable to client’s specifications.
5. Terminate submains to specifications.
6. Clean area
7. Test installation
8. Remove DANGER TAGS
9. Energise main switchboard.
10. Install signs or labels are required.
Tripping and exposed nails
Electric shock
N/A
Falls
Manual handlingElectric shock
Electric shock
Hand injuries
Electric shock
N/A
Electric shock
Hand injuries
3
1
N/A
2
21
1
3
1
N/A
1
3
Ensure area is clear (1.5)Wear safety foot wear (3.4)
Connections to the main switchboard to be made only when it is CONFIRMED DEAD (6.1)
N/A
Use ladders in accordance with WMS 006 (5.3)Use fall protection as appropriate (3.5)Implement manual handling risk control procedures (1.7)Ensure that no bare conductors can contact any live parts.Effectively insulate both ends of all cables near any live parts.Restrain the ends of all cables near any live parts.Isolate main switchboard and install DANGER TAGS.CONFIRMED DEAD before making any connections (6.1)Use suitable gloves (3.4)
CONFIRMED DEAD and identify cables before commencing work (6.1)
N/A
Follow Standard Working Procedures (Chapter 6)
Use tools appropriately (5.6)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 36: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/36.jpg)
WORK METHOD STATEMENT : INSTALLATION OF POWER AND LIGHT CABLING WMS No. 016 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. EWP Certificate.
4. No previous experience required. 3. EWP training if using EWP.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS 3000 and client’s specifications Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Portable drills, ladders, appropriate mechanical handling equipment. Maintenance Checks: Mechanical handling equipment to be checked in accordance with Statutory and manufacturer’s requirements.
Hand tools and ladders to be checked daily. EWP in accordance with manufacture's recommendations.
Read and Signed by All Employees on Site:
![Page 37: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/37.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement INSTALLTION OF POWER POINTS WMS No 017 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check layout to drawings and specifications and confirm client.
2. Check walls, cavities and ceilings for other services and confirm location of any water pipes, gas lines or power or telephone cables.
3. Check equipment is tagged.
4. Fit power point mounting brackets as required.
5. Tape or insulate ends of new cable to prevent electrical contact.
6. Run cables.
7. Connect power points.
8. Confirm fittings are secure and installed to specifications
9. Clear area and remove Isolation or DANGER TAGS.
N/A
FallsHand injuries
Electric shock
Debris and noise from drilling
Electric shock
Hand injuries Electric shock
Electric shock
Falling
Hand injuries
N/A
23
1
3
1
31
1
2
3
N/A
Ensure area is clear (1.5)Wear safety footwear. (3.4) Use suitable gloves (3.4)Use ladders in accordance with WMS 006 (5.3)Use fall protection as appropriate (3.5)
Use only correctly tagged equipment. (4.2)
Use minimum drilling speed consistent with effective work. Use appropriate respirators, eye and hearing protection (3.4)Keep drill bits sharp. Use ladder or platform appropriately. (5.3)
Use suitable insulating material
Use suitable gloves (3.4)Confirm DEAD before commencing work (6.1)
Confirm DEAD before commencing work (6.1)
Use ladder or platform appropriately. (5.3)
Use suitable gloves (3.4)
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 38: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/38.jpg)
WORK METHOD STATEMENT : INSTALLATION OF POWER POINTS WMS No. 017 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to complete work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified electrical Supervisor by the Department of Fair Trading.
3. No previous experience required. 3. EWP Training if using EWP
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
AS3000 and clients specifications. Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Portable drill, pipe detection equipment, leads and ladders. Maintenance Checks: Hand tools and ladders to be checked daily.
Read and Signed by All Employees on Site:
![Page 39: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/39.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement MANUAL HANDLING WMS No 018 Page 1 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Identify characteristics:
(a) The object to be handled.
(b) The task.
(c) The working environment
(d) The individuals involved.
Sizes, shapes, weight, bulk, stability, hot, cold, sharp edges grip.
Frequency, bending, reaching, twisting, balance, distances, forces.
Space, access, lighting, floor surfaces, hot/cold.
New, ages, disabilities, PPE & C, training, hazard awareness. If team lifting, training and physically matched
2
2
2
2
Complete Risk Identification as in Appendix 1.
Complete Risk Identification as in Appendix 1.
Complete Risk Identification as in Appendix 1.
Complete Risk Identification as in Appendix 1.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 40: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/40.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement MANUAL HANDLING WMS No 018 Page 2 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
2. Assess characteristics of:
(a) The working area.
(b) The people.
(c) The actions of people.
(d) The object.
Heights, space, chairs, lighting, floors, and access.
Sufficient, new, ages, disabilities, PPE & C, training, hazard awareness. If team lifting, training and physically matched.
Posture, bending, stretching, reaching, twisting, and handling techniques.
Size, shape, weight, bulk, stability, hot, cold, sharp edges, grip, accurate placement.
2
2
2
2
Complete Risk Identification as in Appendix 2.
Complete Risk Identification as in Appendix 2.
Complete Risk Identification as in Appendix 2.
Complete Risk Identification as in Appendix 2.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
![Page 41: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/41.jpg)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement MANUAL HANDLING WMS No 018 Page 3 of 3
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
3. Control hazards using the Hierarchy of Control and measures
developed from 1 and 2.
Personal injuries and property damage.
2 Formulate action plans to include What is to done, Who will be responsible for completion, When will the work be completed, and Monitoring and reviewing the outcomes.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 42: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/42.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement WORKING WITH BOOM HOISTS WMS No 019 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Check that machine is safe to use mechanically.
2. Check electrical equipment on machine.
3. Check surfaces on which the machine is to be used.
4. Secure working area.
5. Prevent falls.
6. Check services in work area.
Machine failure, personal injury
Electric shock
Machine instability
Personal injuries
Personal injuries
Personal injuries
2
1
2
2
2
2
Check logbook, hydraulics, tyres, audile alarm, and warning lights
Check general purpose outlet, residual current device and earth continuity between earth pin and machine frame. Trip test RCD.
Use machine only on stable, level surfaces in accordance with the manufactures instructions.
Barricade working area, erect signs, tie tools on, and secure objects left at height.
Use parachute harness with lanyard and shock absorber. Ensure attachment point is appropriate.Stay wholly within the bucket at all times.Enter or exit bucket only while lowered.Use the machine only in wind less than 12.5 m/sec
Isolate as required.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 43: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/43.jpg)
WORK METHOD STATEMENT: WORKING WITH BOOM HOISTS WMS 019 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. Operators to hold appropriate Certificates of Competency.
4. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Boom hoists to be checked in accordance with the manufacture's instructions.
Maintenance Checks: Maintenance to be carried out in accordance with the manufacture's schedule.
Read and Signed by All Employees on Site:
![Page 44: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/44.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement USING MOBILE SCAFFOLDS WMS No 020 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Erect scaffold in accordance with the manufactures or supplier’s instructions.
2. Check surfaces on which the scaffold is to be used.
4. Secure working area.
5. Observe safe work procedures.
6. Check services in work area.
Unstable ground.Overturning.Collapse.Falling.
Electric shock.
Scaffold instability.
Personal injuries.
Personal injuries.
Personal injuries.
2
1
2
2
2
2
Place appropriate sole boards under standards.
Ensure handrails are fitted as erection proceeds.Use fall protection as appropriate.Ensure safe distances are maintained from conductors.
Use scaffold only on stable, level surfaces in accordance with the manufacture’s instructions.
Barricade working area, erect signs, tie tools on, and secure objects left at height. Wear appropriate personal protective equipment.Stay wholly within the scaffold at all times.
Use appropriate fall protection. Ensure SWL is observed and wheels are locked when in working position.Use the scaffold only in wind less than 12.5 m/sec.
Isolate as required.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 45: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/45.jpg)
WORK METHOD STATEMENT: USING MOBILE SCAFFOLDS WMS 020 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. Erectors to hold appropriate Certificates of Competency.
4. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Scaffolds to be checked in accordance with the manufacture's instructions.
Maintenance Checks: Maintenance to be carried out in accordance with the manufacture's schedule.
Read and Signed by All Employees on Site:
![Page 46: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/46.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement DISMANTLING MOBILE SCAFFOLDS WMS No 021 Page 1 of 2
Issue Date 1/3/2002 Revision Date Revision No Prepared By: Matt Reed
Project: All Sites Applicable Section Project Manager
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
1. Dismantle scaffold in accordance with the manufacture or supplier’s instructions.
2. Secure working area.
Falling objects.Electric shock.Overturning.
Personal injury.
Personal injury.
212
2
2
Ensure work platform is clean prior to dismantling.Ensure safe distances are maintained from conductors.Remove lower ties only when the scaffold is dismantled down to that level.
Wear appropriate personal protective equipment.Ensure ropes for lowering equipment are securely tied.
Barricade working area and erect signs.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 47: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/47.jpg)
WORK METHOD STATEMENT: DISMANTLING MOBILE SCAFFOLDS WMS 021 Page 2 of 2
Personal Qualifications and Experience Personnel, Duties and Responsibilities Training Required to Complete Work
1. Minimum of trades assistant or apprentice working under a qualified Supervisor.
1. Supervisor to carry out daily inspections of work site for hazards.
1. Supervisor to be trained in hazard identification, risk assessment and control.
2. Appropriate industry induction. 2. All personnel to maintain a tidy work site. 2. Supervisor to be certified as a qualified Electrical Supervisor by the Department of Fair Trading.
3. Erectors to hold appropriate Certificates of Competency.
4. No previous experience required.
Engineering Details/Certificates/WorkCover Approvals: Codes of Practice, Legislation:
Occupational Health and Safety Act 2000, OHS Regulation 2001 and Code of Practice, Electrical Practices for Construction Work.
Plant/Equipment: Maintenance Checks:
Read and Signed by All Employees on Site:
![Page 48: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/48.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement BOSTIK SOLVENT CEMENT TYPE ‘N’ FAST
WMS No 0023 Page 1
Issue Date 1/10/2002 Revision Date Revision No Prepared By : Matt Reed
Project: All Sites Applicable Section Project Manager:
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
4. Brush applied solvent based adhesive for unplasticised pvc pipe and fittings.
5. Thin blue or clear liquid with solvent odour.
Harmful by inhalation.
Highly flammable.
Irritation due to skin and eye contact.
Hazardous to environment
2
1
3
3
3
Ensure adequate ventilation.Use respiratory protection – organic vapour cartridge mask or air supplied system.
Keep away from sources of ingnition –no smoking.
Use suitable (solvent resistant) gloves.
Use safety goggles if risk of eye contact exists.
Avoid contaminating drains and water-ways.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 49: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/49.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement FLOURO SPOT MARKING PAINT WMS No 0022 Page 1
Issue Date 1/10/2002 Revision Date Revision No Prepared By : Matt Reed
Project: All Sites Applicable Section Project Manager:
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
Aerosol marking paint for spot marking of surfaces.
Highly Flammable.
Harmful by inhalation.
2
2
Keep away from sources of ignition – no smoking
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 50: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/50.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement SILICONE – INDUSTRIAL GRADE WMS No 0026 Page 1
Issue Date 1/10/2002 Revision Date Revision No Prepared By : Matt Reed
Project: All Sites Applicable Section Project Manager:
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
Coloured or translucent non-flowing paste with oxime odour.
Harmful by inhalation.
2 Ensure adequate ventilation.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 51: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/51.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement SLIPRY LOOB WMS No 0025 Page 1
Issue Date 1/10/2002 Revision Date Revision No Prepared By : Matt Reed
Project: All Sites Applicable Section Project Manager:
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
Cable pulling lubricant (thick yellow emulsion – odourless).
Minimal N/A
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 52: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/52.jpg)
Company Name REEDS ELECTRICAL SERVICES PTY LTD
Work Method Statement ZINC IT WMS No 0024 Page 1
Issue Date 1/10/2002 Revision Date Revision No Prepared By : Matt Reed
Project: All Sites Applicable Section Project Manager:
Client Distribution Client OHS Company Personal
Work Method Description Risk Assessment Risk Levels Recommended Actions * (Clause No.)
Aerosol Spray PaintSpray earth bond Irritation & burning
to eyes.
Harmful by inhalation.
Highly flammable.
1
2
1
Use safety goggles.
Use respiratory protection.
Keep away from sources of ignition.
RISK LEVELS: CLASS 1 (HIGH) CLASS 2 (MEDUIM) CLASS 3 (LOW)
* To be read in conjunction with NECA Safety Guide for Electrical Industry Employees 2001 (Clause No.) where applicable
![Page 53: Work Method Statements for Reed Select](https://reader036.fdocuments.in/reader036/viewer/2022062303/552b299a4a795911588b45ae/html5/thumbnails/53.jpg)