with the Climate Technology Centre and Network (CTCN) through UNIDO for Federal Republic of Nigeria 22 November 2019 | Strategic Frameworks

Transcript of with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... ·...

Page 1: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

with the Climate Technology Centre and Network (CTCN) through UNIDO

for Federal Republic of Nigeria

22 November 2019 | Strategic Frameworks

Page 2: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Programme title: Technology Needs Assessment and associated action plan for climate change mitigation and adaptation in Nigeria’s most vulnerable economic sectors

Country: Nigeria

National designated authority: Dr. Yerima Peter Tarfa,

Implementing Institution: UNIDO

Date of first submission: 26 February 2019

Date of current submission / version number

26 February 2019 V.##

Page 3: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 2 of 32

How to complete this document?

- Please visit the Empowering Countries page of the GCF website to download the Readiness Guidebook and learn how to access funding under the GCF Readiness and Preparatory Support Programme.

- This document should be completed by National Designated Authorities (NDA) or focal points with support from their Delivery Partners where relevant. Once completed, this document should be submitted to the GCF by the NDA or focal point to [email protected].

- Please be concise. If you need to include any additional information, please attach it to the proposal. - If the Delivery Partner implementing the Readiness support is not a GCF Accredited Entity for project Funding Proposals, please

complete the Financial Management Capacity Assessment (FMCA) questionnaire and submit it prior to or with this Readiness proposal. The FMCA is available for download at the Library page of the GCF website.

Where to get support?

- If you are not sure how to complete this document, or require support, please send an e-mail to [email protected]. - You can also complete as much of this document as you can and then send it to [email protected], copying both the

Readiness Delivery Partner and the relevant GCF Country Dialogue Specialist and Regional Advisor. Please refer to the Country Profiles page of the GCF website to identify the relevant GCF Country Dialogue Specialist and Regional Advisor.

- We will get back to you within five (5) working days to acknowledge receipt of your submission and discuss the way forward.

Please submit the completed form to:

[email protected]

Please use the following naming convention for the file name:

“GCF Readiness Proposal-[Nigeria]-[190226]”

Note: Environmental and Social Safeguards and Gender

Throughout this document, when answering questions and providing details, please make sure to pay special attention to environmental, social and gender issues, particularly to the situation of vulnerable populations, including women and men. Please be specific about proposed actions to address these issues. Consult Annex IV of the Readiness Guidebook for more information.

Page 4: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 3 of 32

1. SUMMARY

Country submitting the proposal

Country name: Nigeria

Name of institution representing NDA or Focal Point: Federal Ministry of Environment

Name of contact person: Dr. Yerima Peter Tarfa,

Contact person’s position: Director, Department of Climate Change

Telephone number: +234 802 492 0107

Email: [email protected]

Full office address: Department of Climate Change, Plot 444, Aguiyi Ironsi Way, Green Building Federal Capital Territory, Abuja, Nigeria

Additional email addresses that need to be copied on correspondences: [email protected]; [email protected]; [email protected]; [email protected]; [email protected];

Date of initial submission 27 February 2019

Last date of resubmission

Click or tap to enter a date. (Please update for each resubmission.) Version number V.1

Which institution will implement the Readiness and Preparatory Support project?

☐ National designated authority

☐ Accredited entity

☒ Delivery partner Please provide contact information if the implementing partner is not the NDA/focal point

Name of institution: The United Nations Industrial Development Organization, UNIDO, PO Box 300, A1-400 Vienna, Austria Name of official: Philippe Scholtès Position: Managing Director, Directorate of Programme Development and Technical Co-operation Telephone number: +431260263101 Email: [email protected]

Additional email addresses that need to be copied on correspondences: Rose Mwebaza, Director CTCN, [email protected] Rajiv Garg: Regional Manager CTCN, [email protected]

Title of the Readiness support proposal

Technology Needs Assessment and associated action plan for climate change mitigation and adaptation in Nigeria’s most vulnerable economic sectors

Type of Readiness support sought

Please select the relevant GCF Readiness activity area below (click on the box):

☐ I. Country capacity for engagement with GCF ☒ II. Country programming process ☐ III. Direct access to climate finance ☐ IV. Climate finance accessed ☐ V. Formulation of national adaptation planning and/or other adaptation planning processes

Page 5: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 4 of 32

Brief summary of the request

This proposal seeks to provide assistance to Nigeria to aid its development of a comprehensive Technology Needs Assessment (TNA) and action plan aimed at conducting a categorization and prioritization of technologies that will comply with the Nigerian NDC. This work will enable Nigeria to implement its climate targets (included in the country’s NDC) using the most appropriate technologies. In this context, it will be used as a basis by the country to develop and strengthen its pipeline of projects to be submitted to the GCF. The technologies prioritized and associated actions can also be used by national planners to inform ongoing planning processes, such as climate-focused and sectoral policies. Nigeria’s (draft) third National Communication document prioritises sectors with the highest mitigation potential, namely (a) agriculture and land use (b) energy (c) industry and commerce. The requested assistance will allow for the NDC implementation while also identifying, by means of the development of local content, the low-carbon technologies that will be integral to delivering on Nigeria’s ambitious mitigation plans to 2030. While the TNA technology prioritization process focuses on the benefits and costs of technologies within the national context, the technology action plan focuses on a group of measures for addressing barriers and accelerating the development and transfer of prioritized technologies. This readiness proposal will enable the development of scalable, bankable projects that target prioritised sectors and that deliver quantifiable emissions reductions. The anticipated outcome is a TNA that presents a number of strategic, long-term, participatory transformational measures across 3 identified and prioritised sectors (agriculture, energy and industry) that will drive climate resilient and low carbon growth in Nigeria. Crucial to its implementation is the achievement of high level political support, fund mobilisation and private sector engagement. The GCF assistance will enable Nigeria to meet the goals of the current climate political strategies, such as the NDC sectoral analysis plans for mitigation sectors, NAMA readiness document, National science, Technology and Innovation Roadmap, Nigeria’s Economic Recovery and Growth Plan, as well as GCF investment criteria.

The technical direction of Nigeria’s low carbon development will be documented through this TNA and associated plans for implementation Without guidance on priority sectors and technologies, the approach may hinder the country’s approach to adaptation. This mitigation TNA report and Action Plan and an adaptation TNA report and Action Plan will provide the necessary guidance to evolve the prioritised technologies and address future country needs and community vital information to aid Nigeria’s adaptation plan and country programme. It will target the international and institutional climate finance landscape and associated opportunities for project implementation and so can act as connector between technology, policy and investor communities.

All stakeholders agreed at this project inception workshop (September 2018) that this readiness proposal would complement planned and ongoing initiatives. Activities will focus on identification of development needs already formulated in national development strategies for the country (assessing national policies, existing sectoral plans and strengths in the context of economic, social and environmental development priorities). Planned activity synergy includes Nigeria’s GCF Readiness Support request for access to finance to contribute to the Nationally Determined Contribution (NDC) pledge. Such synergies and economies could be achieved through joint engagement through the stakeholder process, a sharing of resources and inputs into communication strategies, approach to regional training and round table dialogues, utilization of existing tools (such as GCF monitoring tools) and approaches to private sector engagement via proposed partnerships. A number of targeted stakeholder workshop are anticipated through this assistance that focus on training for private organisations that manage technologies.

Page 6: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 5 of 32

Total requested amount and currency USD 397,143 Anticipated duration 18 months

Has the country received or is expecting to receive other Readiness and Preparatory Support funding allocations (including adaptation planning) from GCF or other donors?

☐ Yes ☒ No

If yes, please describe the scope of work and the scope of support provided or expected to be provided by the GCF and/or other institutions (100 words).

Page 7: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 6 of 32

2. BACKGROUND

Nigeria ratified the Kyoto Protocol in 2004 and is currently at the final stage of submitting its third National Communication to the UNFCCC. Nigeria is yet to develop a TNA but has quantified a number of climate challenges including drought, water scarcity, desertification, low agricultural yields and emerging epidemics. National political strategies reflect a context of widespread food insecurity, drought, desertification and flood vulnerability, poor access to energy, forced migration from rural areas, negative economic impacts1 and high unemployment (with GDP per capita at $2,950 in 2014). In understanding how to best challenge these problems, Nigeria developed its NDC as a starting point for effective action on climate change (Figure 3). Nigeria’s NDC clearly indicates a number of barriers, investment requirements and the strategy to acquire environmentally sound technologies. Nigeria’s NDC offers a first step to implement climate technology action, and constitutes a great source of information useful to plan the removal of potential barriers and create the enabling environment for technology options prioritized by Nigeria.

This proposal builds upon the information communicated by stakeholders via an inception workshop (September 2018) aimed at shaping the Nigerian approach to this readiness proposal. This workshop included representatives from government, academia, private sector and community interests and enabled a sharing of information that laid the groundwork for this proposal. A significant gap identified at the TNA Inception workshop was Nigeria’s inability to apply technology in order to mitigate and adapt to climate change. The Nigerian NDC was presented, while a number of barriers to implementation were introduced. The country’s plans for economic development and adaptation planning was introduced and it was agreed that this readiness proposal would complement existing planned and ongoing initiatives including Nigeria’s GCF Readiness Support request for access to finance to contribute to the Nationally Determined Contribution (NDC) pledge.

While this proposal will complement the readiness proposal submitted with UNDP, the two proposals are fundamentally different in scope and proposed impact. The proposed UNDP project focused on building general capacity through a coordination mechanism within the NDA, the CTCN proposal focuses specifically on technology related capacity building and the establishment of a coordination mechanism within the NDA. This is indeed a specialized subset of the overall coordination mechanism being proposed through the UNDP proposal. Through implementation, coordination will be achieved through discussion with the Nigerian Ministries whose remit focuses on technical areas. This engagement will ensure synergies are identified and maximized and duplication avoided.

1 The Post disaster need assessment (PDNA) report following Nigeria’s 2012 flood revealed $16.9b of damage to Nigeria’s economy.

Page 8: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 7 of 32

Nigeria’s country planning process is in its infancy with a major first step being the development of its NDC and committee to guide its implementation. A key component to the country programming process involves the development of a technology needs assessment and associated action plan for mitigation and adaptation technologies.

Nigeria’s NDC identifies technologies and key sectors for the fulfilment of national mitigation commitments and provides financial investors with a clear pathway for Nigeria’s development. While a set of thirteen sector specific strategies, policies, programmes and measures have been prepared, Nigeria’s (draft) third National Communication document prioritises sectors with the highest mitigation potential, namely (a) agriculture and landuse2 (b) energy (c) industry and commerce. Under this request, the focus of attention will be on these 3 sectors and work will include further selection of mitigation and adaptation technologies for the fulfilment of Nigeria’s TNA.

The methodological approach will encompass stakeholder engagement and a consultative approach that aids TNA preparation (including project inception workshops) and will reflect a country-driven, participatory approach. The approach will improve local constituents and stakeholder knowledge about project funding opportunities and enable endogenous capacities to be developed across the core Ministries involved in the process (Environment, Science and Technology, Finance, Statistics, Agriculture and Landuse). This will aid the development and submission of environmentally sound, robust and bankable project ideas resulting from the technical assistance.

Throughout the NDC process a number of enablers have been identified that are imperative for Nigeria to access climate finance for technology development. They include (a) building local capacities to enhance the ability and skills to develop coherent, robust project proposals, (b) facilitating access to funding through developing a pipeline of bankable projects eligible for funding (c) enhancing strong private sector participation in technology development and (d) engaging domestic financial institutions to optimize opportunities while creating fiduciary standards of funding entities.

Figure 3: NDC Targets

2 Strategies include Education and Awareness, Climate Forecasting, Water Management, Appropriate Soil, tillage, Utilization of Improved Crop Varieties, Cropping Adjustments, Restoration of Degraded Lands, Diversification of Food Production, Establishment of Strategic Food Reserves, Alternative Economic Activities,

Page 9: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 8 of 32

3. LOGICAL FRAMEWORK AND IMPLEMENTATION SCHEDULE

Outcomes Baseline Targets Activities (brief description and deliverables)

Anticipated duration: 18 months

Monthly implementation plan of activities

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Outcome 1: Institutional capacity and coordination mechanisms in place to govern and coordinate climate action and finance

Sub-Outcome Effective coordination mechanism between NDA and National Designated Entity (NDE) for the UNFCCC Technology Mechanism and other climate finance focal points

1.Communication initiated between NDA, NDE and other climate finance focal points to identify points of coordination.

2. Coordination mechanism for implementation of TNA is fully institutionalized . . 2.

Activity 1: Institutionalization of a coordination mechanism for the implementation of the TNA This first activity aims to engage key actors from relevant sectors (agriculture, energy and industry) to enable the prioritization of technology options and ensure success of the action plans that will derive from the TNA exercise. Activity 1.1. Conduct stakeholder’s analysis This stakeholder analysis will provide a valuable input into the stakeholder engagement strategy developed via the Nigerian GCF Readiness proposal entitled “GCF Readiness and Preparatory Support Programme for Nigeria” with UNDP as delivery partner. The 3 identified sectors that are identified for prioritization are not homogeneous and not uniform. Significant effort will be required to identify various stakeholders across each of the three sectors. This stakeholder identification is especially critical and challenging for industry and energy sectors. The stakeholder input will be critical for identification of the various sub-sectors and technologies that will inform the technology fact sheets/briefs that will result in robust proposals ready for GCF support.

Page 10: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 9 of 32

This also includes those directly involved in National TNA Committee running the project, including institutions from line ministries and governmental organizations, private sectors, research organizations, key stakeholders from the three sectors identified, etc. This will be an input into Activity 1.2 The activity includes identifying key stakeholders (public, private and civil society) and facilitating their participation. Civil society includes engagement of the private sector, NGOs and academia and will be facilitated through bilateral meetings between experts/ stakeholders. The input from the Nigerian NDE and NDA will be critical to shaping and informing the TNA and associated action plans from the outset but also interfacing with the CTCN and its host organisations UNIDO/UNEP. Deliverable 1.1. Reports of stakeholders’ consultation processes are made available; Work plan for stakeholders’ engagement in TNA processes developed, highlighting stakeholder’s roles; Stakeholder matrix identifying primary and secondary stakeholders to be consulted as part of the development of the TNA. The TNA activity requires a range of actors, institutions and sectors. Such a matrix will consider key national/ regional representatives from private, public and academic sectors and will target stakeholders across the 3 prioritized sectors identified by the NDC. This will be a key input into delivering activities 2.2-2.4 and 3.1. Estimated completion date: Month 2

X

Activity 1.2 Support establishment of a TNA Committee The TNA Committee and constitution in place will be responsible for appointing key stakeholder groups and

Page 11: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 10 of 32

ensure their participation and engagement during its execution. The first activity is the establishment of the Committee. The TNA Committee will include representatives from the public, NGOs, private, and academic sectors. The roles and responsibilities of stakeholders will be defined for the TNA process, including for the review of outcomes and for providing technical input. This activity will be conducted in compliance with the TNA handbook and methodology. Special attention will focus on the participation of vulnerable populations throughout the process of TNA Committee formation. The targeting of such groups will aid the composition of the TNA Committee and special attention should target small farmer holders and associations, private sector organisations, disabled groups, gender specific groups and indigenous people. The objective is also to ensure equitable access to the benefits accruing from the TNA. This activity will include to:

- Institutionalize an effective coordination mechanism for the implementation of the TNA process. This committee will be in place in month 3 and formally meet every quarter to facilitate quarterly reporting on project progress.

- Coordinate with the activities conducted under the Nigerian CP, especially aligning to findings of Report of the capacity gaps assessment and the capacity-building action plan for the NDA

- Provide training on TNA process, including quality assurance, to all stakeholders. [The TNA Committee, while experts in their own fields, are not familiar with the process involved in development of action plans nor methodologies for prioritizing and selecting technologies based on multi-criteria analysis. The Nigerian NDA and NDE both identified a specific

Page 12: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 11 of 32

requirement for the TNA Committee to receive dedicated training on these aspects. Quality assurance refers to the approach to maintain the integrity of the TNA process and action planning in line with best practice approaches] (Quarter 3-6)

- Identify the appropriate reporting and governance arrangements to enable the National Designated Entity (NDE) to report on the progress of the TNA and associated action plans and enhance communication channels with CTCN and its host organisations UNIDO/UNEP. (Every 3 months)

Training materials will include the Nigeria GCF handbook completed published & disseminated under the Nigerian GCF Readiness Support request for access to finance to contribute to the Nationally Determined Contribution (NDC) pledge. This will enhance synergies between training materials. A full list of participants will be provided alongside accompanying photo/reporting documentation. Deliverable 1.2: Work plan of National Coordination Mechanism (TNA Committee and Constitution) developed. Management office in place for Institutionalized coordination mechanism, TNA Training, including quality assurance, delivered to stakeholders. Estimated completion date: Month 15. Regular reporting every 3 months from Month 3.

X

.

Activity 1.3: Development of a work plan for monitoring and oversight The Work Plan will define and schedule TNA meetings to be conducted in Abuja. Venues will be assigned by the responsible Ministry. Stakeholders engaged in the TNA committee will be engaged in contributing to the work

Page 13: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 12 of 32

plan. This activity will be assessed for its compliance with the TNA handbook and methodology. The activity involves promoting a comprehensive participation of key stakeholders in the development of a workplan. Deliverable 1.3. TNA Work plan and TNA Constitution developed and endorsed, citing the roles/ responsibilities of main stakeholder groups in the TNA process and method of engagement. Estimated completion date: Month

X

Outcome 2: Country Programming process

Sub-Outcome Technology solutions identified and prioritized in accordance with national strategies and plans

0: No appropriate climate technologies have been identified and prioritized. There is a lack of robust data for the selection of key technologies aimed at implementing the NDC Sectoral priorities. Knowledge on climate change sectors for prioritization is robust but the measures

2 The most appropriate climate technology solutions have been identified and prioritized in accordance with national strategies and plans, based on a comprehensive analysis of technology options to address specific climate impacts. Technology Action Plans that quantifies the potential impact of priority

Activity 2: Prioritization of technologies and relevant action for increased access to finance Activity 2.1: Pre-selection of sub-sectors for the fulfilment of Nigeria’s TNA The objective of this activity is to identify and obtain consensus about priority sectors (and subsectors) to shape the TNA. The starting point are the 3 sectors identified in the Nigerian NDC, namely agriculture, energy and industry. The first sub-activity aims at assessing the Nigerian Government’s sectoral plans and proceedings from the technology workshops conducted, where stakeholders aimed to establish sectoral priorities for the fulfilment of TNA. Such outcomes will be validated by key stakeholders in a workshop. These sectoral priorities will allow for technology identification for mitigation and adaptation and a drafting of the TNA and action plan. Activities will focus on identification of development needs already formulated in national development strategies for the country (assessing national policies, existing sectoral plans and strengths in the context of economic, social and environmental development priorities).

Page 14: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 13 of 32

and technology priorities have not been explicitly detailed

technologies have been developed

The prioritization of the technologies will be consistent with the country programme and a number of variables could be considered to facilitate comparison, assessment, evaluation vis-à-vis other technology solutions. These could include:

- Supporting policy framework (regulatory, institutional, financial and information frameworks)

- Maturity of industry - Availability of natural resource - Available of skillset and competency - Infrastructure requirements - Device technology research requirements - An analysis of value chains, risks and overall

barriers to implementation - Technology impact potential in terms of

Nigeria’s GHG emissions reduction targets (conditional and unconditional)

- Employment impact - Qualitative analysis of the co-benefits

(mitigation and adaptation) in terms of both environmental and social perspectives resulting from the implementation of technologies prioritized.

While priorities have been identified in the Nigeria’s NDC, and 3 sectors have been prioritized as part of the draft 3rd Communication process, Nigeria lacks consistent technical information to support the indication of environmentally sound technologies. Such outcomes will be validated by key stakeholders in a workshop. These sectoral priorities will allow for technology identification (2.1.2) for mitigation and adaptation and a drafting of the TNA action plan (3.1) Barrier analysis could include an analysis of value chains, risks and overall barriers to implementation to aid policy development. It may consider the realms of regulatory,

Page 15: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 14 of 32

institutional, financial and information frameworks that may prevent the accelerated development of markets for environmentally sound technologies. Such a process may identify regulatory barriers, a lack of information, policy uncertainty and deficiencies in the understanding of economic and institutional frameworks. Prioritization will be achieved in consultation with the Nigerian NDC Support Programme and will align with the proposed UNDP readiness project. Specifically project implementation alignment will be via UNDP’s planned multi-stakeholder consultations (with private sector, women-led organizations, CSO, ministries, sub-national level authorities, etc.) outlining the procedure with clearly defined rationale and criteria for prioritization of sectors, geographical areas and initiatives. Deliverable 2.1: Report describing methodology to sector and subsector selection, including rationale and executive summary delivered; Estimated completion date: Month 5.

X

.

Activity 2.2: Pre-selection of mitigation and adaptation technologies for the fulfilment of Nigeria’s TNA The aim of this activity is to validate and prioritize key technologies, aligned to Nigeria’s NDC. This will be done through a multi-criteria analysis and market assessment for technology selection that considers endogenous capabilities, natural resources, skills base, NDC focus

Page 16: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 15 of 32

areas and sectoral plans through a participatory process for the fulfilment of Nigeria’s TNA. This activity will focus on identifying and obtaining consensus about priority technologies by sector to fulfil the NDC. Such outcomes will be validated by key stakeholders in a workshop. With this, priorities for the fulfilment of the NDC will be defined, and together with factsheets for each technology, will allow for the drafting of the technology action plan and will be produced to enable input into the country programme. Without guidance on priority sectors and technologies, the approach may hinder the country’s approach to adaptation. This mitigation TNA report and Technology Action Plan (TAP) and an adaptation TNA report and Action Plan will provide the necessary guidance to evolve the prioritised technologies and address future country needs and community vital information to aid Nigeria’s adaptation plan and country programme. A key outcome of the TNA process is the technology action plan (TAP). A TAP is a concise plan for the uptake and diffusion of prioritised technologies that will contribute to the country’s social, environmental and economic development and climate change mitigation and adaptation. Attention should be drawn to the fact that the participation of key stakeholders in the validation process of priority technologies must also consider the long-term development priorities. Activities should focus on a multi-criteria analysis for technology selection that considers endogenous capabilities, natural resources, skills base, NDC focus areas and sectoral plans through a participatory process for the fulfilment of Nigeria’s TNA Deliverable 2.2

X

Page 17: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 16 of 32

Final reports including a mitigation TNA report and Action Plan (TAP) and an adaptation TNA report and Action Plan with key stakeholders elaborated. Report detailing the technology prioritization process is delivered. Report of the validation workshop that elaborates multi-criteria analysis, market assessment and participatory process conducted. Development of a number of TNA fact sheets briefs, summarizing main findings, recommendations and next steps. Estimated completion date: Month 8.

0.

Activity 2.3: Technology Action Plan(s) The process for the development of this Technology Action Plan will involve a number of interviews and consultations with key stakeholders across the public, private and academic setting and will target various experts depending on the (sub) sectors and technology prioritized. The Action Plan should: - elaborate very detailed project ideas, including

comprehensive time frames and a breakdown of the estimated budget for the project idea.

- articulate project idea objectives, outputs, relation to national development priorities, deliverables, activities, timeline, budget and evaluation methods.

- consider elements such as research on the prioritized technology, capacity-building, financial schemes, pilot projects and technology demonstration.

- include an analysis of value chains, risks and overall barriers to implementation to aid policy development.

- consider the realms of regulatory, institutional, financial and information frameworks that may prevent the accelerated development of markets for environmentally sound technologies. Such barrier identification includes regulatory barriers, a lack of information, policy

Page 18: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 17 of 32

uncertainty and deficiencies in the understanding of economic and institutional frameworks.

- determine technology impact potential in terms of Nigeria’s GHG emissions reduction targets (conditional and unconditional), employment impact, and qualitative analysis of the co-benefits (mitigation and adaptation) in terms of both environmental and social perspectives resulting from the implementation of technologies prioritized.

Each TAP will be financially robust to enable funding to be secured and will identify measures for overcoming barriers and identify the responsible authority for implementation. The deliverable will: - Recommend enabling frameworks to address identified

barriers, including conducting an analysis of the economic and social barriers that hinder the transfer and uptake of prioritized technologies.

- Assess the policy, institutional and financial options and technology risks to overcome these barriers and present project ideas and multiple actions that are categorized based on quantity of their identifications.

- Prioritize a number of subsectors, (such as renewable energy production, biofuels, energy efficiency, water collection and harvesting, drip irrigation and the efficient production and improvement of crop varieties).

- Present a clear financial plan with timelines, benchmarks and indicators that will elaborate measures to overcome these barriers and so aid policy makers, market actors and technology innovators. Financial assessments could include costs benefit analysis, return on investment, internal rate of return, net present value of a particular technology action /idea versus an alternate.

- Target the high initial costs for technology deployment, transaction costs and the lack of an

X

Page 19: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 18 of 32

appropriate policy environment to enable such deployment.

- Provide cost indications and assessments (financial incentives for implementation of an action), including potential domestic and international funding sources to deliver such actions, institutional/policy strengthening costs, market assessments and RD&D studies.

- Develop legal and regulatory instruments co create a sound enabling environment for identified technologies.

Deliverable 2.3. Report and executive summary of each Technology Action Plan for each of the priority technologies in compliance with the TNA, including project supports and project ideas as concrete actions for implementation. Estimated completion date: Month 14.

:

Activity 2.4: Validation of Technology Action Plan (TAP) with stakeholders This activity aims to discuss and validate the technology action plan by the TNA key stakeholders. It will facilitate collaboration and sharing of experience, lessons learnt and best practices, including external engagement with other sub-saharan country NDEs and NDAs and private sector entities. This is aimed at assisting stakeholders with the familiarization of identified technologies, such as awareness campaigns and training to enhance technical capacity, operation and maintenance, and data collection. Common methods utilized for that process included: interviews with experts and stakeholders; market mapping and problem trees; dedicated workshops; desk studies; and logical problem analyses.

X

Page 20: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 19 of 32

Stakeholders engaged in consultative processes include governments, private sector, associations, civil society, academia. Deliverable 2.4 Meeting report of the workshop for the validation of technology action plan and analysis of co-benefits elaborated. (20-30 stakeholders and key institutions, for 2 days in Abuja/Lagos.). List of attendance of the validation workshop provided. Report to GCF outlining implementation of the coordination mechanism, including reports on activities undertaken by the committee in fulfilling its role throughout TNA process. Estimated completion date: Month 16.

0: )

Activity 2.5: Support the implementation of the Technology Action Plan with communications, guidance and training Delivery of a capacity building package for TNA key stakeholders including training and support materials for the development and application of prioritized technologies. Relevant participants will include the NDA, NDE, GCF and GEF focal points. A key input into the development of this training is the national- level training on GCF standards and processes, M&E, and decision-making delivered through the Nigerian GCF Readiness Support request for access to finance to contribute to the NDC pledge. The stakeholder matrix and training workshops identified within this proposal will provide a key input into the Communication strategy of the Nigerian GCF Readiness Support request for access to

Page 21: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 20 of 32

finance to contribute to the NDC pledge aimed at raising awareness and facilitating stakeholder engagement in the GCF processes Stakeholders will be provided with 6 regional training seminars on modules including (a) market mapping and problem trees to enable them to become more familiar with identified technologies (b) gender awareness tools to enhance implementation capacities (c) access to financing of prioritized technologies across domestic and international sources (aligned to Nigerian Readiness Request NDC Proposal aimed at delivering a GCF monitoring tool) (d) technical capacity, operation, maintenance and data collection and (e) energy data assessment and modelling. The project implementers will consider enhancing the synergy and efficiencies between these regional training workshops and the Sub-national level stakeholders, (including private sector entities) round table dialogues in the Readiness Request NDC Project proposal. This activity aims to develop tools that will enhance existing data assessment and modelling of the Nigerian GHG inventory system. This potentially will build on existing modelling techniques, such as the Long range energy alternatives planning system (LEAP) currently utilized by the Nigerian Government to track energy consumption and production It will also consider modelling techniques associated with agriculture and land use change. This will assist in data inventories, measure identification and energy projections, financial assessments of technology project ideas and marginal abatement cost curves. The project will also utilize the Climate finance monitoring tool developed as part of the Nigerian GCF Readiness Support request for access to finance to contribute to the Nationally Determined Contribution (NDC) pledge.

Page 22: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 21 of 32

Deliverable 2.5 Capacity building package developed Deliver a Dissemination strategy. Deliver market use cases for technologies resulting from stakeholder engagement. Deliver a number of policy briefs informing the regional workshops. Advanced energy models, capability and data inventory analysis to quantify costs of effective measures by sector and subsector. Termes of reference to share with GCF, Training reports, material and tools Estimated completion date: Month 18.

X

Outcome 3: Climate finance strategies strengthened , private sector mobilized and project pipeline enhanced

Sub-Outcome 3 /Private sector engagement

1. Some private sector actors are engaged in consultative processes, however no structured dialogue established (e.g. some private sector events organized).

2 Private sector engagement is systematically part of the country consultative processes and structured dialogues with the NDA/FP, Accredited Entities and the GCF Secretariat .

Activity 3.1: Engaging the private sector in Nigeria’s consultative processes Engage the Nigerian private sector via a number of consultative workshops across the Technology Action Plan development process. This will achieve input and perspective sharing on the market readiness of technologies and the potential deployment. This engagement will also align with the Nigeria’s (NDC) Readiness Support proposal project deliverables including the identification of partnerships/ investments from the private sector for GCF-funding priorities Workshop is delivered that enables private sector input into the technology prioritization. Workshop enabling Private sector input into the Sector, Sub-Sector and Technology Prioritisation . Deliverable 3.1 Private sector actors are informed of the TNA process, the methods for technology and sectoral prioritization and their inputs are incorporated into the draft deliverable.

X

Page 23: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 22 of 32

A list of workshop participants and a detailed summary of proceedings is provided. Recommendations on how to integrate inputs from the private sector are also provided Termes of reference to share with GCF, Workshop reports and materials/tools Estimated completion date: Month 9

Page 24: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 23 of 32

4. ADDITIONAL INFORMATION (ONLY FOR ADAPTATION PLANNING SUPPORT)

Not applicable.

5. BUDGET, PROCUREMENT, IMPLEMENTATION, AND DISBURSEMENT

5.1 Budget plan Please complete the Budget Plan in Excel using the template available in the Library page of the GCF website. Note in addition to the Budget Plan in excel:

The “Consultants” cost category in the budget refers to both international and local personnel to be hired for the execution of the work (for more details please refer to the attached budget in the Excel Sheet).

UNIDO will be responsible for the selection of the executing agency through a competitive tendering process in accordance with UN policies and procurement guidelines. Within CTCN technical assistance a minimum amount of 1% of total budget is dedicated to gender mainstreaming, assuring that the gender topic is properly embedded into the technical analysis.

5.2 Procurement plan Please complete the Procurement Plan in Excel using the template available in the Library page of the GCF website. For goods, services, and consultancies to be procured, please list the items, descriptions in relation to the activities in section 2, estimated cost, procurement method, relevant threshold, and the estimated dates. Please include the procurement plan for at least the first tranche of disbursement requested below and provide a full procurement plan for the entire duration of the implementation period if available at this stage. Note in addition to the Procurement Plan in excel Readiness Proposal that falls within a Framework Agreement with the GCF Disbursements will be made in accordance to Clause 4 “Disbursement of Grants” and Clause 5 “Use of Grant Proceeds by the Delivery Partner” of the Framework Readiness and Preparatory Support Grant Agreement entered into between GCF and UNIDO on 15 January 2019 (the “Framework Agreement”). The Delivery Partner is entitled to submit 2 requests for disbursement each year and an Interim Request for Disbursement within 30 days of approval by the GCF of a proposal, which must be in accordance with the Framework Agreement. Overall financial management and procurement of goods and services under this readiness and preparatory support proposal will be guided by UN regulations, rules, policies and procedures. UNIDO will be responsible for the implementation of the readiness activities and for procurement and contractual services, as well as reporting on the progress of this implementation in close coordination and strategic guidance from the NDA/FP. The procurement actions and the operational services will be carried forward in accordance with UN policies and procurement guidelines. The specific procedures for procurement through the CTCN are as follows: For a request that is eligible and prioritized, the Climate Technology Managers in charge of the respective request sources the appropriate expertise to develop the Terms of Reference of the assistance (called ‘Response Plan’ as per CTCN procedures). The response plan provides specific information on the technical assistance to be delivered, including activities, outputs, expected outcomes and impacts, timeline, indicators or measuring assistance progress and success, stakeholders to be involved, etc. The response plan, once finalized, is signed by the national focal point of the CTCN in the concerned country (National Designated Entity), the institution which originated the CTCN request for technical assistance and the CTCN Director, and constitutes the basis of the assistance to be implemented and monitored upon the approval and in cooperation with the NDA. Based on the needs and expertise required in the response plan, a CTCN Network Member will be selected to implement it. The selection of organizations from the Network is conducted through a competitive procurement process as per UN Rules and Regulations, in line with CTCN and UNIDO procedures. The CTCN nurtures a Network of some 500 expert organizations in the field of low-carbon and climate resilient technologies. The required expertise to carry out the activities that define this intervention will be sourced in accordance with four principles: i. Best value for money principle; i ii. Fairness, accountability, integrity and transparency of the procurement process; ii iii. Effective competition; iii iv. The best interest of the CTCN.

Page 25: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 24 of 32

5.3 Disbursement schedule Please specify the proposed schedule for requesting disbursements from the GCF. For periodicity, specify whether it’s quarterly, bi-annually or annually only. UNIDO will manage the disbursement request and schedule guided by the appropriate agreement and in line with its rules and regulations.

☒ Readiness Proposal that falls within a Framework Agreement with the GCF

Disbursements will be made in accordance to Clause 4 “Disbursement of Grants” and Clause 5 “Use of Grant Proceeds by the Delivery Partner” of the Framework Readiness and Preparatory Support Grant Agreement entered into between GCF and UNIDO on 15 January 2019. The Delivery Partner is entitled to submit 2 requests for disbursement each year.

☐ Readiness Proposal that requires a bilateral Grant Agreement to be signed with the GCF (please add more disbursement as needed)

• The first disbursement amounting [Choose Currency] will be transferred upon approval of the readiness request and effectiveness of the Grant Agreement;

• The second disbursement amounting [Choose Currency] will be transferred upon submission of an interim progress report [and audited financial report]3, in form and substance acceptable to the Fund, [including an audited expenditure statement]; and

• The third disbursement amounting [Choose Currency] will be made upon submission of a completion report and financial report, in form and substance acceptable to the Fund, including an audited expenditure statement.

Please include an indicative disbursement table showing the expected amounts to be requested and keep to multiples of USD 5,000.

4 UNIDO is fully accredited by the GEF. UNIDO came into full compliance with the GEF fiduciary standards in October 2013 and, since then, with the GEF Environmental and Social Safeguards and Gender policies in May 2015. Please see GEF council documents, confirming UNIDO’s compliance with relevant GEF policies and standards, under the following links:

Page 26: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 25 of 32

6. IMPLEMENTATION ARRANGEMENTS AND OTHER INFORMATION

6.1 Implementation map Please describe how funds will be managed by the NDA and/or the Readiness Delivery Partner.

The CTCN (hosted by UNEP-UNIDO) is providing technical assistance to the Government of Nigeria, as per its COP Mandate, and supporting Nigeria to develop this readiness proposal. This included engagement with the project inception workshop (Sept 2018). The CTCN Engagement with the Government of Nigeria is mature with close co-operation between the NDA and NDE. The implementing partner will be procured through formal tendering procedures if the Readiness proposal is approved for implementation. The relevant COP decisions are provided below for easy reference:

Decision 14/CP.22: Linkages between the Technology Mechanism and the Financial Mechanism of the Convention Para 4. Welcomes the increased engagement between the Green Climate Fund and the Climate Technology Centre and Network, particularly with respect to utilizing the Readiness and Preparatory Support Programme and the Project Preparation Facility of the fund, noting the potential of such engagement in supporting developing country Parties to build their capacity for implementing technology projects and programmes; Para 6. Invites Green Climate Fund national designated authorities and focal points to use the support available to them under the Readiness and Preparatory Support Programme to, inter alia, conduct technology needs assessments and develop technology action plans; Para 7. Also invites developing country Parties to develop and submit technology-related projects, including those resulting from technology needs assessments and from the technical assistance of the Climate Technology Centre and Network, to the operating entities of the Financial Mechanism for implementation, in accordance with their respective policies and processes; Decision 15/CP.22: Enhancing climate technology development and transfer through the Technology Mechanism Para 13. Underlines the importance of well-functioning and strengthened collaboration between the national designated authorities for the Green Climate Fund, the focal points for the Global Environment Facility and the national designated entities for technology development and transfer Para 15. Welcomes the increased engagement between the Green Climate Fund and the Climate Technology Centre and Network, particularly with respect to utilizing the Readiness and Preparatory Support Programme and the Project Preparation Facility of the fund in order to respond to country-driven requests for technical assistance; Para 16. Encourages the advancement of the engagement referred to in paragraph 15 above, including through the strengthening of collaboration between national designated authorities for the Green Climate Fund and national designated entities for technology development and transfer; Para 17. Invites the Climate Technology Centre and Network to include the outcomes of the engagement referred to in paragraphs 15 and 16 above in its annual report to the Conference of the Parties at its twenty-third session.

UNIDO will manage the funds for the activities under this readiness agreement4. UNIDO will agree on a plan with the NDA of Nigeria to monitor the implementation of the activities using the grant proceeds. However, UNIDO will be responsible for the implementation of the activities under this readiness and preparatory support proposal.

4 UNIDO is fully accredited by the GEF. UNIDO came into full compliance with the GEF fiduciary standards in October 2013 and, since then, with the GEF Environmental and Social Safeguards and Gender policies in May 2015. Please see GEF council documents, confirming UNIDO’s compliance with relevant GEF policies and standards, under the following links:

- GEF/C.48/06 - GEF AGENCY COMPLIANCE WITH POLICIES ON ENVIRONMENTAL AND SOCIAL SAFEGUARDS, GENDER, AND FIDUCIARY STANDARDS-May 07, 2015: https://www.thegef.org/sites/default/files/council-meeting-documents/EN_GEF.C.48.06_Agency_Compliance_with_Safeguards_May%207.pdf

- GEF/C.45/Inf.04 - AGENCY PROGRESS ON MEETING THE GEF FIDUCIARY STANDARDS - October 9, 2013:

https://www.thegef.org/sites/default/files/council-meeting-documents/rev.GEF_.C.45.Inf_.04_Agency_Progress_on_Meeting_the_GEF_Fiduciary_Standars_October_9_2013_Final_0_4.pdf

- GEF/C.46/Inf.05 - AGENCY PROGRESS ON MEETING THE GEF FIDUCIARY STANDARDS - April 25, 2014:

https://www.thegef.org/sites/default/files/council-meeting-

Page 27: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 26 of 32

UNIDO is the responsible party who will ensure the delivery of anticipated outputs and outcomes and report to the GCF The selected entity from the Network will report to UNIDO as per their contractual arrangement and in line with UN rules and regulations. They will produce regular progress and financial reports and will submit deliverables to UNIDO. Funds will only be released if and when the deliverables are satisfactory and cleared by UNIDO. They will return any unspent funds within ninety days of expiry or notice of termination of the UNIDO. The UNFCCC country focal points for technology (NDE) and finance (NDA) will provide active support to the implementer in the execution of this technical assistance. Their roles as country focal points will include, but not be limited to: Ensuring the activities associated with the implementation of this technical assistance are aligned with national climate priorities; promote and engage with key stakeholders as identified by the implementer; promote and present this technical assistance in climate change-related events; and participate in CTCN events and in national workshops affiliated with this technical assistance, if required. They will also be expected to provide guidance and review any relevant documents produced, and will be kept apprised of the progress of the technical assistance. The implementation map below summarizes the different interactions between the different parties involved in this technical assistance:

CTCN processes before the selection of the implementer (described in the implementation map)

documents/GEF.C.46.Inf_.05%20Agency%20Progress%20on%20Meeting%20the%20GEF%20Fiduciary%20Standards_April%2022%202014.pdf

Page 28: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 27 of 32

The CTCN process for managing technical assistance is the following: Requests for technical assistance can be prepared by any applicant organization from a developing country, but all requests must be submitted by the CTCN NDE (national focal point in the concerned country). Once submitted, all requests submitted by developing countries are assessed as per eligibility, balancing and prioritization criteria approved by the CTCN Advisory Board. The three eligibility criteria are the following: 1) The support provided will contribute to increased resilience and/or mitigate emissions, and is aligned with national plans; 2) The support will enhance endogenous capacities; and; 3) Processes are in place in the requesting country to monitor and evaluate any support provided (that is, project accountability is ensured). Balancing criteria are looking at inter and intra-regional an geographical balance (with a preference for requests submitted by LDCs and other highly vulnerable and low capacity countries; balance between adaptation and mitigation objectives, and balance between various types of support spanning the technology cycle. Prioritization criteria consider a number of elements that demonstrate project strengthen and potential for success, including the promotion of endogenous capacities and appropriate technologies, potential for scale up, for South-South cooperation, for leveraging public and private financing, for creating social, economic and social benefits, promoting gender equality etc. Once a request is deemed eligible and prioritised, the CTCN selects the best expertise among its consortium partners to develop a response plan. The criteria for selection are: Relevant technical expertise, Experience and network in national context, Relevant language capacity, Response Planning track record, Representative use of the consortium partners in Response Planning and Feedback/ preference from the NDE. Based on the discussion with the NDE, NDA and request proponent and feedback from the CTCN, the consortium partner develops the response plan. Once an advanced version is prepared, it is presented to CTCN’s director NDE and NDA for signature. Once the response plan is signed, the contracting of the implementer starts.

6.2 Risks, monitoring and evaluation (M&E), and other relevant information

Below can be found potential risks that might prevent the project objectives from being achieved and the proposed measures that address these risks at the time of project implementation:

Risk

Rating

Mitigation Engagement risk: Lack of engagement from key stakeholders

Low Dissemination strategy and an organizational targeting to enhance primary stakeholders attend TNA related events

Delay risk: Delay in implementation of readiness programme

Low Project management procedures in place. UNIDO actively engaged.

Recruitment risk: Delays due to inability to procure consultants

Medium Highlight need to expedite the process. Dissemination of procurement process through CTCN network and channels

Involvement risk: Lack of interest by the public and private sector key stakeholders, resulting in limited interest of local players to scale up the results of this intervention

Low During project implementation a thorough consultative and participatory approach will be applied; key private sector and industry stakeholders have been identified and targeted in consultation with the NDA/ NDE of Nigeria. UNIDO will manage the risk alongside the implementing partners.

Technical/Capacity risks: Lack of capacity by the national counterparts to use or implement the results and conclusions of this technical assistance.

Low The project is in line with national policies and the project will be executed in close coordination with the respective Ministry and authorities; A number of regional workshops and policy briefs will be delivered to enhance capabilities.

Management Risk: Lack of effective coordination between various project partners

Low A proper coordination will be sought through the CTCN.

Page 29: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 28 of 32

Ownership of the results: True ownership by the government and system operator to ensure results are used and up scaled accordingly

Medium The ownership of the project has been secured by the Government of Nigeria given that it falls under their Work Plan.

Adverse project Risks Money laundering, terrorist financing or prohibited practices

Medium Nigeria has made some progress in building their government (2019 elections). Strengthening governance, tackling corruption and economic reforms remain critical to the country’s and region’s long-term stability. .The Economic and Financial Crimes Commission (EFCC) recorded notable strides in its fight against corruption across Nigeria, with a number of arrests due to misappropriation of the states funds. International actors, notably the United States, France and the United Kingdom, continue to support the Nigerian government’s effort to tackle security challenges and provide humanitarian aid to vulnerable communities. During a joint visit to Nigeria in July, the United Nations Office on Counter Terrorism and the Counter Terrorism Executive Directorate pledged continued technical assistance, including support for criminal justice processes that comply with human rights and rule of law, to help Nigeria to counterterrorism. In September, Germany, Nigeria, Norway and the United Nations co-hosted a high-level conference on the Lake Chad Region in Berlin that raised over $2 billion in support, and $467 million in concessional loans for humanitarian, peacebuilding, and development activities in Cameroon, Chad, Niger, and Nigeria. The European Union also announced the release of €138 million ($157 million) to assist vulnerable communities in the region affected by prolonged violence, insecurity, and environmental degradation This project can be effectively implemented within the current environment while the level of security remains high. Maintain continuous coordination with Consultants (alongside NDA/NDE). Ensure consultants have conducted all required UN SAFE training and accreditation. UNIDO will liaise with the NDA/NDE and Government of Nigeria to reduce the impact of such risks.

Climate Change Risk: Negative impacts of climate change and extreme weather events

Low The potential impact of extreme weather events in Nigeria will be considered through the engagement process.

Page 30: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 29 of 32

Access to data: Data accessibility, mainly from the Utility and other involved stakeholders

Medium Communication channels and information sharing has been secured and their ownership clarified. Same for the other stakeholders. UNIDO will manage the risk alongside the implementing partners.

Gender Risk: Resistance against or lack of interest in, the project activities from stakeholders, especially with regard to the active promotion of gender equality. Low participation rates of suitable female candidates due to lack of interest, inadequate project activity or missing qualified female population within the i.e. engineering sector.

Low This Project will pursue thorough and gender responsive integration and ensure stakeholder involvement at all levels, with special regard to involving women and men.It will feed into the National Gender Climate Change strategy proposal as per the Nigerian GCF Readiness Support request for access to finance to contribute to the Nationally Determined Contribution (NDC) pledge.

Monitoring & Evaluation

Upon contracting of the implementing partners to implement this Response Plan, the lead implementer will produce a monitoring and evaluation plan for the technical assistance. The monitoring and evaluation plan must include specific, measurable, achievable, relevant, and time-bound indicators that will be used to monitor and evaluate the timeliness and appropriateness of the implementation. The CTCN Technology Manager responsible for the technical assistance will monitor the timeliness and appropriateness of the Response Plan implementation. Upon completion of all activities and outputs, evaluation forms will be completed by the (i) NDE about overall satisfaction level with the technical assistance service provided; (ii) the Lead Implementer about the knowledge and learning gained through delivery of technical assistance; and (iii) the CTCN Director about timeliness and appropriateness of the delivery of the activities and outputs.

Page 31: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 30 of 32

7. ANNEX 1: PROPOSED METHODOLOGY

On the basis of the consultations with officials within the Government of Nigeria the following sectors have been selected: Agriculture, Energy and Industry.

Agriculture is the mainstay of the Nigerian economy and is critical for the achievement of the overall development objectives of the country. The objective of a technology needs assessment and action planning exercise is to target the transfer and diffusion of technology for mitigation and adaptation. It prioritizes agriculture as a means to reduce food insecurity and improve nutrition security. Climate change induced dry spells and erratic rainfall patterns are affecting crop production in Nigeria. Most farmers are dependent on rainfall for crop production and are therefore vulnerable to reduced rainfall and accompanying moisture stress on crops. The development of a TNA and the associated prioritization of sectors and technologies that result will help farmers in Nigeria to adapt to changing climate and substantially improve food production. Central to the development of this proposal was identification of actions that best meet the environmental, energy-efficient and resource-saving requirements of Nigeria. Consideration was placed on increasing productivity and strengthening the adaptive capacities of people that are heavily dependent on agriculture. In terms of the energy sector, the proposal identifies significant potential that currently exists in the Nigerian energy sector to deploy technologies including energy efficient buildings, combined heat and power using biomass fuel, and solar PV. A number of potential impacts have been identified below. Proposed Measures and Metric (Examples) are cited in Annex O. These result from a number of identified measures that act as a framework that will enable the desired impact to be achieved.

Sector Potential Impact Agriculture Reduction of GHG emissions from agriculture resulting from increased use of microdrip

irrigation, crop diversification, enhanced soil management practices and reduced use of charcoal. Skills capacity of farmers enhanced through capacity development from increased use of mechanized planters and enhanced crop production techniques. Enhanced viability of technologies resulting from increased deployment of wattle and bamboo, backyard vegetable planters and mini dams.

Energy Reduction of GHG emissions and efficiency deployment from building retrofit initiatives/ codes. Sustainable energy sources expanded and decentralized transmission in order to reduce vulnerability of energy infrastructure to climate impacts. Improving Energy Efficiency and diversifying sources of energy to facilitate access to clean energy towards NDC goal achievement Decarbonisation of energy supply through increased non grid connected renewable energy, PPPs for CHP and from deployment of LEDs/ low emission lighting. Enhanced air quality resulting from increased use of clean cookstoves. Decreased flaring. More information data bases on relevant technologies to forecast contribution to conditional and unconditional targets and increase UN reporting reliability. Increased networking and exchange of best energy efficiency practice by the largest industrial energy users and benchmark results. Mechanisms deployed to stimulate research, development and information dissemination on solar PV, building materials, energy efficient equipment, energy conservation and efficiency.

Industry Circular economy/ GDP benefits from enhanced local production of technology components and training and accreditation of technology installers, building technicians and power engineers.

Page 32: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 31 of 32

Increased local building material manufacture and standards across all technical installations, providing more low carbon solutions to economy. SMEs and entrepreneurs strengthened through targeted scheme providing assessments of energy use and advice on energy management. .Demonstrate the significant potential available through ICT efficiencies, working closely with the industry, utilizing technological solutions such as virtualization, co-location, efficient IT hardware, optimized cooling technologies, and energy management controls

Page 33: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Readiness and Preparatory Support Page 32 of 32

8. ANNEX 2: SUPPLEMENTARY INFORMATION

This proposal supported by CTCN seeks to develop a comprehensive ‘Technology Needs Assessment and associated action plan of climate change mitigation and adaptation needs identified in Nigeria’s most vulnerable economic sectors. This is to be achieved through the following three outcomes:

• Outcome 1. Institutional capacity and coordination mechanisms in place to govern and coordinate climate action and finance

• Outcome 2: Country Programming process • Outcome 3: Climate finance strategies and project pipeline strengthened

This assistance will promote utilization of a wealth of science and technology, energy and environmental policies and gather key data for the prioritized technologies and sectors. The anticipated outcomes from the assistance will be tailored to the conditions in Nigeria and will ultimately support the goals of the current climatic political strategies, such as Nigeria Climate Change Policy Response and Strategy’ (2012), National Science, Technology and Innovation Roadmap 2030 (2017), Economic Recovery and Growth Plan (2017) and the Nigerian NDC

The anticipated outcome is a TNA that presents a number of strategic, long-term, participatory transformational measures across 3 identified and prioritised sectors that will drive climate resilient and low carbon growth in Nigeria. Crucial to its implementation is the achievement of high level political support, fund mobilisation and private sector engagement.

Page 34: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

The following considerations are important when completing the budget:

1. Before preparing the Readiness and PPF budget, please read the full guidance on our website

2. You can select the appropriate budget categories from the dropdown list in the budget plan:

3. To insert additional rows, right click on the row number below where you wish to insert the new row and choose INSERT.

4. Additional budget categories may be added by manually typing them on the Budget Category sheet. :

Project Management Cost: Project management costs (PMC) are the direct administrative costs incurred to execute a project. They should cover only incremental costs incurred due to the GCF contribution. In most cases, these costs are directly related to the support of a dedicated project management unit (PMU) which managesthe day to day execution related activities of the project.

General Principles for PMC costs: 1. The percentage of PMC financed by GCF should not be more than the percentage share of the overall budget financed by GCF 2. PMC budget thresholds: Up to 7.5 per cent of total activity budget. > PMC exceeding 7.5 per cent for the readiness (including NAPs) proposals, and PPF proposals, up to $ 3 million will require detailed documentation and justification supporting the entire PMC budget. > The PMC should be shown as a separate component in the project budget. A detailed breakdown of PMC should be provided by budget category. > Indicative list of eligible project management costs:

> Project staffing and consultants: Project manager, Project Assistant, Procurement personnel, Finance personnel & Support/admin. Personnel> Other direct costs: Office equipment, Mission related travel cost of the PMU, Project management systems and information technology, Office supplies, Audit cost

Contingency :1. Select the appropriate % of Contingency Budget from the dropdown list :

2. Contingency budget for unforeseen costs arising during the project implementation should not be included in the outcome budget separately.3. Contingency budget must be used for any unforeseen programme (output level) cost that is unrelated to implementation/service fee.4. Any use of contingency must be reported to and agreed by the GCF Secretariat in writing in advance provided with justifications that are acceptable to the GCF5. If you get to the end of the project and you haven’t spent Contingency, you can’t increase the scope of the project or buy some more equipment to use it up.

6. The Budget Notes sheet should be used to record explanations, further details or cost breakdowns for individual lines

(https://www.greenclimate.fund/how-we-work/empowering-countries).

If you are unsure about how to complete the budget template, please send your query to: [email protected]

Readiness Grant Budget Preparation Guidelines

Page 35: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

5.1 Budget PlanPlease add rows for Outcomes, Outputs and Cost Categories as required. Additional budget categories may be added by manually typing them on the Budget Category sheet.

Consultant - Individual - International

W/Day 35 500.00 17,500.00

Consultant - Individual - Local W/Day 60 300.00 18,000.00 Consultant - Individual - Local W/Month 18 1,200.00 21,600.00 Workshop/Training Lumpsum 2 1,500.00 3,000.00 Travel – Local Trip 7 300.00 2,100.00 Travel - International Trip 2 3,000.00 6,000.00

1.2. Support the establishment of a TNA Committee

Consultant - Individual - International

W/Day 5 500.00 2,500.00 2,500.00

Consultant - Individual - Local W/Day 10 300.00 3,000.00

Consultant - Individual - International

W/Day 30 500.00 15,000.00

Consultant - Individual - Local W/Day 80 300.00 24,000.00 Workshop/Training Lumpsum 3 1,500.00 4,500.00 Consultant - Individual - International

W/Day 50 500.00 25,000.00

Consultant - Individual - Local W/Day 100 300.00 30,000.00 Travel – Local W/Day 10 300.00 3,000.00 Workshop/Training Lumpsum 3 1,500.00 4,500.00 Consultant - Individual - International

W/Day 50 500.00 25,000.00

Consultant - Individual - Local W/Day 90 300.00 27,000.00

Consultant - Individual - International

W/Day 20 500.00 10,000.00

Workshop/Training Lumpsum 3 4,000.00 12,000.00 Travel - International Trip 1 1,000.00 1,000.00 Travel – Local Trip 5 100.00 500.00 Consultant - Individual - Local W/Day 20 300.00 6,000.00 Consultant - Individual - International

W/Day 12 500.00 6,000.00 6,000.00

Workshop/Training Lumpsum 12 3,000.00 36,000.00 36,000.00

Outcome 3: Climate finance strategies and project pipeline strengthened

3.1 Private sector Engagement Consultant - Individual - Local W/Day 18 300.00 5,400.00 23,400.00

Workshop/Training Lumpsum 6 3,000.00 18,000.00 Total Outcome Budget 329,100.00 91,200.00 - 153,000.00 84,900.00 - - Project Management Cost (PMC)Up to 7.5% of Total Activity Budget

Consultant - Individual - International

W/Day 22 500.00 11,000.00 Actual amount and % of PMC requested:

Maximum PMC that can be requested:

Office Supplies Lumpsum 5 500.00 2,475.00

Travel - International Lumpsum 2 1,000.00 2,000.00 do not change the formula

do not change the formula

Outcome 1 : Institutional capacity and coordination mechanisms in place to govern and coordinate climate action and finance

23,400.00

Total Budget(per outcome) 6m 15m

53,500.00

37,000.00

91,200.00

153,000.00

61,500.00

Outcome 2: Country Programming process

2.1Pre-selection and Prioritisation of sub-sectors as input into TNA (in line with endogenous capacities)

2.3 Develop a technology action plan(s) that quantify the impact of each prioritised technology

153,000.00

23,400.00

2.4 Validation of the national roadmap by the TNA key stakeholders

19,500.00

61,500.00 2.5 Support implementation of the TAP(s) through communications/ guidance/(6) training workshops (in 6 zones, 2 days per zone)

Outcomes

Disbursement Plan

Budget Categorieschoose from the drop-down list Unit 3m 12m

Detailed Budget (in US$)

9mUnit Cost# of Unit Total Budget(per sub-outcome) 18m

Total Budget(per budget category)

2.2 Pre-selection of mitigation and adaptation technologies for the fulfilment of Nigeria’s TNA

62,500.00

18,000.00

91,200.00

70,700.00 1.1 Conduct a stakeholder analysis

1.3 Develop the TNA Committee Work Plan for monitoring and oversight

Page 36: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Audit Fee Lumpsum 2 2,500.00 5,000.00 20,475.00 24,682.50- 6.22% 7.50%

FOR GREEN CLIMATE FUND SECRETARIAT'S

USE ONLYBreakdown (per budget

category) Total (per budget category)

Audio Visual & Printing -

Audit Fee 5,000.00

FOR GREEN CLIMATE

FUND SECRETARIAT

Consultant - Individual - International 112,000.00

Consultant - Individual - Local 135,000.00 Total Outcome Budget 329,100.00 Professional Services – Companies/Firm - Project Management Cost (PMC) 6.2% requested 20,475.00 IT Equipment - Contingency 5% requested 16,455.00 Office Supplies 2,475.00 Travel - International 9,000.00

Travel – Local 5,600.00

Sub-Total (Total Outcome Budget + Contingency + PMC)

366,030.00

Workshop/Training 78,000.00

0 -

Delivery Partner Fee (DP) - Up to 8.5% of the Sub-Total

31,112.55

0 - 0 -

0 -

Total Project Budget (Total Activity Budget + Contingency + PMC + DP)

0 - 347,075.00 Total Outcome Budget + PMC

397,143.00$

Page 37: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Budget Note Detailed Description

A International Climate Change Consultant (Sub-Outcomes 1.1, 1.2-2.1, 2.2, 2.3, 3.3) charges at $500 per day.

B Local Climate consultant (Sub-Outcomes 1.1, 1,2, 3.2) charged at $300 per day.C Two Local consultant @ $1200 per months for 18 monthsD Costs of $3,000 per trip for international consultant to participate in planning and stakeholder events (2)E Costs of $300 per trip for local consultant meetings (USD 300 x 5)F Private sector engagement, stakeholder and capacity building workshops (3 workshops at USD 4,000) in terms of validation with key stakeholder

(Private sector mobilisation workshop at $1500) (Technology prioritisation 3 x $1500) in Abuja and Lagos.

(Sectoral prioritisation at 3 workshops $1500 x 3)

Page 38: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

Budget CategoriesAudio Visual & PrintingAudit FeeConsultant - Individual - InternationalConsultant - Individual - LocalProfessional Services – Companies/FirmIT EquipmentOffice SuppliesTravel - InternationalTravel – LocalWorkshop/Training

Indicate additional budget categories

Page 39: with the Climate Technology Centre and Network (CTCN ... › sites › default › files › ... · Crucial to its implementation is the achievement of high level political support,

5.2 Procurement Plan

Item Estimated Cost (US$)

$ -

Contract of services to implement the technical assistance

Technical Assistance 'Technology Needs Assessment and associated action plan for climate change mitigation and adaptation in Nigeria’s most vulnerable economic sectors'

349,575.00

$ 349,575.00 Note: Inlcuded as procurement (contract to network member): activity costs +PMC

UNIDO will manage the disbursement request and schedule guided by the appropriate agreement and in line with its rules and regulations.

Overall financial management and procurement of goods and services under this readiness and preparatory support proposal will be guided by UN regulations, rules, policies and procedures. UNIDO will be responsible for the implementation of the readiness activities and for procurement and contractual services, as well as reporting on the progress of this implementation in close coordination and strategic guidance from the NDA/FP. The procurement actions and the operational services will be carried forward in accordance with UN policies and procurement guidelines. The specific procedures for procurement through the CTCN are as follows: For a request that is eligible and prioritized, the Climate Technology Managers in charge of the respective request sources the appropriate expertise to develop the Terms of Reference of the assistance (called ‘Response Plan’ as per CTCN procedures). The response plan provides specific information on the technical assistance to be delivered, including activities, outputs, expected outcomes and impacts, timeline, indicators or measuring assistance progress and success, stakeholders to be involved, etc. The response plan, once finalized, is signed by the national focal point of the CTCN in the concerned country (National Designated Entity), the institution which originated the CTCN request for technical assistance and the CTCN Director, and constitutes the basis of the assistance to be implemented and monitored upon the approval and in cooperation with the NDA. Based on the needs and expertise required in the response plan, a CTCN Network Member will be selected to implement it. The selection of organizations from the Network is conducted through a competitive procurement process as per UN Rules and Regulations, in line with CTCN and UNIDO procedures. The CTCN nurtures a Network of some400 expert organizations in the field of low-carbon and climate resilient technologies. The required expertise to carry out the activities that define this intervention will be sourced from the Network. For this, the following four principles shall be given due consideration when undertaking the procurement functions: i i. Best value for money principle; ii ii. Fairness, accountability, integrity and transparency of the procurement process; iii iii. Effective competition; iv iv. The best interest of the CTCN.

Sub-Total (US$)

Consultancy Services

Sub-Total (US$)

For goods, services, and consultancies to be procured, please list the items, descriptions in relation to the activities in Section 3, estimated cost, procurement method, relevant threshold, and the estimated dates. Please include the procurement plan for at least the first tranche of disbursement requested below and provide a full procurement plan for the entire duration of the implementation period if available at this stage.

Goods and Non-Consulting Services

Procurement MethodThresholds

(Min-Max monetary value for which indicated procurement method must be used)

Estimated Start Date Projected Contracting Date