What You Should Know About PMP Formulas
-
Upload
nicole-martinez -
Category
Documents
-
view
17 -
download
1
description
Transcript of What You Should Know About PMP Formulas
What You Should Know About PMP Formulas
A guide from the Project Management Centre of Excellence
IPD/OUM([email protected])
For PMP Aspirants 2
Content of Presentation
Aims of PresentationWhat & Why of FormulasTypes and Classes of
formulasEarned Value
CalculationsPERT CalculationEstimation ClassesProject selection
CriteriaCommunication
Channels
Types and Classes of formulas-cont
ProbabilitiesProcurementDepreciationControl Limits
(Sigmas') Project Network
calculations Other Important
Formulas
10/4/2013
For PMP Aspirants 3
Aims of Presentation
To provide a ‘ONE STOP’ junction to view all formulas and more likely ones used for PMP Exam
To help PMP aspirants to acquire a clear understanding of the related formulas as an aid for a quick exam review
10/4/2013
For PMP Aspirants 4
What & Why of Formulas
A formula is an entity constructed using the symbols and formation rules of a given logical language
A formula is a concise way of expressing information symbolically
The informal use of the term formula in science refers to the general construct of a relationship between given quantities
In a general context, formulas are applied to provide a mathematical solution for real world problems.
Source: Wikipedia10/4/2013
For PMP Aspirants 5
What & why of Formulas-cont.
Formulas are,the configuration of
concepts/theoriesSnap shot of concepts /theories
We need them to, Understand concepts/theories evaluate concepts/theories Apply concepts/theories
10/4/2013
For PMP Aspirants 6
Types and Classes of formulas
Earned ValueBasis of Estimate is the first tool used in
the field of project management whereby members of the project team (estimators, project managers, or cost analysts) usually apply to calculate the total cost of the project
Earned Value Management is a second tool within project management that allows for the tracking of progress throughout the life cycle of a project.
10/4/2013
For PMP Aspirants 7
Types and Classes of formulas
Earned Value Metrics- Earned Value Calculations
Earned Value Management (EVM), or Earned Value Project/Performance Management (EVPM) is a project management technique for measuring project performance and progress in an objective manner
The fundamental values that are focused on are,PV - Planned Value or Budgeted Cost of Work scheduled
(BCWS)AC - Actual Cost or Actual cost of work Performed
(ACWP)EV - Earned Value or Budged Cost of Work Performed
(BCWP)
10/4/2013
For PMP Aspirants 8
Types and Classes of formulas Earned Value Metrics- Earned Value Calculations-cont.
Earned Value Field Name
Description
BCWS (Planned Value)-PV
Budgeted Cost of Work Scheduled
BCWP (Earned Value)-EV
Budgeted Cost of Work Performed
ACWP (Actual Cost)-AC
Actual Cost of Work Performed/Produced
SV (EV-PV) Schedule Variance
CV (EV-AC) Cost Variance
SPI = EV / PV Schedule Performance Index-measures effectiveness
CPI = EV/AC Cost Performance Index-measures efficiency
EAC Estimate at Complete
BAC Budget at Complete
VAC Variance at Complete
TPCI To Complete Cost Index
10/4/2013
For PMP Aspirants 9
Types and Classes of formulas Earned Value Metrics- Earned Value Calculations-cont
CPI greater than 1 is good (under budget):< 1 means that the cost of completing the work is higher than
planned (bad);= 1 means that the cost of completing the work is right on plan
(good);> 1 means that the cost of completing the work is less than
plannedSPI greater than 1 is good (ahead of schedule)
< 1 is bad; the work is performed longer than planned (behind schedule) = 1 means that the work schedule or the work is right on plan
(good); > 1 is good; the work is performed shorter than planned (ahead
of schedule) The SV will be zero at project completion because then all of the
planned values will have been earned
10/4/2013
For PMP Aspirants 10
Project tracking with EVM
10/4/2013
For PMP Aspirants 11
Types and Classes of formulas
Earned Value Metrics- Earned Value Calculations-cont
CV = EV – AC (cost variance)
SV = EV – PV (schedule variance)
EAC (fundamentally Flawed) = BAC-AC
EAC (no variances) = BAC/CPI
EAC (Atypical) = AC + BAC – EV
EAC (Typical) = AC + [(BAC –EV)/CPI]
TCPI (To Complete Performance Index)
= (BAC – EV)/ (BAC -AC), based on BAC= (BAC - EV)/ (EAC – AC), based on EAC=(work Remaining/Fund Remaining)
10/4/2013
ETC (Atypical) = BAC – EV
ETC (Typical) = (ETC – EV)/CPI
ETC (Flawed) = New Estimate = EAC - AC
% Complete = EV/BAC *100%
% SPENT = AC/BAC *100%
VAC = BAC – EAC
BAC = VAC + EAC
EV = % Complete* BAC
CV% = EV/CV * 100%
SV% = EV/SV* 100%
SPI = EV / PV (schedule efficiency)
CPI = EV / AC (cost efficiency)
For PMP Aspirants 12
Types and Classes of formulas
Earned Value Metrics- Earned Value Calculations-cont
Point of Total Assumption (PTA).Used in a fixed price incentive fee (FPIF) contract It is the point where buyer stops bearing costIn other words, it is the point up to where buyer
bears the cost. However, any cost above the PTA is not shared by
buyer and totally imbibed by the sellerThe Formulae: PTA
= [(Ceiling Price - Target Price)/Buyer's Share Ratio] + Target Cost
= {[Ceiling Price – ({Target Cost +Fixed Fee)]/ Buyer's Share Ratio} + Target Cost
10/4/2013
For PMP Aspirants 13
Types and Classes of formulas PERT & Critical Path Estimations
PROGRAM EVALUATION REVIEW TECHNIQUE
PERT 3-point estimate = [Pessimistic+(4*Most Likely)+Optimistic]/6
PERT Activity Variance = ((Pessimistic – Optimistic) / 6^2
PERT Variance of all activities = sum((Pessimistic – Optimistic) / 6^2
PERT Standard Deviation =6 = Square Root of 6^2
CRITICAL PATH METHOD Forward Pass
ES - EF of the predecessor nodeEF - ES plus Duration
Backward Pass
LF - LS of the Successor
LS - LF minus DurationSlack = LF - EF = LS - ESFree Float = ES(Successor) -
EF(Predecessor)Zero Float is on CPM Activity
10/4/2013
For PMP Aspirants 14
Types and Classes of formulas Activity Duration Estimates
• are the likely number of work periods required to complete an activity
• do not include leads and lags• may include range of possible results
e.g. a) 2weeks +/- 2days (i.e. 8 days to 12 days range for a target date of 10 days)
b) 15% probability of exceeding 2 weeks (i.e. 85% likely that the activity will take 2 weeks or less)
10/4/2013
For PMP Aspirants 15
Types and Classes of formulas Classes of Estimates
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = - 15% to + 50%Budget estimate = - 10% to +25%Definitive estimate = - 5% to +10%Final estimate = 0%
10/4/2013
For PMP Aspirants 16
Types and Classes of formulas Project Selection Estimation Methods
PV = FV / (1+r)^nFV = PV * (1+r)^nNPV = Select biggest number. A discount methodROI = Select biggest number. A comparative methodIRR = Select biggest number. A comparative discount
methodPayback Period = Add up the projected cash inflow minus
expenses until you reach the initial investment. A non- discount method
BCR = Benefit / Cost RatioCBR = Cost / Benefit RatioOpportunity Cost = The value of the project not chosen.Expected Value = Probability(%) x Consequence($)
10/4/2013
For PMP Aspirants 17
Types and Classes of formulas Contract Incentives
Savings = Target Cost - Actual Cost
Bonus = Savings x Percentage
Contract Cost = Bonus + Fees
Total Cost = Actual Cost + Contract Cost
10/4/2013
18
Types and Classes of formulas Quality Management Methods
CoQ –Cost of Quality = ( Review + Test Efforts + Training Efforts + Rework Efforts + Efforts of Reinvention) ------------------------------------------------------x 100 % Total Efforts
P - O------- = Variance 6
PERT = O + 4ML +P --------------- 6
STANDARD DEVIATION of TASK = SQ Root of (P - O)/6 = VARIANCE^2
MEAN --> Average CP STD. DEV. = √ σ² + σ² + σ²
MODE --> The "most found" numberEfforts
COMMON CAUSE or RANDOM CAUSE- Chance cause, Non-assignable cause, Noise, Natural pattern
RANGE --> Largest – Smallest Measure. SPECIAL CAUSE - Assignable Cause, Signal, Unnatural pattern
MEDIUM --> Number in the Middle or average, e.g. of 2 Middle Numbers
INSPECTION is better than REWORK
10/4/2013 For PMP Aspirants
For PMP Aspirants 19
Types and Classes of formulas Control Limits using SIGMA
1 sigma = 68.26%2 sigma = 95.46%3 sigma = 99.73%6 sigma = 99.99%
10/4/2013
For PMP Aspirants 20
Types and Classes of formulas Depreciation Valuation Methods
Straight-line Depreciation:Depr. Expense = Asset Cost /
Useful LifeDepr. Rate = 100% / Useful
LifeDouble Declining Balance
Method:Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (e.g. 4/15th)
10/4/2013
For PMP Aspirants 21
Types and Classes of formulas Some Other Significant Measurements
Control Limits = 3 sigma from meanControl Specifications = Defined by
customer; less than the control limitsFloat on the critical path = 0 daysPareto Diagram = 80/20Time a PM spends communicating = 90%Crashing a project = Crash least expensive
tasks on critical path.Just In Time inventory = 0% (or very close to
0%.)10/4/2013
For PMP Aspirants 22
Types and Classes of formulas Some Other Significant Measurements-cont.
CommunicationsCommunication Channels = n * (n-1) / 2
ProbabilityEMV = Probability * Impact in currency
ProcurementPTA = ((Ceiling Price - Target Price) /
Buyer's Share Ratio) + Target Cost
10/4/2013
For PMP Aspirants 23
Congrats!
Pass the ‘formula’ test in your PMP 100%10/4/2013