What We Learned about 3D Modeling & Coordination of MEP ...MEP / FP Coordination Process for Camino...

20
Presentation to Presentation to Virtual Builders Roundtable Virtual Builders Roundtable Washington DC Workshop Washington DC Workshop December 12, 2005 December 12, 2005 What We Learned about 3D Modeling & Coordination of MEP Systems on the Camino Medical Project Atul Khanzode, DPR Construction, Inc. Dean Reed, DPR Construction, Inc. John Mack, Southland Industries

Transcript of What We Learned about 3D Modeling & Coordination of MEP ...MEP / FP Coordination Process for Camino...

  • Presentation toPresentation to

    Virtual Builders Roundtable Virtual Builders Roundtable Washington DC WorkshopWashington DC WorkshopDecember 12, 2005December 12, 2005

    What We Learned about 3D Modeling & Coordination of MEP Systems on the

    Camino Medical Project

    Atul Khanzode, DPR Construction, Inc.Dean Reed, DPR Construction, Inc.John Mack, Southland Industries

  • 2

    Parking Structure & Medical Office Building

  • 3

    The Camino Medical Center• For the Camino Medical Group (CMG)• In Mountain View, California• Site & Infrastructure development (420,790sf)• Parking structure (1,110 stalls, 420,000sf)• Medical Office Building (110 Providers,

    250,000sf)• Urgent Care Center (6,000sf)• Outpatient Surgery Center (5 Suites, 20,000sf)• Pharmacy (6,000sf)• Laboratory and Diagnostics Radiology Center

    (30,000sf)• $100 million in construction costs

  • 4

    How Does Virtual Building Help?

  • 5

    Objectives• Share Lessons Learned from the MEP / FP

    Coordination Process using 3D / 4D Tools on the Camino MOB

    • Provide Specific Examples of the Clash Detection and Resolution Process

    • Identify Opportunities for Improvement in the process

  • 6

    MEP / FP Coordination Process for Camino MOB1. Defining the MEP/FP Design Collaboration

    process2. Implementing the Design to Engineering

    handoffs3. Coordination and conflict resolution using

    3D tools4. Lessons we learned by Pulling design

    coordination from construction

  • 7

    Camino MOB MEP/FP Coordination Process

    1. Defining MEP Design Collaboration Process

    ContractorInput to Design

    Alternatives

    EngineerEngineering & Design in 2D

    SD100%

    SD50%

    ContractorInput to Design Criteria & Equip

    Selection, Sizing, Routing &

    Coordination

    EngineerDesign in 2D

    DD50%

    ContractorDetailed Design & Coordination in 3D

    EngineerDesign Review &

    RFIsDocumentaion in

    2D

    BldgDept Set Permit

    Build

    EngrStampsDrwgs

    CD100%

    Collaboration

    Collaboration

    Collaboration

    = Drawing Author

    DD100%

  • 8

    Camino MOB MEP/FP Coordination Process

    2.a. Design to Engineering Handoffs

    1. Created a Pull schedule for Engineering and Design based on construction schedule

    2. Agreed to work by quadrants to match the construction schedule

    3. Worked backwards to determine the completion date milestone for Engineering and Design

    4. Used Navisworks to identify and resolve conflicts

  • 9

    Camino MOB MEP/FP Coordination Process

    2.b. 3D Coordination Drawings Pulled from Construction Schedule

    A screenshot of the Pull Design Schedule By Quadrant A screenshot of the Pull Design Schedule By Quadrant for the Camino MOB MEP / FP Coordination process for the Camino MOB MEP / FP Coordination process using Lean process and 3D / 4D tools. Coordination is using Lean process and 3D / 4D tools. Coordination is driven by Insert Scheduledriven by Insert Schedule

  • 10

    Camino MOB MEP/FP Coordination Process

    3. Coordination & Conflict Resolution Process Established

  • 11

    Coordination and Conflict Resolution Process

    Specific Examples – 1st Floor SE QuadScreenshot Screenshot from 1from 1stst Clash Clash Detection Detection session on session on 7/19/05 shows 7/19/05 shows multiple multiple clashes clashes between the between the Sprinkler main Sprinkler main and supply and supply ducts on south ducts on south side. It was side. It was decided to decided to move the main move the main to correct the to correct the issueissue

  • 12

    Coordination and Conflict Resolution Process

    Specific Examples – 1st Floor SE Quad

    Screenshot Screenshot from 2nd from 2nd Clash Clash Detection Detection session on session on 7/26/05 7/26/05 shows that shows that the Sprinkler the Sprinkler main was main was moved and moved and clashes with clashes with supply ducts supply ducts on south on south side have side have been been resolvedresolved

  • 13

    Coordination and Conflict Resolution Process

    Specific Examples – 1st Floor SE Quad

    Clash Clash Detection Detection Test to Test to check check clashes clashes between between HVAC and HVAC and Fire Fire Sprinkler Sprinkler Pipe on Pipe on 7/19/05 7/19/05 shows 85 shows 85 Hard Hard ClashesClashes

  • 14

    Coordination and Conflict Resolution Process

    Specific Examples – 1st Floor SE Quad

    Clash Clash Detection Detection Test to Test to check check clashes clashes between between HVAC and HVAC and Fire Fire Sprinkler Sprinkler Pipe on Pipe on 7/26/05 7/26/05 shows 41 shows 41 Hard clashesHard clashes

  • 15

    Coordination and Conflict Resolution Process

    Specific Examples – 1st Floor SE Quad

    Clash Clash Detection Detection Report Report published for published for the Review the Review of the Super of the Super plot of MEP / plot of MEP / FP by the FP by the AE TeamAE Team

  • 16

    Camino MOB MEP/FP Coordination Process

    4. Lessons Learned• Design Team wanted to hold Engineering

    (detailing) work until Design was complete for the whole project

    • At the outset had an agreement between Design and Engineering Team on how the Detailed Engineering models would be developed (By Quadrant)

    • Engineering team expected design released by quadrant, which did not happen for the first 4 quadrants

  • 17

    Lessons Learned

    Possible Solutions

    • Solution that we could have delayed the Engineering work until we were confident that enough Design info was available

    • We could implement handoffs by system (Plumbing / Mechanical) rather than by Geographical Areas (Quadrants)

  • 18

    Lessons Learned

    Technology Solutions

    • Every Detailer should have access to Clash Detection and Resolution software from the very beginning of the project (Not just the GC)

    • Use a document collaboration system to share drawing and model files (No FTP)

  • 19

    Building a Team to Make the Process Work

    • Dr. SlavinCamino Medical Group

    • Curtis, Henry, David, Gary, Mark, Kevin, CoreyHawley, Peterson & Snyder

    • Bryan, SteveCapital Engineering Consultants

    • ChristinaThe Engineering Enterprise

    • BruceSandis Humber Jones

    • Blake, RichKPFF – SF

    • Heather, KenWatry

    • Dave C, Dave P, Will, John, AmayaSutter Health

    • Scott, Mark, John, Jerry and CesarSouthland

    • Jeremy, Tim, NorbertCupertino Electric

    • Clint, Ray, David, SeanJW McClenahan

    • Harry, DavidNorthstar Fire Protection

    • Eric, George, Bill, Ian, Tracy, Scott, Ralph, Dan, Eddie, Atul, DeanDPR

  • Presentation toPresentation to

    Virtual Builders Roundtable Virtual Builders Roundtable Washington DC WorkshopWashington DC WorkshopDecember 12, 2005December 12, 2005

    Questions & Answers in the Roundtable