Well Control and Blowout Prevention
-
Upload
ferry-andri -
Category
Documents
-
view
185 -
download
12
description
Transcript of Well Control and Blowout Prevention
WELL CONTROL AND BLOWOUT PREVENTION
SECTION A: INTRODUCTION AND RESPONSIBILITIES
1. INTRODUCTION
The single most important step in blowout prevention is closing the blowout preventers when the well
kicks. The decision to do so ranks as high as keeping the hole full of fluid as a matter of extreme
importance in drilling operations.
The successful detection and handling of threatened blowouts (“kicks”) is a matter of maximum
importance to our Company. Considerable studies and previous experience have enabled the
industry to develop simple and easily understood procedures for detecting and controlling kicks. It
is crucial that supervisory personnel have a thorough understanding of these procedures as they
apply to Chevron operated drilling rigs.
There are many reasons for promoting proper well control and blowout prevention. An uncontrolled
flowing well can cause any, or all, of the following: personal injury and/or loss of life; damage and/
or loss of contractor equipment; loss of operator investment; loss of future production due to
formation damage and/or loss of reservoir pressures; damage to the environment through pollution;
and adverse publicity or negative governmental reaction, especially near populated areas.
NOTE:
While definite procedures are outlined herein, it should be understood that this
manual is meant to be a guide for company drilling personnel, and is not an
infallible rule book. It should not override sound and mature judgement based
upon knowledge of well control principles and individual circumstances.
Experience has shown that wells are drilled most efficiently with lower costs and fewer hazards when
bottomhole pressures are maintained only slightly above formation pressures. Therefore, it's
imperative that supervisors using this method understand it thoroughly and follow good well control
procedures as described herein.
This is a training manual designed for Company and contract personnel, as a reference for Company
supervisors, and as a general information guide about blowout prevention.
2. RESPONSIBILITIES OF THE OFFICE DRILLING STAFF
Most drilling offices include a drilling staff comprised of a Drilling Manager, Engineering Advisor,
Drilling Superintendents, and Drilling Engineers.
Well Planning: Planning for maximum efficiency and safe operations is primarily the office drilling
staff's responsibility. With concurrence of the Drilling Manager, they must use their knowledge and
good judgment to make the best possible well plan for a particular area.
A-1
Rev12/94
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Drilling Program: This program should include the casing and mud program, special equipment that
will be required for specific well problems, and any other information pertinent to the safe and efficient
drilling of a particular well. The drilling program is usually written by the Drilling Engineer and
approved by the Drilling Superintendent and/or Drilling Manager.
A directional program is also required to avoid existing holes when the target location is different than
the surface location, or in case a relief well is needed. The amount of detail required depends on the
depth, pressure, presence of H2S, crookedness, etc. In high angle holes, singleshot readings should
be taken on two instruments, and an ellipse-of-uncertainty calculated. It is very important, especially
in offshore operations, to know the precise surface and subsurface locations of the well.
In directionally drilled wells, the well course should be carefully planned and horizontal and vertical
sections should be maintained continuously during drilling to ensure that the well course is accurate.
Deviations should be corrected early to avoid excessive doglegs.
Multishot readings are often made prior to setting surface casing so that its position is accurately
known. Effort must be made to know the well position and course accurately from the surface to the
total depth. The degree of effort required varies with the drilling operation.
Geological Information: The Drilling Engineer needs all available geological information for the
area to prepare a good drilling program. Good communication with the geologists is necessary to
determine possible drilling problems and prepare methods of handling them.
Area Drilling Experience:
Each area has characteristic drilling problems that experienced
personnel can handle efficiently and safely. The Drilling Superintendent and Manager should be
primarily responsible for guaranteeing that such assignments are filled with qualified Drilling
Representatives.
Casing Design and Depths of Setting: Compliance with proper casing design and setting depths
calculated from expected formation pressures and fracture gradients is vital, particularly in high-
pressure areas. In some areas, governmental regulations on casing design must be considered in
addition to company practices.
Equipment Selection: Proper equipment is necessary for an efficient and safe operation. Consid-
erable care must be exercised in selecting the proper equipment with the correct pressure rating and
design for a specific job. Primarily, this should be the Drilling Superintendent’s responsibility and the
Drilling Manager and Engineering Advisor should agree.
Hiring Contract Rigs: The Drilling Superintendent and Engineering Advisor will usually provide the
proper rig for the job. How long the rig has been in the area could be a factor, and rig evaluations
should include past performance and the condition of the equipment. If crews change seasonally, the
decision could be based on the general performance of the contractor.
Specification of Rig Equipment: Selecting the proper equipment to do a particular job is of utmost
importance. The Drilling Superintendent’s familiarity with the operation makes him best qualified to
recommend equipment.
Contract Responsibilities: The Drilling Superintendent and Drilling Manager have the responsi-
bility to see that the contracts between Chevron and the drilling contractor are written programs
clearly defining the obligations of both contracting parties.
Rev 12/94
A-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Training of Company and Contract Personnel: The Drilling Superintendent and Engineering
Advisor should maintain a training program for the least experienced drilling employees. The
program should pair the newer employees with experienced Drilling Representatives at the wellsite,
and include attendance at DTC schools and seminars. Drilling Superintendents should periodically
review well control procedures with the Drilling Representatives.
The contractor should be required to train employees in well control either by contract or under the
direction of the Drilling Superintendent or supervisors.
BOP Equipment: The Drilling Representative must ensure that the proper BOP equipment is
available in good working order and installed correctly. Equipment must be in compliance with all
Chevron and governmental requirements. All sections of the “BOP Test and Equipment Checklist”
should be completed upon initial nipple-up.
BOP Testing: Most Chevron wells are required to test the blowout preventer stack once a week and
before drilling out each new casing string. Accurate and complete testing of the BOP’s is the
responsibility of the Drilling Representative on location. The "BOP Test and Equipment Checklist"
should be completed after each test.
Well Control: The Drilling Representative is primarily responsible for keeping the well under control.
This responsibility includes maintaining proper mud properties, recognizing indicators of abnormal
pressure, and executing the proper well control procedures after the well kicks.
Prerecorded Data Sheet: The Prerecorded Data Sheet should be filled-out as completely as
possible at all times on drilling wells. The Data Sheet lists critical wellbore information which will be
needed in nearly all well control situations.
Slow Pump Rate Data: The Drilling Representative must make sure that slow pump rates and
pressures are recorded at least once per tour, or each time the mud weight is changed.
Blowout Prevention Training: The finest equipment and the best procedures are of little use unless
the rig crews are properly trained to use them. The Drilling Representative must make sure that the
crews are properly trained and respond immediately in all well control situations. The Drilling
Representative should also verify that the shut-in procedures while tripping and drilling are clearly
posted at several locations around the rig, and that every crew member knows shut-in responsibilities.
If working in an OCS area, the Drilling Representative is responsible for verifying that all crew
members are MMS certified for well control training.
Information to be Posted: The Drilling Representative should post the following information:
•
•
•
•
•
Maximum allowable initial shut-in casing pressure to fracture shoe.
Maximum allowable casing pressure.
Maximum number of stands pulled prior to filling the hole (collars, HW, and
DP).
Volume required to fill the hole on trips (collars, HW, and DP).
Crew responsibilities for well control drills.
A-3
Rev12/94
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
SECTION B : BASIC CALCULATIONS AND TERMINOLOGY
1. UNDERSTANDING PRESSURES
Hydrostatic Pressure: All vertical columns of fluid exert hydrostatic pressure. The magnitude of
the hydrostatic pressure is determined by the height of the column of fluid and its density. It should
be remembered that both liquids and gases can exert hydrostatic pressure. Hydrostatic pressure
exerted by a column of fluid can be calculated using Equation B.1, below:
Hydrostatic Pressure
Eqn B.1 HP = MW x 0.052 x TVD
where:
HP =
MW =
TVD =
Hydrostatic Pressure (psi)
Mud Weight (ppg)
True Vertical Depth (ft)
While drilling ahead, hydrostatic pressure exerted by the drilling mud is the major deterrent against
kicks.
Pressure Gradient: When comparing fluid densities and hydrostatic pressures, it is often useful to
think in terms of a pressure gradient. The pressure gradient associated with a given fluid is simply
the hydrostatic pressure per vertical foot of that fluid. Heavier (more dense) fluids have higher
pressure gradients than lighter fluids. The pressure gradient of a given fluid can be calculated by using
the formula in Equation B.2.
Pressure Gradient
Eqn B.2
where:
PG
= MW x 0.052
PG = Pressure Gradient (psi/ft)
MW = Mud Weight (ppg)
As you can see from the above equation, the pressure gradient can be thought of as an alternate way
of describing a fluid’s density. This is useful because other parameters (such as reservoir pressure)
are often expressed in terms of pressure gradients as well.
Formation Pressure: Formation pressure is the pressure contained inside the rock pore spaces.
Knowledge of formation pressure is important because it will dictate the mud hydrostatic pressure
and also the mud weight required in the well. If the formation pressure is greater than the hydrostatic
pressure of the mud column, fluids such as gas, oil, or saltwater can flow into the well from permeable
formations. Normal pressure gradients for formations will depend on the environment in which they
were laid down and will vary from area to area.
Rev. 12/94
B-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Consider a formation located at a vertical depth of 5,000' and with a reservoir pressure of 2,325 psi.
The pressure gradient of this formation can be easily figured with the following formula:
Pressure
2,325 psi
PG =
-----------------------
=
---------------
= 0.465 psi/ft
Vertical Depth
5,000 ft
In order to keep this formation from flowing into the well, the mud in the hole must also have a pressure
gradient of at least 0.465 psi/ft. This condition is achieved by filling the hole with 9.0 ppg saltwater.
Surface Pressure: We use the term surface pressure to describe any pressure that is exerted at the
top of a column of fluid. Most often we refer to surface pressure as that which is observed at the top
of a well. Surface pressure may be generated from a variety of sources, including downhole formation
pressures, surface pumping equipment, or surface chokes.
Some surface pressures are conveyed throughout the wellbore, while others are not. For example,
circulating an open well with 1,000 psi pump pressure will not increase the bottomhole pressure by
1,000 psi. The reason is that the pump pressure is created by internal drillpipe friction which acts
opposite to the direction of flow. In a similar way, the annular friction loss generated while circulating
will increase the bottomhole pressure, but will not increase the annular surface pressure. The key to
understanding frictional pressure losses is to remember that they only increase the pressures in the
fluids that are upstream of the point of friction.
Under static conditions (not pumping or flowing) frictional pressure losses are equal to zero.
Therefore, under static conditions, any pressure that we observe at the surface will also be conveyed
downhole.
Bottomhole Pressure: Bottomhole pressure is equal to the sum of all pressures in a well. Generally
speaking, bottomhole pressure is the sum of the hydrostatic pressure of the fluid column above the
point of interest, plus any surface pressure which may be exerted on top of the fluid column, and the
effect of friction pressure must be added or subtracted depending on the direction of flow. This is
expressed mathematically in Equation B.3 to the right:
Bottomhole Pressure
Eqn B.3B
HP = HP + SP +/- FP
where: BHP = Bottomhole Pressure (psi)
HP = Hydrostatic Pressure (psi)
SP = Surface Pressure (psi)
FP = Friction Pressure (psi)
When the hole is full and the mud column is at rest with no surface pressure, the bottomhole pressure
is the same as the mud hydrostatic pressure. However, if circulating through a choke or separator
at the surface, the annular surface pressure and friction pressure (back pressures) will be conveyed
downhole and must be added to the mud hydrostatic pressure to obtain the total bottomhole pressure.
If the well is closed-in under static conditions, the bottomhole pressure will be equal to the sum of the
hydrostatic pressure and any observed surface pressure. In this case, the bottomhole pressure will
also equal the formation pressure.
Rev. 12/94
B-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Equivalent Circulating Density: When circulating fluid in a wellbore, frictional pressures occur in
the surface system, drillpipe, bit, and annulus which in turn are reflected in the standpipe pressure.
As mentioned previously, these frictional pressures always act opposite to the direction of the flow.
When circulating conventionally (the "long way"), all the frictional pressures, including annular
friction, act against the pump. The annular friction, or annular pressure loss, acts against the bottom
of the wellbore, resulting in an increase in bottomhole pressure. This is known as Equivalent
Circulating Density, or ECD. ECD is normally expressed as a pound per gallon equivalent mud
weight, and is shown mathematically in Equation B.4.
Equivalent Circulating Density
Annular Pressure Loss + Present Mud Weight
Eqn B.4
ECD = ------------------------------------------------------------
0.052 x TVDhole
ECD is the result of annular friction and is affected by such items as:
•
•
•
Clearance between large OD tools and the ID of the wellbore.
Circulating rates (or AV).
Viscosity of the mud.
An accurate value for annular pressure loss, and subsequently ECD, is very difficult to arrive at for
any particular situation and once calculated would change with increasing hole depth and changes
in hole geometry (hole washout, etc.). Thus, attempting to keep up with ECD in the field would be an
effort in futility. The important thing to remember is that while circulating through a wellbore,
bottomhole pressure will be higher than when the well is static due to the presence of annular friction.
Differential Pressure: In well control, differential pressure is the difference between the bottomhole
pressure and the formation pressure. The differential is positive if the bottomhole pressure is greater
than the formation pressure, which creates what is called an “overbalanced” condition.
Choke Pressure: Choke pressure is the pressure loss created by directing the return flow from a
closed-in well through a small opening or orifice for the purpose of creating a back pressure on the
well while circulating out a kick. The choke, or back pressure, can be thought of as a frictional pressure
loss that will be imposed on all points in the circulating system, including the bottom of the hole.
Swab and Surge Pressures: Swab pressure is the temporary reduction in the bottomhole pressure
that results from the upward movement of pipe in the hole. Surge pressure has the opposite effect,
whereby wellbore pressure is temporarily increased as pipe is run into the well. The movement of the
drill string or casing through the wellbore is similar to the movement of a loosely fit piston through
a vertical cylinder. A pressure reduction or suction pressure occurs below as the piston or the pipe
is moved upward in the cylinder or wellbore and a pressure increase occurs below as they move
downward.
Rev. 12/94
B-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Swab and surge pressures are mostly affected by the velocity of upward or downward movement in
the hole. Other factors affecting these pressures include:
1)
2)
3)
4)
5)
Mud gel strength.
Mud weight.
Mud viscosity.
Annular clearance between pipe and hole.
Annular restrictions, such as bit balling.
In order to prevent the influx of formation fluids into the wellbore during times when the pipe is moved
upward from bottom, the difference between mud hydrostatic and swab pressure must not fall below
the formation pressure.
Fracture Pressure: The formations penetrated by the bit are under considerable stress due to the
weight of the overlying sediments. If additional stress is applied while drilling, the combined stresses
may be enough to cause the rock to fail or split, allowing the loss of whole mud to the formation.
Fracture pressure is the amount of borehole pressure a formation can withstand before it fails or splits.
Rock strength usually increases with increasing depth and overburden load. As load is increased, the
rock becomes highly compacted, giving it the ability to withstand higher horizontal and vertical
stresses. Therefore, fracture pressure normally increases with depth.
Fracture pressure is normally expressed as a gradient or an equivalent density with units of psi/ft or
ppg, respectively.
2. RELATIONSHIP OF PRESSURE TO VOLUME
All fluids under pressure will change in volume as the pressure changes. As pressure increases, the
volume of the fluid will decrease (i.e. the fluid will compress). As pressure decreases, the volume will
increase (i.e. the fluid will expand). Volume of a fluid is also related to its temperature. In general,
volume will increase with an increase in temperature and decrease with a decrease in temperature.
Fluids will compress or expand differently depending on their compressibility. Liquids have a low
compressibility compared to gas. The relative compressibility of liquids and gases is an important
factor in well control.
Liquids: Liquids of concern in well control include mud, saltwater, oil, brine, and combinations of
these liquids. Since the compressibility of these liquids is low, little change in volume due to pressure
or temperature changes should be expected as liquids are circulated from the wellbore. Therefore,
liquid expansion due to pressure and temperature changes are considered negligible for nearly all
well control calculations.
Gases: Gases, on the other hand, are very compressible and are subject to large changes in volume
as they migrate or are circulated from the wellbore. The expansion of a gas bubble while circulating
out a kick displaces large volumes of mud from the annulus, which lowers the hydrostatic pressure.
In order to maintain the bottomhole pressure at a constant value equal to formation pressure, surface
pressure must be allowed to increase. The expanding gas also causes the pit level to increase and
must be considered. With constant surface pressure, the volume of the gas bubble will roughly double
Rev. 12/94
B-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
each time the bubble depth is halved. If V is the volume of a gas and P is the pressure, disregarding
temperature effects, the relationship between volume and pressure of a gas is given by Boyle's Law,
as shown in Equation B.5.
Boyle's Law
Eqn. B.5
where:
P1 x V1 = P2 x V2
P1 = Pressure of gas at depth 1
V1 = Volume of gas at depth 1
P2 = Pressure of gas at depth 2
V1 = Volume of gas at depth 2
3. CAPACITY FACTORS AND DISPLACEMENT
In well control and in routine drilling operations, frequent calculations of capacity and displacement
must be made. A brief review of the mechanics involved is provided below.
The Capacity Factor is defined as the volume of fluid held per foot of container. The container may
be a mud pit, an open hole, the inside of a drillstring, or an annulus. Capacity factors change as the
dimensions of the container change. The internal capacity factor is used to calculate internal
drillstring volumes, and the annular capacity factor is used to calculate annular volumes. Formulas
for calculating these capacity factors are given below:
Internal Capacity Factor:
ID2
Eqn B.6
where:
CF =
CF =
ID =
----------
1029
Capacity Factor (bbl/ft)
Internal pipe diameter (inches)
Annular Capacity Factor:
ID2 - OD2
Eqn B.7
where:
CF = --------------
1029
CF = Capacity Factor (bbl/ft)
ID = Diameter of hole or inside diameter of larger pipe (inches)
OD= Outside diameter of smaller pipe (inches)
In lieu of these equations, Tables P.1 through P.4 can be used to determine internal and annular
capacity factors for several wellbore configurations.
Rev. 12/94
B-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Capacity is the volume of fluid held within a specific container. Internal (drillstring) and annular
capacities are two of the most important parameters that are calculated in a well control situation.
Capacity is determined by multiplying the height (or length) of the container by its capacity factor.
Displacement is the volume of fluid displaced by placing a solid, such as drillpipe or tubing into a
fixed volume of liquid such as drilling mud. Total displacement of drillpipe, casing, tubing, etc. can
be determined by multiplying the length of pipe immersed times the displacement factor (bbls/ft), as
determined from Tables P.1 through P.3.
The volume of mud in the hole is always equal to the capacity of the entire hole, minus the
displacement of the pipe in the hole (assuming the pipe and annulus are full). The annular capacity
between drillstring components and the casing or hole can be calculated by subtracting both the
capacity and displacement of the drillstring component from the capacity of the hole.
Rev. 12/94
B-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
SECTION C: CAUSES AND DETECTION OF KICKS
1. CAUSES OF KICKS
A kick is defined as any undesirable flow of formation fluids from the reservoir to the wellbore that
occurs as a result of a negative pressure differential across the formation face. Wells kick because
the reservoir pressure of an exposed permeable formation is higher than the wellbore pressure at that
depth. There are many situations which can produce this unfavorable downhole condition. Among
the most likely and recurring are:
Causes of Kicks
•
•
•
•
•
Low density drilling fluid.
Abnormal reservoir pressure.
Swabbing.
Not keeping the hole full on trips.
Lost circulation.
These causes will be examined in detail in this section with emphasis placed upon what can be done
early to avoid this situation.
A. Low Density Drilling Fluid
Density of the drilling fluid is normally monitored and adjusted to provide the hydrostatic
pressure necessary to balance or slightly exceed the formation pressure. Accidental dilution of
the drilling fluid with makeup water in the surface pits or the addition of drilled-up, low density
formation fluids into the mud column are possible sources of a density reduction that could
initiate a kick. Diligence on the mud pits is the best way to ensure that the required fluid density
is maintained in the fluids pumped downhole.
Most wells are drilled with sufficient overbalance so that a slight reduction in the density of the
mud returns will not be sufficient to cause a kick. However, any reduction in mud weight during
circulation must be investigated and corrective action taken. A major distinction should be
drawn between density reductions caused by gas cutting and those caused by oil or salt water
cutting.
Gas Cutting: The presence of large volumes of gas in the returns can cause a drop in the
average density and hydrostatic pressure of the drilling fluid. However, the appearance of gas
cut mud at the surface usually causes unnecessary concern, and often results in over-weighting
of the mud. The reduction of bottomhole pressure due to gas cutting at the surface is illustrated
in the following table.
Rev. 12/94
C-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Effect Of Gas Cut Mud On The Bottom Hole Hydrostatic Pressure
Pressure Reduction (psi)
---------------------------------------------------------------------------------------------------------------
10.0 PPG Cut To 18.0 PPG Cut To 18.0 PPG Cut To
Depth 5.0 PPG 16.2 PPG 9.0 PPG
1000
5000
10000
20000
51
72
86
97
31
41
48
51
60
82
95
105
Notice that the total reduction in hydrostatic pressure at 20,000 feet is only about 100 psi even
though mud density is cut by 50 percent at the surface. This is because gas is very compressible
and a very small volume of gas that has an insignificant effect on mud density downhole will
approximately double in size each time the hydrostatic pressure is halved. Near the surface, this
small volume of gas would have expanded many times, resulting in a substantial reduction of
surface density.
It is interesting to note that most gas cutting occurs with an overbalanced condition downhole.
For example, if a formation containing gas is drilled, the gas in the pore space of the formation
is circulated up the hole along with the cuttings. The hydrostatic pressure of the gas in a cutting
is greatly reduced as it moves up the annulus, allowing the gas to expand and enter the mud
column. The mud will be gas cut at the surface, even though an overbalanced condition exists
downhole. If the amount of "drilled gas" is large enough, it is possible that a well could be flowing
at the surface as the gas breaks out and still be overbalanced downhole. However, a flowing well
is always treated as a positive indication that the well has kicked, and the well should be shut-
in immediately when this occurs.
In a balanced or slightly overbalanced condition, gas originating from cuttings could reduce the
bottomhole pressure sufficiently to initiate a kick. Gradual increases in pit level would be
observed at first, but as the influx of gas caused by the underbalanced condition arrives at the
surface, rapid expansion and pit level increase will occur. The well should be shut-in and the
proper kill procedure initiated. When gas cut mud causes a hydrostatic pressure reduction large
enough to initiate a kick, the density of the mud being pumped downhole will usually not have
to be increased to kill the well. This can be verified by shutting-in the well and confirming that
the shut-in drillpipe pressure is zero.
Oil or Salt Water Cutting Oil and/or saltwater can also invade the wellbore from cuttings or
swabbing, reduce the average mud column density, and cause a drop in mud hydrostatic
pressure large enough to initiate a kick. However, since these liquids are much heavier than gas,
the effect on average density for the same downhole volumes is not as great. Also, since
liquids are only slightly compressible, little or no expansion will occur when circulating them out.
However, a given mud weight reduction measured at the surface due to oil and/or saltwater
invasions will cause a much greater decrease in the bottomhole pressure than a similar mud
which is cut by gas. This is because the density reduction is uniform throughout the entire mud
column when it is cut by a liquid.
Rev. 12/94
C-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
B. Abnormal Reservoir Pressure
Formation pressure is due to the action of gravity on the liquids and solids contained in the
earth's crust. If the pressure is due to a full column of saltwater with average salinity for the area,
the pressure is defined as normal. If the pressure is partly due to the weight of the overburden
and is therefore greater, the pressure is known as abnormal. Pressures below normal due to
depleted zones or less than a full fluid column to the surface are called subnormally pressured.
In the simplest case (usually at relatively shallow depth), the formation pressure is due to the
hydrostatic pressure of formation fluids above the depth of interest. Saltwater is the most
common formation fluid and averages about 8.95 ppg or 0.465 psi/ft along the U.S. Gulf Coast.
Therefore, 0.465 psi/ft is considered the normal formation pressure gradient for the Gulf Coast.
Normally pressured formations are often drilled with about 9.5 to 10.0 ppg mud in the hole.
For the formation pressure to be normal, fluids within the pore spaces must be interconnected
to the surface. Sometimes a seal or barrier interrupts the connection. In this case, the fluids
below the barrier must also support part of the rocks or overburden. Since rock is heavier than
the fluids, the formation pressure can exceed the normal hydrostatic pressure. During normal
sedimentation, the water surrounding the shale is squeezed out because of the addition of
overburden pressure. The available pore space, or porosity, will decrease and the density per
unit volume will increase with depth. However, if a permeability barrier or rapid deposition
prevents the water from escaping, the fluids within the pore space will support part of the
overburden load which results in above normal pressure. This scenario is depicted in Figure C.1
below.
Figure C.1
Abnormally Pressured Sand Formation
Less Dense Shale
Denser Shale
Normal Sand
Denser Shale
Less Dense Shale
(due to free water)
Over-Pressured Sand Formation
Denser Shale
Rev. 12/94
C-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Figure C.2 - Abnormal Pressure Due to Faulting
8,000 ft.
10,000 ft.
4650 psi
4650 psi
Another common cause of ab-
normal pressure is faulting.
As can be seen in Figure C.2,
a formation originally depos-
ited under normal pressure
conditions is uplifted 2,000 ft.
The pressure within the up-
lifted section is trapped in the
formation. The pressure in the
formation is now abnormal for
that depth. There may be no
rig floor warning prior to drill-
ing into an abnormal pressure
zone of this nature.
Abnormal pressure
can also occur as the
result of depth and
Figure C.3 - Abnormal Pressure due to Folding
structure changes
within a reservoir. As
shown in Figure C.3 ,
at 3,000 ft. the forma-
tion pressure at the
gas-water contact is
normal and equal to
0.465 psi/ft x 3000 ft =
3,000 ft.
WATER
2,000 ft.
GAS
1,395 psi. However,
at the top of the struc-
ture (2,000 ft), the formation is overpressured and approximately equal to 1,295 psi. (Note: The
pressure at 3,000 ft (1,395 psi) less a 1,000 ft. gas column (1,000' x .1 psi/ft) equals 1,295 psi.)
The mud weight required at 2,000 ft to balance this formation is 1,295/(0.052 x 2,000') = 12.5
ppg.
Prior to drilling a particular well, all information regarding abnormally pressured zones should
be gathered and on hand for the Drilling Engineer. Seismic data can often be helpful. Logs on
nearby wells, along with the drilling reports of these wells, should be studied. If the well is a rank
wildcat in a new area, no knowledge of pressures to be encountered may exist. In these cases,
pressure determination from techniques such as plotting the "dc" exponent while drilling, and
pore pressure calculations from electric logs run in the well are invaluable. Other warning signs
are available while drilling, and are discussed later in this chapter.
Usually, abnormally pressured formations give enough warning that proper steps can be taken.
As noted elsewhere in this guide, low mud weights best indicate abnormal or high-pressure
zones. Once these zones are detected, it's possible to drill into them a reasonable distance while
raising the mud weight as necessary to control formation fluid entry. However, when pressure
due to mud weight approaches the fracture gradient of the highest exposed formation, it is good
practice to set casing. Failure to do this has been the cause of many underground blowouts and
lost or junked holes.
Rev. 12/94
C-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
If abnormal pressure zones are drilled with mud weights insufficient to control the formation, a
kick situation develops. This occurs when the pressure in the formation drilled exceeds the
hydrostatic head exerted by the mud column. A pressure imbalance results and fluids from the
formation enter into the wellbore.
C. Swabbing
Swabbing is a condition that arises when pipe is pulled from the well and produces a temporary
bottomhole pressure reduction. In many cases, the bottomhole pressure reduction may be large
enough to cause the well to go underbalanced and allow formation fluids to enter the wellbore.
By strict definition, every time the well is swabbed-in, it means that a kick has been taken. While
the swab may not necessarily cause the well to flow or cause a pit gain increase, the well has
produced formation fluids into the annulus that have almost certainly lowered the hydrostatic
pressure of the mud column. Usually, the volume of fluid swabbed-in to the well is an
insignificant amount and creates no well control problems (e.g., a small amount of connection
gas). Many times, however, immediate action will need to be taken to prevent a further reduction
in hydrostatic pressure which could cause the well to flow on its own.
It can be very difficult at times to recognize swabbing. The most reliable method of detection
is proper hole filling. If a length of drillpipe composed of five barrels of metal volume is pulled
from the well and the hole fill-up is only four barrels, a barrel of gas, oil, or saltwater has probably
been swabbed into the wellbore. If swabbing is indicated (even if there's no flow), the pipe should
be immediately run back to bottom, the mud circulated out, and the mud densified or conditioned
before making the trip.
A short trip is often made to determine the combined effects of bottomhole pressure reductions
that are caused by a loss of equivalent circulating density and swabbing. When drilling under
or near balanced conditions, a short trip is particularly important since it quickly indicates a need
to raise mud density or slow pulling speeds. Expansion of swabbed gas or flow from the
formation later during the trip can be much more difficult to overcome, possibly requiring
stripping back to bottom to kill the well.
Many downhole conditions tend to increase the likelihood that a well will be swabbed-in when
pipe is pulled. Several of these are discussed below.
Balled-Up Bottomhole Assembly: The drill string becomes a more efficient piston when drill
collars, stabilizers and other bottomhole assembly components are balled-up. This causes a
greater bottomhole pressure reduction that can swab more fluids into the wellbore. If the well
is almost at balance, only a few vertical feet of fluid swabbed-in can cause the well to flow on
its own.
Pulling Pipe Too Fast: The piston action is also enhanced when pipe is pulled too fast. The
Rig Supervisor should be sure that the pipe is pulled slowly off bottom for a reasonable distance.
However, the hole should be watched closely at all times to be sure it is taking the correct amount
of mud. The maximum pulling speed can be determined for a given set of mud properties using
the available DRILPRO programs.
Poor Mud Properties: Swabbing problems are compounded by poor mud properties, such as
high viscosity and gels. Mud in this condition tends to cling to the drill pipe as it moves up or down
the hole, causing swabbing coming out and lost circulation going in.
Rev. 12/94
C-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Heaving or Swelling Formations: Swabbing can result if the formations exposed either heave
or swell, effectively reducing the diameter of the hole and clearance around the bit or stabilizers.
In these formations, even a clean bit acts like a balled bit or stabilizer.
Large OD Tools: Drill stem testing tools, fishing tools, core barrels, or large drill collars in small
holes enhance swabbing by creating a piston action when the pipe is pulled too fast. Extra care
should be taken whenever pulling equipment with close tolerances out of the hole.
Good practices to prevent or minimize swabbing are aimed at keeping the mud in good
condition, pulling pipe at a reasonable speed, and using some type of effective lubricant mud
additive to reduce balling. Additives such as blown asphalt, gilsonite, detergent, and EP
additives are effective in many cases. Good hydraulics will often help clean a balled-up bit or
bottomhole assembly.
D. Not Keeping Hole Full
Blowouts that occur on trips are usually the result of either swabbing or not keeping the hole full
of mud. Substantial progress has been made in blowout prevention, but constant vigilance must
be maintained. As drill pipe and drill collars are pulled from the hole during tripping operations,
the fluid level in the hole drops. In order to maintain fluid level and mud hydrostatic pressure,
a volume of mud equal to the volume of steel removed must be pumped into the annulus. An
accurate means of measuring the amount of fluid required to fill the hole must be provided.
The volume of steel in a given length of collars can be as much as five times the volume for
the same length of drill pipe. The fluid level in the hole will also drop five times farther, and the
reduction in bottomhole pressure will be five times as great. If the hole is normally filled after
pulling fives stands of drill pipe, it may be necessary to fill the hole after pulling each stand of
drill collars. As a general rule, the hole should always be filled on trips before the reduction in
hydrostatic pressure exceeds 75 psi.
It is the responsibility of the Drilling Representative to see that the rig crews are thoroughly
schooled in the necessity of keeping the hole full. Many mechanical devices have been
developed to help keep the hole full. These include:
Use of Mud Log Unit: These units are equipped with pump stroke counters normally used for
correlating well cuttings with depth. Counters can also be used during trips to aid in determining
the proper amount of mud to keep the hole full and to detect swabbing. However, the mud log
crews must be alerted to the need for this service during trips, when there is no logging.
Stroke Counter: These counters, mounted near the Driller’s position, are convenient for
checking filling volume requirements. Because they are operated only by the Driller, there
should be no communication problem.
Pit Volume Monitoring: Bulk mud volume checking is also very helpful, but large pits will not
indicate small changes; these can best be seen in a trip tank. The trip tank should be near the
rig floor and calibrated so the driller can easily see and compare the volumes pumped into the
hole vs. steel pulled out. If the trip tank cannot be monitored from the floor, it should be manned
by an experienced crew hand.
Rev. 12/94
C-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Flowline Monitors:
Besides monitoring flow while drilling, these devices detect fluid
immediately when the hole fills, ensuring a good comparison between pump strokes and
returning fluid flow rate. Also, these devices detect “no-flow” when lost circulation occurs. Their
proper use should prevent blowouts due to not keeping the hole full or swabbing. Since flowline
monitors can detect flow while the drill string is out of the hole, they should be left on
continuously.
E. Lost Circulation
An important cause of well kicks is the loss of whole mud to natural and/or induced fractures and
to depleted reservoirs. A drop in fluid level in the wellbore can lower the mud hydrostatic
pressure across permeable zones sufficiently to cause flow from the formation. Some of the
more common causes of lost circulation include:
High Mud Weight: If the bottomhole pressure exceeds the fracture gradient of the weakest
exposed formation, circulation is lost and the fluid level in the hole drops. This reduces the
effective hydrostatic head acting against the formations that did not break down. If the mud level
falls far enough to reduce the BHP below the formation pressure, the well will begin flowing.
Thus, it is important to avoid losing circulation. If returns cease, loss of hydrostatic pressure can
be minimized by immediately pumping measured volumes of water into the hole. Measuring the
volumes will enable the Drilling Supervisor to calculate the correct weight of mud that the
formation will support without fracturing. Upon gaining returns, verify that the well is not flowing
on its own.
Going into the Hole Too Fast: Loss of circulation can also result from rapidly lowering the drill
pipe and bottom assembly (drill collars, reamers, and bit). This is similar to swabbing, but in
reverse; the piston action forces the drilling fluid into the weakest formation. This problem is
compounded if the string has a float in it and the pipe is large compared to the hole. Particular
care is required when running pipe into a hole having exposed weaker formations and heavy
mud to counter high formation pressure. Surging calculations can be easily made using the
available DRILPRO programs.
Pressure Due to Annular Circulating Friction: Another item to be considered when drilling
with a heavy mud near the fracture gradient of the formation is the pressure added by circulating
friction. This can be quite large, particularly in small holes with large drill pipe, or stabilizers
inside the protective casing. It is sometimes necessary to reduce the pumping rate to lower the
circulating pressure. This problem can become acute when trying to break circulation with high
gel fluids.
Sloughing or Balled-Up Tools: Partial plugging of the annulus by sloughing shale can restrict
the flow of fluids in the annulus. This imposes a backpressure on the formations below and can
quickly cause a breakdown if pumping continues. Annular plugging is most common around the
larger drillstring components such as stabilizers, so efforts to reduce balling will also diminish
the chances of this type of lost circulation.
Rev. 12/94
C-7
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
2. DETECTION OF KICKS
It is highly unlikely that a blowout or a well kick can occur without some warning signals. If the crew
can learn to identify these warning signals and to react quickly, the well can be shut-in with only a
small amount of formation fluids in the wellbore. Smaller kick volumes decrease the likelihood of
damage to the well bore and minimize the casing pressures.
Kick indicators are classified into two groups: positive and secondary. Anytime the well experiences
a positive indicator of a kick, immediate action must be taken to shut-in the well. When a secondary
indicator of a kick is identified, steps should be taken to verify if the well is indeed kicking.
Positive Indicators of a Kick
The "Positive Indicators of a Kick" are shown to the
left. Immediate action should be taken to shut-in the
→
→
Increase in Pit Volume
Increase in Flow Rate
well whenever these indicators are experienced. It is
not recommended to check for flow after a positive
indicator has been identifed.
The "Secondary Indicators of a Kick" are shown
to the right. The occurence of any of these
Secondary Indicators of a Kick
indicators should alert the Drilling Representa-
tive that the well may be kicking, or is about to
kick. These indicators should never be ignored.
Instead, once realized, steps should be taken
to determine the reason for the indication.
Indicators of Abnormal Pressure
→
→
→
→
→
Decrease in Circulating Pressure
Gradual Increase in Drilling Rate
Drilling Breaks
Increase in Gas Cutting
Increase in Water Cutting or Chlorides
→
→
→
→
→
→
Decrease in Shale Density
Change in Cuttings Size and Shape
Increasing Fill on Bottom After a Trip
Increase in Flow Line Temperature
Increase in Rotary Torque
Increasing Tight Hole on Connections
"Indicators of Abnormal Pressure" are shown to
the left. Observance of any of these indicators
often means that the well is penetrating an
abnormally pressured formation. Remedial ac-
tion may range from increasing the mud weight
to setting casing.
The following pages describe these indicators in detail and prescribe the proper remedial action to
take in the event of their occurrence.
A. Increase in Pit Volume
A gain in the total pit volume at the surface, when there are no mud materials being added at
the surface, indicates either an influx of formation fluids into the wellbore or the expansion of
gas in the annulus. Fluid influx at the bottom of the hole shows an immediate gain of surface
Rev. 12/94
C-8
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
volume due to the incompressibility of a fluid, (i.e. a barrel in at the bottom pushes out an extra
barrel at the surface). The influx of a barrel of gas will also push out a barrel of mud at the surface,
but as the gas approaches the surface, an additional increase in pit level will occur due to gas
expansion. This is a positive indicator of a kick, and the well should be shut-in immediately any
time an increase in pit volume is detected.
All additions to the mud system should be done with the Driller's knowledge. Each change in
addition rate, particularly of water or barite, should be reported. Any change in valve settings
that could affect fluid into or out of the system should be noted and relayed to the Driller. This
is the only way to prevent unnecessary shut-ins of the well. Again, the Driller should always shut
the well in first, and then determine the reasons for a pit gain.
B. Increase in Flow Rate
An increase in the rate of mud returning from the well above the normal pumping rate indicates
a possible influx of fluid into the wellbore or gas expanding in the annulus. Flow rate indicators
like the "FloSho" measure small increases in rate of flow and can give warning of kicks before
pit level gains can be detected. Therefore, an observed increase in flow rate is usually one of
the first indicators of a kick. This is a positive indicator of a kick, and the well should be shut-
in immediately any time an increase in flow rate is detected.
Positive readings of a shut-in drillpipe pressure indicate that the well will have to be circulated
using the Driller's or Engineer's Kill Procedure. If the increase in flow was due to gas expansion
in the annulus, the shut-in drillpipe pressure will read zero because no drillpipe underbalance
exists.
C. Decrease in Circulating Pressure
Invading formation fluid will usually reduce the average density of the mud in the annulus. If the
density of mud in the drillpipe remains greater than in the annulus, the fluids will U-tube. At the
surface, this causes a decrease in the pump pressure and an increase in the pump speed.
The same surface indications can be caused from a washout in the drillstring. To verify the
cause, the pump should be shut down and the flow from the well should be checked. If the flow
continues, the well should be shut-in and checked for drillpipe pressure to determine whether
an underbalanced condition exists.
D. Gradual Increase in Drilling Rate
While drilling in the normally pressured shales of a well, there will be a uniform decrease in the
drilling rate. Assuming that bit weight, RPM, bit types, hydraulics and mud weight remain fairly
constant, the decrease will be due to the increase in shale density. When abnormal pressure
is encountered, the density of the shale is decreased and so is the porosity. Higher porosity
shales are softer and can be drilled faster. Therefore, the drilling rate will almost always increase
as the bit enters an abnormally pressured shale. This increase will not be rapid but gradual. A
penetration rate recorder simplifies detecting such changes. In development drilling, this
recorder can be used with offset well electric logs to pinpoint the top of an abnormal pressure
zone before any other indicators appears.
Rev. 12/94
C-9
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
In areas where correlation with other wells
may be difficult, calculation and plotting of
the "d" exponent can be helpful in detect-
ing abnormal pressure. The "d" exponent
is obtained from the basic drilling equation
shown below. As penetration rate is ef-
fected by mud weight, a correction for
actual mud weight must be made, as shown
to the right:
Corrected "d" Exponents
9.0
dc = ---------------------------- x d : for Gulf Coast
Actual Mud Weight
8.25
dc = ---------------------------- x d : for Hard Rock
Actual Mud Weight
"d" Exponent Equation
R= K
12 Wd
-------------
10 3 D
60N
Figure 11C.4
dc Exponent vs. Depth
where:
10000
1
1.5
2
2.5
R = Penetration Rate (ft/hr)
K = Formation Drill Constant
W = Weight on Bit (m-lbs)
D = Bit Diameter (in)
N = Rotary Speed (rpm)
d = Drilling Exponent
Plotting “dc” versus depth result in a plot similar to
the one shown in Figure C.4. The point at which the
plot shifted left is where abnormal pressure was
encountered. A Mud Logger on location would
normally maintain a plot of this type.
E. Drilling Breaks
Abrupt changes in the drilling rate without changes
in weight on bit and RPM are usually caused by a
change in the type of formation being drilled. A
universal definition of a drilling break is difficult
because of the wide variation in penetration rates,
types of formations, etc. and experience in the
Well
Depth, ft.
11000
12000
13000
specific area is required. In some sand-shale se-
quences, a break may be from 10 ft/hr to 50 ft/hr, or
perhaps from 5 ft/hr to 10 ft/hr. In any case, while
14000
8 9 10 11
Mud Weight, ppg.
drilling in expected high pressure areas, if a rela-
tively long interval of slow (shale) drilling is sud-
denly interrupted by faster drilling ( indicating a sand) the kelly should be picked up immediately,
the pump shut off, and the hole observed for flow.
Very fast flow from the wellbore can result if permeability is high and mud weight is low. Then
the well must be shut in immediately. If the permeable sand formation has only slightly higher
pressure than the mud hydrostatic, flow may be difficult to detect. If there is doubt and drilling
is in an expected abnormal pressure area, it may be best to circulate the break to the surface.
Rev. 12/94
C-10
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
If the sand is abnormally pressured, the gassy mud nearing the surface will expand, causing a
rise in pit level. It may be necessary to control this expansion through the choke manifold (with
the blowout preventer closed) before increasing the mud weight and drilling ahead.
F. Increase in Gas Cutting
A gas detector, or hot wire device, provides a valuable warning signal of an impending kick.
These instruments measure changes in the relative amounts of gas in the mud and cuttings, but
do not provide a quantitative value. Increases in the gas content can mean increase in gas
content of the formation being drilled, gas from cavings, and/or an underbalanced pressure
condition. Gas in the drilling mud is reported in several different ways.
F.1. Drilled Gas
This is the gas entrained in the rocks that are drilled. The drilled (or background) gas will
usually increase as the bit penetrates an abnormally pressured shale. Abnormally pres-
sured shale gas will continue to feed in after all drilled-up gas has been removed from the
mud. Occasionally, drilled gas will be slow to drop out, but will finally do so if the mud weight
is high enough to control the formation pressure.
F.2. Connection Gas
Connection gas is a measure of gas which is either swabbed into the hole while pulling up
for a connection or is a result of a loss in ECD while shutting the pumps off for a connection.
It is reported in total units observed. Connection gas can be identified by estimating the time
it takes to pump mud from the bottom of the hole to the surface and checking the gas
detector to record the time. The connection gas will almost always increase when an
abnormal pressure zone is penetrated. At low mud weights, the gas increase will be gradual.
That is, one connection may show 20 units; the next, 30 units; and the third, 40 units. Mud
weight increases may be necessary, even though there may be little or no change in
background gas.
F.3. Trip Gas
Trip gas is very similar to connection gas, except that it is a measure of swabbed gas over
an entire trip. Often a short trip of 15-20 stands is made in order to circulate bottoms up and
measure units of swabbed gas. Excessive units of trip gas could indicate the need for
increasing the trip margin and/or reducing swab pressure. Failure to fill the hole on trips may
also cause an increase in trip gas. Trip gas will generally increase when an abnormal-
pressure section has been penetrated and the mud weight has not been raised. This is not
a good indicator of abnormal pressure by itself, but is useful with other evidence. Trip gas
should be reported as the total units observed.
G. Increase in Chlorides
Invasion of the drilling mud by formation water can sometimes be detected by changes in the
average density or the salinity of the mud returning from the annulus. Depending on the density
of the mud, dilution with formation water will normally reduce average density. If the density of
the invading fluid is close to that of the mud, the density will be unaffected, but perhaps a change
in salinity will be apparent. This would depend on the salinity contrast between the formation
Rev. 12/94
C-11
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
fluid and the mud. Usually formation fluids are more salty than drilling muds and an influx can
be detected by marked increases of chloride content of the mud filtrate. Chloride changes alone
are not a good indicator of abnormal pressures, but can be used in conjunction with other
indicators to present a clearer picture.
H. Decrease in Shale Density
The shale density will generally decrease when an abnormal pressure zone is penetrated. This
would be a good indicator if bulk densities of representative samples could be accurately
measured. A decrease in density is a result of an increase in the water content within the shale.
I. Change in Cutting Size and Shape
The amount of shale cuttings will usually increase and change in shape will take place when an
abnormal pressure zone is penetrated. Cuttings from normally pressured shales are small with
rounded edges and are generally flat, while cuttings from an abnormally pressured often
become long and splintery with angular edges. As the differential between the pore pressure and
the drilling fluid hydrostatic pressure is reduced, the pressured shales will explode into the
wellbore rather than being drilled up. This change in shape, along with an increase in the amount
of cuttings recovered at the surface, could be an indication that the mud hydrostatic pressure
is too low and that a kick could occur while drilling the next permeable formation.
J. Increasing Fill on Bottom After Trips
Increasing fill on bottom after a trip, accompanied by an increase in trip gas, may indicate
abnormally pressured shale. This condition can also be created by not filling the hole or poor
mud properties during a trip, so it is not conclusive by itself.
K. Temperature
Flow line temperature often increases before an abnormal pressure zone is penetrated. This has
been observed in many parts of the world, but can be deceiving. Temperatures are also
increased temporarily by the addition of barites or caustic, and by changes in hydraulics, such
as hole size. Sharp, stable increases in temperature possibly indicating abnormally pressured
shale are best seen on a relatively large-scale depth vs. temperature plot.
L. Increasing Rotary Torque
Torque sometimes increases when an abnormal shale section is penetrated due to the
pressured shales above the bit continuing to explode into the hole.
M. Tight Hole on Connections
When making connections, a tight hole can indicate that an abnormally pressured shale is being
penetrated with low mud weight. Often the hole must be reamed several times before a
connection can be made. The drillpipe could stick or a blowout could occur if abnormal pressure
goes undetected.
Rev. 12/94
C-12
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
SECTION D: SHUT-IN PROCEDURES
1. MINIMIZE THE SIZE OF THE INFLUX
Chevron's Shut-in Procedure is designed with an overriding purpose in mind: minimizing the size
of the influx. Early recognition of a kick and rapid shut-in are the keys to effective well control. By
taking action quickly, the amount of formation fluid that enters the wellbore and the amount of drilling
fluid expelled from the annulus are minimized. As Figure D.1 illustrates, smaller kicks yield lower
initial shut-in casing pressure and lower maximum casing pressures while circulating out the kick.
This translates to lower casing shoe pressures at all points during the circulation and reduces the
chance of formation breakdown and an underground blowout. Remember, the larger the influx, the
higher the casing pressures, so, minimize the size of the influx.
Figure D.1 - Effect of Influx Size on
Casing Pressure
Driller's Method
3000
2500
2000
1500
1000
500
0
0
50
100
150
200
250
300
350
400
450
500
Volume of Mud Pumped - Bbls
2. SHUT-IN PROCEDURE WHILE DRILLING
Drilling crews must be alert while drilling ahead and be on the lookout for indicators that the well is
kicking or that the bit is penetrating abnormal pressure. These items were discussed in detail in
Section C. The well must be shut-in immediately when there is a positive indicator of a kick in the
form of an increase in pit volume or flow rate. If a secondary indicator of a kick is recognized, then
the well should be checked for flow before shutting in.
Rev. 12/94
D-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Chevron's recommended "Three S" Shut-in Procedure While Drilling is given below:
Shut-In Procedure While Drilling
(1)
(2)
(3)
SPACE OUT
SHUT DOWN
SHUT-IN
Pull the kelly out of the hole. Position the kelly so that there are
no tool joints in the preventer stack.
Stop the mud pumps.
Close the annular preventer or uppermost pipe ram
preventer. Confirm that the well is shut-in and flow has stopped.
The person most likely to shut-in the well is the Driller. The Chevron Drilling Representative must
make sure that the Driller is trained and will be able to take the initiative to perform this important
function on his own without prompting or assistance. After the well is securely shut-in, the Driller
should notify the Chevron Drilling Representative and the Contract Toolpusher. At this time, all
members of the drilling crew should be at their predetermined stations awaiting further instructions.
Chevron recommends a “hard shut-in” procedure. This means that the choke line valves on the
drilling spool are in the closed position while drilling and remain closed until after the preventer is
sealed and the well is shut-in. In the “soft shut-in” procedure, the choke line valves are opened to
allow the well to flow through the surface choke. After the preventers are sealed, the choke is then
closed to stop the flow. The soft shut-in procedure gives the well additional time to flow before shut-
in. Therefore, it is not recommended because it doesn't minimize the size of the influx.
3. POST SHUT-IN PROCEDURES WHILE DRILLING
After the well has been shut-in, the Drilling Representative has several items to read and record.
These include:
(1) SICP
(2) SIDP
(3) PIT GAIN
Read and record the shut-in casing pressure. Valves on the drilling spool and
choke manifold will need to be lined-up so that wellbore pressure is transmitted to
the closed drilling choke. The shut-in casing pressure should be read from a gauge
installed upstream of the closed choke.
Read and record the shut-in drillpipe pressure. If no float is in the drillstring, this
pressure can be read directly from a pressure tap on the standpipe manifold.
However, since it is recommended practice, most drillstrings should have floats
installed which will require “bumping” in order to determine the SIDP. The float
bumping procedure is given later in this section.
Read and record the pit gain. The amount of influx is important for accurate
calculation of the maximum casing pressure. Pit level charts or other volume
totalizers can be examined to determine the pit gain.
Rev. 12/94
D-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
(4) TIME
Make a note of the time the kick occurred. Also, keep an accurate log of the entire
kill operation as it progresses.
(5) CLOSING PRESSURES If the Drilling Representative decides to work the pipe during the kill
circulation, then the closing pressure on the annular preventer should probably be
reduced to prolong the life of the element. The proper amount of closing pressure
will depend on the size and make of the preventer and the wellbore pressure
underneath. It should be high enough to prevent wellbore fluid from leaking around
the element.
After this information has been gathered, the Drilling Representative should notify his Supervisor to
discuss the appropriate method for killing the well.
4. SHUT-IN PROCEDURE WHILE TRIPPING
Statistics indicate that the majority of kicks occur while tripping. Pulling out of the hole is a critical
operation that demands diligence by the drilling crews and is not the time to be lax about well control!
Hole filling and hole monitoring equipment should be in top condition so that the kicking well can be
detected as early as possible. Preparation for a trip should be the same as the one to penetrate a
known abnormal pressure zone. Be prepared for the well to kick on every trip.
Every time a well is swabbed-in, it takes a mini-kick; formation fluids enter the wellbore from the
negative pressure differential generated by the swabbing effect. The well may not continue to flow
after the pipe is stopped, but formation fluids that have entered the annulus reduce the hydrostatic
pressure. If the well continues to swab-in on successive stands, then the hydrostatic pressure in the
annulus may be sufficiently reduced to allow the well to flow when the pipe is stationary. For this
reason, any time swabbing is indicated during a trip, the drillpipe should be run back to bottom and
the well circulated at least to bottoms-up. Furthermore, any time the well is detected to be flowing
during a trip, it must be shut-in immediately using the following "Three S" Shut-in Procedure:
Shut-In Procedure While Tripping
(1) STAB VALVE Install the fully opened safety valve in the drillstring. Close the safety valve.
(2) SPACE OUT
(3) SHUT-IN
Position the drillstring so that there are no tool joints in the preventer stack.
Close the annular preventer or uppermost pipe ram preventer. Confirm that
the well is shut-in and flow has stopped.
After the well is securely shut-in, the Driller should notify the Chevron Drilling Representative and the
contract Toolpusher while all members of the drilling crew are at their assigned stations awaiting
further instructions.
Rev. 12/94
D-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
NOTE:
It is recommended that this "Three S" Shut In Procedure be followed even when the rig
is equipped with a top drive unit. The temptation would be to screw in the top drive unit instead of
the safety valve hoping that it would be quicker and safer. This can be problematic if it is necessary
to strip and the float leaks. The manual valve on the top drive unit will not necessarily be strippable
and it may not be possible to install the Inside BOP on top of it.
5. POST SHUT-IN PROCEDURES WHILE TRIPPING
Taking a kick while tripping is a severe well control complication. Because there is no steady-state
while tripping, the data that was previously relied upon to kill the well may not be valid. Nevertheless,
after the well is securely shut-in, the Drilling Representative will need to gather as much information
about the wellbore condition as possible. These will include:
(1) SICP
(2) PIT GAIN
(3) TIME
Read and record the shut-in casing pressure. Valves on the drilling spool and
choke manifold will need to be lined-up so that wellbore pressure is transmitted up
to the closed drilling choke. The shut-in casing pressure should be read from a
gauge installed upstream of the closed choke.
Read and record the pit gain. The amount of influx is important for accurate
calculation of the maximum casing pressure. If a trip tank is in use and an accurate
trip log was being maintained, then the pit gain is simply the difference between
the present trip tank volume and the volume after the last fill-up, plus the volume
of metal pulled from the well since the last fill-up. If the hole was being filled out
of the active pits, which is not recommended, then determination of the kick
volume is much more difficult. Pit level charts or other volume totalizers can be
examined in an attempt to determine the pit gain in these instances.
Make a note of the time the kick occurred. Also, keep an accurate log of the entire
kill and/or stripping operation as it progresses.
(4) BIT DEPTH Determine the bit depth from the Driller’s pipe figures. This number is important
for a variety of calculations and determinations discussed later in this section.
NOTE:
It will usually not be necessary to record a value for the shut-in drillpipe pressure. This
is because the mud weight does not usually have to be increased when a kick is taken during a trip
unless the well is going to be killed off-bottom. However, if a shut-in drillpipe pressure is taken, then
allowances must be made for the volume of drillpipe slug remaining in the pipe. If this volume cannot
be determined, then an accurate value for shut-in drillpipe cannot be calculated.
After this information has been gathered, the Drilling Representative should consult with a Drilling
Supervisor to determine the proper remedial action to take in controlling the well. This will usually
involve stripping back to bottom, which is covered in Section I.
Rev. 12/94
D-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
6. BUMPING THE DRILLPIPE FLOAT
If a drillpipe float is installed, the pressure gauge on the drillpipe will read near zero. In order to obtain
an accurate value for the shut-in drillpipe pressure, the float will have to be bumped open by slowly
pumping down the drillpipe. The correct procedure for bumping the float is given, on the following
page.
Float Bumping Procedure
(1)
(2)
(3)
(4)
(5)
(6)
Make sure the well is shut-in and that the shut-in casing pressure is recorded.
Slowly pump down the drillpipe while monitoring both the casing and drillpipe
pressure.
The drillpipe pressure will increase as pumping is begun. Watch carefully for a “lull”
in the drillpipe pressure (a hesitation in the rate of increase) which will occur as the
float is pumped off of its seat. Record the drillpipe pressure when the lull is first
detected.
To verify that the float has been pumped open, continue pumping down the
drillpipe very slowly until an increase in the casing pressure is observed. This
should occur very soon after the lull was observed on the drillpipe gauge.
Shut down the pumps as soon as the casing pressure starts to increase and record
the shut-in drillpipe pressure as the previously recorded pressure at the time of the
lull in step 3 above (not the final drillpipe pressure after the pumps are stopped).
Check the shut-in casing pressure again. Any excess pressure may be bled-off in
small increments until equal readings are observed after two consecutive bleed-
offs. Do not allow the casing pressure to drop below its original shut-in value while
bleeding back.
The float bumping procedure as described above can be difficult if the rig has big duplex pumps which
are compounded. It may be necessary to clutch the pumps in short bursts to slowly build up pressure
on the drillpipe. A drillpipe “lull” may never occur before the casing pressure starts to increase when
using this procedure. To determine the shut-in drillpipe pressure in these instances, subtract the
increase in shut-in casing pressure from the final value of shut-in drillpipe pressure after the pumps
have been stopped. Use this value as the official shut-in drillpipe pressure.
7. UNDERSTANDING SICP AND SIDP
Shut-in surface pressures depend mostly on the amount of underbalance and the amount and density
of the influx of formation fluids. Shut-in drillpipe and casing pressure indicate the difference between
formation pressure and the hydrostatic pressures in the drillpipe and annulus respectively. Both shut-
in pressures are affected equally by the amount of underbalance. More specifically, the greater the
difference between formation pressure and hydrostatic pressure, the larger the shut-in pressures.
Rev. 12/94
D-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Higher shut-in casing pressures can cause formation breakdown in this instance. In order to decrease
the likelihood of excessive downhole pressures and the resultant breakdown at the casing seat, early
detection and quick closure of the preventers are essential.
Normally, the shut-in casing pressure is greater than the shut-in drillpipe pressure because of the low
density formation fluids in the annulus. In this case, the total hydrostatic pressure in the annulus is
less than that in the drillpipe, so it requires a higher shut-in casing pressure to balance formation
pressure. The difference in hydrostatic pressures between the annulus and drillpipe depends not only
on volume (height) of the influx, but also on its density. The shut-in casing pressure for a gas kick
is much higher than for a saltwater and/or oil kick of equal volume.
Often, the shut-in drillpipe and casing pressures will read the same when the well is closed in with
the bit off bottom and all or most of the formation fluids are below the bit. In this case, the reduction
of hydrostatic pressure caused by the influx of low density formation fluids affects the drillpipe and
casing pressures equally. A similar condition will occur with a hole in the drillpipe and with all of the
influx trapped below the hole.
When considering the effects of underbalance and the size of the influx on downhole pressure, the
position of the influx fluid in relation to the depth of interest must be considered. If the depth of interest
is above the kick, the full amount of the shut-in casing pressure must be added to the mud hydrostatic
pressure to that depth. If, however, the depth of interest is within the interval of kick or below, then
the total effect of surface pressure on the depth of interest is less. This also applies during the time
that the kick fluid is circulated out of the hole. For example, the shoe pressure at a shallow casing
seat will normally increase while circulating out a gas kick until the gas reaches the casing seat. At
this point, the shoe pressure will drop until the gas is in the casing. From this point, until all the gas
is removed from the annulus, the shoe pressure at the casing seat will be constant. The location of
the kick fluid in the annulus with respect to the depth of interest will determine the effect of excessive
casing pressure on the shoe pressure.
7. DIFFERENTIAL PRESSURE STICKING
The drill string can become stuck immediately after the well is shut-in on a kick. Sometimes this can
be attributed to collapse of the filter cake and/or wellbore caused by the presence of formation fluids.
More often, it is due to differential pressure sticking of the drillpipe in lower pressured formations
uphole.
Large shut-in casing pressures cause an increase in the wellbore pressures above the influx. This
serves to increase the pressure differential across permeable zones, which leads to differential
sticking. In an attempt to avoid differential sticking during the kill operation, many Superintendents
will instruct their Drilling Representatives to “work the pipe” during the kill. Others rely on killing the
well first and then getting unstuck. While working the pipe has probably kept many wells from
becoming stuck, it can cause hazards. Each well control situation must be examined individually in
order to make a sound decision.
Rev. 12/94
D-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
SECTION E: WELL KILLING PROCEDURES
1. CONSTANT BOTTOMHOLE PRESSURE
Chevron recommends two well killing methods: the Driller’s Method and the Engineer’s (or Wait and
Weight) Method. Both of these methods, discussed later in this section, are designed to remove the
influx from the wellbore while maintaining a constant bottomhole pressure equal to or slightly greater
than the formation pressure. These procedures prevent additional influx from entering the well while
the kick is being circulated out.
Constant bottomhole pressure is maintained by pumping at a constant rate and using the drillpipe
and casing pressure gauges to monitor the bottomhole pressure. The surface pressures on both
gauges are adjusted by manipulation of the drilling choke orifice size.
The constant bottomhole pressure method offers several advantages. It allows the person controlling
the kick to observe or calculate pressures throughout the system. Also, it provides the minimum
pressure needed to balance the reservoir pressure, which helps prevent a second fluid influx and
holds surface pressures low enough to prevent formation breakdown and lost circulation.
Except for Volumetric Control, all methods discussed in this guide require circulation to remove the
influx and kill the well. In each case, efforts are made to maintain a constant bottomhole pressure
by adjusting the combination of surface and hydrostatic pressures. As discussed in Section B.1, when
circulating through a well, bottomhole pressure is increased due to annular friction. As the value of
ECD is very difficult to calculate and varies greatly from one situation to another, the effect of ECD
is not taken into account in any of the methods. However, it is important to realize that annular friction
does increase BHP throughout the circulation. Thus, holding more backpressure than required is
not necessary to prevent taking an additional influx, and could result in formation breakdown or lost
circulation.
Figure E.1 - Simple U-Tube Analogy
2. THE U-TUBE PRINCIPLE
A thorough understanding of the relation-
ship between bottomhole pressure, cas-
ing pressure, and drillpipe pressure is
necessary to effectively use the well con-
trol procedures discussed in this volume.
Perhaps the best way to illustrate this
relationship is through the concept of a U-
Tube.
Figure E.1 illustrates the cross section of
two vertical tubes of the same size con-
nected at the base by a horizontal tube.
When a fluid of uniform density is added
to the system, the levels will equalize in
columns A and B. This assembly is often
referred to as a U-Tube because its shape
Column A
Bottomhole Pressure
Column B
Rev 12/94
E-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
resembles the letter U. The U-Tube is a convenient way to depict conditions in the wellbore with
drillpipe in the hole. The inside of the drillpipe can be represented by Column A and the annulus by
Column B. The opening at the base of the U can be thought of as the opening through the nozzles
in the bit. The pressure at the bottom of Column A is equal to the pressure at the bottom of Column
B, which can be considered as the bottomhole pressure.
Basic Well Control Equations (Static Conditions)
Two equations that were pro-
vided earlier are needed to
understand and explain the
concept of the U-Tube.
These are shown again to
the right:
In U-Tubes where the fluid
levels are static, the bot-
tomhole pressure gener-
Bottomhole Pressure = Hydrostatic Pressure + Surface Pressure
Hydrostatic Pressure = 0.052 x Mud Weight x True Vertical Depth
Basic U-Tube Concept
ated by Column A is equal
to the bottomhole pressure
Hydrostatic Pressure
(Column A)
+ Surface Pressure
generated by Column B.
This relationship is stated
mathematically:
is equal to
Hydrostatic Pressure (Column B) + Surface Pressure (Column B)
is equal to
Bottomhole Pressure
U-Tubes are not very interesting when the same density fluid fills both columns. In these instances,
the hydrostatic pressure and surface pressure of both columns are equal. This is the case when
a bit is run to the bottom of the hole and the drillpipe and annulus are filled with the same weight
drilling mud. The fluid levels remain static at the top of the well, the surface pressure on both the
casing and drillpipe side is zero, and the hydrostatic pressure on the drillpipe side is equal to the
hydrostatic pressure on the casing side.
However, U-tubes are more interesting when fluids of different densities occupy both columns. In
these instances, both the hydrostatic pressure and surface pressure of both columns are likely to
be different. An example of this occurs when a kick is taken with the bit on bottom. The well kicked
because the bottomhole pressure was greater than the hydrostatic pressure generated by the mud
in the well. When the well is shut-in, the well stops flowing, and the amount of pressure
underbalance is reflected as a surface pressure on the drillpipe gauge. The fluid in the annulus
is no longer composed of drilling mud alone; it also includes lighter weight formation fluid which
reduces the total hydrostatic pressure in the annulus. Thus, the annulus side is more
underbalanced than the drillpipe side and the resultant shut-in casing pressure is higher than the
shut-in drillpipe pressure. This effect is shown in Figure E.2 on the following page.
Rev. 12/94
E-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Figure E.2
5740
540
680
Drill Pipe Mud
10 ppg
540
Annulas Mud
10 ppg
5740
680
Gas Kick
In Figure E.2, a 10,000 ft. well with 10 ppg mud has penetrated an overpressured sand with a reservoir
pressure of 5,740 psi and taken a 30 bbl kick. Since the hydrostatic head of the 10 ppg mud is only
5,200 psi (10,000' x 10 ppg x 0.052 = 5,200 psi), the drillpipe is underbalanced by 540 psi, which is
reflected on the shut-in drillpipe gauge and at the top of Column A of the U-Tube. The hydrostatic
pressure on the annulus side is equal to the sum of the hydrostatic pressure of the mud in the annulus
and the hydrostatic pressure of the gas in the annulus. Since 30 barrels of annular mud has been
displaced by the lighter weight gas, there is less total hydrostatic pressure in the annulus than in the
drillpipe. The hydrostatic pressure generated by 30 barrels of mud is 140 psi more than the
hydrostatic pressure generated by 30 barrels of gas in this wellbore configuration. Therefore, the
shut-in casing pressure and the pressure at the top of Column B is 140 psi higher than the value
indicated on the drillpipe gauge.
3. THE DRILLER’S METHOD
The Driller’s Method of well control requires two separate circulations of the well. The first circulation
is required to remove the influx from the annulus using the mud density in the hole at the time of the
kick. After the pumps are started, the drillpipe pressure is held constant by choke manipulation to
maintain bottomhole pressure equal to, or slightly greater than, formation pressure. If the kick
contains gas, it will expand in the annulus under controlled conditions as it nears the surface.
Therefore, an increase in casing pressure and pit volume should be expected. Drillpipe pressure and
pump rate must be held constant. At any time during or immediately after this first circulation, the
well can be shut-in and the drillpipe pressure will read the same as it did originally.
Rev 12/94
E-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
After the kick fluid has cleared the choke, the well can be shut-in. At this time, shut-in drillpipe and
casing pressures will be the same, assuming that all of the influx has been removed and mud
hydrostatic is the same inside the drillpipe and the annulus. The original shut-in drillpipe pressure
is converted to an equivalent density at the bit, and the mud density is increased accordingly.
During the second circulation, bottomhole pressure is held constant by first maintaining casing
pressure equal to the shut-in value while filling the drillpipe with the kill mud. When the drillpipe is
filled, as determined by the number of strokes pumped, the drillpipe pressure is recorded and control
shifts to maintaining a constant drillpipe pressure while the annulus is filled with heavy mud. When
the kill mud reaches the surface, the pressure on the choke should be minimal. The pumps can be
stopped while holding casing pressure constant and the well is checked for flow.
Any time a well under pressure is circulated, the start-up and shut-down procedures are critical and
should be done with exceptional care. Whenever the pump speed is increased or decreased
(including start-up and shut-down), the casing pressure must be held constant at the value it had
immediately before the pump speed change was initiated. This ensures that bottomhole pressure
remains constant. This procedure is valid because casing pressure should be the same whether the
well is closed-in or being pumped. However, the drillpipe pressure must vary depending upon the
circulating pressure loss in the system, which is a function of the pump speed. The casing pressure
cannot be held constant for very long though due to the changing height of the influx caused by the
irregular annulus and gas expansion.
4. THE ENGINEER’S METHOD
Also called the Wait and Weight Method, the Engineer’s Method of well control requires only one
complete circulation. The kill mud is circulated at the same time the influx is removed from the
annulus. After the well has been shut-in and the pressures and pit volume increase have been
recorded, the mud density in the pits is increased and a drillpipe pressure schedule is created. The
schedule must be prepared in order that drillpipe pressure can be properly adjusted downward as kill
mud fills the drillpipe. A sample drillpipe schedule with an internal drillpipe volume of 800 strokes
is provided:
Sample Drillpipe Pressure Schedule for the Engineer's Method
Strokes
Drillpipe
Pumped
0
100
200
300
400
500
600
700
800
Pressure
540
520
500
480
460
440
420
400
380
Comment
Well is shut-in.
100 strokes of kill mud pumped.
Kill mud half-way to the bit.
600 strokes of kill mud pumped.
Kill mud reaches the bit.
Rev. 12/94
E-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Once the kill mud reaches the bit, the drillpipe pressure should be held constant until it reaches the
surface. Bottomhole pressure will be equal to, or slightly greater than formation pressure throughout
the procedure as long as pump rate is maintained at the same rate.
If the kick contains gas, it will expand in the annulus under controlled conditions as it nears the surface.
Therefore, an increase in casing pressure and pit volume should be expected. However, the drillpipe
pressure and pump rate must be held constant.
As with the Driller’s Method, any time a well under pressure is circulated, the start-up and shut-down
procedures are critical and should be done with exceptional care. The following advice on this topic
warrants repeating. Whenever the pump speed is increased or decreased (including start-up and
shut-down), the casing pressure must be held constant at the value it had immediately before the
pump speed changed in order to keep bottomhole pressure constant. This procedure is valid because
casing pressure will virtually be the same whether the well is closed-in or being pumped. However,
the drillpipe pressure will vary depending upon the circulating pressure loss in the system which is
a function of the pump speed. The casing pressure cannot be held constant for very long due to the
changing height of the influx caused by the irregular annulus and gas expansion.
5. COMPARISON OF THE METHODS
Both the Driller’s and Engineer’s Methods have advantages and disadvantages, depending on the
general conditions of the area of operation or the specific conditions in a well. The correct kill method
is determined through discussions between the Drilling Representative on location and the Drilling
Supervisor.
Figures E.3 and E.4 illustrate a gas kick being circulated to the surface using both the Driller’s and
the Engineer’s Method. Observing both figures, note that when the gas bubble reaches the casing
shoe, the Driller’s method produces a surface casing pressure which is higher than the initial casing
pressure, whereas the Engineer’s Method is less. In the Driller’s Method, the hydrostatic pressure
in the annulus is reduced as the gas bubble expands while being circulated out of the well. Since the
bottomhole pressure is held constant, the surface casing pressure must increase. The hydrostatic
pressure above the shoe is the same as it was when the well was initially shut-in, as long as the bubble
is below the shoe. The pressure at the shoe will increase an amount equal to the increase in the
surface casing pressure plus any circulating friction generated in the annulus above the shoe. This
increase in pressure could be sufficient to cause a formation breakdown at the shoe. Consequently,
the maximum pressure at the casing shoe occurs when the top of the bubble reaches the shoe if the
Driller’s Method is used.
Conversely, when the Engineer’s Method is used, the maximum pressure at the shoe will generally
occur when the kill mud reaches the bit. Exceptions to this take place when the kick volume enters
the well filling it above the shoe, or when a small kick volume does not increase the casing pressure
as it rises into a larger annular area at the top of the collars by the time kill mud reaches the bit, or
at any time the top of the bubble reaches the shoe before the kill mud reaches the bit. The introduction
of kill mud into the annulus through the bit increases the hydrostatic pressure. In order to maintain
constant bottomhole pressure, the surface pressure must be reduced and the pressure at the shoe
is reduced.
Rev 12/94
E-5
Figure E.3 - Removing Gas Influx with the Driller's Method
Driller's Method -
First Circulation
500
Well
Shut-In
700
1500
Break
Circulation
700
1500
Kill Mud
at the Bit
850
1500
1000
Gas Bubble
at Shoe
1500
1800
Gas Bubble
at Surface
500
Influx
Removed
500
Figure E.4 - Removing Gas Influx with the Engineer's Method
Engineer's Method
500
Well
Shut-In
700
1500
700
Break
Circulation
1000
Kill Mud
at the Bit
850
1000
950
Gas Bubble
at Shoe
1000
1000
Gas Bubble
at Surface
0
Influx
Removed
0
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
In both methods, once the top of the bubble passes the shoe, the shoe pressure decreases until the
bottom of the bubble rises above the shoe. Once the bottom portion of the bubble rises above the
shoe, the shoe pressure remains constant with the Driller's Method. In the Engineer's Method, as long
as BHP is kept constant, shoe pressure continues to decline until kill mud fills the annulus below the
shoe. Therefore, the Engineer's Method will always be less than or equal to the shoe pressure with
the Driller's Method. A summary of the advantages and disadvantages of both methods is provided
in Table E.1 below.
Table E.1 - Kill Method Comparison
Method
Driller’s
Advantages
1. Simplicity, few calculations
2. Can be used until barite arrives
3. Circulate quickly, reduce sticking
and gas migration.
Disadvantages
1. Requires two circulations
2. Higher surface pressures
3. Higher casing shoe pressures
Engineer’s
1. One circulation required
2. Lower surface casing pressures
3. Lower casing shoe pressures
1.
2.
3.
4.
More complex calculations
Waiting may stick pipe
Waiting allows gas to migrate
Mud mixing capabilities
6. OTHER WELL CONTROL METHODS
The Volumetric Control Method: This method is used when the pumps are inoperative or when
the drillpipe is either out of the hole, plugged, or has a hole in it. This is not a kill method, but simply
a method of controlling bottomhole and surface casing pressures as the gas migrates up the hole.
The gas is allowed to expand as it migrates up the hole. A relatively constant bottomhole pressure
is maintained by bleeding off mud with an equivalent hydrostatic head equal to the rise in pressure
caused by the migrating gas. The basis of the method equates pit volume change with annulus
pressure. When possible, the drillpipe should be stripped back to bottom and the well killed using
the Driller’s Method. This procedure will be discussed later in detail later.
The Low Choke Pressure Method: This method is used if pressures threaten to become excessive.
Choke pressure must be reduced sufficiently to prevent casing burst or formation breakdown while
circulating out. In kick situations requiring weight increases, the mud weight should be increased as
soon as practical. Kicks occurring while drilling tight formations or after trips where tight formations
have been drilled may be circulated out using this method without increasing the mud weight.
It is important to realize that the formation will continue to flow until the combined effect of the new
kill mud, light weight mud, and low choke pressure all balance the formation pressure. Formations
with high permeabilities cannot be effectively killed by this method; the influx won't be controllable.
The corresponding reduction of hydrostatic pressure will prevent the killing of the well and possibly
cause loss of the hole. Numerical analysis of the Darcy equation indicates that this method is
questionable where formation permeabilities are greater than 200 millidarcys. This method should
not be used when there is uncertainty about formation permeability, and therefore is not
generally recommended.
Rev. 12/94
E-8
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
SECTION F: PRERECORDED DATA SHEET
1. PURPOSE OF THE PRERECORDED DATA SHEET
The Prerecorded Data Sheet is a two-sided information page which lists the wellbore capacities and
volumes for a particular well. This is a critical well control document that must be kept as current and
as accurate as possible. The Drilling Representative will need this information to complete the
Engineer’s or Driller’s Method Worksheets if a kick occurs.
The information on the Prerecorded Data Sheet is used to calculate pumping volumes and strokes
and is therefore crucial to the successful completion of most well killing operations. A sheet must
be filled out when a kick is taken so that the information it contains will be readily available. When
the Data Sheet has been filled out ahead of time, the Drilling Representative does not have to spend
his time figuring wellbore capacities and volumes after a kick has occurred when time may be critical.
Also, this gives the Drilling Representative additional time to check the accuracy of the figures.
NOTE: Therefore, it is strongly recommended that the Prerecorded Data Sheet be
filled-out as completely as possible at all times while drilling.
Much of the data on the Prerecorded Data Sheet remains the same from day-to-day, so it’s fairly
simple to keep it up-to-date. Many of the measurements are easily memorized because they are used
so frequently. However, it's advisable to keep important figures written down and on hand for
everyone on the rig to refer to in a critical situation.
2. USING THE PRERECORDED DATA SHEET
The following is a guide for Drilling Representatives on filling in the blanks on a Prerecorded Data
Sheet:
Well Data
The well data section is composed of the well name, field name, and rig name. These items should
be filled out completely.
Hole Data
Size: Record the hole size as the diameter of the bit in the hole.
Hole MD and TVD: These items are recorded after the well has kicked. It should take only a short
while to determine these values from the Driller’s pipe figures and survey data.
Capacity Factor: Record the capacity factor of the hole size listed above in bbls/ft. Use Table P.4
for reference. This is an approximation and does not account for hole washout or actual casing
diameter. Multiply this number by the Measured Depth to determine the hole capacity (bbls).
To determine the open hole capacity for subsea wells, multiply by the measured depth minus the RKB
to mud line length by the open hole capacity factor.
Rev. 12/94
F-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Pump Data
Liners: Record as the pump liner diameter (inches) for duplex or triplex pumps.
Stroke: Record as the pump stroke (inches) for duplex or triplex pumps.
Rod Size: Record as the pump rod diameter (inches) for duplex pumps only.
% Efficiency: Record as the mechanical pump efficiency as determined by top plug displacement
during a cement job or by pumping into the trip tank.
Bbl/stk: Use Table P.5 to determine the theoretical pump displacement and multiply by % Efficiency
above to determine the actual pump output.
Casing Data
Record the outside diameter, inside diameter, measured depth, and true vertical depth of the last full
string of casing in the ground.
Wellhead or Casing Pressure Limitation
Record as the lesser of:
a) 100% of wellhead pressure rating.
b) 100 % of blowout preventer pressure rating.
c) 80% of last casing string burst rating.
Liner Casing Data
Record the outside diameter, inside diameter, measured depth to top and vertical depth to shoe of
any liner casing in the ground.
Drillstring Data
Record the outside diameter (inches) and weight (lb/ft) of all drillpipe, heavyweight drillpipe and drill
collars in the string. This data should be reviewed and updated on every trip in the hole.
Internal Capacities
Record the length of each drillstring component by its associated internal capacity factor (bbl/ft). Use
Tables P.1 through P.3 for reference. Treat bottomhole assembly components (stabilizers, crossover
subs, etc.) as drill collars for capacity calculations. Calculate the total volume (bbls) for each
component section by multiplying the component length by its capacity factor. Since the length of
drillpipe will not be known until after the well kicks, the drillpipe capacity and total internal capacity
will have to be calculated after the kick. Check that the Measured Depth indicated is equal to the sum
of the individual component lengths.
Divide the Total Internal Capacity (bbls) by the pump displacement (bbls/stk) to determine these
capacities in strokes.
Rev 12/94
F-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Annulus Capacities (surface stacks only)
Record the length of each drillstring component and its associated annular capacity factor in the given
hole size. Use Tables P.1 through P.3 for reference. Treat bottomhole assembly components
(stabilizers, crossover subs, etc.) as drill collars for capacity calculations. Calculate the annular
capacity (bbls) opposite each component section by multiplying the component length by the annular
capacity factor. Since the length of drillpipe will not be known until after the well kicks, the annular
capacity opposite the drillpipe and the total annular capacity will have to be calculated after the kick.
Check that the Measured Depth indicated is equal to the sum of the individual component lengths.
Finally, add the Total Internal Capacity to the Total Annular Capacity to determine the System Total
Capacity (not including the active pit volume).
Divide the Total Annulus capacity (bbls) and the System Total capacity by the pump output (bbls/stk)
to determine these capacities in strokes.
Maximum Initial SICP
The maximum casing pressure that will fracture the formation at the shoe upon shut-in can be
determined by subtracting the present mud weight from the shoe test (in lbs/gal) and then multiplying
this figure by the true vertical depth of the shoe and by 0.052. This formula is stated in equation form
below:
MISICP = (Shoe Test, lb/gal EMW - Present Mud Weight, lb/gal) x TVDshoe ,ft x 0.052
3. “KEEP THIS WELL DATA SHEET CURRENT AT ALL TIMES”
The Prerecorded Data Sheet should be kept as current and as accurate as possible so that time won’t
be wasted looking up routine capacity numbers after a kick has been taken. The Data Sheet has been
designed so that nearly all of the Sections can be completed prior to a kick. These Sections include:
Sections Fully Completed
Well Data Section
Pump Data Section
Casing Data Section
Wellhead or Casing Pressure Limitation Section
Liner Casing Data Section
Drillstring Data Section
Maximum Initial SICP Section
However, some of the Sections on the Prerecorded Data Sheet cannot be fully completed until after
the well has kicked. These include:
Sections Partially Completed
Hole Data Section:
Internal Capacities:
Annulus Capacities:
All items should be completed except the Measured Depth and True
Vertical m Depth. These depths are recorded after the kick occurs.
All items should be completed except the Drillpipe Length (ft) and
Volume (bbls). These items are recorded after the kick occurs.
All items should be completed except Drillpipe x Casing or Hole (ft)
and Volume (bbls). These items are recorded after the kick occurs.
Rev. 12/94
F-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
If the Prerecorded Data Sheet is completed as described above, the only blanks remaining on the
sheet will be those whose which require the length of drillpipe in the hole (which is constantly
increasing as you drill deeper). If a kick is taken, the Drilling Representative simply needs to
determine the length of drillpipe in the hole and the remaining capacities (hole, internal, and annulus)
can be easily calculated.
4. SOME COMPLICATING SITUATIONS
Sometimes, complicated wellbore and drillstring configurations combine to make completion of the
Prerecorded Data Sheet unclear. Some of these special situations (with remedies) are described
below.
Drilling Liner: A drilling liner is a complicating situation because the change in casing diameters
at the liner top changes the annular capacity figures. To resolve the situation, you will need to add
additional annular capacity figures to the Prerecorded Data Sheet.
The drillstring component, which is opposite the liner top needs to have two separate annular capacity
figures (one for the liner, a second for the casing). Therefore, include the annular capacity figures
for both the liner and the casing in the Annulus Capacity Section. Make a note in the left hand margin
to indicate which capacity figure is for the liner and which is for the casing. Remember to do this only
for the drillstring component that is opposite the liner top.
If drillpipe is opposite the liner top while drilling, then the length of Drillpipe x Casing can be
determined and recorded on the Data Sheet. On the other hand, if the heavyweight drillpipe is
opposite the liner top while drilling, then the length of heavyweight inside the liner and casing will be
constantly changing when drilling. In these instances, it will not be possible to record the correct
lengths until after a kick has been taken and the measured depth determined.
Tapered Drillstring: A tapered drillstring changes both the internal and the external capacity figures
at the point of crossover. Include the capacity figures (bbl/stk) for both sizes of drillpipe on the
Prerecorded Data Sheet. Compute the internal and annular capacities opposite the smaller diameter
drillpipe in the same manner as the Drill Collars.
5. SUBSEA CONSIDERATIONS
Use of a subsea preventer stack creates several situations that are not addressed in the previous
discussions. The opposite side of the Prerecorded Data Sheet is designed for subsea use only and
replaces or augments the prerecorded information on the front.
Internal Capacity: The internal capacity of the drillstring is transferred from the front side of the
sheet.
Annular Capacity: The annular capacity calculations must be modified when a subsea blowout
preventer is used. The Annular Capacity Section on the front side of the sheet should not be used.
Instead, the following subsea items of interest must be considered.
Rev 12/94
F-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
1. Choke line length is recorded as the total length of the actual piping from the subsea
stack to the choke manifold. Allowances may be made for loops in the moon pool and
other turns when determining this length. Record this length in the Annulus Capacity
Section.
2. D.P. x Casing or Hole Length is determined by the subtracting the D.C. x Hole Length
and the RKB to Mud Line Length from the Measured Depth of the hole. This will provide
the length of drillpipe from the bottomhole assembly to the subsea stack.
DP x Casing or Hole Length = Measured Depth - (D.C. x Hole Length) - (RKB to Mud
Line Length)
3. D.C. x Hole Length is simply the length of the bottomhole assembly.
NOTE: Addition of these three lengths may yield a value which is greater than the Measured Depth
of the hole. This is normal and should be expected. The difference should be equal to the difference
between the RKB to Mud Line Length and the Choke Line Length.
Choke Line Friction:
This section is provided to record the most recent choke line friction
measurements. Refer to Section M on Subsea Well Control Procedures later in this volume for more
information.
Riser Capacity: Use this section to record the riser capacity.
6. EXAMPLE PRERECORDED DATA SHEET
The following pages contain two prerecorded data sheets that have been completed for a surface and
a subsea well. The raw information used to complete the data sheets is provided above each one.
On bottom drilling depths are also provided.
Rev. 12/94
F-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
SURFACE WELL
Well Depth - 9000'MD/TVD
2-duplex pumps - 16-in. stroke, 3-in. rod, 96% vol. eff.,
6-1/4-in. liner.
Casing size - 10-3/4 in., set at 4000 ft.
Drill collar size - 7 in. OD x 2-13/16 in. ID x 450 ft long.
Mud weight - 10 lb/gal
Active surface mud system - 450 bbls before kick; 200 bbl at
start of kill operation.
Hole size - 9-7/8 in.
Casing pressure limitation - 2864 psi (80% burst)
Remaining collapse resistance of drill pipe- 4109 psi
PRERECORDED WELL DATA
KEEP THIS DATA SHEET CURRENT AT ALL TIMES
(use the Tab key to advance to next required input)
Well Name
OCSG 0544 #5
Field
E. Cam. 160
Rig
DIGGER #4
Hole Data:
Size(avg)
9.8750
Hole MD
9,000
ft.
Hole TVD
9,000
ft.
Hole Capacity: no pipe in hole
0.0948
bbls/ft x
9,000
ft. =
852.9
bbl
(from BOP to MD)
*Use
DP
PUMP DATA:
Liners (in.) Stroke(in.)
Rod(in. )
% Eff.
bbl./stk For Kill?
CSG
No. 1
No. 2
CASING (LAST SET) DATA:
* X if used, empty if not
10.7500
by
9.8750
Shoe MD
4,000
Shoe TVD
4,000
(in. OD) (in. Avg ID)
WELLHEAD OR CASING PRESSURE LIMITATION:
(feet)
(feet)
The lessor of: 100% BOP Rating
10,000
psi.
100% Wellhead Rating
80% Casing Burst
5,000
2,864
psi.
psi.
Limitation =
2,864
psi.
LINER CASING DATA:
by
Top @
ft. Shoe @
(in. OD)
DRILL STRING DATA:
(in. Avg ID)
(feet)
(feet)
DRILL COLLARS
Drill Pipe
5.0000
in. (OD)
19.5
lb./ft.
OD(in.) ID(in.)
Drill Pipe
HW Drill Pipe
in. (OD)
in. (OD)
lb./ft.
lb./ft.
7
by
by
2.8125
INTERNAL CAPACITIES:
Drill Pipe 8,550
Drill Pipe
HW Drill Pipe
ft.
ft.
ft.
x
x
x
0.0178
bbl./ft. =
bbl./ft. =
bbl./ft. =
152.1
bbl.
bbl.
bbl.
Drill Collars
450
ft.
x
0.0077
bbl./ft. =
3.5
bbl.
Drill Collars
ft.
x
bbl./ft. =
bbl.
M. Depth(Bit)
9,000
ft.
Total Internal = 155.6
bbl. =
905
Strokes
ANNULUS CAPACITIES:
(Note: Use other side for subsea)
DP x Csg. 4,000
or Hole 4,550
HW DP
DC x Hole 450
DC x Hole
ft. x 0.0704 bbl./ft. =
ft. x 0.0704 bbl./ft. =
ft. x bbl./ft. =
ft. x 0.0471 bbl./ft. =
ft. x bbl./ft. =
281.8
320.5
21.2
bbl.
bbl.
bbl.
bbl.
bbl.
M. Depth(Bit)
9,000
ft.
Total Annulus
623.5
bbl. =
3,626
Strokes
System Volume =
779.1
bbl.
=
4,530
Strokes
(Internal + Annulus)
Active Pit Volume
MAX INITIAL SICP TO FRACTURE FORMATION AT SHOE:
Max. SICP = (Shoe Test - Present Mud Wt.) x 0.052 x Shoe TVD
200
bbl.
(
13.5
lb./gal EMW -
10.0
lb./gal) x 0.052 x
4,000
ft. =
728
psi.
Version 1.3 (8/1/94)
Rev 12/94
F-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
SUBSEA WELL
Well Depth - 8200' MD, 7500' TVD
Water Depth - 1930'
Casing Size - 9-5/8", 53.5#, S-95 (assume 8-1/2" average ID)
Hole Size - 8-1/2"
Shoe Test - 17.3 ppg
Drillpipe Size - 4-1/2", 20.0 #, S-135 XH
Drill Collar Size - 6" x 2-1/4", 360' long
Mud Weight - 12.0 ppg
Pumps - 2 Triplex, 15" stroke, 5" liners, 95% eff.
Choke Line - 3" ID, 2100' long
Subsea Wellhead - 18-3/4", 15M
Riser ID - 18-3/4"
Active Pit Capacity - 680 Bbls
RKB to Mudline - 2010'
Heavy Weight DP Size - 4-1/2", 41.5 #, 990' long
PRERECORDED WELL DATA
KEEP THIS DATA SHEET CURRENT AT ALL TIMES
(use the Tab key to advance to next required input)
Well Name
Boots #1
Field
DeeTee "C"
Rig
TMB #713
Hole Data:
Size(avg)
8.5000
Hole MD
8,200
ft.
Hole TVD
7,500
ft.
Hole Capacity: no pipe in hole
0.0702
bbls/ft x
6,190
ft. =
434.6
bbl
(from BOP to MD)
*Use
DP
PUMP DATA:
Liners (in.) Stroke(in.)
Rod(in. )
% Eff.
bbl./stk For Kill?
CSG
No. 1
No. 2
CASING (LAST SET) DATA:
* X if used, empty if not
9.6250
by
8.5000
Shoe MD
7,200
Shoe TVD
6,500
(in. OD) (in. Avg ID)
WELLHEAD OR CASING PRESSURE LIMITATION:
(feet)
(feet)
The lessor of: 100% BOP Rating
10,000
psi.
100% Wellhead Rating
80% Casing Burst
10,000
7,528
psi.
psi.
Limitation =
7,528
psi.
LINER CASING DATA:
by
Top @
ft. Shoe @
(in. OD)
DRILL STRING DATA:
(in. Avg ID)
(feet)
(feet)
DRILL COLLARS
Drill Pipe
4.5000
in. (OD)
20
lb./ft.
OD(in.) ID(in.)
Drill Pipe
HW Drill Pipe 4.5000
in. (OD)
in. (OD)
41.5
lb./ft.
lb./ft.
6
by
by
2.2500
INTERNAL CAPACITIES:
Drill Pipe 6,850
Drill Pipe
HW Drill Pipe 990
ft.
ft.
ft.
x
x
x
0.0130
0.0074
bbl./ft. =
bbl./ft. =
bbl./ft. =
89.1
7.3
bbl.
bbl.
bbl.
Drill Collars
360
ft.
x
0.0049
bbl./ft. =
1.8
bbl.
Drill Collars
ft.
x
bbl./ft. =
bbl.
M. Depth(Bit)
8,200
ft.
Total Internal =
98.2
bbl. =
1,135
Strokes
ANNULUS CAPACITIES:
(Note: Use other side
for subsea)
DP x Csg. 6,850
or Hole
HW DP 990
DC x Hole 360
DC x Hole
ft. x 0.0505
ft. x 0.0505
ft. x 0.0505
ft. x 0.0352
ft. x
bbl./ft. =
bbl./ft. =
bbl./ft. =
bbl./ft. =
bbl./ft. =
346.0
50.0
12.7
bbl.
bbl.
bbl.
bbl.
bbl.
M. Depth(Bit)
8,200
ft.
Total Annulus
408.7
bbl. =
4,722
Strokes
System Volume =
506.9
bbl.
=
5,857
Strokes
(Internal + Annulus)
Active Pit Volume
MAX INITIAL SICP TO FRACTURE FORMATION AT SHOE:
Max. SICP = (Shoe Test - Present Mud Wt.) x 0.052 x Shoe TVD
200
bbl.
(
17.3
lb./gal EMW -
12.0
lb./gal) x 0.052 x
6,500
ft. =
1,791
psi.
Version 1.3 (8/1/94)
Rev. 12/94
F-7
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
PRERECORDED WELL DATA (page 2)
(SUBSEA USE ONLY)
INTERNAL CAPACITIES:
(from other side)
DP
Csg
Total Internal Capacity
98.2
bbl. =
1,135
strokes
choke
kill line
ANNULUS CAPACITIES:
(replaces other side)
Choke Line
2,100
ft.
x
0.0087
bbl./ft. =
18.3
bbl.
RKB to ML
2,010
ft.
DP x Csg.
or Hole
4,840
ft.
ft.
x
x
0.0505
0.0505
bbl./ft.
bbl./ft.
=
=
244.5
bbl.
bbl.
annul
HWDP x Hole
DC x Hole
990
360
ft.
ft.
x
x
0.0505
0.0352
bbl./ft.
bbl./ft.
=
=
50.0
12.7
bbl.
bbl.
DC x Hole
ft.
x
bbl./ft.
=
bbl.
connec
annul
M. Depth(Bit)
8,200
ft.
blind/sh
Total Annulus =
325.4
bbl. =
3,760
strokes
pipe
System Volume =
423.6
bbl. =
4,895
strokes
pipe
pipe
connec
mud
(Internal + Annulus)
RISER CAPACITY:
(with no pipe in the hole)
Riser ID
Capacity Fact.
Length
Capacity
18.7500
inches
0.3417
bbl./ft. x
2,010
ft.
=
686.7 bbls.
inches
bbl./ft. x
Total Riser = 686.7
bbl. =
ft.
=
7,934
strokes
bbls.
Notes:
1. Use slow pump rate through riser for calculations on Engineers Method worksheet
2. All barite requirements and system volume calculations exclude riser capacity.
3. If monitoring static Kill Line pressure while adjusting pump rate, ignore Choke
Line Friction.
CHOKE LINE FRICTION:
Choke Line Change in
SPM
BPM
Psys(Riser)Psys(Choke) Friction Choke Friction
Rev 12/94
F-8
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
SECTION G: DRILLER'S METHOD
1. DESCRIPTION OF THE METHOD
The Driller's Method of well control is a well killing method that requires two complete circulations.
During the first circulation, mud is pumped to displace the influx from the well; in the second
circulation weighted kill mud is pumped around to kill the well. While circulating, the bottomhole
pressure is maintained equal to or slightly greater than the formation pressure. The following
discussion describes the Driller's Method in detail from kick to kill.
Step 1 - The Kick Is Detected - Shut The Well In.
As always, it is extremely important to shut-in the well as quickly as possible in order to minimize
the size of the influx. The best way to achieve this is by using the "Three S" Shut-in Procedure
While Drilling or the "Three S" Shut-in Procedure While Tripping.
Shut-In Procedure While Drilling
(1) SPACE OUT
(2) SHUT DOWN
(3) SHUT-IN
(1) STAB VALVE
(2) SPACE OUT
(3) SHUT-IN
Pull the kelly out of the hole. Position the kelly so that the tool joints
are clear of the preventers.
Stop the mud pumps.
Close the annular preventer or uppermost pipe ram preventer.
Confirm that the well is shut-in and flow has stopped.
Shut-In Procedure While Tripping
Install the fully opened safety valve in the drillstring. Close the
safety valve.
Position the drillstring so that the tool joints are clear of the
preventers.
Close the annular preventer or uppermost pipe ram preventer.
Confirm that the well is shut-in and flow has stopped.
It should be emphasized that in nearly all well kicks, the Driller will be responsible for closing
the preventers and shutting the well in. The Driller must have the experience and the initiative
to do this by himself if he is working alone. It is the responsibility of the Chevron Drilling
Representative to make sure that the Driller knows the proper shut-in procedure. The Driller will
have plenty of time after the well is shut-in to retrieve crews from the mud pits and notify the
Toolpusher. The Driller must not delay when shutting the well in.
Rev 12/94
G-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 2a - Allow The Well To Stabilize, Record Pressures And Volume Gained
After the well is shut-in, it may take a few minutes for the shut-in pressures to stabilize. If the
pipe is reciprocated through the annular preventer during the kill, it may be advisable to reduce
the annular closing pressure to lessen element wear. The crew should ensure that the bag does
not leak at the reduced pressure!
If the choke manifold is lined-up properly, it should be possible to open the choke line valve at
the preventer stack and read the shut-in casing pressure at the choke manifold. If no drillpipe
float is installed, read and record the shut-in drillpipe pressure as well. Finally, examine the pit
volume charts to determine the volume gained during the kick and verify this number with the
Derrickman.
Step 2b - Bumping The Drillpipe Float
If a drillpipe float is installed, the pressure gauge on the drillpipe will probably read near zero.
In order to get an accurate value for the shut-in drillpipe pressure, the float will have to be
"bumped" open by slowly pumping down the drillpipe. The correct procedure for bumping the
float is given below.
Float Bumping Procedure
(1)
(2)
(3)
(4)
(5)
(6)
Make sure the well is shut-in and that the shut-in casing pressure is recorded.
Slowly pump down the drillpipe while monitoring both the casing and drillpipe
pressure.
The drillpipe pressure will increase as pumping is begun. Watch carefully for a "lull"
in the drillpipe pressure (a hesitation in the rate of increase) which will occur as the
float is pumped off its seat. Record the drillpipe pressure when the lull is first seen.
To verify that the float has been pumped open, continue pumping down the drillpipe
very slowly until an increase in the casing pressure is observed. This should occur
very soon after the lull was recorded on the drillpipe gauge.
Shut down the pump as soon as you see the casing pressure start to increase
and record the shut-in drillpipe pressure as the pressure at which the lull was first
seen in Step 3 above (not the final drillpipe pressure after the pumps are stopped).
Check the shut-in casing pressure again. Any excess pressure may be bled-off in
small increments until equal readings of casing pressure are observed after two
consecutive bleed-offs.
The float bumping procedure, as described above, can be difficult at times if the rig has big
duplex pumps which are compounded. Clutch the pumps in short bursts to slowly build up
pressure on the drillpipe. It is most likely that a drillpipe "lull" won't occur before the casing
pressure starts to increase. To determine the shut-in drillpipe pressure in these instances,
subtract the increase in shut-in casing pressure from the final value of shut-in drillpipe pressure
after the pumps have been stopped. Use this value as the official shut-in drillpipe pressure.
Rev. 12/94
G-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
If excess pressure is trapped on the
drillpipe when bumping the float ...
Shut-in
Shut-in drillpipe
Increase in shut-in
Drillpipe
Pressure
= pressure after
bumping float
-
casing pressure while
bumping float.
Step 3 - Perform The Kick Control Calculations
Calculations should be performed using the Driller's Method Worksheet before the influx is
displaced from the well on the first circulation. Several critical items will be determined
including:
•
•
•
•
Bottomhole reservoir pressure.
Mud weight necessary to balance the kick.
Maximum surface casing pressure during the first circulation.
Maximum excess mud volume gained during the first circulation.
An example problem illustrating the use of the Driller's Method Worksheet is provided later in
this Section.
One thing that must be kept in mind while performing calculations is that the formation fluids
in the annulus, especially gas, may migrate up the hole and cause an increase in the shut-in
casing pressure. If the shut-in casing pressure starts increasing substantially ( i.e., to the point
of risking shoe breakdown or exceeding the wellhead or casing pressure limitation), you may
have to bleed-off some of the excess pressure through the choke. It is better to bleed the
pressure off in small increments rather than one large slug. Any excess pressure that appears
on the annulus due to the migrating gas bubble may be bled-off in small increments until equal
readings are observed after two consecutive bleed-offs.
There is more likelihood of pipe sticking if formation fluids are kept longer in the annulus and
it's important to proceed as quickly as possible.
Step 4 - Establish Circulation
After the kick control calculations have been performed, use the information recorded on the
Driller's Method Worksheet to circulate the influx from the well. Before breaking circulation, be
sure to check the following items.
1.
2.
Be sure that every member of the crew knows exactly what his duties are before the
kill operation begins. (See Section O in this manual for more details.)
Eliminate all sources of ignition in the immediate vicinity of the rig and vent lines.
See that the vent lines on the mud-gas separator and mud degasser are secured
properly and, if possible, are downwind from the rig.
Rev 12/94
G-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
3.
4.
Make sure your circulating system (including manifolds and pits) are lined-up
correctly.
Zero the stroke counter and make a note of the time.
When establishing circulation in a well closed in under pressure, back pressure on the well is
very difficult to control. This procedure is critical since additional influx will result if too little back
pressure is held, or the formation can breakdown if too much back pressure is held.
The procedure requires simultaneous manipulation of the choke and the pump speed. While
the pumps are being brought up to speed, the choke is opened in such a way that casing pressure
is maintained constant at its shut-in value just prior to beginning pumping. As the pump speed
is increased up to the desired kill rate, drillpipe pressure will increase but casing pressure must
be held constant. Successful manipulation of the choke while establishing circulation in this
manner will maintain constant bottomhole pressure.
A predetermined pump rate must be held constant throughout the killing of the well. If the pump
rate is allowed to vary without adjusting the drillpipe pressure, constant bottomhole pressure will
not be maintained. If the pump rate is increased, additional frictional pressure will be reflected
in the drillpipe pressure. If the choke is adjusted to bring the drillpipe pressure down to the value
predetermined using a constant rate, then the bottom hole pressure is reduced possibly allowing
additional influx. Conversely, if the pump rate is reduced, the reduction in frictional pressure will
be noted and if the choke is adjusted to increase the drillpipe pressure, it may create sufficient
overpressure at the casing shoe to cause a breakdown. Therefore, any change in pump rate
should be made known to the choke operator and the pump must be returned to the original rate.
Step 5 - Circulate Out The Influx Holding Drillpipe Pressure Constant
As soon as the pumps are operating at the desired kill rate, the drillpipe pressure should be
observed and recorded. Hold the observed drillpipe pressure constant for the entire first
circulation by manipulating the choke as the contaminant is circulated from the well. (Note: In
all probability, the observed initial circulating pressure on the drillpipe will be equal to the sum
of the initial shut-in drillpipe pressure and the prerecorded slow pump rate pressure at the same
kill rate.)
As the gas and contaminated mud are circulated to the surface, the gas will begin to expand,
increasing both the casing pressure and pit volume. A pure gas contaminant will increase the
casing pressure to the value shown at "R" on the worksheet, but will be less if the contaminant
includes water and/or oil. This is probably the most critical stage of the killing operation, where
panicking could very easily turn a good job into a disaster.
It can sometimes be difficult to bleed the gas off fast enough to keep the drillpipe pressure within
limits, but excessive pressure could cause formation breakdown. If the gas cannot be released
fast enough from the annulus to prevent an increase in drillpipe pressure, the pumps may have
to be slowed or even stopped until the casing pressure can be bled down. For this reason it is
a good idea to take several slow pump rates, including one at the slowest pump rate possible,
so that the new drillpipe pressure can be determined at the reduced pumping rate. If the pumps
must be stopped while bleeding down the casing pressure, attempt to hold the drillpipe pressure
at or above the original shut-in pressure while bleeding. If the drillpipe pressure drops below this
value, another kick may be taken. The pumps should be returned to the original rate as soon
Rev. 12/94
G-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
as possible. This method is not ideal, but is necessary when the surface facilities cannot safely
handle the high flow rates.
Step 6 - Shut Down The Pumps - Weight Up The Mud Pits
After the contaminant has been circulated out of the well, the pumps can be shut down and the
well shut-in. When shutting down the pumps, the choke should be closed gradually as the pump
speed is reduced. The choke should be closed in a way that holds the casing pressure constant
as the pumps are slowed down. As the pump speed decreases, the drillpipe pressure will
decrease but casing pressure must be held constant at its value just prior to slowing down. This
procedure insures that constant bottomhole pressure is maintained during the shutdown. When
the well is shut-in after the first circulation, the shut-in casing pressure and the shut-in drillpipe
pressure should be equal. A casing pressure higher than the drillpipe pressure indicates that
there is still some contaminant in the annulus or that another kick was taken during the first
circulation. Such a situation will warrant an additional circulation of the well with existing mud
before kill weight fluid is mixed and pumped. (Note: After shutdown, the SICP and the SIDP
should be equal to the initial shut-in drillpipe pressure that was observed when the well was first
shut-in)
If the shut-in casing pressure is equal to the shut-in drillpipe pressure at the completion of the
first circulation, weight-up the mud in the pits. The first step is to reduce the mud volume in the
active pits to make room for weighting material. The mud mixing facilities and pit volumes on
the particular rig will dictate to some extent just how the mud should be handled. The ideal
situation is to maintain a reasonably low-volume active system so that the mud circulated out
of the hole can be weighted up without having to stop circulating. It may be desirable to weight
up enough mud to displace the entire hole before the killing operation is started. Many variables
will enter into this decision and every situation is different. It is important to remember that the
mud weight can be raised while the well is being circulated.
Step 7 - Re-Establish Circulation and Circulate Kill Mud
After the mud has been properly weighted-up , the second circulation should be started. First,
establish the desired pump rate by holding the shut-in casing pressure constant while bringing
the pump up to the kill rate (as described in Step 3). Make sure to hold this pump rate constant
throughout the killing of the well.
As the kill mud goes down the drillpipe, adjust the choke so that the casing pressure remains
constant at the shut-in value it had before the start of the second circulation. Hold the casing
pressure constant until the kill mud reaches the bit (as determined by the drillpipe capacity in
strokes).
When the kill mud reaches the bit, the pressure on the drill pipe should be observed and recorded
on the Driller's Method Worksheet. Adjust the choke to hold this drill pipe pressure constant
throughout the remainder of the kill operation. Continue circulation until the hole is full of kill
mud. The approximate strokes and volume required are indicated on the Prerecorded Well Data
Sheet. The casing pressure should drop to zero as the light weight mud is displaced from the
annulus.
Rev 12/94
G-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 8 - Shut Down And Check For Flow
After the entire hole volume has been displaced with kill mud, the pumps can be shut down and
the well shut-in. When shutting down the pumps, the choke should be closed (holding casing
pressure constant) gradually as the pump speed is reduced. As the pump speed decreases, the
drillpipe pressure will slowly decrease to zero (Note: The casing pressure may already be
reading zero before the pumps are shut down. This is normal and may be expected.) After the
well is shut-in, the casing and drillpipe pressures should be zero. Confirm that the well is dead
by cracking open the choke; the well should not flow. If the well is dead, the BOPs can be opened.
Keep in mind that a small volume of gas may be trapped between the preventer and the choke
line. Exercise caution on the rig floor when opening the preventers.
Step 9 - Circulate And Condition The Mud
After the BOP's are opened, circulate the mud and condition it to the desired properties. Usually
the yield point is too high. Therefore, running or pulling pipe can cause excessive pressure on
the formation or swabbing, and either could lead to another kick.
To prepare for a trip after conditioning the mud, raise the mud weight to provide a suitable "trip
margin," as determined by the DRILPRO Swab/Surge calculations.
2. USING THE DRILLER'S METHOD WORKSHEET
The Driller's Method Worksheet is a step-by-step instruction sheet to help the Drilling Representative
calculate the critical well control parameters that are necessary to successfully kill a well using the
Driller's Method. Use of the Worksheet is demonstrated below with an example problem.
Sample Problem - A well is being drilled, and the following data are known prior to a kick:
2-duplex pumps - 16-in. stroke, 3-in. rod, 96% vol. eff., 6-1/4-in. liner.
Casing size - 10-3/4 in, set at 4000 ft.
Hole size - 9-7/8 in.
Casing pressure limitation - 2864 psi (burst)
Shoe Test: 720 psi with 10 lb/gal mud
Drill pipe size - 5 in., 19.5 lb/ft (20.7 lb/ft w/tool joints).
Remaining collapse resistance of drill pipe - 3885 psi
Drill collar size - 7 in. OD x 2-13/16 in. ID x 450 ft long.
Mud weight - 10 lb/gal.
Active surface mud system - 450 bbls, before kick; 200 bbls at start of kill operation.
Slow Pump Rate Data:
Strokes/min
20
30
PSI
280
590
Rev. 12/94
G-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
While drilling at 9000' TVD, the well kicked and the BOP's were closed. The following data was
observed:
Initial drill pipe pressure = 470 psi.
Initial casing pressure = 600 psi.
Pit volume gain = 15 bbl.
The following pages describe a step-by-step procedure for determining the well control
parameters which are necessary to kill the well in the example problem using the Driller's
Method.
Step 1 - Prerecorded Information
Prior to the kick (and at all times), your Prerecorded Data Sheet should be completely filled-out
except for the measured depth and the length of drillpipe in the hole. Enter these items and
calculate the internal drillstring capacity and the system totals. Transfer the slow pump rate data
from the Prerecorded Data Sheet to line "A" of the Driller's Method Worksheet.
Step 2 - Information To Be Recorded When Well Kicks
Many items of information need to be gathered when a well kicks, including:
Old Mud Weight
Initial Shut-in Drill Pipe Pressure
Initial Shut-in Casing Pressure
Pit Volume Increase
True Vertical Depth Of Hole
Measured Depth Of Hole
This information should be recorded in lines "B" through "F" on the Driller's Method Worksheet.
Step 3 - Determining Pressures For The First Circulation
One of the biggest advantages of the Driller's Method is that it is not necessary to calculate any
circulating drillpipe pressures before the first circulation can begin. However, while circulating,
it is very important to record and maintain a constant drillpipe pressure once it is established.
Space is provided on the Driller's Method Worksheet to record the circulating drillpipe pressure
which is observed after the pumps are operating at a predetermined kill rate. (The kill rate should
be between 2-5 barrels per minute for most cases.) Space is also provided to record the kill rate
(in strokes per minute) before the circulation begins. Remember to keep the kill rate constant
for the entire circulation and to maintain constant drillpipe pressure by making choke
adjustments until the influx is circulated out.
Rev 12/94
G-7
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
NOTE: For added peace of mind during the kill operation, it's possible to make a quick
estimation of what your initial circulating drillpipe pressure should be after
circulation is established. Simply add the prerecorded slow pump rate pressure
at the desired circulating rate to the initial shut-in drill pipe pressure. In this
example 30 SPM is the kill rate, so use the slow pump rate pressure at 30 SPM.
The initial circulating pressure should be approximately 590 + 470 = 1060 psi.
Jot down this value down in the margin for comparison purposes when the
circulation begins. However, the actual value that is observed on the drillpipe
pressure gauge when circulation is established is the value that should be held
constant for the entire circulation (not your estimated value).
Step 4 - Determining Mud Weight To Balance The Kick
Using the equation below, calculate the increase in mud weight necessary to balance the kick.
Initial Shut-in Drillpipe Pressure
Increase in Mud Weight = -------------------------------------------------------
0.052 X True Vertical Depth
470
=
=
--------------------------- = 1.0043
0.052 X 9000
1.0 lb/gal
Rounding-Up Rule: The increase in mud weight should be calculated to the hundredths place.
If the number in the hundredths place is greater than zero, then round the number in the tenths
place up one full tenth. In this example, the number in the hundredths place is zero, so the
number in the tenths place is not rounded-off.
Record a 1.0 lb/gal increase on line "G" of the Driller's Method Worksheet. Adding the mud
weight increase "G" to the old mud weight "B" yields the new mud weight required to balance
the kick.
New Mud Weight To Balance The Kick = Old Mud Weight + Increase In Mud Weight
= 10.0 + 1.0
= 11.0 lb/gal
Enter the new mud weight in part "H" of the worksheet.
Rev. 12/94
G-8
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 5 - Total Volume To Weight-Up
There are several reasons why the volume of mud in the surface pits should be reduced after
the first circulation, but before weighting-up. Some of these reasons include:
•
•
•
It takes less time to weight-up less volume.
It requires less barite to weight-up less volume.
It may overflow the pits if barite is added without reducing first.
Whatever the reasons, decide on an appropriate pit volume and add it to the total system volume
(from your Prerecorded Data Sheet) to determine the total volume to weight-up. In our example,
we decided on 200 bbls of active pit volume with 779 bbls of system volume for a total volume
of 979 bbls. to weight-up. Record this value on part "I" of the Worksheet.
Step 6 -Barite Required To Weight-Up
Its an easy matter to determine the amount of barite that will be required once the total volume
to weight-up is known. Use the following formula and record the value at "J".
15.0 X Increase In Mud Weight
Barite Required = Total Volume to Weight-up x ----------------------------------------------
35.0 - New Mud Weight
15.0 x 1.0
= 979 x -------------------
35.0 - 11.0
= 612 sacks
Step 7 - Determining Pressures For The Second Circulation
Remember, when using the Driller's Method circulating pressures aren't calculated, but are self-
determined. This means that the pressures observed on the gauges are the pressures that are
held constant while circulating. The values recorded on the Driller's Method Worksheet for the
casing and drillpipe pressures should be observed values.
On the Driller's Method Worksheet, record the casing pressure as observed immediately before
the start of the second circulation. It should not be much higher than the observed shut-in
drillpipe pressure. If it is, another kick could be in the hole and it may be necessary to circulate
the well as before using the first circulation techniques in order to clear the well of the additional
influx. Otherwise, begin the second circulation by holding the observed casing pressure
constant while establishing circulation until the kill mud reaches the bit. Record the drillstring
internal capacity (in strokes) on the Worksheet to determine when kill mud will reach the bit.
Rev 12/94
G-9
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
As soon as the kill mud reaches the bit, attention should turn to the drillpipe gauge. The observed
drillpipe pressure at this point should be recorded on the Worksheet and held constant for the
remainder of the kill. The total system capacity must be written in the appropriate space on the
Driller's Method Worksheet.
Step 8 - Determining Reservoir Pressure
We need to calculate the reservoir pressure as an intermediate step in determining the more
critical well control parameters such as maximum casing pressure and excess volume. To
determine the reservoir pressure, simply multiply the following:
Reservoir Pressure= New Mud Weight X 0.052 x True Vertical Depth
= 11.0 x 0.052 x 9000
= 5148 psi
Record this value on the back of the Worksheet.
Step 9 - Determining Equivalent Bottomhole Gas Bubble Height
This is the height of the gas bubble at the bottom of the hole with an annulus equal to that at
the top of the hole. It is used to determine the maximum surface pressure when the gas bubble
reaches the surface. Use the following equation and record the height on the Worksheet.
Initial Pit Volume Increase
Gas Bubble Height = -----------------------------------------------------------
Annulus Capacity Factor (D.P. x Hole)
15 bbl
= -----------------------
0.0704 bbl/ft
=
213 feet
Step 10 - Determining Maximum Casing Pressure
If the kick is gas, then the maximum casing pressure will occur when the gas first reaches the
surface. This value must be calculated before its arrival to determine if the wellhead and casing
can withstand the pressure. The mathematical formula used to determine the maximum casing
pressure is shown in sections ) and Q. To simplify the calculation of maximum casing pressure
for those who do not want to use the formula, charts have been developed that are included in
Section P of this manual. The maximum casing pressure (Pc Max) is calculated in two steps.
An equation is used to calculate Part 1, and either the equation or a chart is used to calculate
Part 2.
Rev. 12/94
G-10
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Pc Max - Part 1: The first part of Pc Max is determined with the following simple formula:
Shut-in Drillpipe Pressure
Pc Max - Part 1, Driller's Method = ------------------------------------
2
For our example, Pc max part 1 is therefore equal to:
470
Pc Max - Part 1, Driller's Method = -------- = 235 psi
2
Pc Max - Part 2: Pc Max - Part 2 is calculated using the equations in sections P and Q or it can
be obtained from charts. Both "low pressure" and "high pressure" charts are provided to
calculate Pc Max Part 2. Figure P.1a is designed for use with "low pressure" wells, whereas
Figure P.1b is more suitable for high pressure wells. On either chart, enter the upper left vertical
axis at the original mud weight (10 lb/gal). Read across to an imaginary line for the reservoir
pressure (5,148 psi); then drop vertically to the line matching the equivalent bottom hole gas
bubble height (213 ft). Run a horizontal line to the curve for the PcMax-I value calculated earlier;
then run a vertical line up to the PcMax-II axis and read 720 psi. Record this value at "Q" on the
worksheet. Add "O" and "Q" to determine "R", the maximum surface casing pressure (955 psi).
Generally speaking, the casing pressure is significant only if it should exceed the pressure rating
of the casing, wellhead or BOP's. It is seldom possible to accurately calculate whether oil, gas,
or water has entered the hole, but with rare exceptions gas is always present. The method
described above will indicate the maximum possible casing pressure and pit volume gain if pure
gas has entered. Water or oil will decrease the casing pressure and volume gain somewhat from
those shown on the worksheet, and can be handled satisfactorily.
At this point, the maximum permissible casing pressure should have been determined and a
decision made on whether to circulate the formation fluid out of the hole or not.
Step 11 - Determining Volume Gain For A Gas Kic k
In part "T" an equation or a convenient chart can be used to determine the maximum pit volume
gain which will occur if the kick is completely gas. To use a chart, if the value for Pc max
calculated above is less than 1,000 psi, then figure P4.a should be used, else if Pc max is greater
than 1,000 psi, use Figure P.4b. On either chart, enter the left vertical axis at the maximum
surface casing pressure (955 psi). Read across to the reservoir pressure (5,148 psi), then down
to the original kick volume (15 bbl). Read across to the right vertical axis to obtain the volume
of gas at the surface (62 bbl). Record this volume at "T" on the Worksheet. Subtract the initial
pit volume increase "E" from "T" to determine the pit volume gain when the gas bubble is
circulated to the surface (47 bbl). Record this value at "U".
Rev 12/94
G-11
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 12 - Determining Maximum Casing Pressure And Excess Volume
Subtract the volume of gas at the surface "T," from the annulus capacity on the Prerecorded
Well Data Sheet. This will show approximately when the maximum casing pressure and
excess volume will occur. (623 - 62 = 561 bbl, 3264 strokes.) Record these values in the
proper spaces provided.
The following pages provide completed examples of the Worksheets and Figures described
previously, including:
• The Driller's Method Worksheet
• Figure P.1a (Pc Max Part 2)
• Figure P.4 a (Volume Gain)
Rev. 12/94
G-12
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
DRILLER'S METHOD WORKSHEET
(use the Tab key to advance to next required input)
PRERECORDED INFORMATION
SPM psi
bbl/stk
bbl/min
A. Slow Pump Rate Data Pump #1
( Use SPR Pressure through Riser for Subsea ) Pump #2
INFORMATION RECORDED WHEN WELL KICKS
Time of Kick:
1:30
B.
C.
D.
E.
F.
Old Mud W eight
Initial Shut-In Drill Pipe Pressure (SIDP)
Initial Shut-In Casing Pressure (SICP)
Initial Pit Volume Increase
True Vertical Depth of Hole
Measured Depth of Hole (for Capacity Calculations ONLY)
B
C
D
E
F
10.0
470
600
15
9,000
9,000
lb/gal
psi
psi
bbl
ft (TVD)
ft (MD)
FIRST CIRCULATION TO CLEAR WELL OF INFLUX
Bring Pumps up to Speed While Holding Casing Pressure Constant
{Account for Choke Line Friction if Subsea}
Read and Record Initial Circulating Pressure on Drill Pipe
[Should Approximately = Slow Pump Rate Pressure (A) + SIDP (C)]
Maintain Constant DP Pressure Until Influx is Circulated Out. Then Shut Down
Pumps W hile Holding Casing Pressure Constant. {Remember CLF for Subsea}. If Drill
Pipe and Casing Shut-In Pressures are not Equal, Continue to Circulate Out Influx.
G. Increase in Mud Weight required to Balance Kick
30
1060
SPM
psi
G
Initial SIDP
0.052 TVD
C
0.052 F
G
1.0
lb/gal
H. New Mud Weight
I. Total Volume to W eight up
J. Barite Required
H=B+G=
I = Active Pit Vol + System Vol =
J I
H
I
J
11.0
979
612
lb/gal
bbl
sacks
SECOND CIRCULATION TO BALANCE WELL
Bring Pumps up to Speed While Holding
Casing Pressure Constant. {Account for
≈ SIDP (C)
Casing Pressure
470
psi
CLF if Subsea} Maintain Constant Casing
Pressure Until New Mud Reaches the Bit.
Drill String Internal Capacity
905
strokes
Read and Record Drill Pipe Pressure
When New Mud Reaches the Bit
≈ SPRP ( A )
KWM ( H )
Old MW (B )
Final Circulating Pressure
649
psi
Maintain Constant Drill Pipe Pressure
Until the System is Displaced.
System Volume
4,530
strokes
Version 1.3 (8/1/94)
Rev 12/94
G-13
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
DRILLER'S METHOD WORKSHEET
RESERVOIR PRESSURE (Pr)
(page 2)
K . Pr
0 . 052
New MW
TVD
0 . 052
H
F
K
5148
psi
HEIGHT OF GAS BUBBLE AROUND DRILL PIPE (KH)
L. Annulus Capacity Factor (DP x Casing) Right Below Wellhead
L
0.0704
bbls/ft
M. Height
=
Initial Pit Vol Increase
Annulus Capacity Factor
(E )
( L )
M
213
ft.
MAXIMUM CASING PRESSURE (Pcmax) WHEN GAS GETS TO SURFACE
N. Grad = Mud W eight Gradient
MW (B) 0.052 =
N
0.52
psi/ft.
O.
Pc
max
Part 1 = SIDP
2 = ( C ) 2 =
(Surface) O
235
psi
(Optional Correction for Subsea Wells)
O. (Subsea) A correction must be added to Pcmax, Part1 calculated above to
account for the choke line.
(Subsea) O = Subsea Correction + (Surface) O =
Vol . Choke Line
Subsea Correction = ( ft ) -
L
(bbl )
(Subsea) O
2
0
psi
(use this new O for Part Q. and Part R. below)
P. TZ= Compressibility and Temperature Effects (fig 11P.5)
or Tz = 4.03 - (0. 38 ln(Pr)) = 4.03 - (0. 38 ln(K ))
Q. Pcmax, Part2 (figure 11P.1)
P
0.78
=
( O )
2
( K )( M )( N )( P )
Q
708
psi
R. Maximum Casing Pressure,
Pc MAX = (Pc MAX , Part 1 ) + (Pc MAX , Part 2) = O + Q =
R
943
psi
S. Does Pcmax Exceed the Wellhead or Casing Pressure Limitation?
YES
VOLUME GAIN WHILE CIRCULATING OUT GAS BUBBLE
T. Volume of Gas at Surface (from Fig. 11P.4 or Formula below)
NO
X
Vg , Volume of gas at surface
, bbl
E K P
R
T
64
bbl
U. Volume Gain While Circulating Out Gas Kick
U T− E
U
49
bbl
STROKES TO MAXIMUM CASING PRESSURE AND VOLUME
Maximum casing Pressure and Excess Volume Occur When the Pumped Volume Equals
Total Annulus Capacity - Volume of Gas at Surface bbl
559
strokes
3253
A
l
C
{
d d} T
Rev. 12/94
G-14
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
(Ref. 11P-16 to 18, Symbols and Equations)
Rev 12/94
G-15
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
(Ref. 11P-16 to 18, Symbols and Equations)
Rev. 12/94
G-16
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
SECTION H: ENGINEER'S METHOD
1. DESCRIPTION OF THE METHOD
The Engineer's Method (also called the wait and weight method) is a well killing method that requires
only one complete circulation. The kill mud is circulated into the well at the same time the kick is being
removed from the annulus. During the circulation, the bottomhole pressure is maintained at level
equal to or slightly greater than the formation pressure. The following information describes the
Engineer's Method in detail from kick to kill.
Step 1 - The Kick Is Detected - Shut The Well In.
As always, it is extremely important to get the well shut-in as quickly as possible in order to minimize
the size of the influx. The best way to achieve this is by using the "Three S" Shut -in Procedure While
Drilling or the "Three S" Shut-in Procedure While Tripping, shown below.
Shut-In Procedure While Drilling
(1)
(2)
SPACE OUT Pull the kelly out of the hole. Position the kelly so that the tool
joints are clear of the preventer stack.
SHUT DOWN Stop the mud pumps.
(3)
SHUT-IN
Close the annular preventer or uppermost pipe ram preventer.
Confirm that the well is shut-in and the flow has stopped.
Shut-In Procedure While Tripping
(1)
(2)
STAB VALVE Install the fully opened safety valve in the drillstring. Close the
safety valve.
SPACE OUT Position the drillstring so that the tool joints are clear of the
preventer stack.
(3)
SHUT-IN
Close the annular preventer or uppermost pipe ram preventer.
Confirm that the well is shut-in and the flow has stopped.
It should be stressed that in nearly all well kicks, the Driller will be responsible for actually closing the
preventers and shutting the well in. It is the duty of the Chevron Drilling Representative to make sure
the Driller can execute the proper shut-in procedure. The Driller must have the initiative and
experience to do this alone if required. There will be plenty of time after the well is shut-in to retrieve
crews from the mud pits and notify the Toolpusher. The Driller must not delay when shutting the
well in.
Rev 12/94
H-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 2a - Allow The Well To Stabilize, Record Pressures And Volume Gained
After the well is shut-in, it may take a few minutes for the shut-in pressures to stabilize. If the pipe
is reciprocated through the annular preventer during the kill, use this time to reduce the annular
closing pressure to reduce element wear. Make sure the bag does not leak at the reduced pressure!
With your choke manifold lined-up properly, open the choke line valve at the preventer stack and
read the shut-in casing pressure at the choke manifold. If no drillpipe float is installed, read and record
the shut-in drillpipe pressure as well. Finally, examine the pit volume charts to determine the volume
gained during the kick and verify this with the Derrickman.
Step 2b - Bumping The Drillpipe Float
If a drillpipe float is installed, the pressure gauge on the drillpipe will probably read near zero. In order
to get an accurate value for the shut-in drillpipe pressure, "bump" the float open by slowly pumping
down the drillpipe. The correct procedure for bumping the float is given below.
Float Bumping Procedure
(1)
(2)
(3)
(4)
(5)
(6)
Make sure the well is shut-in and that the shut-in casing pressure is recorded.
Slowly pump down the drillpipe while monitoring both the casing and drillpipe
pressure.
The drillpipe pressure will increase as pumping is begun. Watch carefully for
a "lull" in the drillpipe pressure (a hesitation in the rate of increase), which will
occur as the float is pumped off its seat. Record the drillpipe pressure when
the lull is first seen.
To verify that the float has been pumped open, continue pumping down the
drillpipe very slowly until an increase in the casing pressure is observed. This
should occur very soon after the lull is detected on the drillpipe gauge.
Shut down the pump as soon as you see the casing pressure begin to
increase and record the shut-in drillpipe pressure as the pressure at which the
lull was first seen, in Step 3 above (not the final drillpipe pressure after the
pumps are stopped).
Check the shut-in casing pressure again. Any excess pressure may be bled-off
in small increments until equal casing pressure readings are observed after two
consecutive bleed-offs.
Sometimes the float bumping procedure can be difficult to perform if the rig has big duplex pumps
which are compounded. Clutch the pumps in short bursts to slowly build up pressure on the drillpipe.
It's more likely that a drillpipe "lull" won't take place before the casing pressure starts to increase when
using this procedure. To determine the shut-in drillpipe pressure in these instances, subtract the
increase in shut-in casing pressure from the final value of shut-in drillpipe pressure after the pumps
have been stopped. The equation for this calculation is given below. Use this value as the official shut-
in drillpipe pressure.
Rev 12/94
H-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
If excess pressure is trapped on the
drillpipe when bumping the float ...
Shut-in
Shut-in drillpipe
Increase in shut-in
Drillpipe
Pressure
= pressure after
bumping float
-
casing pressure while
bumping float.
Step 3 - Perform the Kick Control Calculations
Calculations should be performed using the Engineer's Method Worksheet before the kill mud is
circulated into the well. Several critical items will be determined including:
•
•
•
•
•
Drillpipe pressure schedule
Bottomhole reservoir pressure.
Mud weight necessary to balance the kick.
Maximum surface casing pressure during the kill circulation.
Maximum excess mud volume gained during the kill circulation.
An example problem illustrating the use of the Engineer's Method Worksheet is provided later in this
Section.
One thing to keep in mind while performing your calculations is that the formation fluids in the annulus,
especially gas, may migrate up the hole and cause an increase in the shut-in casing pressure. If the
shut-in casing pressure starts increasing substantially to the point of risking an underground blowout
or exceeding the wellhead or casing pressure limitation, bleed-off some of the excess pressure
through the choke. It is better to bleed the pressure off in small increments rather than one large slug.
Any excess pressure which appears on the annulus due to the migrating gas bubble may be bled-
off in small increments until equal readings are observed after two consecutive bleed-offs.
Step 4 - Raise The Mud Weight In The Pits
As soon as the required mud weight has been calculated, raising the mud weight in the pits should
begin. The first step is to reduce the mud volume in the active pits to make room for weighting
material. The amount of barite required to increase the mud weight is determined in Part "J" of the
Engineer's Method Worksheet. If barite required exceeds barite on hand, either further reduce the
volume in the active system or proceed with the Driller’s Method. The mud mixing facilities and pit
volumes on a particular rig will dictate to some extent just how the mud should be handled. The ideal
situation is to maintain a reasonably low-volume active system so that the mud circulated out of the
hole can be weighted up without having to stop circulating. It may be desirable to weight up enough
mud to displace the entire hole before the killing operation is started. Many variables will enter into
this decision, so each situation must be handled on its own merits. The important thing is that the mud
weight can be raised while the well is being circulated.
Meanwhile, formation fluids in the annulus, especially gas, will migrate, causing an increase in casing
pressures. Also, the longer formation fluids are in the annulus, the more likely pipe sticking becomes.
Therefore, it is important to proceed as quickly as possible.
Rev 12/94
H-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 5 - Establish Circulation
After the kick control calculations have been performed and the mud has been weighted up properly,
the well should be circulated through the choke using the information recorded on the Engineer's
Method Worksheet. Before breaking circulation, be sure to check the following items.
(1) Be sure that all members of the crew knows exactly what their duties are before the
kill operation begins. (See Section O, "Training and Well Control Drills," for more
detail.)
(2) Eliminate all sources of ignition in the immediate vicinity of the rig and vent lines.
See that the vent lines on the mud-gas separator and mud degasser are secured
properly and, if possible, are downwind from the rig.
(3) Make sure the circulating system (including manifolds and pits) are lined-up
correctly.
(4) Zero the stroke counter and make a note of the time.
When establishing circulation in a well closed in under pressure, back pressure on the well is very
difficult to control. The procedure is critical, since additional influx will result if too little back pressure
is held, and the formation can break down if too much back pressure is held.
The procedure requires simultaneous manipulation of the choke and the pump speed. While the
pumps are being brought up to speed, the choke is opened in such a way that casing pressure is
maintained constant at its shut-in value just prior to the start of pumping. As the pump speed is
increased up to the desired kill rate, drillpipe pressure will increase, but casing pressure must be held
constant. Successful manipulation of the choke while establishing circulation in this manner will
maintain constant bottomhole pressure.
The chosen pump rate must be held constant throughout the killing of the well. If the pump rate is
allowed to vary without adjusting the choke size, constant bottomhole pressure will not be maintained.
If the pump rate is increased, additional friction pressure will cause the drillpipe pressure to increase.
If the choke is adjusted to lower the drill pipe pressure to its assumed correct value, then the
bottomhole pressure is reduced, possibly allowing another influx. Conversely, if the pump rate is
reduced, the reduction in friction pressure will be noted and the choke adjusted to increase the drill
pipe pressure, possibly creating sufficient overpressure at the casing shoe to cause a breakdown.
Therefore, any change in pump rate should be made known to the choke operator and the pump
should be returned to the original rate.
Step 6 - Follow The Drillpipe Pressure Schedule While Pumping Kill Mud.
After circulation has been established and the pumps are operating at the desired kill rate, the
previously calculated initial circulating pressure should be observed on the drillpipe pressure gauge.
As the kill mud goes down the drill- pipe, gradually adjust the choke so that the drillpipe pressure
closely tracks the drillpipe pressure schedule calculated earlier. At this point in the kill procedure,
constant bottom- hole pressure is being maintained by following the drillpipe pressure schedule and
by making slight choke adjustments. Do not change the pump rate to accomplish this. Also, do not
make choke adjustments in order to keep the casing pressure constant while the drillpipe is being
Rev 12/94
H-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
displaced with kill mud. When an influx rises above the drill collars and around the drillpipe, the influx
column height is reduced as a result of the larger annular capacity around the drillpipe as compared
to around the drill collars. This reduction increases the hydrostatic head in the annulus. Therefore,
as constant bottomhole pressure is being maintained by following the drillpipe profile, it's possible
to see a drop in casing pressure as the influx height shortens.
When the kill weight mud gets to the bottom of the drill string, the pressure on the drill pipe should
be the final circulating pressure, as recorded at "L" on the worksheet.
Step 7 - Hold The Drillpipe Pressure Constant For The Remainder Of The Kill.
When kill mud starts to be circulated up the annulus, the choke must be manipulated so that drillpipe
pressure is maintained constant at the final circulating pressure.
As the gas and contaminated mud are circulated to the surface, the gas will begin to expand,
increasing both the casing pressure and pit volume. A pure gas contaminant will increase the casing
pressure to the value shown at "W" on the worksheet. It will be less if the kick also includes water
and/or oil. Probably the most critical stage of the killing operation takes place at this time, and
panicking can very easily turn a good job into a disaster.
It can sometimes be difficult to bleed the gas off fast enough to keep the drillpipe pressure within
limits, but excessive pressure could cause formation breakdown. If the gas cannot be released fast
enough from the annulus to prevent an increase in drill pipe pressure, the pumps may have to be
slowed or even stopped until the casing pressure is bled down. For this reason, it's a good idea to take
several slow pump rates (including one at the slowest pump rate possible) so that the new drillpipe
pressure at the reduced pump rate can be determined. If the pumps must be stopped while bleeding
down the casing pressure, attempt to hold the drillpipe pressure at or above the original shut-in
pressure while bleeding. If the drillpipe pressure drops below this value, another kick may occur. The
pumps should be returned to the original rate as soon as possible. This method is not ideal, but is
necessary when the surface facilities cannot safely handle the high flow rates.
Continue circulation until the entire system is full of the kill weight mud. The approximate strokes
required are indicated on the prerecorded data sheet.
Step 8 - Shut Down And Check For Flow.
After the entire hole volume has been displaced with kill mud, the pumps can be shut down and the
well shut-in. When shutting down the pumps, the choke should be closed (holding casing pressure
constant) gradually as the pump speed is reduced. (Note: The casing pressure may already be zero
before the pumps are shut down. This is normal and may be expected). As the pump speed
decreases, the drillpipe pressure will slowly decrease to zero. After the well is shut-in, both the casing
and drillpipe pressures should be zero. Confirm that the well is dead by cracking open the choke; the
well should not flow. If the well is dead, the BOP's can be opened. Keep in mind that a small volume
of gas may be trapped between the annular preventer and the choke line. Exercise caution on the
rig floor when opening the preventers.
Rev 12/94
H-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 9 - Circulate And Condition The Mud.
After the BOP's are opened, the mud should be circulated and conditioned to the desired properties.
Usually, the yield point is too high. Thus, running or pulling pipe can cause excessive pressure on
the formation or swabbing, and either could lead to another kick.
After the mud has been conditioned and the yield point reduced, if a trip is made, it may be necessary
to raise the mud weight slightly to provide a suitable "trip margin". This can be determined with the
DRILPRO Swab/Surge calculations.
2. USING THE ENGINEER'S METHOD WORKSHEET
The Engineer's Method Worksheet is a step-by-step instruction sheet to help the Drilling Represen-
tative calculate the critical well control parameters that are necessary to successfully kill a well using
the Engineer's Method. Use of the Worksheet is demonstrated here through the use of an example
problem described below:
Example Problem - A well is being drilled and the following data are known prior to a kick:
2-duplex pumps - 16-in. stroke, 3-in. rod, 96% vol.. eff., 6-1/4-in. liner.
Casing size - 10-3/4 in., set at 4,000 ft. Hole size - 9-7/8 in.
Casing pressure limitation - 2,864 psi (burst)
Shoe Test - 720 psi with 10 lb/gal. mud
Drill pipe size - 5 in., 19.5 lb/ft. (20.7 lb/ft. w/tool joints).
Remaining collapse resistance of drill pipe - 4,109 psi
Drill collar size - 7 in. OD x 2-13/16 in. ID x 450 ft. long.
Mud weight - 10 lb./gal.
Active surface mud system - 450 bbl. before kick; 200 bbl. at start of kill operation.
Slow pump rate data:
Strokes/min.
20
30
PSI
280
590
While drilling at 9,000 ft. TVD, the well kicked and the BOP's were closed.
The following data was observed.
Initial drill pipe pressure = 470 psi.
Initial casing pressure = 600 psi.
Pit volume gain = 15 bbl.
Following is a step-by-step procedure for determining the well control parameters which are
necessary to kill the example well using the Engineer's Method.
Rev 12/94
H-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Engineer's Method Worksheet
Step 1 - Prerecorded Information
Prior to the kick (and at all times), a Prerecorded Data Sheet should be completely filled out except
for the measured depth and the length of drillpipe in the hole. After entering these items, calculate
the internal drillstring capacity and the system totals. Transfer the slow pump rate data from the
Prerecorded Data Sheet to line "A" of the Engineer's Method Worksheet.
Step 2 - Information To Be Recorded When Well Kicks
Many items of information need to be gathered when a well kicks. These include:
Old Mud Weight
Initial Shut-in Drill Pipe Pressure
Initial Shut-in Casing Pressure
Pit Volume Increase
True Vertical Depth Of Hole
Measured Depth Of Hole
This information should be recorded in lines "B" through "F" on the Engineer's Method Worksheet.
Step 3 - Determining Mud Weight To Balance The Kick
Using the equation below, calculate the increase in mud weight necessary to balance the kick.
Initial Shut-in Drillpipe Pressure
Increase in Mud Weight = -------------------------------------------------------
0.052 X True Vertical Depth
470
= ------------------------ = 1.0043
0.052 X 9000
Therefore,
Increase in Mud Weight = 1.0 lb./gal
Rounding-Up Rule: The increase in mud weight should be calculated to the hundredths place. If
the number in the hundredths place is greater than zero, then round up the number in the tenths place
one full tenth. In this example, the number in the hundredths place is zero, so the number in the tenths
place is not rounded up.
Record a 1.0 lb/gal increase on line "G" of the Engineer's Method Worksheet. Adding the mud weight
increase "G" to the old mud weight "B" yields the new mud weight required to balance the kick.
Rev 12/94
H-7
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
New Mud Weight To Balance The Kick = Old Mud Weight + Increase In Mud Weight
= 10.0 + 1.0
= 11.0 lb/gal
Enter the new mud weight in part "H" of the worksheet.
The mud weight determined by this procedure will provide a hydrostatic pressure equal to the BHP
and sufficient to kill the well, but perhaps not high enough for making a trip. Weighting up a mud
increases its yield point, causing increased pressure on the formation during circulation (the
equivalent circulating density). As extra mud weight and a higher yield point could fracture the
formation, it is best to adjust the yield point and add a trip margin after the well is killed.
Step 4 - Total Volume to Weight-Up
As discussed in the Driller's Method, there are several reasons why the volume of mud in surface pits
should be reduced before weighting up. Again, some of these reasons are:
(1) It takes less time to weight up less volume.
(2) It requires less barite to weight up less volume.
(3) While circulating the influx out, the pits may overflow.
Whatever the reason, decide on the volume to use and add it to the system volume from the
Prerecorded Data Sheet to determine the total volume to weight up. In our example, we again used
200 bbl. to arrive at a total volume to weight up of 979 bbl. Record this value at "I" on the worksheet.
Step 5 - Barite Required to Weight-Up
Again, the same formula used to determine barite requirements for the Driller's Method will be used
to calculate the volume required for the Engineer's Method. The equation is shown below:
15.0 x Increase in Mud Weight
Barite Required =Total Volume to Weight Up x -----------------------------------------------
35.0 - New Mud Weight
Step 6 - Determining Initial Circulating Pressure
Immediately after the pumps are operating at the desired kill rate and kill mud is going down the hole,
the initial circulating pressure should be observed on the drillpipe gauge. The initial circulating
pressure can be calculated by adding the slow pump rate pressure at the desired kill rate "A" to the
initial shut-in drill pipe pressure "C". This is expressed mathematically by:
Initial Circulating Pressure = Slow Pump Rate Pressure + Shut-in Drillpipe Pressure
In this example, 30 SPM was selected. Therefore, the initial circulating pressure will be 590 + 470 =
1060 psi. Record this value at "K."
Rev 12/94
H-8
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
NOTE: If for some reason the prerecorded circulating pressures at various rates are unavailable,
the initial drillpipe circulating pressure can be determined by proceeding as follows: a) hold the casing
pressure constant until the pump is at the desired speed, b) read the drillpipe pressure at that time.
This pressure minus the initial shut-in drill- pipe pressure will be the reduced circulating pressure at
the desired speed and would be used to calculate the final circulating drillpipe pressure.
Step 7 - Determining Final Circulating Pressure
The final circulating pressure is the pressure the drillpipe gauge should read when kill mud reaches
the bit. The final circulating pressure can be estimated by the formula:
New Mud Weight
Final Circulating Pressure = Slow Pump Rate Pressure X --------------------------------
Old Mud Weight
11
= 590 X -----
= 649 psi
10
Step 8 - Drillpipe Pressure Schedule
Successful well killing with the Engineer's Method requires that the drillpipe pressure decrease from
a higher value (the Initial Circulating Pressure) to a lower value (the Final Circulating Pressure) as
kill mud is pumped down the drillstring. It is very important that the drillpipe pressure be reduced
smoothly in small increments as the drillpipe is filled with kill mud. The drillpipe pressure should not
be reduced all at once when the kill mud reaches the bit.
In order to accomplish a smooth transition from Initial Circulating Pressure to the Final Circulating
Pressure, create a drillpipe pressure schedule which displays the correct circulating drillpipe pressure
at 50 or 100 stroke increments as kill mud is pumped down the drillstring. The Drilling Representative
can track the drillpipe pressure and the pump strokes and make small choke adjustments so that the
observed drillpipe pressures are equal to the calculated values displayed on the schedule at all points
during the circulation. It is important to realize that this drillpipe pressure drop should require minimal
choke adjustments since the hydrostatic pressure in the drillpipe will be increasing automatically as
the kill mud is pumped down.
The first step in creating the drillpipe pressure schedule is to transfer the internal, annulus and system
capacity values from the Prerecorded Data Sheet to lines "M" and "N" on the Engineer's Method
Worksheet.
Next, record the calculated Initial Circulating Pressure, "K", on the top/right side of the schedule table
and record zero strokes on the left-side.
Next, record the calculated Final Circulating Pressure, "L", on the bottom line of the schedule table
(on the right) opposite the total internal stroke capacity (on the left).
Rev 12/94
H-9
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
We now need to fill-in the lines between the Initial Circulating Pressure and the Final Circulating
Pressure on the Drillpipe Pressure Schedule table. The drillpipe pressure drop per stroke can be
calculated with the following formula:
Initial Circulating Pressure - Final Circulating Pressure
Drillpipe Pressure Drop = ----------------------------------------------------------------------------------
(per stroke) Total Internal Stroke Capacity
1060 - 649
= -----------------
905
= 0.45 psi/stroke
This equation will normally yield a fraction of a psi reduction per pump stroke, which is too small to
accurately measure on the rig. Therefore, we arbitrarily choose a stroke increment of 100 strokes,
which becomes our point of reference as kill mud is pumped down the drillpipe. Instead of reducing
the drillpipe pressure 0.45 psi per stroke, we reduce it 45 psi per 100 strokes (which is essentially
the same thing).
We can then subtract this pressure decline (45 psi per 100 strokes) from the initial circulating pressure
at each increment until the final circulating pressure at the total internal capacity is reached. The
schedule is completed by adding stroke increments on the left side and subtracting pressure
increments from the right side.
Step 9 - Determining Reservoir Pressure
We need to calculate the reservoir pressure as an intermediate step in determining the more critical
well control parameters such as maximum casing pressure and excess volume. To determine the
reservoir pressure, simply multiply the following:
Reservoir Pressure = New Mud Weight X 0.052 X True Vertical Depth
= 11.0 X 0.052 X 9000
= 5148 psi
Record this value on the back of the Worksheet.
Step 10 - Determining Maximum Casing Pressure
If the kick is gas, then the maximum casing pressure will occur when the gas first reaches the surface.
We can calculate this value before the kick arrives at surface to determine if the wellhead and casing
can withstand the pressure. Mathematical formulas used to determine the maximum casing pressure
are used in parts "U" and "V" of the Killsheet. For those who do not wish to make this calculation, charts
Rev 12/94
H-10
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
have been developed and are included in the back of this section and in Section P. The maximum
casing pressure (Pc Max) is calculated in two steps, so two charts are required.
Pc max part 1: On Figure P.2, enter the left vertical axis at the total internal drillpipe capacity (156
Bbl.), and read across to the line for the drillpipe x hole annulus capacity factor (0.0704 bbl./ft.). Drop
a vertical line to the increase in mud weight (1.0 lb/gal), then read across to the right vertical axis to
find Pc max part 1(60 psi). Record this figure at "U".
Pc max part 2: On Figure P.3, begin at the upper horizontal axis, at the new mud weight (11.0 lb/
gal). Drop a vertical line to the reservoir pressure curves at 5,150 psi, then run a horizontal line to
the curve corresponding the original kick volume (15 bbl). Drop another vertical line to the drillpipe
x hole annulus capacity factor (0.0704 Bbl/ft.), then run a horizontal line to the right vertical axis, Pc
max part 2. Record this value (690 psi) at "V" on the worksheet.
To determine the maximum surface casing pressure while properly circulating out a pure gas kick
(Pc Max) simply add "U" and "V" to obtain 750 psi. Record this value at "W". The next question is
very important and its answer may determine the course of action that will be taken for the kill. In most
cases, it can go to 100% of the wellhead pressure or BOP ratings, but only 80% of the casing burst
pressure.
Generally speaking, the casing pressure is significant only if it should exceed the pressure rating of
the casing, wellhead or BOP's. It is seldom possible to calculate with accuracy whether oil, gas, or
water has entered the hole, but with rare exceptions gas is always present. The method described
above will indicate the maximum possible casing pressure and pit volume gain if pure gas has
entered. Water or oil will decrease the casing pressure and volume gain from those shown on the
worksheet.
At this point, the maximum permissible casing pressure should have been determined and a decision
made as to whether to circulate the formation fluid out of the hole.
Step 11 - Determining Pit Volume Gain For A Gas Kic k
The volume of the gas at surface is calculated in part "X". Again for those who do not wish to make
this calculation, a convenient chart is also provided to determine the maximum pit volume gain which
will occur if the kick is completely gas. If the value for Pc max that was calculated above is less than
1,000 psi, then use Figure P.4a to calculate the volume gained. If Pc max is greater than 1000 psi,
use Figure P.4b. On either chart, enter the left vertical axis at the maximum surface casing pressure
(750 psi). Read across to the reservoir pressure (5,150 psi), then down to the original kick volume
(15 bbl). Read across to the right vertical axis to obtain the volume of gas at the surface (78 bbl).
Record this volume at "X". Subtract the initial pit volume increase "E" from "X" to determine the pit
volume gain due to gas expansion while the bubble is being circulated to the surface (60 bbl). Record
this at "Y".
The volume gained due to barite addition is simplified by the equation shown in part "Z". It is
approximated by dividing the barite required to weight up "J" by 15 sacks of barite per bbl of additional
volume increase. Record this figure at part "Z". The total volume gain while circulating out a gas kick
is calculated by adding part "Y" to part "Z". Record this value.
Rev 12/94
H-11
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Step 12 - Determining When Maximum Casing Pressure And Excess Volume Will Occur.
Subtract the volume of gas at the surface "X" from the annulus capacity "N" to determine when the
maximum casing pressure and excess volume will occur (624 - 79 = 544 bbl, or 3,163 strokes).
Record these values in the proper spaces provided.
NOTE: The maximum casing pressure and excess volume may not occur exactly at the
number of strokes calculated due to gas migration or hole washout.
The following pages provide completed samples of the Worksheet and
Figures used in the previous example problem, including:
1.
2.
3.
4.
5.
The Prerecorded Data Sheet
The Engineer's Method Worksheet
Figure P.2 (Pc Max part 1)
Figure P.3 (Pc Max part 2)
Figure P.4 (Volume Gain)
Rev 12/94
H-12
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
PRERECORDED WELL DATA
KEEP THIS DATA SHEET CURRENT AT ALL TIMES
(use the Tab key to advance to next required input)
Well Name
OCSG 0544 #5
Field
E. Cam. 160
Rig
DIGGER #4
Hole Data:
Size(avg)
9.8750
Hole MD
9,000
ft.
Hole TVD
9,000
ft.
Hole Capacity: no pipe in hole
0.0948
bbls/ft x
9,000
ft. =
852.9
bbl
(from BOP to MD)
*Use
DP
PUMP DATA:
Liners (in.) Stroke(in.)
Rod(in. )
% Eff.
bbl./stk For Kill?
CSG
No. 1
No. 2
CASING (LAST SET) DATA:
* X if used, empty if not
10.7500
by
9.8750
Shoe MD
4,000
Shoe TVD
4,000
(in. OD) (in. Avg ID)
WELLHEAD OR CASING PRESSURE LIMITATION:
(feet)
(feet)
The lessor of: 100% BOP Rating
10,000
psi.
100% Wellhead Rating
80% Casing Burst
5,000
2,864
psi.
psi.
Limitation =
2,864
psi.
LINER CASING DATA:
by
Top @
ft. Shoe @
(in. OD)
DRILL STRING DATA:
(in. Avg ID)
(feet)
(feet)
DRILL COLLARS
Drill Pipe
5.0000
in. (OD)
19.5
lb./ft.
OD(in.) ID(in.)
Drill Pipe
HW Drill Pipe
in. (OD)
in. (OD)
lb./ft.
lb./ft.
7
by
by
2.8125
INTERNAL CAPACITIES:
Drill Pipe 8,550
Drill Pipe
HW Drill Pipe
ft.
ft.
ft.
x
x
x
0.0178
bbl./ft. =
bbl./ft. =
bbl./ft. =
152.1
bbl.
bbl.
bbl.
Drill Collars
450
ft.
x
0.0077
bbl./ft. =
3.5
bbl.
Drill Collars
ft.
x
bbl./ft. =
bbl.
M. Depth(Bit)
9,000
ft.
Total Internal = 155.6
bbl. =
905
Strokes
ANNULUS CAPACITIES:
(Note: Use other side
for subsea)
DP x Csg. 4,000
or Hole 4,550
HW DP
DC x Hole 450
DC x Hole
ft. x 0.0704
ft. x 0.0704
ft. x
ft. x 0.0471
ft. x
bbl./ft. =
bbl./ft. =
bbl./ft. =
bbl./ft. =
bbl./ft. =
281.8
320.5
21.2
bbl.
bbl.
bbl.
bbl.
bbl.
M. Depth(Bit)
9,000
ft.
Total Annulus
623.5
bbl. =
3,626
Strokes
System Volume =
779.1
bbl.
=
4,530
Strokes
(Internal + Annulus)
Active Pit Volume
MAX INITIAL SICP TO FRACTURE FORMATION AT SHOE:
Max. SICP = (Shoe Test - Present Mud Wt.) x 0.052 x Shoe TVD
200
bbl.
(
13.5
lb./gal EMW -
10.0
lb./gal) x 0.052 x
4,000
ft. =
728
psi.
Version 1.3 (8/1/94)
Rev 12/94
H-13
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
ENGINEER'S METHOD WORKSHEET
(use the Tab key to advance to next required input)
PRERECORDED INFORMATION
SPM
psi
bbl/stk
bbl/min
A. Slow Pump Rate Data
( Use SPR Pressure thru Riser for Subsea )
Pump #1
Pump #2
INFORMATION RECORDED WHEN WELL KICKS
Time of Kick:
1:30
B.
C.
D.
E.
F.
Old Mud Weight
Initial Shut-In Drill Pipe Pressure (SIDP)
Initial Shut-In Casing Pressure (SICP)
Initial Pit Volume Increase
True Vertical Depth of Hole
Measured Depth of Hole (for Capacity Calculations ONLY)
B
C
D
E
F
10.0
470
600
15
9000
9000
lb/gal
psi
psi
bbl
ft (TVD)
ft (MD)
MUD WEIGHT TO BALANCE KICK
G. Increase in Mud Weight required to Balance Kick
G
Initial SIDP
0.052 TVD
C
0.052 F
G
1.0
lb/gal
H. New Mud W eight
I. Total Volume to Weight up
H=B+G=
I = Active Pit Vol + System Vol =
H
I
11.0
979
lb/gal
bbl
J. Barite Required
J I
35.0− H
J
612
sacks
INITIAL CIRCULATING PRESSURE
K. Slow Pump Rate Pressure + SIDP
K =A+C=
K
1060
psi
FINAL CIRCULATING PRESSURE
L. Slow Pump Rate Pressure X (New Mud Wt / Old Mud Wt)
L A
H
B
L
649
psi
DRILL PIPE PRESSURE PROFILE
strokes
M. Total Internal Capacity (from Prerecorded W ell Data)
M
905
N. Total Annulus Capacity (from Prerecorded W ell Data)
O. System Volume (from Prerecorded Well Data)
N
O
3626
4530
624
bbl
Pressure Decline
Internal Capacity Strokes (M)
Strokes
Pressure (psi)
0
100
200
300
400
500
600
700
800
900
1060
1015
969
924
878
833
787
742
697
651
= Initial Circ Press (K)
Total Internal Cap (M) =
905
649
= Final Circ Press (L)
Version 1.3 (8/1/94)
Rev 12/94
H-14
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
ENGINEER'S METHOD WORKSHEET
RESERVOIR PRESSURE (Pr)
(page 2)
P. Pr 0.052 New MW TVD 0. 052 H F
P
5148
psi
MAXIMUM CASING PRESSURE (Pcmax) WHEN GAS GETS TO SURFACE
Q. Drill String Capacity from Prerecorded Data
R. Annulus Capacity Factor DP x Casing Right Below Wellhead
Q
R
156
0.0704
bbl
bbl/ft
S. Temperature and Compression Effects. (from fig. 11P.5 or formula below)
S TZ 4.03− (0.38 ln(P))
T. New Mud Weight Gradient, psi/ft
S
0.78
0.052 H =
U. PcMAX , Part 1 (from Fig. 11P. 2 or from Formula Below )
= =
T
(Surface) U
0.572
57
psi/ft
psi
(Optional Correction for Subsea Wells)
U. (SUBSEA) A Correction must be added to Pcmax,Part 1 calculated above to
account for the choke line.
(Subsea)U = Subsea Correction + (Surface)U
(Subsea) U
0
psi
Subsea correction
= RKB to ML
( ft ) -
Vol . Choke Line(
R
bbl )
T
(use this new U for Part V. and Part W. below)
V. PcMAX Part 2 (from Fig. 11P.3 or from Formula Below )
2
U
V
703
psi
W. Maximum Casing Pressure,
PCmax=PCmax, Part 1 + PCmax, Part2 = U + V =
W
760
psi
Does Pcmax Exceed the Wellhead or Casing Pressure Limitation?
VOLUME GAIN WHILE CIRCULATING OUT GAS BUBBLE
X. Volume of Gas at Surface (From Formula Below)
YES
NO
X
Vg , Vol gas at surf , bbl
E P S
W
X
79
bbl
Y. Volume Gain While Circulating Out Gas Kick
Y=X-E
Y
64
bbl
Z. Volume Gain due to Barite Addition
Z
Total Volume Gain While Circulating Out Gas Kick
J
15 sacks / bbl
= Y+Z
Z
41
105
bbl
bbl
STROKES TO MAXIMUM CASING PRESSURE AND VOLUME
Maximum casing Pressure and Excess Volume Occur When the Pumped Volume Equals
bbl
strokes
Total Annulus Capacity - Volume of Gas at Surface
= N - X 544
3163
Rev 12/94
H-15
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Figure 11P.2
Pc Max Part 1 for Engineer's Method
(Internal DP Cap) (0.052) ( Mud Wt)
Pc Max, 1 =
(2) (Annulus Capacity Factor)
(Ref. 11P-16 to 18, Symbols and Equations)
Rev 12/94
H-16
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
Figure 11P.3
Pc Max Part 2 for Engineer's Method
Pc Max, 2 = (PR )(H1) (P 2) (TZ)
(Ref. 11P-16 to 18, Symbols and Equations)
Rev 12/94
H-17
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION GUIDE
(Ref. 11P-16 to 18, Symbols and Equations)
Rev 12/94
H-18
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
SECTION I: VOLUMETRIC CONTROL
1. INTRODUCTION
In controlling a threatened blowout, special problems may arise that interfere with routine methods
of well control. One of these problems is not being able to circulate an influx out of the wellbore. This
may be due to several things, such as inoperative pumps, plugged bit or drillpipe, drillpipe above the
influx (as in a kick taken while tripping), or when pipe is out of the hole completely. When one of these
problems occurs, the well cannot be circulated with kill mud until corrective measures have been
taken and the ability to circulate out the influx is regained. In the case of a plugged bit, it would be
necessary to perforate the drillpipe; or if the drillpipe was off bottom, it would be necessary to strip
back to bottom.
Monitoring the casing pressure while initiating corrective procedures will dictate the method of
controlling the well. If the casing pressure does not increase above the original shut-in pressure, a
salt water kick is indicated. Since there is less density differential between salt water and mud than
between gas and mud, the salt water will migrate much slower than gas. Thus, the shut-in casing
pressure will remain relatively constant and the only consideration is to leave the well shut in until
it can be killed. However, if the casing pressure increases above the original shut-in pressure, a gas
kick is indicated. The expansion characteristics of gas coupled with the density differential between
gas and mud that cause the gas to migrate up the hole dictate the use of the Volumetric Control
Method.
Successful use of the Volumetric Control Method requires a thorough understanding of three basic
principles. The first is Boyle's Law, which states that the pressure of a gas is directly related to its
volume. The second is hydrostatic pressure, and the third involves fluid volume and height as
determined by annular capacities.
2. BASIC VOLUMETRIC CONTROL PRINCIPLES
First Basic Principle - Boyle's Law: Boyle's Law states that the pressure of a gas is directly related
to its volume. If a volume of gas is compressed, the pressure in the gas will increase. Conversely,
if a gas is allowed to expand, the pressure in the gas will decrease. Stated mathematically, Boyle's
Law is written as:
Boyle's Law
This equation is a simplification of
the gas law equation, PV=ZnRT,
(Equation I.1)
P 1V1 = P2V2
which neglects the effect of the tem-
perature and gas compressibility fac-
where: P1
V1
P2
V2
= Pressure in gas at condition 1
= Volume of gas at condition 1
= Pressure in gas at condition 2
= Volume of gas at condition 2
tors.
Rev 12/94
I-1
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Relating this phenomenon to well control, as a gas kick migrates up without expansion the pressure
of the gas bubble will remain constant. If the gas bubble is allowed to expand as it migrates, then the
pressure in the gas bubble will decrease.
Allowing the gas bubble to migrate to the surface without expansion will usually result in disastrous
consequences. This is because the pressure in the bubble as it enters at the bottom of the wellbore
is equal to the formation pressure. Owing to the nature of gas bubbles, they tend to rise in a fluid which
has a greater density than their own. If a gas bubble rises without expansion, it will have the same
pressure on the surface as it had on bottom and will bring bottomhole formation pressure to the
surface! The consequences can be disastrous, often resulting in ruptured casing or an underground
blowout.
On the other hand, if we allow the volume of gas to increase as it rises in the annulus, then according
to Boyle's Law, the pressure in the gas bubble will decrease. This is precisely the action taken when
using Volumetric Control. We allow the gas bubble to expand by bleeding off mud at the surface
through the choke.
Second Basic Principle - Hydrostatic Pressure: The rising gas bubble can be treated as a surface
pressure with respect to the mud below it. Any time the gas bubble rises by one foot in the annulus,
there will be one additional foot of mud below the gas bubble. The additional foot of mud below the
gas bubble increases the hydrostatic pressure of the mud below the gas bubble, which increases the
bottomhole pressure by a like amount according to the following formula:
Bottomhole Pressure = Hydrostatic Pressure +Surface Pressure
If we bleed mud from the annulus in order to lower the pressure in the gas bubble, then we naturally
reduce the volume of mud in the annulus and therefore, the hydrostatic pressure as well. When the
mud is bled from the annulus, it is very important that it is done in a way that holds the casing pressure
(surface pressure) constant. From the above equation, it's clear that if we bleed mud from the annulus
while holding the casing pressure constant, then the bottomhole pressure will decrease.
Therefore, in Volumetric Control, there are two ways to influence the bottomhole pressure:
1. Do nothing. The gas bubble will rise, and bottomhole pressure will go up.
2. Bleed mud from the annulus. The hydrostatic pressure and bottomhole pressure
will go down.
We must be very careful when bleeding mud from the annulus, because if the hydrostatic pressure
is lowed too much, an underbalanced condition may result and additional gas may enter the well. We
want to bleed off just enough mud at the surface so that the bottomhole pressure never drops below
the reservoir pressure. In order to accomplish this, we need to equate the loss in hydrostatic pressure
with the volume of mud bled-off at the surface. The casing pressure can be allowed to increase by
this lost pressure in order to keep bottomhole pressure from changing. It is for this reason, that we
measure the amount of mud bled-off from the annulus and equate that volume to a reduction in
hydrostatic pressure.
Third Basic Principle - Volume and Height: Everyone should be comfortable with annular volume
and height relationships. They are used in cement jobs, Pre-Recorded Data Sheets, and numerous
other everyday calculations on the rig. Annulus capacity factors are tabularized in Tables P.1, P.2,
and P.3, or can be calculated with the formula on the following page:
Rev 12/94
I-2
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
These factors are required
Annulus Capacity Factor
OD2 -ID2
ACF = ------------------
1029
in order to calculate the re-
duction in hydrostatic pres-
sure which occurs each time
mud is bled from the annu-
lus. The drop in hydrostatic
Where:
ACF = Annulus Capacity Factor (bbl/ft)
OD = Outside Diameter of Annular Space(in)
ID = Inside Diameter of Annular Space (in)
pressure occurring as a re-
sult of each mud volume bled
must be known.
3. DESCRIPTION OF THE METHOD
The Volumetric Control Method is not a kill method, but instead is a method of controlling the
bottomhole pressure until provisions can be made to circulate or bullhead kill mud into the well.
The purpose of Volumetric Control is to control the expansion of the gas bubble as it migrates up the
hole. We allow the gas bubble to expand by bleeding off mud at the surface while holding casing
pressure constant. Casing pressure is held constant only while the mud is being bled off; at other
times it is allowed to increase naturally. Each barrel of mud that we bleed off at the surface changes
the wellbore environment in four ways, as follows:
Each barrel of mud that we bleed from the annulus causes......
......
......
......
......
the gas bubble to expand by one barrel.
the hydrostatic pressure of the mud in the annulus to decrease.
the bottomhole pressure to decrease.
the surface casing pressure to stay the same.
Volumetric Control is accomplished in a series of steps that causes the bottomhole pressure to rise
and fall in succession. We let the gas bubble rise and the casing pressure and bottomhole pressure
go up. We keep casing pressure from increasing further by bleeding mud from the annulus and the
bottomhole pressure goes down. Then we let the gas bubble rise, and then we hold casing pressure
constant by bleeding mud, and so on... In this way, bottomhole pressure is held within a range of
values that is high enough to prevent another influx and low enough to prevent an underground
blowout.
Step One - Calculations
There are three calculations which need to be performed before a Volumetric Control procedure
can be executed. These are:
1. Safety Factor
2. Pressure Increment
3. Mud Increment
Rev 12/94
I-3
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
The safety factor is an increase in the bottomhole pressure which occurs naturally as gas
migrates up the annulus. By allowing the gas bubble to rise in the annulus, we are allowing the
bottomhole pressure to increase. It is important that we allow the bottomhole pressure to
increase to a value which is well above the formation pressure to ensure that we don't go
underbalanced when we bleed mud from the annulus in later steps. An appropriate value for the
safety factor is in the range of 200 psi in most cases. Depending on the depth, angle, and fluid
in the well, it may take several hours for the gas bubble to rise sufficiently to increase the casing
pressure by 200 psi.
Depending on how close the shoe is to exceeding its fracture pressure under initial shut-in
conditions, it may be advisable to select a safety factor smaller than 200 psi. Any increase in
the bottomhole pressure will be reflected as an equal increase in the shoe pressure as well. If
the shoe is close to its fracture pressure, then the safety factor will have to be appropriately
reduced. If you calculate that a 200 psi safety factor will break the shoe down, then a 100 psi
safety factor would be more suitable.
The pressure increment is the reduction in hydrostatic pressure that occurs each time a given
volume of mud is bled from the annulus. The Drilling Representative should select a pressure
increment which produces a reduction in hydrostatic pressure equal to one-third of the value of
the initial safety factor (rounded to the nearest 10 psi). For example, if a 150 psi safety factor
was chosen, then the pressure increment should produce a reduction in hydrostatic pressure of
50 psi (i.e., one-third of 150 psi).
Pressure Increment
Safety Factor
Pressure Increment = ---------------------
3
The mud increment is the volume of mud which must be bled from the annulus in order to
reduce the annular hydrostatic pressure by the amount of the pressure increment determined
above. The mud increment can be calculated with the equation given below. It is very important
that some means be available to measure the small volumes of mud that are bled from the
annulus.
Mud Increment
PI x ACF
Mud Increment = --------------------
MW x 0.052
where:
PI = Pressure Increment (psi)
ACF = Annulus Capacity Factor (bbl/ft)
MW = Mud Weight (ppg)
As an example, if a hydrostatic reduction (pressure increment) of 50 psi is desired, and the
annulus capacity factor is 0.0704 bbl/ft with a mud weight of 11.3 ppg, then the proper mud
increment is 6 bbl.
Rev 12/94
I-4
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Step Two - Allow Casing Pressure to Increase to Establish Safety Factor
After the calculations are completed, the next step in Volumetric Control is to wait for the gas
bubble to migrate up the hole and cause an increase in the shut-in casing pressure. This would
actually be occurring as calculations were made. We allow the casing pressure to increase by
an amount equal to the safety factor. No mud has been bled off from the annulus, so the
hydrostatic pressure of the mud has not changed since the well was first shut in.
While Gas Bubble Migrates
Bottomhole Pressure = Hydrostatic Pressure + Surface Pressure
(Goes Up)
(Stays the Same)
(Goes Up)
At this point, the bottomhole pressure has also increased by the amount of the safety factor and
the well should be safely overbalanced.
Step Three - Hold Casing Pressure Constant By Bleeding Off The Mud Increment
After the safety factor overbalance is applied to the well, the casing pressure can be kept from
rising further by bleeding mud from the well. This can be done until the first mud increment has
been bled from the well. The manner in which the mud is bled off from the annulus is very
important; it must be bled in such a way that the casing pressure remains constant
throughout the entire bleeding. This is done to ensure that the bottomhole pressure is reduced
only by a loss in the mud hydrostatic pressure, and not by an additional loss in surface pressure.
During the bleeding process, the hydrostatic pressure is reduced by the pressure increment while
the surface pressure is held the same, so the bottomhole pressure is also reduced by the pressure
increment.
While Bleeding Mud From The Annulus
Bottomhole Pressure = Hydrostatic Pressure + Surface Pressure
(Goes Down)
(Goes Down)
(Stays the Same)
Each time the mud is bled from the annulus, the gas bubble expands to fill the volume vacated
by the mud. As the gas bubble expands, the pressure in the bubble decreases according to
Boyle's Law.
Rev 12/94
I-5
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Step Four - Wait for the Casing Pressure to Rise as the Gas Bubb le Migrates
Each volume of mud bled from the annulus reduces the bottomhole pressure by the amount of
the pressure increment. This decreases the safety factor overbalance. In order to get the full
value of overbalance back on the well, we simply wait for the gas bubble to migrate up the
annulus. As the gas bubble migrates, both surface pressure and bottomhole pressure increase
(just as when the safety factor was applied). We wait for the gas bubble to rise until the surface
casing pressure has increased by an amount equal to the pressure increment. At this point,
bottomhole pressure has also increased by the amount of the pressure increment, and the well
is back at full overbalance.
Step Five - Hold Casing Pressure Constant By Bleeding Mud From The Annulus
Once full overbalance returns to the well, the casing pressure can again be held constant by
bleeding mud from the annulus. As with the first bleed step, this has to stop when the mud
increment has been bled from the well. This reduces the bottomhole pressure by the amount
of the pressure increment because a like amount of mud hydrostatic pressure has been bled
from the well. This has also caused the gas bubble to expand by the volume of the mud
increment.
Step Six - Wait for Casing Pressure to Increase as the Gas Bubb le Migrates
After the bleed step, again we wait for the gas bubble to migrate with the well shut-in in order
to raise the bottom- hole pressure back to its full overbalanced condition. We know when this
has occurred because the casing pressure will have risen by the amount of the pressure
increment.
Step Seven - Alternate Holding Casing Pressure Constant and Letting It Rise
The remainder of the Volumetric Control procedure is simply a succession of holding casing
pressure constant and letting it rise, holding casing pressure constant and letting it rise, holding
casing pressure constant and letting it rise, until the gas has finally migrated all the way to the
surface. Each time the casing pressure is held constant and mud is bled, the bottomhole
pressure falls and each time the casing pressure is allowed to rise as the bubble migrates, the
bottomhole pressure rises. During each bleed step, the gas bubble expands and lowers the
pressure in the bubble. By the time the gas reaches the surface, it has expanded to many times
its original volume so its pressure is greatly reduced.
Step Eight - Lubricate Mud Into The Well
The casing pressure should stop increasing after the gas has reached the surface. The well is
stable at this point, but in most cases it's essential to bleed the gas from the well and replace
it with mud before attempting further well work. This step involves bleeding gas from the well
to reduce the casing pressure by a predetermined increment. Then, a measured volume of mud
should be pumped into the well to increase the hydrostatic pressure in the annulus by the amount
of surface pressure which was lost when the gas was first bled off. These steps should be
repeated until gas can no longer be bled from the well.
Rev 12/94
I-6
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
4. LUBRICATE & BLEED
Sometimes during major well control situations, there comes a time when gas is at surface and it is
not possible to circulate (as could easily be the case during a Volumetric Control procedure. This is
the point in time that the surface pressure is the highest due to decreased hydrostatic in the well. When
this occurs, the best way to remove the gas is by circulating. However, when circulation is not possible
the well has to be “lubricated and bled”. The theory involved in lubricating and bleeding is the same
as that for Volumetric Control but in reverse. Surface pressure is replaced with hydrostatic pressure
by pumping mud into the well on top of the gas. The gas and mud are allowed to change places in
the hole and some of the surface pressure is bled off. The lubricate and bleed procedure is listed in
the following steps.
Step One - Calculate
Calculate the hydrostatic pressure that will be exerted by 1 barrel of mud.
Step Two - Lubricate
Slowly pump a given volume of mud into the well. The amount chosen will depend on many
different well conditions & may change throughout the procedure. The rise in surface pressure
can be calculated by applying Boyle's law of P1V 1 = P 2V2 and realizing that for every barrel of
mud pumped into the well the bubble size decreases by 1 barrel.
Step Three - Wait
Allow the gas to migrate back to the surface. This step could take quite some time and is
dependent on a number of factors such as mud weight and viscosity.
Step Four - Bleed
Bleed gas from the well until the surface pressure is reduced by an amount equal to the
hydrostatic pressure of the mud pumped in. It is very important to bleed only gas. If at any time
during the procedure mud reaches the surface and starts bleeding, the well should be
shut in and the gasallowed to migrate.
Step Five - Repeat Previous Steps
Repeat steps 2 through 4 until all of the gas has been bled off or a desired surface pressure has
been reached.
5. VOLUMETRIC CONTROL EXAMPLE
"JJ" Flash, the Chevron Drilling Representative, was glad he had been to Well Control School last
week on his days off because he needed to use what he had learned now. Kicks were common while
drilling through "The Trend," but this one had just turned ugly. Just moments after he started pumping
using the Engineer's Method, something had plugged him off at the bit. He noticed one of the
roustabouts searching for a glove out by the pipe racks and knew he would have to use Volumetric
Control. JJ gathered up the following information and jotted it down in his tally book:
Rev 12/94
I-7
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
Hole Size: 8-1/2"
Drill Pipe: 5" X.H.
Ann. Cap. Factor: 0.0459 bbl/ft
TD:14,400' MD/TVD
Shoe Test:16.8 ppg EMW
Kick Size: 24 bbl
Mud Weight: 15.2 ppg
SICP: 640 psi
SIDP: 520 psi
Casing Shoe: 12,220' MD/TVD
JJ knew that he had to determine the safety factor, pressure increment, and mud increment. But, he
knew he had to check the shoe pressures first. Under shut-in conditions, he calculated the shoe
pressure as:
Shoe Pressure = (TVD shoe x Mud Weight x 0.052) + SICP
or,
= (12220' x 15.2 ppg x 0.052) + 640 psi = 10298 psi
He knew the shoe would break down at a pressure of,
Shoe Fracture Pressure = (TVDshoe x Shoe Test x 0.052)
= (12220 x 16.8 ppg x 0.052) = 10675 psi
JJ saw that the casing pressure could rise another 377 psi (10675 psi - 10298 psi = 377 psi) before
breaking the shoe down, so he decided on a safety factor of 200 psi.
The pressure increment was quickly calculated by dividing the safety factor by 3:
200 psi
Pressure Increment = ------------ = 67 psi, or 70 psi
3
JJ then had to calculate the mud increment, or the volume of mud to generate 70 psi of hydrostatic
pressure in the annulus.
PI x ACF 70 x 0.0459
Mud Increment = -------------------- = ------------------- = 4.0 bbls
MW x 0.052 15.2 x 0.052
He then knew that for every 4.0 bbls of mud that was bled from the annulus, the hydrostatic pressure
would be reduced by 70 psi. With these calculations completed, he was ready to proceed.
JJ had a Roughneck bring a chair up to the rig floor because he knew that the operation was going
to take a long time. He then told the Rig Welder to weld a bead in a small tank at the 4.0 barrel mark
up from the bottom. JJ had determined that he would use the small tank to measure the mud volume
which was bled from the well. JJ sat and waited for the casing pressure to rise.
In less than an hour, the casing pressure rose 200 psi, from the initial shut-in value of 640 psi to 840
psi. JJ knew that the this was as far as he was going to let it rise.
The choke manifold was lined up to bleed directly into the small tank through the blooey line out near
the reserve pit. He had a Roughneck with a walkie-talkie out there to measure the volume. As the
Rev 12/94
I-8
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
pressure tried to creep up above 840 psi, JJ cracked the choke and bled-off the first little bit of mud from
the annulus; the drop on the casing pressure gauge was imperceptible. He bled a little more mud and
the casing pressure gauge dropped back to 840 psi. JJ closed the choke. He continued prevent the
casing pressure from rising above 840 psi by bleeding mud in small increments. Over two hours later,
the Roughneck finally had 4.0 bbls in the small tank.
JJ knew that he had lowered the bottomhole pressure by 70 psi as he had bled the 4.0 bbls from the
annulus, so he waited while the gas bubble migrated up the hole and watched as the casing pressure
gauge rose 70 psi to 910 psi (840 psi + 70 psi = 910 psi).
Now that he had his full 200 psi of bottomhole overbalance back on the well, it was time to hold the casing
pressure constant again. He kept the casing pressure from rising above 910 psi until he had bled another
4.0 barrels of mud from the annulus. It took a long time to accumulate this 4.0 barrels of mud but not
as long as the first 4.0 barrels.
For the next seven hours, JJ held the casing pressure constant until he had bled 4.0 bbls of mud and
then let it rise to replace the lost 70 psi, then held casing pressure constant and then let it rise, and then
held it constant and let it rise again for a total of fourteen steps. The fifteenth time he was holding casing
pressure constant (at 1820 psi) JJ started getting gas through the choke. He stopped bleeding and
checked to make sure the pipe rams weren't leaking. Everything was in order and he felt fine. Just then
the perforating truck pulled up to the location to shoot some holes in the drill collars. He'd be circulating
within the hour.
Figure 1.1 Volumetric Control Example Pressures
12200
12100
12000
11900
Migrate
Bleed
1180 0
0
4
8
12 16 20 24 28 32 36 40 44 48 52 56 60
1400
1000
Migrate
Bleed
600
0
4
8
12 16 20 24 28 32 36 40 44 48 52 56 60
Rev 12/94
I-9
CHEVRON DRILLING REFERENCE SERIES
VOLUME ELEVEN
WELL CONTROL AND BLOWOUT PREVENTION
A plot of JJ's Volumetric Control procedure is shown in Figure I.1. Each time he held the casing
pressure constant, the bottomhole pressure decreased, and on each time he let the casing pressure
rise the bottomhole pressure increased. The gas bubble volume increased by 4.0 bbls each time he
held casing pressure constant by bleeding mud and it rose from its initial volume of 24 bbls to 84 bbls
when it finally reached the surface (24 bbl kick + 60 bbls bled = 84 bbls).
6. OTHER CONSIDERATIONS
Annulus Capacity Factor: The annulus capacity factor, which is used to determine the mud
increment, should be taken at the top of the gas bubble. Note that the annulus capacity factor may
change as the gas bubble migrates up the hole if a tapered drillstring is in use or a drilling liner is
installed in the well. If the bubble migrates into a smaller annular space, then less mud needs to be
bled from the annulus to produce the same hydrostatic pressure reduction. In these instances, the
rate of rise of the gas bubble should be calculated to help in predicting when the new annulus capacity
factor should be used. This rate of rise of the gas bubble can be estimated with the formula below:
Rate of Gas Bubble Rise
∆ SICP
Eqn I.2 ROR =
-------------------------
MW x 0.052 x∆T
where:
ROR = Rate of Rise (ft/min)
∆ SICP = Change in Shut-in Casing Pressure
MW = Mud Weight (ppg)
∆T = Time from end of last bleed to start of next bleed (min)
If an accurate time log is kept of the Volumetric Control procedure, then the rate of rise can be
calculated each time the casing pressure is allowed to rise. Remember, however, that the gas bubble
will continue to rise when the casing pressure is being held constant.
Directional Wells: Bubble migration rates will be higher and the bubble will tend to spread out more.
Similarity to Driller's Method: In essence, the Volumetric Control procedure is identical to the first
circulation of the Driller's Method, except that no pumps are used. With volumetric control, the influx
is allowed to migrate out of the hole rather than being circulated out of the hole. Once the influx is
removed and mud is lubricated into the annulus, the well should be in the same state that it would
have been if the first circulation of Driller's Method had been completed, except that the casing
pressure may be higher due to the additional safety factor applied to the well.
Casing Pressure Continues to Rise With Gas at the Surface: This may occur if the gas bubble
is strung-out. Since gas contributes very little to the hydrostatic pressure of the fluids in the well, it
can usually be bled from the well without causing much of a pressure reduction at the bottom of the
hole. Therefore, if gas reaches the surface and the casing pressure continues to rise, the Drilling
Representative should keep the casing pressure from rising by bleeding gas from the well, until the
casing pressure is no longer trying to rise.