Week 8 Network Scheduling

download Week 8 Network Scheduling

of 60

Transcript of Week 8 Network Scheduling

  • 8/13/2019 Week 8 Network Scheduling

    1/60

    Network Scheduling

  • 8/13/2019 Week 8 Network Scheduling

    2/60

    Some Definitions

    Network: A diagram which shows the inter-relation ship and inter-dependency.

    Activity: The performance of a task/work package/operation is known

    ac

    tivity. Activity consumes time and other resources.

    Event: An event shows the start or completion of activities and doesnot consume time or any other resource. It is indicated in network by anumber enclosed in circle, square or triangle. It is also known as Nodeor Connector 

    Dummy Activities: It is an artificial activity shown by a dotted line in anetwork.

    It does not consume time.

    It is used to maintain logical sequence.

    1

    3

    2 4

    5

     A

    B

    C

    D

    Dummy Activity

  • 8/13/2019 Week 8 Network Scheduling

    3/60

    Network Techniques Fundamental concept of a net work based planning and scheduling

    is that the net work represents a time- oriented model of a system.

    Net work planning and scheduling has immense scope in assisting

    completion of complex civil engineering projects in time and within

    reasonable cost.

    There are two types of Net work used in most

    • Activity-on-Arrow (A-O-A) Type or Arrow diagramming.

     Activity shown by arrow and event shown by number in a geometrical

    figure like circle

    • Activity-on-node (A-O-N) Type or Precedence diagram.

     Activity shown by boxes or circle and arrow represents inter-

    relationship between activities

  • 8/13/2019 Week 8 Network Scheduling

    4/60

     AOA Project Network for House

    3 2 01

    3

    1 1

    11 2 4 6 7

    3

    5

    Lay

    foundation

    Design house

    and obtain

    financing

    Order and

    receive

    materials

    Dummy

    Finish

    work 

    Select

    carpet

    Select

    paint

    Build

    house

    AON Project Network for House

    13

    2

    2

    43

    31 5

    1

    61

    71Start

    Design house and

    obtain financing

    Order and receivematerials

    Select paint

    Select carpet

    Lay foundations Build house

    Finish work 

  • 8/13/2019 Week 8 Network Scheduling

    5/60

    Situations in network diagram

    AB

    C

    A must finish before either B or C can start

    A

    B

    C  both A and B must finish before C can start

    D

    C

    B

    A both A and C must finish before either of B

    or D can start

    A

    C

    B

    D

    Dummy

    A must finish before B can start

     both A and C must finish before D can start

  • 8/13/2019 Week 8 Network Scheduling

    6/60

    Network Examples

    1. A Precedes B and B Precedes C

    1 20

     A B

    3

    C

    B C A

    2. A Precedes both B and C

    1

    2

    0 A B

    3

    C

    B

    C

     A

    1

    2

    0 A

    B3C

    3. A and B Precede C

    B

    C

     A

  • 8/13/2019 Week 8 Network Scheduling

    7/60

    1 2C

    4. A Precedes C and B Precedes D

    4 5D

     A C

    B D

    0  A

    3 B

    5. A Precede C and D; B Precede D

    2 31 A C

    4D B

    D

     A

    21B

    C

    2

    0

    1 A

    B

    4

    3C

    D

    6. A Precedes B and C; B and C Precede D

    B

    D

     A

    C2

    0 1 A

    B

    43

    C D

  • 8/13/2019 Week 8 Network Scheduling

    8/60

    7. A project consist of 5 activities (A, B, C, D, E, F):

    A (2 days), preceding B and C B (4 days), preceding D and E

    C (5 days), preceding E D (6 days), preceding F

    E (2 days), preceding F F (8 days)

    2

    0 1 A

    B

    4

    3

    C

    D

    2

    4

    5

    6

    2

    8E

    F5

    B

    4

    E

    2

    C

    5

    D

    6

     A

    2

    F8

  • 8/13/2019 Week 8 Network Scheduling

    9/60

    Construction of Concrete Footing

    1. Foundation Chain

     A. Lay out of foundation

    B. Dig foundation

    C. Place formwork

    G. Place steel reinforcementD. Place concrete

    2. Steel Chain

    E. Lay out of foundation

    F. Dig foundation

    G. Place steel reinforcement

    D. Place concrete

    3. Concrete Chain

    H. Obtain Concrete

    D. Place concrete

     A B C G D

    E F G D

    H D      S      T      A      R      T

          F      I      N      I      S      H

    S E

     A B C

    G DF

    H

    F

    0 2

    1 3

    4

    5 6

     A

    B C

    EF

    H

    D

    G

  • 8/13/2019 Week 8 Network Scheduling

    10/60

    Network Schedule Analysis

    • Objectives:

    1. Find the critical set of activities that establishes the longest pathand defines the minimum duration of the project.

    2. Calculate the early start times for each activity.

    3. Calculate the late start times for each activity.

    4. Calculate the float, or time, available for delay for each activity.

  • 8/13/2019 Week 8 Network Scheduling

    11/60

    • Path

    • A connected sequence of activities leading from thestarting event to the ending event

    • Critical Path• The longest path (time); determines the project duration

    • Critical Activities

    • All of the activities that make up the critical path

    • Cannot be delayed without extending the projectduration.

    • Float associated with a critical activity is zero.

    • Critical activities lie along the longest path through thenetwork.

    S E

     A B C

    G DF

    H

    F

  • 8/13/2019 Week 8 Network Scheduling

    12/60

    Logical Relationships

    There are four types of logical relationship between activities:

    Start to Start (SS)

    This means activity starts at same time when predecessor activity starts.In figure Activity B has SS relation with activity A

    Finish to Start (SF)

    This mean activity start when predecessor activity is finished.

    In figure Activity C has FS relation with activity B

    Start to Finish (SF)This means B finishes with start of Activity A

    In figure Activity C can start only after activity D is finished

    Finish to Finish (FF)

    This means activity finishes together at same time with predecessor activity

    In figure Activity E has FF relation with activity B

    Activity

    A

    Activity

    B

    Activity

    C

    Activity

    D

    Activity

    E

    Activity

    C

  • 8/13/2019 Week 8 Network Scheduling

    13/60

    Forward Pass

    • Earliest Start Time (ES)

    • earliest time an activity can start

    • ES = maximum EF of immediate predecessors

    • Earliest finish time (EF)

    • earliest time an activity can finish

    • earliest start time plus activity time

    Backward Pass

    Latest Start Time (LS)

    Latest time an activity can start without delaying

    critical path timeLatest finish time (LF)

    latest time an activity can be completed without

    delaying critical path time

    LS = minimum LS of immediate predecessors

    EFT(I) = EST(I) + DUR(I)

    LST(J) = LFT(J) - DUR(J)

  • 8/13/2019 Week 8 Network Scheduling

    14/60

    • Float

    •  Amount of duration by which activity can be delayed without affecting project

    completion.

  • 8/13/2019 Week 8 Network Scheduling

    15/60

  • 8/13/2019 Week 8 Network Scheduling

    16/60

    Example on Activity-on-Node (A-O-N) or Precedence Diagram MethodA project consist of activities (A, B, C, D, E, F):

    A (20 days), preceding B and C B (40 days), preceding D and E

    C (50 days), preceding D and E D (60 days), preceding F

    E (20 days), preceding F F (80 days)

    B

    40

    E

    20

    C

    50

    D

    60

     A

    20

    F

    80

    0 20

    0 20 20 70

    20 70

    20 60

    30 70

    70 130

    70 130

    70 90

    110 130

    130 210

    130 210

     Activity A

    B

    C

    D

    EF

    Total Float (LF-EF)20  – 20 = 0

    70  – 60 = 10

    70  – 70 = 0

    130  – 130 = 0

    130 –

    90 = 40210  – 210 = 0

    FF (ESsucc -EF)20  – 20 = 0

    70  – 60 = 0

    70  – 70 = 0

    130  – 130 = 0

    130 –

    90 = 40210  – 210 = 0

    Interfering F (TF-FF)0  – 0 = 0

    10  – 10 = 0

    0  – 0 = 0

    0  – 0 = 0

    40 –

    40 = 00  – 0 = 0

  • 8/13/2019 Week 8 Network Scheduling

    17/60

    ACTIVITY DURATION(DAY) PREDECESSOR

     A 3 -

    B 5 A

    C 3 B

    D 4 -

    E 4 A

    F 10 E,D

    G 9 C,F

    Example 1 on Activity-on-Arrow (A-O-A)

  • 8/13/2019 Week 8 Network Scheduling

    18/60

    ACTIVITY DURATION(DAY) PREDECESSOR

    A 3 -

    B 5 A

    C 3 BD 4 -

    E 4 A

    F 10 E,D

    G 9 C,F

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G3

    5

    3

    4 10

    4

    9

  • 8/13/2019 Week 8 Network Scheduling

    19/60

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G

    3

    5

    3

    4 10

    4

    9

    Early Start Box

    Late Start Box Make forward pass through the network by adding durationtimes.

    0

    Forward Pass

  • 8/13/2019 Week 8 Network Scheduling

    20/60

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G3

    5

    3

    4 10

    4

    9

    0

    0+3=3

    38

    If two or more activities terminate at a junction node, place the larger sum at ES box.

    3+4=7

    Larger=7

    7

  • 8/13/2019 Week 8 Network Scheduling

    21/60

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G3

    5

    3

    4 10

    4

    9

    0

    38

    7

    8+3=11

    7+10=17

    17 26

    Early Start of 26 in the node 6 shows that it will take 26 days to complete the project.

    Therefore, 26 days represents Late Finish of the project.

  • 8/13/2019 Week 8 Network Scheduling

    22/60

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G3

    5

    3

    4 10

    4

    9

    0

    38

    7

    17

    Enter 26 into Late Finish box at the node 6, and make a backward pass toestablish LF for each activity by deducting the durations.

    26-9=17

    17

    14

    26

    26

    Backward Pass

  • 8/13/2019 Week 8 Network Scheduling

    23/60

    In the case of junction nodes (with two or more activities),

    place the smaller value in the LF box of that node.

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G

    3

    5

    3

    4 10

    4

    9

    0

    38

    7

    17 26

    2617

    14

    7

    14-5=9

    7-4=3

    3Smaller=3

    0

  • 8/13/2019 Week 8 Network Scheduling

    24/60

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G

    3

    5

    3

    410

    4

    9

    0

    38

    7

    17 26

    2617

    14

    7

    3

    0

  • 8/13/2019 Week 8 Network Scheduling

    25/60

    Total Float (TF) =LF-D-ES

    1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G3

    5

    3

    4 10

    4

    9

    0

    3 8

    7

    17 26

    2617

    14

    7

    3

    0

    TFA = LF-D-ES

    = 3-3-0

    = 0

    TFA=0

    TFB=6

    TFC=6

    TFD=3

    TFE=0

    TFF=0

    TFG=0

  • 8/13/2019 Week 8 Network Scheduling

    26/60

    AKTIVITY DURATION (DAY) PREDECESSOR

    START 0 -

     A 6 START

    B 5 START

    C 4 START

    D 5 A

    E 4 B

    F (DUMMY) 0 C

    G 7 C

    H 2 D

    I 3 D

    J 5 E,F

    K 4 G

    L 5 I,J,K

    M 2 H

    FINISH 0 M,L

    Example 2 on Activity-on-Arrow (A-O-A)

  • 8/13/2019 Week 8 Network Scheduling

    27/60

    1

    2 7 8

    3 6 9 10

    4 5

     A

    6

    B5

    C

    4

    E

    4

    5

    D

    I

    H

    2

    J

    5

    L

    2M

    G

    7

    K4

    F

    0

    5

    3

  • 8/13/2019 Week 8 Network Scheduling

    28/60

    1

    2 7 8

    3 6 9 10

    4 5

     A

    6

    B5

    C

    4

    E

    4

    5

    D

    I

    H

    2

    J

    5

    L

    2M

    G

    7

    K4

    F

    0

    5

    3

    0

    6 11

    5

    4

    9

    13

    15

    11

    20

    FORWARD PASS

  • 8/13/2019 Week 8 Network Scheduling

    29/60

    1

    2 7 8

    3 6 9 10

    4 5

     A

    6

    B5

    C

    4

    E

    4

    5

    D

    I

    H

    2

    J

    5

    L

    2M

    G

    7

    K4

    F

    0

    5

    3

    0

    6 11

    5

    4

    9

    13

    15

    11

    20

    0

    7 12

    6

    4

    10

    18

    15

    11

    20

    BACKWARD PASS

  • 8/13/2019 Week 8 Network Scheduling

    30/60

    1

    2 7 8

    3 6 9 10

    4 5

     A

    6

    B5

    C4

    E

    4

    5

    D

    I

    H

    2

    J

    5

    L

    2M

    G

    7

    K4

    F

    0

    5

    30 0

    6 7 11 12

    5 6

    4 4

    9 10

    13 18

    15 15

    11 11

    2020

    Chapter 6 - Project Planning and Scheduling

    Total Float (TF) =LF-D-ES

    TFA = LF-D-ES

    = 7-6-0

    = 1

    TFA=1

    TFB=1

    TFC = LF-D-ES

    = 4-4-0

    = 0

    TFC=0

  • 8/13/2019 Week 8 Network Scheduling

    31/60

    1

    2 7 8

    3 6 9 10

    4 5

     A

    6

    B5

    C4

    E

    4

    5

    D

    I

    H

    2

    J

    5

    L

    2M

    G

    7

    K4

    F

    0

    5

    30 0

    6 7 11 12

    5 6

    4 4

    9 10

    13 18

    15 15

    11 11

    2020

    FFA = EF-D-ES

    = 6-6-0

    = 0

    FFA=0

    Free Float (FF) =EF-D-ES

    FFC = EF-D-ES

    = 4-4-0

    = 0

    FFC=0

  • 8/13/2019 Week 8 Network Scheduling

    32/60

    TOTAL FLOAT (TF) = LF  – ES - D

    TF H = 18 –

    11 - 2= 5

    FREE FLOAT (FF) = EF  – ES - D

    FF H = 13  – 11 - 2

    = 0

     ACTIVITY H

    TOTAL FLOAT (TF) = LF  – ES - D

    TFI

    = 15 – 11 - 3

    = 1

    FREE FLOAT (FF) = EF  – ES - D

    FF I = 15  – 11 - 3

    = 1

     ACTIVITY I

  • 8/13/2019 Week 8 Network Scheduling

    33/60

    ACTIVITY DURATION ES EF LS LF FF TF

    START 0

     A 6

    B 5

    C 4

    D 5

    E 4

    F 0

    G 7

    H 2

    I 3

    J 5

    K 4

    L 5

    M 2

    FINISH 0

  • 8/13/2019 Week 8 Network Scheduling

    34/60

    Example 3 on Activity-on-Arrow (A-O-A)

    • Estimate the total project duration.

    • Calculate the total float for each activity in the project

    • Draw the bar chart according to your calculation

     Activity Successor Duration

    (week)

     A B, C 2

    B D 3

    C E 2

    D F 4

    E G 5

    F H 2

    G H 3

    H - 1

  • 8/13/2019 Week 8 Network Scheduling

    35/60

    Solution

     A1 2

    2

    3

    4

    5

    6

    8 9

    B

    C

    D

    E

    F

    G

    H3

    2

    4

    5

    2

    3

    1

    7

  • 8/13/2019 Week 8 Network Scheduling

    36/60

    Solution

    Total Project Duration = 13 weeks

     A1

    0

    02

    2

    22

    35

    6

    44

    4

    59

    10

    69

    9

    71

    21

    2

    813

    13

    B

    C

    D

    E

    F

    G

    H3

    2

    4

    5

    2

    3

    1

    12,112,3

  • 8/13/2019 Week 8 Network Scheduling

    37/60

    Solution

    Critical Path : A  C  E  G  H

    Event Activity

    Duratio

    n ES LS EF LF Total Float

    (1) (2) (3) (4) (5) (6) (7) (8) = 7-3-4

    1 - 2 A 2 0 0 2 2 0

    2 - 3 B 3 2 2 5 6 1

    2 - 4 C 2 2 2 4 4 0

    3 - 5 D 4 5 6 9 10 1

    4 - 6 E 3 4 4 9 9 0

    5 - 7 F 2 9 10 12 12 1

    6 - 7 G 3 9 9 12 12 0

    7 - 8 H 1 12 12 13 13 0

  • 8/13/2019 Week 8 Network Scheduling

    38/60

    SolutionNo Activity week

    1 2 3 4 5 6 7 8 9 10 11 12

    1  A

    2 B

    3 C

    4 D

    5 E

    6 F

    7 G

    8 H

    13

  • 8/13/2019 Week 8 Network Scheduling

    39/60

    Example 4 on Activity-on-Arrow (A-O-

     A)

     Activity predecessor Duration

    (week)

     A - 2

    B - 1

    C - 3

    D A 1

    E B 3

    F C 2

    G D 4

    H D, E 1

    I D, E, F 2

    J G 1

    K H 2

    L I 3

    • Estimate the total project

    duration.

    • Calculate the total float foreach activity in the project

    • Draw the bar chart according

    to your calculation

  • 8/13/2019 Week 8 Network Scheduling

    40/60

    Solution

    Total Project Duration = 10 weeks

     A

    B

    C

    D

    E

    F

    G

    L

    K

    3

    2

    2

    3

    41

    2

    0

    0

    2

    4

    1

    2

    3

    3

    3

    5

    7

    9

    5

    8

    5

    5

    10

    10

    3

    1

    4

    5

    7

    7

    I

    2

    H

    1

    3

    3

    J

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

  • 8/13/2019 Week 8 Network Scheduling

    41/60

    Solution

    1. Total Project Duration = 12 weeks

    No Activity Total Floatweek

    1 2 3 4 5 6 7 8 9 10

    1 A 2

    2 B 1

    3 C 0

    4 D 2

    5 E 1

    6 F 0

    7 G 2

    8 H 3

    9 I 0

    10 J 2

    11 K 3

    12 L 0

  • 8/13/2019 Week 8 Network Scheduling

    42/60

    Lag : A period of no activity that mustelapse between two events.

    Lag (+ve)

    Lead (-ve)

    Waiting

    period

  • 8/13/2019 Week 8 Network Scheduling

    43/60

    ACTIVITY DURATION(DAY) PREDECESSOR

     A 2 START

    B 6 A

    C 6 B

    D 1 B

    E 3 A

    F 3 D,E

    G 2 C(+2) ,F

    EXAMPLE 01

  • 8/13/2019 Week 8 Network Scheduling

    44/60

    A

    2

    B

    6

    C

    6

    D

    1

    E

    3

    F3

    G

    2FS +2

  • 8/13/2019 Week 8 Network Scheduling

    45/60

    A

    20 2

    B

    62 8

    C

    68 14

    D

    18 9

    E

    32 5

    F39 12

    G

    216 18

    16,12

    FS +2

    5,9

    FORWARD PASS

  • 8/13/2019 Week 8 Network Scheduling

    46/60

    A

    20 2

    B

    62 8

    C

    68 14

    D

    18 9

    E

    32 5

    F39 12

    G

    216 18

    16,12

    FS +2

    5,9

    0 2 2 8 8 14

    12 13

    1816

    1613

    1310

    8,122,10

    BACKWARD PASS

  • 8/13/2019 Week 8 Network Scheduling

    47/60

    A

    20 2

    0 2

    B

    62 8

    2 8

    C

    68 14

    8 14

    D

    18 9

    12 13

    E

    32 5

    F

    39 12

    G216 18

    16,12

    FS +2

    5,9

    1816

    1613

    1310

    8,122,10

    COMPLETED

  • 8/13/2019 Week 8 Network Scheduling

    48/60

    A

    20 2

    0 2

    B

    62 8

    2 8

    C

    68 14

    8 14

    D

    18 9

    12 13

    E

    32 5

    F

    39 12

    G216 18FS +2

    1816

    1613

    1310

    TOTAL FLOAT

    TFA = LF-EF

    =2-2

    =0

    TFB = LF-EF

    =8-8

    =0

    TFC = LF-EF

    =14-14

    =0

    TFD = LF-EF

    =13-9

    =4

    TFE = LF-EF

    =13-5

    =8

    TFG = LF-EF

    =18-18

    =0

    TFF = LF-EF

    =16-12=4

    00

    4

    8

    0

    4

    0

    Total Float (TF) =LF-D-ES

    =LF-EF

  • 8/13/2019 Week 8 Network Scheduling

    49/60

    A

    20 2

    0 2

    B

    62 8

    2 8

    C

    68 14

    8 14

    D

    18 9

    12 13

    E

    32 5

    F

    39 12

    G216 18FS +2

    1816

    1613

    1310

    FREE FLOAT

    FFA = ESSUCC-EF-

    Lag

    =2-2-0

    =0

    00

    4

    8

    0

    4

    0

    FFB = ESSUCC-EF-

    Lag

    =8-8-0

    =0

    FFC = ESSUCC-EF-

    Lag

    =16-14-2

    =0

    FFD

    = ESSUCC

    -EF-

    Lag

    =9-9-0

    =0

    FFF = ESSUCC-EF-

    Lag

    =16-12-0

    =4

    FFA = ESSUCC-

    EF- Lag

    =18-18-

    0

    =0

  • 8/13/2019 Week 8 Network Scheduling

    50/60

    A

    20 2

    0 2

    B

    62 8

    2 8

    C

    68 14

    8 14

    D

    18 9

    12 13

    E

    32 5

    F

    39 12

    G216 18

    16,12

    FS +2

    5,9

    1816

    1613

    1310

    8,122,10

    CRITICAL PATH

    00

    4

    8

    0

    4

    0

    Activities on critical path : A,B,C and G.

  • 8/13/2019 Week 8 Network Scheduling

    51/60

    Activity

    ATFA = LF- EF

    = 2  – 2

    = 0

    FFA = ESsucc - EF – Lag

    = 2  – 2  – 0

    = 0

    Activity

    BTFB = LF- EF

    = 8  – 8

    = 0

    FFB = ESsucc - EF – Lag

    = 8  – 8  – 0

    = 0

  • 8/13/2019 Week 8 Network Scheduling

    52/60

    Activity

    CTFC = LF- EF

    = 14  – 14

    = 0

    FFC = ESsucc - EF – Lag

    = 16  – 14  – 2

    = 0

    Activity

    DTFD = LF- EF

    = 13  – 9

    = 4

    FFD = ESsucc - EF – Lag

    = 9  – 9  – 0

    = 0

  • 8/13/2019 Week 8 Network Scheduling

    53/60

    Activity

    ETFE = LF- EF

    = 13  – 5

    = 8

    FFE = ESsucc - EF – Lag

    = 9  – 5  – 0

    = 4

    Activity F

    TFF = LF- EF

    = 16  – 12

    = 4

    FFF = ESsucc - EF – Lag

    = 16  – 12  – 0

    = 4

  • 8/13/2019 Week 8 Network Scheduling

    54/60

    Activity

    GTFG = LF- EF

    = 18  – 18

    = 0

    FFG = ESsucc - EF – Lag

    = 18  – 18  – 0

    = 0

  • 8/13/2019 Week 8 Network Scheduling

    55/60

  • 8/13/2019 Week 8 Network Scheduling

    56/60

    SOLUTION

    Total Project Duration = 6 weeks

    B

    2

    2

    4

    4

    2

    D

    1

    1

    2

    2

    1

    L = 0

    L = 1E

    2

    2

    3

    3

    1

    C

    5

    5

    6

    6

    1L = 1

    L = 0 L = 2

    A

    0

    0

    2

    2

    2

    0 0 0

    0 0

    Note

    Total Float (TF):

    Critical Path :

    Tf 

  • 8/13/2019 Week 8 Network Scheduling

    57/60

    No Activity week

    1 2 3 4 5 6

    1  A

    2 B

    3 C

    4 D

    5 E

    L=1

    L=1

    L=2

  • 8/13/2019 Week 8 Network Scheduling

    58/60

    Example 3

    No Activity Duration Relationship Lag

    (week) (week)

    1 A 3 A-B (S-S) 5

     A-C (F-S) 2

    2 B 1 B-D (F-S) 3

    3 C 2 C-D (F-S) -

    4 D 2 D-E (F-F) -

    5 E 3 - -

    1. Estimate the total project duration.

    2. Calculate the total float for each activity in the project

    3. Draw the bar chart according to your calculation

  • 8/13/2019 Week 8 Network Scheduling

    59/60

    Total Project Duration = 11 weeks

    C

    5

    7

    7

    9

    2

    B

    5

    5

    6

    6

    1

    L = 2

    L = 5D

    9

    9

    1

    1

    1

    1

    2

    E

    8

    8

    11

    11

    3

    L = 3L = 2

    A

    0

    0

    3

    5

    3

    2 2 0

    0 0

    Note

    Total Float (TF):

    Critical Path :

    Tf 

    Activities on critical path : B, D, and E

  • 8/13/2019 Week 8 Network Scheduling

    60/60