Warrington Western Link · Management Case/WL-MMD-07-XX-RP-U-1005 - ... 7.1 Introduction 48 7.2...
Transcript of Warrington Western Link · Management Case/WL-MMD-07-XX-RP-U-1005 - ... 7.1 Introduction 48 7.2...
xx xx xx https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business
Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Mott MacDonald
Mott MacDonald Ground floor Royal Liver Building Pier Head Liverpool L3 1JH United Kingdom T +44 (0)151 482 9910 F +44 (0)151 236 2985 mottmac.com
Warrington Western Link
Management Case
December 2017
Mott MacDonald Limited. Registered in England and Wales no. 1243967. Registered office: Mott MacDonald House, 8-10 Sydenham Road, Croydon CR0 2EE, United Kingdom
v
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Issue and Revision Record
Revision Date Originator Checker Approver Description
S2.0 11/10/2017 James Bottomley /Jamie Birtles/John Hughes
Heather Kenyon
Chris Hardwick First draft for internal review
S2.1 25/10/17 Jamie Birtles/John Hughes/Heather Kenyon/Lisa Thomas
Heather Kenyon/ John Hughes
Chris Hardwick Final draft for review
S2.2 03/11/17 Jamie Birtles/John Hughes/Heather Kenyon/Lisa Thomas
Heather Kenyon/ John Hughes
Chris Hardwick Issue for WBC Exec Board
S2.3 12/12/17 Jamie Birtles/John Hughes/Heather Kenyon/Lisa Thomas
Heather Kenyon/ John Hughes
Chris Hardwick Issue for DfT
Document reference: WL-MMD-07-XX-RP-U-1005
Information class: Standard
This document is issued for the party which commissioned it and for specific purposes connected with the above-
captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being
used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied
to us by other parties.
This document contains confidential information and proprietary intellectual property. It should not be shown to other
parties without consent from us and from the party which commissioned it.
This report has been pr epared sol el y for use by the party which commissi oned it (the ‘Client’) i n connecti on with the capti oned proj ect. It should not be used for any other purpose. N o person other than the Client or any party who has expressl y agreed ter ms of r eliance with us (the ‘Reci pient(s)’) may rel y on the content, i nformati on or any vi ews expressed i n the repor t. We accept no duty of care, responsi bility or liability to any other r eci pient of thi s document. This r eport is confi denti al and contains pr opri etar y intell ectual property.
No representati on, warranty or under taki ng, expr ess or i mplied, is made and no responsi bility or liability is accepted by us to any party other than the Cli ent or any Reci pient(s), as to the accuracy or completeness of the i nformati on contai ned i n this r eport. For the avoidance of doubt this r eport does not in any way purport to i nclude any legal , insur ance or fi nanci al advice or opi nion.
We disclai m all and any liability whether arising i n tort or contrac t or other wise which it might otherwise have to any party other than the Cli ent or the Reci pient(s), in r espect of this report , or any infor mation attri buted to i t.
We accept no r esponsibility for any error or omission i n the r eport which is due to an error or omission i n data, infor mation or statements supplied to us by other par ties incl udi ng the client (‘D ata’). We have not i ndependentl y verified such D ata and have assumed it to be accurate, complete, reli abl e and current as of the date of such infor mation.
Forecasts presented i n this document were pr epared usi ng Data and the report is dependent or based on D ata. Inevitabl y, some of the assumptions used to develop the for ecasts will not be realised and unantici pated events and circumstances ma y occur. C onsequentl y M ott MacDonal d does not guarantee or warr ant the concl usi ons contained i n the repor t as there are li kel y to be differ ences between the for ecas ts and the ac tual results and those di ffer ences may be material. Whil e we consi der tha t the infor mation and opini ons gi ven i n this r eport are sound all parti es must rel y on their own skill and j udgement when making use of it .
Under no circumstances may this report or any extr act or summar y ther eof be used in connection wi th any public or pri vate securities offering i ncluding any rel ated memorandum or prospectus for any securities offering or stock exchange listing or announcement.
vi
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Management Case Contents
Executive summary 9
1 Management case overview 24
1.1 Introduction 24
2 Evidence of similar projects 26
2.1 Warrington East Transport Strategy Phase 1: Birchwood Pinch Point 26
2.2 A49 Winwick Road / A50 Long Lane junction improvement scheme 27
2.3 Skyline Drive 28
2.4 Centre Park Link 28
2.5 Time Square Regeneration 29
2.6 Summary 30
3 Programme/Project dependencies 32
4 Governance 34
4.1 Project governance 34
34
4.1.1 Warrington Borough Council 34
4.1.2 Project Board 36
4.1.3 Project team 37
5 Assurance 40
5.1 Formal assurance and review points 40
5.2 Statutory Powers/Consent 40
5.3 Financial Management 41
5.4 Gateway Process 41
5.4.1 End of stage 3 gateway 42
5.4.2 End of stage 4A gateway 42
5.4.3 End of stage 4B gateway: 42
5.5 DfT Assurance 43
6 Delivery programme 44
7 Implementation of work packages 48
7.1 Introduction 48
7.2 Work Package 0 – Project Management, Governance, Review and Communications 49
7.3 Work Package 1 - Technical Design & Approvals 50
vii
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
7.4 Work Package 2 – Planning 51
7.5 Work Package 3 - Procurement 51
7.6 Work Package 4 - Land acquisition, Legal Advice and Public Inquiry 52
7.7 Work Package 5 - Business Case 52
7.8 Construction 52
7.9 Key issues for implementation 52
8 Risk management 54
8.1 Risk Management Strategy 54
8.2 Current Risk management 55
8.2.1 Project Risks 55
8.2.2 Project Management and Delivery Risks 56
9 Contract Management 58
10 Communication and stakeholder management 59
10.1 Introduction 59
10.2 Consultation objectives 59
10.3 Key stakeholders 59
10.4 Consultation 63
10.5 Public Consultation 63
10.5.1 First Round Consultation 63
10.5.2 Second Round Consultation 68
10.6 Future Consultation 72
11 Project reporting 74
11.1 Delivery reporting 74
11.1.1 Work Package Reporting 74
11.1.2 Project Reporting 74
11.1.3 Reporting beyond the project board 75
11.2 DfT Reporting 75
11.2.1 Regular reporting during the delivery programme 75
11.2.2 End of stage reporting 75
12 Benefits realisation 77
13 Monitoring and evaluation plan 85
13.1 Introduction 85
13.2 Monitoring and evaluation 85
13.3 Resourcing 87
13.4 Reporting 88
13.5 Evaluation 88
viii
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
14 Contingency Plan 94
9
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Executive summary
The Management Case assesses whether Western Link is deliverable. It tests project planning,
governance structure, risk management, communications and stakeholder management, benefits
realisation and project assurance. Additionally, it also showcases similar projects that have been
successfully delivered on time and within budget.
Proven delivery experience
Warrington Borough Council (WBC) has a history of successful delivery of projects of a similar
scope and scale, namely;
● Warrington East Transport Strategy Phase 1: Birchwood Pinch Point;
● A49 Winwick Road / A50 Long Lane junction improvement scheme;
● Skyline Drive;
● Centre Park Link (Currently being delivered); and
● Time Square (Currently being delivered).
These projects range in value from £2.4m-£101m and include corridor and junction based highway
improvements as well as entirely new link roads. Together they show a successful history of
highways schemes that have been delivered on time, to budget and have helped further the
attraction of working and living in Warrington. This substantially aligns with the objectives of the
Western Link scheme.
Time Square, whilst not a transportation project, shows the Council has a successful history of
dealing with similar issues that will be encountered in the delivery of Western Link such as, but not
limited to:
● Requirement to enact compulsory purchase powers to assemble the land for the project
● Requirement to progress through Land Inquiry (related to the above); and
● Major structural and civils engineering works.
Project and programme dependencies
Several dependencies have been identified that may potentially affect the delivery of Western Link;
they are noted together with the identified mitigation measures and contingency plans.
Table 1: Project and programme dependencies
Dependency Mitigation Contingency Plan
DfT approval of Western Link Scheme OBC
Prepare robust OBC, commission independent review and liaise with DfT over queries.
If unsuccessful WBC will halt the project at the end of stage 3 and seek funding in future rounds of local majors funding and other government funds.
DfT approval of the Western Link FBC
Prepare robust FBC, commission independent review and liaise with DfT over queries.
If unsuccessful WBC will halt the project at the end of stage 4 and seek funding in future rounds of local majors funding and seek other government funds.
Approval by the Council executive board to CPO and SUO
Hold advance discussion with executive board members to provide briefing on scheme development. Seek legal and land advice to ensure CPO is justified and appropriate.
Should the executive board note support a CPO, WBC will need to review the reasons for this and amend the scheme to address concerns. Efforts will be made to acquire property by negotiation prior to any CPO.
10
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Dependency Mitigation Contingency Plan
Procurement of a suitable D&B Contractor
Issue PQQ to identify and shortlist contactors. Review responses to ensure suitable shortlist is created.
Should the procurement not result in an appropriate contractor being identified, the council will need understand the reasons for this and consider re-running a procurement exercise.
Planning permission granted for the construction of the scheme
Undertake pre-planning discussions with authority. Prepare necessary EIA and transport assessments in advance and submit for third party review.
If planning permission is not granted, WBC will need to review the reasons for rejection and consider amendments to the scheme to enable approval of a revised scheme.
Successful application for works to be carried out in common land (Morley Common)
Undertake pre-planning discussions with authority. Identify exchange land as part of design to off-set loss.
If approval is not granted, WBC will need to review the reasons for rejection and consider amendments to the scheme to enable approval of a revised scheme.
Inspector and Secretary of State finding in favour of the scheme should a Public or Land Inquiry be held
Maintain detailed project records and follow approval procedures and review processes set out. Seek legal advice in advance of Inquiry.
If the scheme fails at public inquiry, WBC will need to re-assess the scheme proposals and consider how a Western Link scheme should be taken forward.
Agreement of statutory approvals with Network Rail, the Environment Agency and Natural England
Undertake advance discussion with each body to understand requirements. Include requirements in design.
Should approvals not be granted, the scheme will need to be amended to enable approval.
Agreement of bridging rights over River Mersey and Manchester Ship Canal
Undertake advance discussion with river authorities. Seek legal advice to support process.
Should bridging rights not be granted, the scheme will need to be placed on hold until the rights can be agreed.
Agreeing of works to be carried out in land not subject to CPO (i.e. crown land)
Undertake advance discussion with land owners. Seek legal advice to support process.
Should land rights not be granted, the scheme will need to be placed on hold until the rights can be agreed.
Source: Warrington Borough Council
Strategic and operational governance
WBC are scheme promoter and delivery agent for Western Link; the overall project governance
structure is shown in Figure 1.
Figure 1: Strategic governance structure
Warrington Borough Council
Source: Warrington Borough Council
External Partner
Warrington &
Co.
External Partner
CWLEP
WBC Capital Investment Programme Group
WBC Waterfront Programme Board
WBC Strategic Management Team
WBC EXECUTIVE BOARD Department for
Transport
WBC Western Link Project Executive
WBC Western Link Project Team
11
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
The WBC Project Executive, in accordance with Prince2 principles, consists of a Project Director,
Senior User and Senior Supplier and operate as the Project Board. They are accountable to
Warrington Borough Council members, and are responsible for scrutinising delivery of the scheme.
At an operational level, the Project Manager and Project Team are responsible for the on-ground
delivery of the scheme and report to the Project Board. The Project Team is made up of the
following work streams:
● Design;
● Planning;
● Procurement;
● Land and CPO; and
● Business Case.
Assurance
Figure 2 highlights the decision and review process for Western Link to ensure the project remains
on track and continues to progress to the next stage of development.
Figure 2: Formal Assurance and Review Points
Any statutory undertakings such as planning permissions, land acquisition, environmental consents
and traffic regulation orders will be obtained and pass through the Executive Board and
Programme Board approval process before being initiated. This approval responsibility has been
incorporated into the governance arrangements for Western Link in order to provide assurance that
major actions that would contribute substantially to scheme development have sufficient levels
review and control. The Executive Board will also be responsible for making all major financial
decisions, or delegating responsibility for those decisions to the relevant departmental
representative
Business Case
Review2019
Pre-Implementation
review2019
Operational Benefits Review
2021
12
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Delivery of the Western Link scheme will be monitored and managed by A Project Manager
through Warrington’s Gateway Process, which is a systematic review process that is undertaken at
critical points in a projects lifecycle. The following key Gateways have been identified for Western
Link and are aligned with the RIBA plan of work:
● Stage 3: Project Board gateway review and approval of:
– Developed Design
– Stage 3 Costs
– Planning Submission
– Procurement Documents
● Stage 3: Council Executive Board Approval of CPO and SUO.
● Stage 4A: Project Board approval of Selected Contractor
● Stage 4B: Project Board Approval of:
– Detailed Design
– Target Cost
– D&B Contract
WBC will draw on the services of third party consultants to assist in the review of the submitted
information; WSP are appointed to provided technical review of designs and Faithful and Gould are
appointed to provide a review of costs.
Scheme delivery
Figure 3: RIBA work stages and Western Link delivery
13
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Figure 3 illustrates that to date RIBA stages 0-2 are complete and the future delivery of the
programme is split into 3 distinct stages (albeit RIBA stage 4 has been sub-divided into stages 4A
and 4B for the purposes of this scheme). Submission of this Outline Business Case (OBC) and
advance preparation activities will be completed as part of a ‘preparation for stage 3 phase’, in
advance of a funding decision in May 2018. Progression through these stages will be facilitated
through 6 distinct work packages:
● Project management; covering communications, consultation, stakeholder engagement as well
as ongoing project review and governance;
● Technical Design and Approvals; this includes key design elements such as highways,
structure, drainage, utilities, environmental, geotechnical and traffic modelling;
● Planning; which will include an Environmental Impact Assessment covering key components
such as ecological mitigations, heath impacts, contaminated land, noise, air quality, heritage
and archaeological assessments;
● Procurement; a 2-step process with initial contractor selection via an OJEU compliant process;
● Land, CPO/SUO and Inquiry; finalisation of land required and discussion and negotiation with
affected land owners; and
● Business Case; to include development of the Full Major Scheme Business Case based on
design information generated at RIBA stage 3.
These are shown in Figure 4 and highlight the key tasks and milestones in each of the work
packages during each stage as well as indicative dates for completion of milestones.
Figure 4: Western Link high level programme
Source: Mott MacDonald
14
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Risk management
The overall risk management strategy for Western Link is owned by the Senior Responsible Officer
(SRO), and is based on the principles for risk management contained within the OGC Prince2
guidance which follows the process shown in Figure 5.
Figure 5: Risk management process
Source: Prince2
Two levels of project based risk management that will be identified. These are:
● Project Risks - those affecting the cost, scope and timescale for the project; and
● Project Management and Delivery Risks - those presenting wider risks to the client body.
A summary of the top 10 risks under each of the above categories are shown below.
Table 2: Top Ten Project Risks
Project Risks Project Management and Delivery Risks
Risk Mitigation Risk Mitigation
Earthworks - Potential for excavated ground to be contaminated.
● Minimise excavation into waste deposits.
● Adoption of geocell within design.
Western Link is the first test of the new Warrington Multi Modal Transport Model (MMTM).
● Assurance role provided by WSP.
● Modelling work has had input and check from both AECOM and Mott MacDonald.
Vertical alignment tie in difficulties due to existing topography and height restrictions.
● Full topographical survey to confirm if horizontal alignment risk can be mitigated.
Council has unclear approach to blight issues, and/or scheme requires CPO and has been subject to some opposition.
● Employ solicitor
● Agree CPO and blight approach with executive board
● Hold consultation events
● Maintain close dialogue with directly affected land owners
● Adjust cost and risk allowance appropriately.
Utility clashes due to limited corridor for route.
● GPR survey of entire preferred route.
● Modify alignment of preferred route to minimise diversions.
Inspector decides against the progress of scheme at Public/Land Inquiry.
● Maintain project records.
● Maintain consistent project team.
● Employ third party for assurance role.
● Maintain a risk register
● Engage solicitor
● Programme ecological surveys in Stage 2B to ensure full dataset.
15
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Project Risks Project Management and Delivery Risks
Cost of acquiring businesses where severance results in whole property being acquired.
● Early negotiations with claimants to ascertain likelihood of such a claim being received.
Network Rail approvals delay or increase cost of project.
● Hold early dialogue with Network Rail.
● Include approval processes in programme.
● Employ consultant with knowledge of Network Rail processes.
Claims for No Land Taken (where properties have now been avoided).
● Maintain access to all properties during works.
● Obtain traffic management plans at the earliest opportunity for review.
If exchange land cannot be offered for affected Commons/open land, scheme could be subject to SPP.
● Investigate options and provide suitable exchange land to avoid SPP.
Weather event, stats diversions delayed, supply chain difficulties.
● Robust monitoring and management.
Stakeholder objection. ● Hold consultation events ahead of planning.
● Maintain close dialogue with directly affected land owners and interested parties.
Additional Inflationary Effects.
● Make allowance in risk register for costs.
● Adjust cost and risk allowance appropriately.
Additional utilities diversions required and/or statutory undertaker objections to any required CPO.
● Carry out ground survey of area and engage statutory undertakers in scheme development.
Poor highway foundation due to Landfill beneath road alignment.
● Minimise excavation into landfill. ● Reinstate capping as required. ● Adopt geocell basal
reinforcement as required. ● Adopt pile load platforms to
transfer load to either Glacial Soils or Rockhead.
● Programme ecological surveys in Stage 2B to ensure full dataset.
Ecological mitigation measures required beyond those allowed for.
● Carry out necessary ecological surveys and hold dialogue with EA and Natural England.
Design scope changes.
● Control and definition of scope by client and delivery team.
Appropriate delivery team is not available.
● Appoint delivery team early to secure service for project.
Traffic Modelling requires wider WBC network Improvements.
● Make cost allowance in capital and risk costs Assess wide. network impacts during stage 3
● Design necessary junction improvements.
Failure to obtain Political Support.
● Hold dialogue with MP, Local Members and neighbouring authorities.
Source: Warrington Borough Council
Contract management
Three contractual arrangements are proposed for use in the Western Link, these are listed below:
● SCAPE national Civil Engineering and Infrastructure Framework 2015;
● Transportation and Public Realm Consultancy Services Framework 2013; and
● Competitive Dialogue Process, OJEU, Public Contracts Regulations (NEC4 Option C).
The first two of the above contractual arrangements for commissioning work and engaging
companies are well established. WBC intends to undertake engagements over RIBA stages 3 and
4 using the first two of these contractual arrangements. The contractor will be engaged in Stage 4A
in order to deliver the detailed design in Stage 4B. Engaging a contractor to deliver the scheme to a
target cost price for construction at stage 5 will require a NEC4 contract to be issued.
Stakeholders and communication
This section outlines the key stakeholders who are involved in Western Link, the communications
strategy for the scheme and the communications and stakeholder management plan. Stakeholder
communications and management has been split into 2 parts:
16
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
● Public engagement; and
● Stakeholder engagement:
Both the public and stakeholders were consulted in 2 rounds, at stage 2A (6 shortlisted options) in
July 2017 and again at stage 2B (preferred option only) in September 2017.
Key stakeholders are identified below in Table 3.
Table 3: Key stakeholders
Stakeholder Interest Influence Strategy
Stakeholder Interest Influence Strategy
Department for transport National government body supporting transport and travel country wide.
Approval and awarding of funding for scheme
Communicate project plans and schedule
Warrington Borough Council
Warrington Borough Council are the scheme promoter and take charge for Western Link’s delivery.
They are also responsible for the schemes funding alongside Cheshire and Warrington LEP.
Warrington Borough Council are the Local Planning Authority and will define the planning conditions before and during construction.
Keep informed
Cheshire and Warrington Local Enterprise Partnership
Cheshire and Warrington LEP seek to drive economic growth and create housing and jobs across the region.
The C&W LEP Performance and Investment Committee is responsible for approving the Business Case and release of Growth Deal funding to support the
delivery of the scheme.
Keep informed
Highways England Operates, maintains and improves England’s Strategic Route Network. Western Link will form a major addition to the primary network in Warrington.
Interest in the schemes locations and integration with current highways network in Warrington.
Communicate project plans and schedule
Warrington & Co Warrington & Co is an external partner to the Western Link project. The organisation is a public and private sector growth delivery agency. The Homes Community Agency, Cheshire and Warrington LEP and Warrington Borough Council are long standing members of Warrington &Co.
Direct activities that relate to land acquisitions, strategic regeneration and ensuring Western Link delivers in terms of jobs and growth for Warrington.
Keep informed
Transport for the North The scheme has been ranked as ‘endorsed intervention’ in the TfN northern scheme review11. This means that TfN recognise the contribution that the scheme would make to the regional economy
Transport for the North (TfN) has endorsed the intervention noting its strong contribution to the labour market and business to business links for goods.
Keep informed
Land Owners There may be some land take as part of the Western Link Scheme. in this case. consultation and negotiation will be pivotal to the schemes success.
Warrington Borough Council will need to consult relevant land owners once a definitive route has been decided upon.
Public meetings to consult on plans, press releases and website
Local residents and community
Arguably the most important of the Stakeholders, they will be the end user of the Western Link scheme.
The community’s views and feedback on design is paramount to the schemes delivery. Sufficient public consultation is required to gauge the community’s thoughts and views on Western Link.
Public meetings to consult on plans, press releases and website
Peel Holdings Peel have had a strong influence in the North West. They look to
In response to public concerns over increases in port traffic and congestion, Peel
Keep informed
17
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Stakeholder Interest Influence Strategy
refurbish and expand the Port of Warrington.
are committed to working with regional stakeholders to lobby Government for funding for surface access transport improvements. Expanding bridge crossings and providing improved transport links through Warrington Town Centre is critical to facilitate the desired growth for Port Warrington
The Homes and Community Agency (HCA)
The HCA currently own land holdings in the south of Warrington, referred to as ‘Warrington South’ – an area which covers 350ha of land and has the potential to create 6000 new jobs and release land for business equating to 11,000 new jobs.
Homes and Communities Agency support the provision of improved transport access that will enable their land to be developed for housing and employment.
Keep informed
Source: Warrington Borough Council
18 consultation events took place during stage 2A July 2017. Of the 2,236 people that provided
feedback, 43% were supportive of the scheme and of the 1907 people who expressed an option
preference, the largest measure of support (31%) was for the red route, the scheme now being
taken forward and which was consulted on further at stage 2B.
It is proposed that for RIBA stage 3 the pre-application consultation for any planning application
would be done in two steps, with a third consultation step post-submission of the planning.
Project reporting
Project reporting is split into:
● Delivery reporting, which focuses on internal reporting within the project team and upward
through the governance structure to the Project board, Waterfront Programme board and
Capital investment programme group.
● DfT reporting, which will involve quarterly reporting to update on progress, raise key issues and
ensure ongoing project review at stages 3 and 4 of the project.
Monitoring and evaluation to measure benefit
A detailed benefits realisation plan has been produced and is included as Appendix T and will be
owned by the SRO. However, the key benefits, beneficiaries, outcomes and the baseline measures
which are monitored to assess if benefits are being realised are included in Table 4.
Table 4: Key benefits
Scheme Objectives
Scheme outcome Benefits experienced Enablers required to realise the benefit
Scheme Objective 1: Relieve congestion and improve air quality in Warrington Town Centre
● Reduced traffic flow within the town centre
● Reduction in town centre congestion, delay and queues
● Refreshment of town centre air quality
● Reduction in traffic noise within the town centre
● Safer pedestrian conditions
● Healthier community
● More attractive place for investment and town centre regeneration
● More employment and recreational opportunities
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Complementary education and travel demand management programme
● Marketing for future investment and development opportunities
● Reduced traffic flow within the town centre
● More reliable commuter times for employment in the town centre.
● Completion of Western Link
18
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Scheme outcome Benefits experienced Enablers required to realise the benefit
● Reduction in town centre congestion, delay and queues
● Reduced journey times for town centre public transport services
● More reliable journey times for leisure trips into the town centre
● More reliable bus travel times and enhancement of bus services.
● Greater accessibility within the town centre and to its many services.
● Modifications to town centre highways network and public walkways
● Proposals for public realm improvements
● Marketing for future investment and development opportunities
● Aligned business marketing programme to promote development of scheme and economic benefits
● Enhanced cycle and walking infrastructure
● Reduced traffic flows at key pinch points and entering the town centre.
● Reduction in town centre congestion, delay and queues at town centre pinch points
● Reduced vehicular greenhouse gas emissions in the town centre
● Reduction in travel times travelling to town centre
● Better journey quality for highways users journeying to the town centre
● Less noise and air pollution at town centre pinch points
● Enhanced living conditions for proximate residential areas
● Enhanced pedestrian and cycling conditions
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Complementary education and travel demand management programme
● Enhanced cycle and walking infrastructure
● Reduction in vehicular emissions in the town centre as a result of reduced traffic flows.
● Improved air quality in the town centre.
● More pleasant and safer pedestrian conditions
● Healthier community
● Contribution to meeting national air quality targets
● Helping to refresh the town centre environment and attracting further investment
● Completion of Western Link
● Landscape remediation works
● Enhanced air quality monitoring programme
● Marketing for future investment and development opportunities
Scheme Objective 2: Improve connectivity between North and South Warrington
● Extra capacity added to highways network
● Extra crossings of River Mersey and Manchester ship canal added.
● Increase in vehicle route choice.
● Reduced queues and delays at existing crossing points.
● Improved network resilience against impacts of uncontrollable bridge swings
● Enhanced journey quality when travelling across Warrington
● Enhanced living conditions for proximate residential areas
● Greater accessibility across Warrington
● More efficient business, freight and commuter movements across Warrington
● Increasing network resilience and prevention of highways degradation
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Complementary education and travel demand management programme
● Reduction in travel times between strategic network and west Warrington and the town centre.
● Increased network resilience with fewer delays and congestion in times of incidents on the wider strategic network
● Enhanced journey quality when travelling across Warrington
● Greater highways resilience and reduced network degradation
● Better connection with the strategic network and improved commercial and freight movements
● Greater opportunities for business growth
● Completion of Western Link
● Effective signing strategy and dissemination of information relating to diversions along Western Link
● Complementary education and travel demand management programme
Strategic Objective 3: Unlock key development
● Construction of Western Link and associated junction to facilitate
● Increased investment in Warrington
● Greater opportunities for employment and business growth
● Completion of Western Link
● Accepted proposal for Warrington Waterfront development
19
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Scheme outcome Benefits experienced Enablers required to realise the benefit
land to support the growth aspirations of ‘Warrington Means Business’ and the Warrington Local Plan
highways access to Waterfront development.
● Realisation of Warrington Waterfront development.
● Job creation
● Construction of new homes.
● Increased economic performance and greater economic prosperity within Warrington
● Contribute to meeting local and national housing targets
● Enhanced quality of life for residents
● Growth of the town and contribution to Warrington town’s redevelopment aspirations
● Marketing for future investment and development opportunities
● Engagement with housing developers
● Aligned business marketing programme to promote development of scheme and economic benefits
● Construction of Western Link and associated junction to facilitate highways access to Port Warrington development.
● Operation of enhanced intra-modal freight facility at Port Warrington
● Improved access to development
● Job creation
● Enhanced freight operations and distribution with the wider region
● Increased investment in Warrington
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Warrington established as a destination for logistics and manufacturing
● Growth of the town and contribution to Warrington town’s redevelopment aspirations
● Further establishment of Warrington as a key player within the NPH
● Completion of Western Link
● Aligned business marketing programme to promote development of scheme and economic benefits
● Engagement with Freight and Logistics Partners on Port Warrington proposals to understand how WL can enhance development options
● Development of Port Warrington intra-modal freight facility
● Engagement with TfN on how freight operations at Port Warrington can benefit wider transport and freight strategy
● Construction of Western Link and associated junction to facilitate highways access to Arpley Meadows.
● Construction of new homes.
● Contribute to meeting local and national housing targets
● Enhanced quality of life
● Increased investment in Warrington
● Growth of the town and contribution to Warrington’s redevelopment aspirations
● Tax benefits for Warrington Borough Council
● Completion of Western Link
● Marketing for future investment and development opportunities
● Engagement with housing developers
● Acceptance of Warrington 2017 Draft Local Plan
● Construction of Western Link and associated junction to facilitate highways access to Waterfront development.
● Job creation
● Increased investment in Warrington
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Enhanced quality of life for residents
● Further establishment of Warrington as a key player within the NPH
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Aligned business marketing programme to promote development of scheme and economic benefits
● Marketing for future investment and development opportunities
Strategic Objective 4: Support the continued growth of Warrington’s economy within the Northern Powerhouse
● Reduced congestion and delays across network
● Reduced journey and commuting times
● Enhanced journey quality for Warrington residents and workforce
● Greater network efficiency
● More efficient freight operations
● Greater access to a wider employment pool
● Completion of Western Link
● Effective Integration with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Improved accessibility to key employment areas in western Warrington
● Enhanced journey quality for Warrington residents and workforce
● Completion of Western Link
20
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Scheme outcome Benefits experienced Enablers required to realise the benefit
● Journey time savings
● Job growth
● Higher GVA
● Better linkages between Warrington’s major employment sites and its workforce
● Supporting the growth of Warrington’s key employment sectors and specialist commercial activities
● Further establishment of Warrington as a key player within the NPH
● Marketing and education plan for use of Western Link and best routing when travelling across Warrington
● Marketing for future investment and development opportunities
● Engagement with TfN over best integration of Warrington’s specialist commercial activities within the NPH
Strategic Objective 5: Make Warrington a more attractive place to live
● Increase trips by walking and cycling
● Reduced congestion
● Healthier communities
● Increasing the use of Warrington’s green areas
● Enhanced pedestrian and cycling conditions
● Rise in cycling and walking in Warrington
● Encouragement of less sedentary lifestyles and reducing the burden on local health services
● Completion of Western Link
● Successful reclamation of Arpley and Gatewarth landfill sites
● Effective marketing campaigns to encourage the use of Warrington’s redevelopment green areas
● Work with environment and conservation sector partners to develop a complementary recreation strategy for the scheme which unlocks additional benefits
● New cycle paths constructed alongside western link
● Increase trips by walking and cycling
● Reduced congestion
● Increased transport access
● Improved S/T
● Increase in active travel in west Warrington
● Healthier communities
● Rise in cycling and walking in Warrington
● Encouragement of less sedentary lifestyles and reducing the burden on local health services
● Increased revenue for bus operators
● Completion of Western Link
● Effective Integration of Western with new highways network associated with Warrington Waterfront development – modifications to signage strategy, road markings, footpaths and to road layout
● Effective marketing campaigns to encourage active travel amongst residents and businesses
● Increased active travel in Warrington
● Increase in business occupancy rates and business start-ups in west Warrington
● Job growth
● Construction of housing
● Reduction in accidents in the town centre
● Healthier communities
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Enhanced quality of life for residents
● Encouragement of less sedentary lifestyles and reducing the burden on local health services
● Completion of Western Link
● Enhanced cycling and walking Infrastructure
● Effective marketing campaigns to encourage active travel amongst residents and businesses
● Aligned business marketing programme to promote development of scheme and economic benefits
● Marketing for future investment and development opportunities
● Work with environment and conservation sector partners to develop a complementary recreation strategy for the scheme which unlocks additional benefits
Source: Mott MacDonald
The success of Western Link will be determined by achievement of the outcomes noted above that
will unlock the benefits and delivery to time, budget and specification. It is progress toward these
outcome that will be monitored.
DfT guidance sets out the requirements for the monitoring of schemes and outlines three tiers of
monitoring and evaluation, these are:
● Standard monitoring
21
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
● Enhanced monitoring
● Fuller evaluation
Western Link follows the enhanced monitoring practice as the scheme is greater than £50m in
value. Therefore, the scheme will be monitored against a set of standard measures which are
summarised in Table 5.
Table 5: Components of enhanced monitoring
Item Type of information to be provided Data Collection timing
Rationale
Scheme build
● Programme/project plan assessment
● Stakeholder management approaches
● A review of the risk register and assessment of the impacts
● Assessment whether the scheme is on track
During delivery Knowledge
Delivered scheme
● Full description of scheme outputs
● Identification of the any changes to the scheme since funding approval.
● Identification of any changes to assumptions.
● Assessment of whether the scheme has reached the intended beneficiaries.
● Identification of changes to mitigation measures.
During delivery/post opening
Accountability
Costs ● Outturn investment costs.
● Analysis of risk in the elements of investment costs.
● Identification of cost elements with savings.
● Analysis for cost elements with overruns.
● Outturn operating costs.
● Outturn maintenance or other capital costs.
During delivery/post opening
Accountability
Scheme Objectives
● Identification of the main objectives. Pre or during delivery / post opening (up to 5 years)
Accountability
Travel demand
● Road traffic flows on corridors of interest.
● Patronage of the public transport system in the area.
● Counts of pedestrians and cyclists.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Travel times and reliability
● Travel times in the corridors of interest.
● Variability in travel times in the corridors of interest.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Impact on the economy
● Travel times/accountability changes to businesses
● Employment levels and
● Rental values
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Carbon ● Effect of the scheme on carbon in the area of interest. Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Noise ● Effect of the scheme on noise levels at important receptor locations.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Local air quality
● Effect of the scheme on local air quality in the area of interest. Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Accidents Effect of the scheme on traffic accidents in the area of interest. Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Source: DfT
Figure 6 shows how, aligned with DfT monitoring guidance, Warrington Borough Council will
interact with the DfT in terms of reporting on progress toward the realisation of outcomes and
benefits:
22
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Figure 6: Monitoring and evaluation engagement process between Local Authority and DfT
Source: DfT
The total budget outlined for evaluation activities is £115,000.
23
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Contingency measures
Contingency measures have been established that relate mostly to ensuring that the impacts of the
project are as close to cost neutral on the Council balance sheet as possible.
In the event the Council is unable to construct the highway following the necessary land acquisition
and the project being halted before the beginning of RIBA stage 5 – construction stage, the council
would need to accept that the money spent to date on the pre-construction and design works would
be abortive and need to be halted.
The Council would then assess the key land assets acquired as part of the scheme. As CPO
would be the background to land acquisition it is likely that, in the first instance, land belonging to
previous owners would be offered for sale back to the previous incumbent on a ‘first refusal’ basis.
If previous owners did not wish to repurchase the land, then WBC would re-market the properties
and holdings to try and cover the potential capital outlay for the land.
In terms of progressing a highways scheme, WBC would continue to investigate low cost alternatives in an attempt to deliver on some of the objectives identified as part of the scheme development.
24
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
1 Management case overview
1.1 Introduction
The Management Case assesses whether Western Link is deliverable. It tests the project planning,
governance structure, risk management, communications and stakeholder management, benefits
realisation and project assurance.
Included is a plan that ensures Western Link can deliver the benefits listed in the economic case,
and a method to measure, assess and evaluate the scheme impacts. The DfT guidance
document, ‘‘The Transport Business Case: Management Case’, outlines the areas that should be
covered in the Management Section and these are set out below together with the relevant section
of this report where they can be found.
Table 6: DfT Management case requirements
Issue Description Status Section
Introduction Outline the approach taken to assess if
the proposal is deliverable.
Complete 1
Evidence of similar
projects
If possible, provide evidence of similar
projects that have been successful, to
support the recommended project
approach. If no similar project approach. If
no similar projects are available for
comparison, outline the basis of
assumptions for delivery of this project
e.g. comparison with industry averages for
this kind of work
Complete 2
Project dependencies Set out deliverables and decisions that are
provided/ received from other projects.
Complete 3
Governance,
organisational
structures & roles
Describe key roles, lines of accountability
and how they are resourced.
Complete 4
Assurance &
approvals plan
Plan with key assurance and approval
milestones.
Complete 5
Project plan Plan with key milestones and progress,
including critical plan.
Complete 6
Risk management
strategy
Arrangements for risk management and
its effectiveness so far.
Complete 8
Communications and
stakeholder
management
Development communications strategy
for the project.
Complete 10
Project reporting Describe reporting arrangements. Complete 11
Implementation of
work streams
Summary of key work streams for
executing the work.
Complete 7
Key Issues for
implementation
Issues likely to affect delivery and
implementation.
Complete 7
Contract
Management
Summarise outline arrangements. Confirm
arrangements for continuity between
those involved in developing the contract
and those who will subsequently manage
it.
Complete 9
25
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Issue Description Status Section
Benefits realisation
plan
Set out approach to managing realisation of benefits.
Complete 12
Monitoring and evaluation
Summarise outline arrangements for monitoring and evaluating the intervention.
Complete 13
Contingency plan
Summarise outline arrangements for contingency management such as fall back plans if service implementation is delayed.
Complete 14
Conclusion Summarise overall approach for project management at this stage of project.
Complete 15
Source: Mott MacDonald
26
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
2 Evidence of similar projects
WBC has had proven success in delivering a number of highways projects and in working with
Balfour Beatty. Table 7 provides a summary of key similar projects delivered by Warrington
Borough Council and Sections 2.1-2.5 provide additional detail.
Table 7: Evidence of Similar Projects
Project Cost Delivered to time Delivered to budget
Warrington East Transport Strategy Phase 1: Birchwood Pinch Point
£5.4m Yes Yes
A49 Winwick Road / A50 Long Lane junction improvement scheme
£2.4m Yes Yes
Skyline Drive £11m Yes Yes
Centre Park Link £19.35m TBC TBC
Time Square £101m TBC TBC
Source: Warrington Brough Council
2.1 Warrington East Transport Strategy Phase 1: Birchwood Pinch Point
This project consisted of several junction improvements along the A574 Birchwood corridor at the
Oakwood and Moss gate roundabouts. The scheme also included a new bus only link between
Ordnance Avenue and Faraday Street. The works finished in July 2016 at a cost of £5.4m.
The scheme was delivered through funding obtained from the growth deal from the Cheshire and
Warrington LEP, as well as local contributions from Warrington Council and Birchwood Park. The
project was delivered by Balfour Beatty and managed through the SCAPE National Civil
Engineering and infrastructure Framework.
The project facilitated a welcome increase in road capacity and eased congestion for 10,000
vehicles that travel through the junction each day. The project had a strong emphasis on economic
development, with the scheme successfully providing more amiable local traffic conditions which
helped to attract more small and medium enterprises to the Birchwood area.
27
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
2.2 A49 Winwick Road / A50 Long Lane junction improvement scheme
The scheme consisted of major improvement works at the A49 Winwick Road/A50 Long Lane
Junction and encompassed the complete removal of a roundabout with the replacement of a traffic
signal cross roads junction. The works were completed in November 2011. The scheme cost was
£2.4m.
The junction improvements were financed by two funding sources, the Local Transport Plan and
the from developer contributions from the Orford Park project and Carrington Wire development.
The scheme brought about a number of benefits including congestion relief along the A49, as well
as improving accessibility to bus services and improving road safety conditions for cyclists.
Relevance to Western Link:
WBC had to deliver a major junction improvement scheme that involved working within a live
carriageway and dealing with significant statutory undertaker works. This was aimed at improving
the efficiency of the junction in all directions by better balancing the traffic demands.
WBC has learned the following from the A49/A50 scheme that will influence the future delivery of the
Western Link:
● Delivery of a major scheme using the statutory powers in the Highways Act 1980;
● Managing live traffic whilst a major scheme is being constructed, something that will be necessary
in progressing major junction tie-in for the Western Link; and
● Liaising, negotiating and enacting statutory undertaker diversions, including major jointing, to
ensure that the scheme did not impact on wider services. This was done in a cost-effective
manner through WBC’s ongoing relationships with the various undertakers.
Relevance to Western Link:
The scheme was aimed at reducing the significant levels of existing, acute traffic delay experienced
based on the heavy volumes of traffic moving in different directions over major junctions. These
junctions required significant improvement in their layout and operation to generate better efficiencies
in vehicle movement and reduction of delay. The improvement in the operation of these junctions has
led to journey time savings across the network, which is anticipated to lead to further economic growth.
WBC has learned the following from the Warrington East scheme that will influence the future delivery
of the Western Link:
● Identifying and delivering a major engineering project within a busy highway network, maintaining
ongoing vehicle access safely, whilst delivering the scheme ahead of schedule;
● Delivering a major improvement project to programme and under-budget. The project was
delivered under the target cost estimate; demonstrating effective financial control but the client and
focused delivery by the contractor;
● The scheme was part-funded by the CWEP so Warrington needed to establish procedures for
reporting to the CWEP regarding progress and issues. This means Warrington has significant
experience of working with partners on the delivery of a major scheme and ensuring that effective
reporting streams are in place;
● Dealing with on-site remediation and work stoppages after a significant amount of asbestos was
found on-site, that had to be evaluated, identified and removed off-site; and
● Demonstrating that Warrington can continue to deliver economic growth through focused
investment in the transport network.
●
28
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
2.3 Skyline Drive
The scheme concerned the construction of a new road between Junction 8 of the M62 and Omega
Boulevard via the Royal Mail depot. Skyline Drive opened in December 2015. The new highway
enabled access to the Omega and Lingley Mere site, with access for heavy goods vehicles and
lorries from the motorway made quicker and easier.
The new road was jointly funded by the consortium group delivering the OMEGA development and
Warrington Borough Council. The project had a strong focus on economic growth in Warrington
and enabled the unlocking of crucial development land in Warrington. The scheme enabled
highways users to successfully access one of Warrington’s most important and prosperous
employment sites.
2.4 Centre Park Link
WBC is currently delivering a major transport project at a cost of £19.35m on Chester Road in
Warrington. The new highway link will connect north and west Warrington, opening up new land for
development and providing additional network resilience around one of the most congested links
on the network. The project includes:
● A new major junction constructed around a busy, operating highway into the town centre;
● A major bridge structure over the River Mersey, requiring significant earthworks on the western
side to ensure effective bridge tie-in;
● Undertaking land acquisition and various legal processes relating to bridging rights, to enable
the passage of the new structure; and
● Constructing a new junction within the town centre highway network, next to Bank Quay Rail
Station.
Relevance to Western Link:
To enable the delivery of the regionally significant OMEGA development, WBC worked with OWL Ltd
(the OMEGA development consortium) to deliver a major highway access from Junction 8 of the M62.
Skyline Drive was the subject a major s278 agreement that has enabled the delivery of major mixed-
use 575ha development on the north side of Warrington, including companies such as The Hut Group,
Plastic Omnium, ASDA, Amazon, Royal Mail, Brakes, Travis Perkins and Hermes. The development
of OMEGA will continue with the next phase delivery of major retail space and 1,100 houses.
WBC has learned the following from the Skyline Drive scheme that will influence the future delivery of
the Western Link:
● Use of the legal procedures to deliver a major highway connected to a major development site;
● How to enable development and generate jobs and economic growth within Warrington – WBC has
learnt how to directly support economic growth within the Borough. This is through the combined
leverage of the engineering skills within Transport for Warrington and the business acumen of
Warrington and Co, the council’s economic delivery arm;
● As part funder of the Western Link, WBC has learnt the necessary skills to deliver within a delivery
consortium; and
● WBC has experience of providing scheme funding as part of the Skyline Drive project, putting in
place rationale and ensuring financial returns for the council.
29
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
The Centre Park Link project has recently gained planning permission and will be on-site early
2018. Earthworks are currently being undertaken to ensure effective tie-in with the new structure
2.5 Time Square Regeneration
The council, in a joint venture with Muse Developments, is currently engaging in a major new development within Warrington Town Centre. The project is currently ongoing and due for completion in 2019, being delivered at an estimated £101m. The works include:
● Demolition and rebuilding of Warrington market, into a new town centre market facility;
● Demolition and rebuilding of the Academy Way car park, providing safer and more secure car
parking for the town centre;
● Major public realm works and pedestrianisation of new town centre public square
● New multi-screen cinema;
● New leisure units for restaurants and bars; and
● New major Grade-A office building in the town centre.
Relevance to Western Link:
The Centre Park Link scheme is a major highway scheme delivered in partnership with the CWEP.
The scheme has required the undertaking of a procurement exercise to find a suitably qualified
contractor, establishing the relevant statutory authorities, liaising with third-party organisations, land
assembly and undertaking a major public consultation exercise.
WBC has learned the following from the Centre Park Link scheme that will influence the future delivery
of the Western Link:
● Use of the legal procedures to deliver a major highway connected to a major development site,
including obtaining Bridging Rights via the Highways Act 1980;
● Taking a major scheme through the planning process, obtaining planning permission and dealing
with reserved matters during the delivery process;
● Engaging with statutory consultees as part of the delivery process, including Natural England, the
Environment Agency, GMEU and Network Rail. Good working relationships have been fostered
within these agencies and WBC has a deep understanding of their requirements and processes;
● WBC undertook an extensive public consultation exercise that will need to be undertaken as part of
the Western Link project.
Relevance to Western Link:
Whilst this is not a transportation project, many of the issues encountered in the delivery of the Time
Square development are similar to those anticipated within the Western Link project, these include:
● Requirement to enact compulsory purchase powers to assemble the land for the project
● Requirement to progress through Land Inquiry (related to the above);
● Major structural and civils engineering works;
● Major project management structure required, with multiple organisations, agents and
professionals involved; and
● Required extensive engagement with the public prior to construction and was submitted for
planning permission.
30
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
2.6 Summary
These projects demonstrate Warrington Borough Council’s extensive and successful experience of
delivering schemes across the Borough. They show a successful history of schemes that have
been delivered on time, to budget and have helped further the attraction of working and living in
Warrington. This substantially aligns with the objectives of the Western Link scheme.
When considering the experienced outlined in section 2.5, WBC has shown its ability to deal with a
variety of major issues and has shown experience in key areas important to the delivery of the
Western Link project. The key issues relevant to Western Link include:
● Dealing with all statutory permissions and legal procedures;
● Establishing and maintaining relationships with the relevant statutory agencies involved in the
delivery of major infrastructure scheme;
● Working as part of a delivery consortium, and with other agencies as part-funders of major
schemes;
● Delivering schemes that are shown to generate economic growth and then putting in place
programmes of work to maximise that economic opportunity;
● Engaging extensively with the public and stakeholders, ensuring wide dissemination and
understanding of information;
● Experience of running a procurement exercise and selecting a suitably qualified contractor;
● Delivering major infrastructure projects to programme and on budget;
● Negotiating, acquiring and assembling land required for scheme delivery through a variety of
different mechanisms, including the use of compulsory purchase orders; and
● Designing and delivering major civil engineering projects.
In order to show how WBC has evaluated their experience of previous project, and how the lessons
learned from those projects should influence the Western Link project, WBC has compiled the
Table below that shows the key lessons learned from each of the five project examples outlined in
this section.
Table 8: Key issues
Project Key Issues Relevance Key Lesson Learned
Warrington East Phase 1
● Working in a live carriageway
● Delivering a project with a major funding partner
● The ‘tie-in’ at the A56 and A57 junctions will require working a live carriageway as these are two major A-Roads
● WBC will be joint-funding the Western Link with the Central Government
● Pro-actively manage the traffic management during the delivery period to ensure rapid responses to any unforeseen issues on site.
● Ensure effective reporting and communication methods between parties, with effective recording of responsibilities and actions.
A49 Long Lane Junction
● Undertaking major statutory undertakers work
● Utilising major legal powers to deliver a major scheme
● Western Link requires some major statutory undertaker works
● Land assembly will use the CPO powers as a last resort, bridging rights will be required as part of the scheme, a land inquiry is likely and other Planning Act and Highways Act sections will need to be used to deliver different elements of the scheme.
● Undertake early and extensive GPR surveys and engage with the relevant contacts at each statutory undertaker
● Engage expert legal support early in the process to advise on the content of documents
31
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Project Key Issues Relevance Key Lesson Learned
Skyline Drive ● Delivering a major scheme to promote economic growth
● Working with a major developer to maximise economic opportunity
● The Western Link releases a major development opportunity on the Warrington Waterfront
● WBC needs to maximise the return on the investment on the Western Link
● Account for the time required to produce the relevant orders between WBC and the developers
● Enable W&Co early to engage with the major landholders, developers and occupiers to bring forward their proposals for development associated with the highway scheme at an early stage.
Centre Park Link ● Assembling land owned by a number of different organisations
● Identification of relevant legal requirements at an early stage
● A high number of land interests have been identified as being required to deliver the Western Link
● Legal powers will be required to deliver Western Link
● Make all landowners with interests aware following a funding commitment and seek to acquire in advance of works
● Engage expert legal support early in the process to advise on the necessary legal works
Time Square Regeneration
● Delivering a complex, multi-disciplinary engineering project
● Identification of relevant legal requirements at an early stage
● The Western Link project requires significant engineering works of varying types, from structural to environmental
● Legal powers will be required to deliver Western Link
● Ensure early contractor involvement and a dedication design team after a funding award
● Engage expert legal support early in the process to advise on the necessary legal works
Source: Warrington Borough Council
32
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
3 Programme/Project dependencies
To realise the Western Link programme, a set of project dependencies have been produced, these
are outlined below. The dependencies relate to items outside of the Western Link project team’s
control and upon which progression or completion of the scheme depends:
Table 9: Western Link programme/project dependencies
Dependency Key issues Timeframe Mitigation Contingency Plan
DfT approval of Western Link Scheme OBC
DfT approval of the OBC is required in to order secure the funds to complete the project.
Decision by May 2018
Prepare robust OBC, commission independent review, liaise with DfT over queries.
If unsuccessful WBC will halt the project at the end of stage 3 and seek funding in future rounds of local majors funding.
DfT approval of the Western Link FBC
DfT approval of the FBC is required in to order secure the funds to complete the project.
Decision by Feb 2021
Prepare robust FBC, commission independent review, liaise with DfT over queries.
If unsuccessful WBC will halt the project at the end of stage 4 and seek funding in future rounds of local majors funding.
Approval by the Council executive board to CPO and SUO
The Council Executive board will need to confirm a resolution to implement a CPO for the scheme in order for the scheme to acquire the land needed in the necessary timescales.
Decision by May 2019
Hold advance discussion with executive board members to provide briefing on scheme development. Seek legal and land advice to ensure CPO is justified and appropriate.
Should the executive board not support a CPO, WBC will need to review the reasons for this and amend the scheme to address concerns. Efforts will be made to acquire property by negotiation prior to any CPO.
Procurement of a suitable D&B Contractor
The detailed design and delivery of the scheme requires a suitably experienced contractor to be procured.
Procurement by October 2019
Issue PQQ to identify and shortlist contactors. Review responses to ensure suitable shortlist is created.
Should the procurement not result in an appropriate contractor being identified, the council will need understand the reasons for this and consider re- running a procurement exercise.
Planning permission granted for the construction of the scheme
Planning approval is required for the scheme to progress.
Decision by September 2019
Undertake pre-planning discussions with authority. Prepare necessary EIA and transport assessments in advance and submit for third party review. Allow for call in period in programme.
If planning permission is not granted, WBC will need to review the reasons for rejection and consider amendments to the scheme to enable approval of a revised scheme.
Successful application for works to be carried out in common land (Morley Common)
Approval for works to common land must be gained in order for the scheme to progress. SoS is required to approve the de-registration of common land- additional risk and approval required.
Decision by September 2019
Undertake pre-planning discussions with authority. Identify exchange land as part of design to off-set loss.
If approval is not granted, WBC will need to review the reasons for rejection and consider amendments to the scheme to enable approval of a revised scheme.
Inspector and Secretary of State
SofS finding in favour of the scheme is
Decision by November 2020
Maintain detailed project records and
If the scheme fails at public inquiry, WBC will
33
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Source: Warrington Borough Council
finding in favour of the scheme should a Public/Land Inquiry be held
necessary for the scheme to progress.
follow approval procedures and review processes set out. Seek legal advice in advance of Inquiry.
need to re-assess the scheme proposals and consider how a Western Link scheme should be taken forward.
Agreement of statutory approvals with Network Rail, the Environment Agency and Natural England
Appropriate approvals must be gained from each body in order for the scheme to be implemented. Failure to secure these approvals will significantly delay the scheme.
Initial approvals prior to planning May 2019, Further approvals prior o construction Feb 2021
Undertake advance discussion with each body to understand requirements. Include requirements in design.
Should approvals not be granted, the scheme will need to be amended to enable approval.
Agreement of bridging rights over River Mersey and Manchester Ship Canal
Agreement of bridging rights is required in order for bridges to be constructed
Prior to construction Feb 2021
Undertake advance discussion with river authorities. Seek legal advice to support process.
Should bridging rights not be granted, the scheme will need to be placed on hold until the rights can be agreed.
Agreeing of works to be carried out in land not subject to CPO (i.e. crown land)
Agreement is required in order for scheme to be constructed.
Prior to construction Feb 2021
Undertake advance discussion with land owners. Seek legal advice to support process.
Should land rights not be granted, the scheme will need to be placed on hold until the rights can be agreed.
34
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
4 Governance
This section outlines the arrangements, organisation structure and roles within the project
governance structure. An overview of the project governance is presented below.
4.1 Project governance
Figure 7: Project governance structure
Source: Warrington Borough Council
WBC are the scheme promoter and delivery agent for Western Link. A summary of the key tiers in
the governance structure is given below:
4.1.1 Warrington Borough Council
WBC are the scheme promoter and delivery agent for Western link. The governance
arrangements, structure and role of Warrington Borough Council for Western Link is set out in
Section 4.1.
4.1.1.1 Executive board
The board is an elected board chaired by the Council Leader. They are the key decision-making
board of elected members within Full Council. The board reviews the progress of the project and
provides corporate and strategic direction for Western Link. Their key responsibilities are stated
below:
● Provides any necessary approvals from one delivery stage to the next;
● Approves the appointment and/or spending over £250,000;
Warrington Borough Council
WBC Capital Investment Programme Group
WBC Waterfront Programme Board
WBC Strategic Management Team
WBC EXECUTIVE BOARD Department for
Transport
WBC Western Link Project Executive
WBC Western Link Project Team
External Partner
Warrington &
Co.
External Partner
CWLEP
35
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
● Provides strategic direction, when required, to the Regeneration and Transport Programme
Boards;
● Reviews and challenges the delivery of the scheme in relation to time, cost and quality
requirements.
4.1.1.2 Strategic Management Team (SMT)
The SMT is the highest level of council officer decision making authority. The SMT includes all the
departmental heads within the council, plus the Chief Executive. SMT is responsible for the
following:
● Making delegated spending decisions, or major spending decisions up to the value of £250k;
● Making major decisions regarding departmental policy;
● Escalating major policy or investment/spending decisions to Executive Board or political
members;
● Providing direction to junior officers on major projects and departmental decisions;
● Managing the operations of all the departments within the authority; and
● Ensuring that all activities engaged in by the departments are scrutinised by the S151 officer.
4.1.1.3 Capital investment programme group (CIPG)
CIPG is the internal council board that makes major spending decisions as it relates to the council’s
capital investment strategy. Essentially CIPG act as a decision-making board regarding borrowing
money for use in capital investment schemes.
4.1.1.4 Waterfront Programme Board
The Board provides strategic direction to the Western Link scheme. The Board is responsible for
identifying risks that require escalation to the Regeneration Programme Board and Executive
Board. The Board also approves the scheme objectives, project plan and programme.
4.1.1.5 External partner – Warrington & Co.
Warrington & Co is an external partner to the Western Link. The organisation is a public and private
sector growth delivery agency. The Homes Community Agency, Cheshire and Warrington LEP and
Warrington Borough Council are long standing members of Warrington &Co. Their key
responsibilities include the direction of activities that relate to land acquisitions, strategic
regeneration and ensuring Western Link delivers in terms of jobs and growth for Warrington.
The organisation ensures that the project falls in line with the wider aims of Warrington Means
Business and helps include private sector involvement in the scheme. Representatives from
Warrington & co are positioned on the Strategic Management Team.
4.1.1.6 External Partner – Cheshire and Warrington LEP
The C&W LEP Executive Board sets the corporate and strategic direction of the organisation. The
financial proposition of the scheme enables the decision for investment to be delegated to the
Performance and investment committee – their principal responsibilities are to ensure the projects
proposed meet the C&W LEP’s strategic priorities and present good value for money.
36
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
4.1.2 Project Board
The Project Board operate to oversee and scrutinise the delivery of Western Link. The Board will
be accountable to Warrington Borough members. The project management team reports to the
project board and will be responsible for the on-ground delivery of Western Link.
The structure of the project board is displayed in Figure 8 below with their respective roles detailed in Table 10.
Figure 8: Project Board structure
Source: Warrington Borough Council
Table 10: Project board roles and responsibilities
Role Who Responsibilities Accountabilities
Senior User Steve Hunter ● Report back to the DfT in accordance with Transport analysis guidance (TAG)
● Represent end users
● Represent
● Ensure end users views fully represented
● Report to TAG
Project Director David Boyer ● Project direction
● Monitor and control project plan
● Organise/chair project board
● Delivery of formal reports to seek appropriate Council approvals
● Direct and control delivery of scheme within approved delegation
Senior Supplier Tom Shuttleworth
● Agree objectives for supplier activities
● Ensure resources available
● Contribute supplier opinions
● Brief non-technical management on supplier aspects
● Manage the procurement of the scheme
● Manage resources to deliver project
● Financial accountability
Project Manager & Project Management Support
TBC ● Manage delivery of the project
● Prepare and monitor Project Plans
● Give direction for work packages
● Report to Project Board
● Planning and development of work programme
Senior Supplier
Tom Shuttleworth
Senior User
Steve Hunter
Project Director
David Boyer
Project Manager
TBC
Project Manager & Project Management Support
Project Executive
37
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Role Who Responsibilities Accountabilities
● Manage project delivery through project delivery team and co-ordination of meeting
● Manage allocated funding
● Prepare and report to project board
● Completion of work packages to meet project timescales
● Directing and co-ordination of Project Team resources
Project Manager & project Management Support
TBC ● Oversee the delivery of the works
● Management of risks and issues on a daily basis
● Project reviews
● Cost loaded schedules
● Monthly update reports in accordance with Warrington Borough Council project and programme management processes
Source: Warrington Borough Council
4.1.3 Project team
The project team is chaired by the Project Manager and reports to the Project Board. The project
team is made up of the leads of each of the defined work packages and exists to ensure co-
ordination and delivery of the full Western Link. The Project Manager will be supported by Assistant
Project Managers, with duties delegated as appropriate.
Responsibilities of the project team include: management of project risk; programming and co-
ordination of work packages; agreeing key project decisions and escalation to the project board as
required. The project team will remain in place throughout stage 3 and 4 of the Western Link.
The following chart displays the organisational structure of the project team.
Figure 9: Western Link Project Team Organisation
Source: Mott MacDonald
38
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
4.1.3.1 Design Team
During RIBA stage 3, the Design Team will be led by the Design Manager who will report to the
Project Manager. The team will encompass the technical disciplines required to design the Western
Link Scheme together with representation from a contractor and internal council technical teams.
● Traffic Modellers – will update the traffic model to account for scheme and policy changes and
provide outputs to inform updated designs
● Highways Engineers – will lead the design of the route alignment and preparation of a BIM
model
● Structural Engineers – will prepare design for each of the bridges and other structures along the
route, co-ordinating with Network Rail.
● Civil Engineers – will prepare design for drainage and earthworks for the scheme.
● Environmental Engineers – will lead ecology surveys and mitigations, air quality and noise
modelling, landscape design and heritage assessments, co-ordinating with the Environment
Agency and Natural England
● Geotechnical Engineers – will scope further ground investigation requirements and advise on
foundation solutions and contaminated land issues.
● Principal Design Advisor – will facilitate hazard reviews and mitigation
● Early Contractor Involvement – will facilitate provision of cost, risk and construction phasing
advise together with on-site survey management.
● Council Technical Teams – will input to specific design inputs relating to operations and
management
The Design Manager and technical disciplines will be provided by Mott MacDonald. Early
contractor involvement will be provided by Balfour Beatty. Both teams have been engaged in the
production of the Western Link OBC and have extensive knowledge of the project. They are
therefore well placed to continue the design process without delay.
During RIBA stage 4 the design team will be led by the D&B Contractor who develop the detailed
design and target cost for the project.
4.1.3.2 Planning Team
Mott MacDonald will provide a planning lead who will report to the Project Manager and co-ordinate
the activities required to prepare a planning application. The planning team will be formulated from:
● Environmental and Technical consultants from within Mott MacDonald, responsible for
producing an Environmental Impact Assessment and Transport Assessment.
● Flood risk consultants from CH2MHill, with responsibilities including flood risk, modelling and
assessment on development land surrounding the Western Link design and any implications a
road may have on the surrounding water courses and local hydrological setting.
● Consultation consultants Resolve Public Affairs responsible for managing public and
stakeholder consultation exercises prior to planning and preparing a statement of community
involvement.
● Internal WBC communications and planning teams who will support the planning and
consultation processes.
During RIBA stage 4, the planning consultant will be retained to provide advice to the council in
discharging planning conditions. Responsibility for discharging appropriate conditions will be
transferred to the D&B Contractor.
39
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
4.1.3.3 Procurement Team
The procurement team will be led directly by the Project Manager and will include representatives
of the council’s internal legal and procurement teams. The procurement team will be responsible
for producing procurement documents for issue as part of the OJEU tender. The team will also lead
the review of tender returns and recommend a contractor selection to the Project Board.
At the end of stage 4, the procurement team will be responsible for drafting the D&B contract and
co-ordinating completion ahead of contract award.
4.1.3.4 Land and CPO Team
The Project Manager will lead the Land and CPO team directly. The team will be made up of:
● Land Consultant – Lambert Smith Hampton who will be responsible for undertaking land
referencing, updating land costs and advising on land acquisition
● Legal Advisor – TLT Partnership who will be responsible for advising WBC on CPO, SUO, Blight
and Part1 Claim issues.
● Council Legal and Property Teams who will provide the project team with further legal and
property support.
During RIBA stage 3 the team will prepare relevant legal documents and orders for the scheme
and lead the process of negotiation with land owners. During stage 4 the team will publish the CPO
and SUO, continue land negotiations and lead preparations for a Public Inquiry and potential land
inquiry.
4.1.3.5 Business Case Team
Mott MacDonald’s Business case lead will continue to lead the Business Case Work Package
during stages 3 and 4. They will co-ordinate responses to DfT queries on the OBC during stage 3
and prepare a draft FBC for DfT review prior to Public Inquiry during stage 4. Their inputs will
conclude with submission and approval of the FBC at the end of stage 4.
The business case work package will necessitate involvement from Mott MacDonald Economic and
Social advisors as well as the council finance team.
40
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
5 Assurance
This section sets out the project plan, key assurances and approval milestones part of the Western
Link. The project assurance responsibilities which have been set by the Project Executive are
outlined below.
5.1 Formal assurance and review points
An internal Warrington Borough Council plan has been put in place to ensure the project is
objectively reviewed at key decision points. This ensures that Western Link remains on track and
progresses to the next stage of project development. A number of key review points have been set
and will be undertaken by a review team comprising of Warrington Borough Council officer’s
independent of the Western Link Scheme.
5.2 Statutory Powers/Consent
For all works that take place under Western Link planning permissions, land acquisition,
environmental consents and traffic regulations will be obtained. These statutory undertakings will
pass through the Executive Board and Programme Board approval process before being initiated.
This approval responsibility has been incorporated into the governance arrangements for Western
Link in order to provide assurance that major actions that would contribute substantially to scheme
development have sufficient levels of review and control.
The following are the relevant pieces of legislation that broadly (but not exclusively) cover how
activity will be coordinated as part of the Western Link:
● Highways Act 1980;
● Planning and Compulsory Purchase Act 2004;
● Town and Country Planning Act 1990;
Business Case
Review2019
Pre-Implementation
review2019
Operational Benefits Review
2021
● Confirm the business case
once the OBC has been
approved
● Review scheme design
● Confirm objectives, outputs
and desired outcomes of the
scheme
● Ensure the proposed plan for
delivery and management is
robust;
● Review procurement process
and the contract in place
● Reaffirm justification for the
investment
● Review project risk and
contingencies
● Ensure change control is in
place
● Review benefits realisation
plan and confirm the benefits
are clearly set out
● Assess the contract and
contract management
procedures
● Identify any key lessons learnt
41
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
● Road Traffic Regulation Act 1984;
● Land and Compensation Act 1973;
● Equality Act 2010; and
● Town and Country Planning Act (Environmental Impact Assessment) 2011.
5.3 Financial Management
The Executive Board will be responsible for making all major financial decisions, or delegating
responsibility for those decisions to the relevant departmental representative. All other approvals
and relevant authorising parties are shown in Table 11.
Table 11: Financial delegation amongst key members of the project governance structure
Role Financial delegation and responsibility
Department for Transport (DfT) Approval authority for the release of DfT funding following submission of a successful MSBC.
Strategic Management Team Responsible for the running of all three departments within WBC. Responsibility for the Western Link falls within the remit of the Director for Economic Regeneration, Growth and Environment.
Capital investment programme Responsible for authority and scrutiny of WBC’s capital borrowing element of the scheme funding.
WBC Waterfront
Programme Board
No financial approval within Terms of Reference.
Waterfront Programme Board makes recommendations to the relevant departmental heads.
Provides oversight of all projects that sit within the ‘waterfront’ project portfolio, of which, Western Link is included.
Western Link Project Board Responsible for the approval of day-to-day exceptions raised by the Project Manager.
Required to report any reports of concern to Programme Board.
Project Manager Responsible for the commissioning of day to day work, approval of invoices and managing the project budget.
Source: Warrington Borough Council
In following the Warrington Borough Procurement Guide – legislation that ensures contracts are
managed appropriately - a contracts register will be used to document all contracts that are more
than £20,000 and under £50,000. For contracts in excess of £50,000, these will be presented to the
Central Commissioning and Procurement Team to update the Central Contracts Register.
In order to the manage escalating works or commissions costs, the Senior Responsible Officer and
Programme Manager will contact the project board as soon any variations occur or are likely to
vary. This includes advising the quantum of the variation and potential options to realign
deliverables with the budget where practicable.
5.4 Gateway Process
To monitor the delivery of Western Link the scheme will be managed through Warrington’s
Gateway Process. The Gateway Process is a systematic review process that is undertaken at
critical points for projects which the council deem to be important or high-risk. The system brings
about the following advantages:
42
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
● Compliance with best practice;
● Stakeholder involvement;
● A robust audit trail;
● Setting of relevant and realistic targets; and
● Deployment of skills to a project.
The staged delivery philosophy outlined in subsequent sections has been used to mould the
gateway stages for Western Link. This has led to the inclusion of the following Gateways which
also align with assurance review points set out in section 5.1.
5.4.1 End of stage 3 gateway
This is aligned with the business case review assurance point and will involve Project Board
gateway review and approval of:
● Developed design;
● Stage 3 costs;
● Planning submission;
● Proposed procurement process and documents;
● Any updates to scheme objectives, outputs or outcomes; and
● Proposed delivery process for stage 4.
It will also extend to Council Executive Board Approval of the recommended approach to property
acquisition, resulting in granting the Project Executive Board approval implement the approach.
5.4.2 End of stage 4A gateway
This is aligned with the ‘Pre-Implementation’ assurance point and will involve Project Executive
Board approval of:
● The selected contractor;
● The procurement process followed; and
● The management processes for the next stage including management of risk and change;
It will also be the point at which the Project Executive Board commences implementation of the
approved property acquisition approach.
5.4.3 End of stage 4B gateway:
This is aligned with the ‘operational benefits’ assurance point and will involve Project Board
Approval of:
● Final detailed designs for the scheme;
● Final target cost;
● Construction Contract include distribution of risk and management processes; and
● The Final Business Case, including plans for benefits realisation.
The Project Manager will monitor the progress of the project during each project stage and be
responsible for submitting the stage 3, 4A and 4B information to the Council for review and
43
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
approval. WBC will draw on the services of third party consultants to assist in the review of the
submitted information. Consultants will be appointed to provided technical review of designs costs.
5.5 DfT Assurance
As the DfT is a primary funding organisation, WBC is required to work within the standards outlined
in the ‘Full Business Case – Guidance for the Technical Project Manager’. This outlines the
process of progressing business cases in Figure 10.
Figure 10: DfT Transport Business Case process
The DfT assurance process is covered by the use of gateways at key stages, these are points
where the scheme promoter (WBC) provides evidence to the DfT regarding continued progression
and funding of the scheme. The current OBC submission would represent the completion of Phase
2 and, if successful, WBC would move onto Phase 3.
Further to the assurance above, WBC has engaged an independent consultant to provide ongoing
scrutiny and review in the development of the business case for submission to DfT. This role will
provide significant independent assurance to the process and be supplemented by a submission to
the DfT regarding their thoughts on whether the OBC is suitable; including an assessment of where
further work is still required.
44
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
6 Delivery programme
Warrington Borough Council is well positioned to deliver the Western Link efficiently and effectively.
The council has committed to proceeding with the next stage of work beyond OBC and progress
preparation tasks from January 2018, working at risk until a DfT decision on the OBC in May 2018.
The project and actions required for delivery are well understood. They have been assessed in
consultation with the full project team and have the support of key stakeholders. Figure 11 below
illustrates the RIBA work stages covered to date and those that will be covered and are described
in this Management Case.
Figure 11: RIBA work stages and Western Link progress
Source: RIBA/ Mott MacDonald
To date RIBA stages 0-2 are complete and the remaining delivery tasks over stages 3-5 have been
split into 6 work packages which are described in more in detail in section 7.0.
The future delivery programme is split into distinct stages as follows:
● Preparation for Stage 3. This includes progression of ecology surveys, further land and legal
reviews including further land referencing; liaison with statutory bodies; liaison with the public
and stakeholders; scoping and arranging access for further survey work as well as liaison with
the DfT over the submitted OBC. The purpose of this stage is maintain project momentum and
place the council in a strong position to commence Stage 3 fully, following fund approval. It
therefore concludes in May 2018.
● Stage 3 which focusses on development of the design and land investigations to a point where
there is appropriate certainty on the route alignment and land requirements to: submit a
45
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
planning application; seek council resolution on CPO and commence procurement of a Design
and Build (D&B) contractor. Stage 3 concludes in May 2019 with a full gateway review.
● Stage 4A during which: a D&B contractor will be procured; planning permission will be
determined and the final CPO will be prepared. Stage 4A concludes in October 2019 with:
Project Board approval of the D&B contractor selection; granting of planning permission and
making of the CPO.
● Stage 4B where the D&B contractor will progress the detailed scheme design and prepare a
target cost. It is also during this stage that a Public Inquiry is expected to occur and a final
business case will be submitted to DfT. Stage 4B will conclude in February 2021 with: a full
gateway review: Secretary of State (SofS) decision on the Inquiry, DfT approval of the FBC and
D&B contract award.
● Stage 5 is the construction stage during which the scheme will be built and be handed over to
WBC. The scheme is expected to be complete in Jan 2024.
Figure 12 provides a high-level delivery programme illustrating the philosophy behind the delivery
methodology.
Figure 12: Western Link Stage 3 & 4 High Level Programme
Source: Mott MacDonald
Tables 12 and 13 provide further detail on the key milestones and associated delivery dates for Western Link.
A full detailed delivery programme is contained in Appendix N.
Table 12: Stage 3 delivery programme – key milestones
Key project milestone Date
WP0 – Project Management
Stage 3 Design and Planning Submission Approval April 2018
Council Executive Board Approval of CPO and SUO April 2018
WP1 – Technical Design and Approvals
Completion of Initial Surveys September 2018
46
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Key project milestone Date
Completion of Ground Investigation. December 2018
3D Model Complete October 2018
Developed Design Complete March 2019
Network Rail Form 2 Approved April 2019
Environment Agency Approvals in Principle Feb 2019
Natural England Approval of HRA and Mitigations Feb 2019
Stage 3 Costs Complete April 2019
WP2 - Planning
EIA Complete Feb 2019
Consultation Complete March 2019
Transport Assessment Complete March 2019
Planning Application Submitted May 2019
WP3 - Procurement
Tender Documents Complete May 2019
Approval to Issue Tender May 2019
WP4 – Land, CPO/SUO and Inquiry
Land Referencing Updated Dec 2019
CPO Prepared April 2019
SUO Prepared April 2019
WP5– Business Case
DfT Decision on OBC May 2018
Table 13: Stage 4 delivery programme – key milestones
Key project milestone Date
WP0 – Project Management
Approval of Selected Contractor Oct 2019
Stage 4 Design and Target Cost Approval Jan 2021
WP1 – Technical Design and Approvals
Additional Survey Complete April 2020
Detailed Design Complete Sept 2020
Target Cost Complete Dec 2020
WP2 - Planning
Planning Permission Granted Aug 2019
Pre-Commencement Conditions Discharged Dec 2020
WP3 - Procurement
Tender Documents Issued May 2019
PQQ Returns July 2019
ITT Issued July 2019
ITT Returns Sept 2019
Contractor Selection Oct 2019
D&B Contract Award Feb 2021
WP4 – Land, CPO/SUO and Inquiry
CPO/SUO Published August 2019
Listing for Inquiry Dec 2019
Public Inquiry July 2020
47
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
SofS Decision Dec 2020
Land Acquired for Scheme Feb 2021
WP5– Business Case
Draft FBC Issued Feb 2020
Final FBC Issued Dec 2020
DfT Approval of FBC Feb 2021
Source: Mott MacDonald
Beyond RIBA stage 4 the project will enter stage 5 – construction. The anticipated programme for
the construction period for the Western Link scheme has been produced with the advice of Balfour
Beatty who has been providing the council with early contractor involvement and who have
benchmarked the construction duration against other highways schemes being delivered. The
construction period is programmed to run from February 2021 to January 2024. Further detail on
the construction programme can be found in Appendices K and N.
48
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
7 Implementation of work packages
7.1 Introduction
This section sets out the key work packages for executing the Western Link in an efficient and well
manged manner. The key issues that may affect the delivery and implementation of Western Link
are also stated.
The Project Manager is responsible for ensuring the day to day delivery of tasks and work
packages, as well as reporting to the Senior Responsible Officer and the Programme board to
bring to light any issues with the project programme. The key work packages and project stages
have been highlighted already in Section 6 and further defined by the Work Breakdown Structure
below in Table 14.
Table 14: Western Link stages 3 & 4 work breakdown structure
Stage 3 Stage 4
WP0 3.0 PM Governance and Review
● 3.0.1 Project Team Meeting
● 3.0.2 Project Board Meeting
● 3.0.3 Stage 3 Gate Review
● 3.0.4 Council Executive board meeting
● 3.0.5 Communications and Engagement
● 3.0.6 Project Management Documents
4.0 PM Governance and Review
● 4.0.1 Project Team Meeting
● 4.0.2 Project Board Meeting
● 4.0.3 Stage 4 Gate Review
● 4.0.4 Council Executive board meeting
● 4.0.5 Communications and Engagement
● 4.0.6 Project Management Documents
WP1 3.1 Technical Design and Approval
● 3.1.1 Design Team Meetings
● 3.1.2 Surveys
– 3.1.2.1 Topographical
– 3.1.2.2 GPR
– 3.1.2.3 CCTV Drainage
– 3.1.2.4 GI
– 3.1.2.5 Ecology
● 3.1.3 Traffic Modelling
● 3.1.4 Junction Design
● 3.1.5 Highways Design
● 3.1.6 Drainage Design
● 3.1.7 Utilities Design
● 3.1.8 Structures Design
● 3.1.9 Environmental Design
● 3.1.10 Geotechnical Design
● 3.1.11 H&S/CDM
● 3.1.12 Construction Phasing
● 3.1.13 Appraisals
● 3.1.14 Costing
● 3.1.15 SARS
4.1 Technical Design and Approval
● 4.1.1 Design Team Meetings
● 4.1.2 Surveys
● 4.1.3 Traffic Modelling
● 4.1.4 Junction Design
● 4.1.5 Highways Design
● 4.1.6 Drainage Design
● 4.1.7 Utilities Diversion
● 4.1.8 Structures Design
● 4.1.9 Environmental Design
● 4.1.10 Geotechnical Design
● 4.1.11 H&S/CDM
● 4.1.12 Construction Phasing
● 4.1.13 Appraisals
● 4.1.14 Target Cost
WP2 3.2 Planning Application
● 3.2.1 Planning Team Meeting
● 3.2.2 Screening
● 3.2.3 EIA
4.2 Discharge of Planning Conditions
● 4.2.1 Planning Team Meeting
● 4.2.2 Planning Condition Discharge
49
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Stage 3 Stage 4
– 3.2.3.1 Ecology
– 3.2.3.2 FRA
– 3.2.3.3 Health Impact Assessment
– 3.2.3.4 Contaminated Land
Assessment
– 3.2.3.5 Noise
– 3.2.3.6 Air Quality
– 3.2.3.7 Heritage
● 3.2.4 SCI
– 3.2.4.1 Consultation
● 3.2.5 Drawings
● 3.2.6 Transport Assessment
● 3.2.7 Submission
WP3 3.3 Procurement (First Stage)
● 3.3.1 Procurement Meetings
● 3.3.2 Preparation
4.3 Procurement (Second Stage)
● 4.3.1 Procurement Meetings
● 4.3.2 Tender
● 4.3.3 Evaluation and Selection
● 4.3.4 PCSA
● 4.3.5 Contract Award
WP4 3.4 CPO, SUO, Land
● 3.4.1 Land Team Meeting
● 3.4.2 CPO
– 3.4.2.1 Preparation
● 4.4.3 SUO
– 4.4.3.1 Preparation
4.4 CPO. SUO, Land
● 4.4.1 Land Team Meeting
● 4.4.2 CPO
– 4.4.2.1 Publication
– 4.4.2.2 Negotiation
● 4.4.3 SUO
– 4.4.3.1 Publication
– 4.4.3.2 Negotiation
● 4.4.4 Public Inquiry
– 4.4.4.1 Preparation
– 4.4.4.2 Inquiry
– 4.4.4.3 Determination
● 4.4.5 CPO/SUO/Implementation
WP5 3.5 OBC/FBC/MSBC
● 3.5.1 OBC DfT Review
4.5 OBC/FBC/MSBC
● 4.5.1 FBC DfT Review
● 4.5.2 FBC DfT Review
● 4.5.3 FBC Update
● 4.5.4 FBC Final
Source: Mott MacDonald
7.2 Work Package 0 – Project Management, Governance, Review and
Communications
Work Package 0 will be led by the WBC Project Manager and includes the activities required to
ensure effective management of the Western Link. This will extend to:
● Management of the project team including project team meetings;
● Reporting to the Project Executive Board;
● Co-ordinating project reviews;
● Preparing and maintaining project documents, such as:
– The project execution plan
50
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
– Financial management plan
– Programme management plan
– Risk management plan
– Quality management plan
– Communications management plan
– Information management plan.
Warrington Borough Council, in partnership with a consultancy firm, will conduct public consultation
and stakeholder engagement. To ensure effective communication of the project to multiple
stakeholders, both the Project Manager and an Officer in the Council’s Communication Department
will be responsible for managing communication with stakeholders.
7.3 Work Package 1 - Technical Design & Approvals
The scheme designer will be principally responsible for the design of the Western Link and are
contracted to deliver the project to completion of stage 3. Work package 1 will be led by the
scheme designer’s Design Manager reporting to the Project Manager, with the delivery team
including the following disciplines:
● Traffic Modelling
● Highways Design
● Drainage Design
● Utilities Design
● Structural Design
● Environmental Design
● Geotechnical Design
● Principal Designer
Responsibilities of the Design Manager and Design Team include scoping of surveys, design and
costing of the preferred route to RIBA stage 3, ahead of a planning application. Hazard
identification and reduction meetings will be held throughout the process.
A key part of the work package will be to obtain the necessary statutory approvals from relevant
bodies based on the developed design. It will be the responsibility of the design team, with support
from the Project Manager, to schedule discussions with key stakeholders and progress the
appropriate documentation to satisfy stakeholder requirements.
The SCAPE Framework will be used to provide early contractor involvement for the design of
Western Link. Acting as a part of the WP1 design team, a contractor will provide: cost advice;
buildability and construction phasing advice; health and safety inputs; survey management and risk
quantification.
The stage 3 design and costs will be presented to the Senior Responsible Officer and third-party
reviewer as part of the stage 3 Gateway review. Advance discussion will be held with relevant
internal council teams to agree the principles of the assessments subsequently formulating the
application.
Stage 4 design will be led by the appointed design and build contractor and will focus on
preparation of detailed design ahead of construction and completion of any outstanding statutory
approvals. Stage 4 Design will conclude with preparation of a Target Cost and submission of a
stage 4 package to WBC for gateway review.
51
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
7.4 Work Package 2 – Planning
A work package specifically related to preparation and submission of a planning application has
been created. This will be led by a planning advisor with a delivery team made up of designers,
Environmental advisors and Transport Planners. There is a close relationship between Work
Package 1 and 2 with many of the delivery team members being involved with both work packages.
The planning application will include an Environmental Impact assessment with the following key
components:
● Ecological Mitigations
● Health Impact Assessment
● Contaminated Land Assessment
● Noise Assessment
● Air Quality Assessment
● Heritage Assessment
● Archaeological Assessment
The Environmental Impact assessment will require a flood risk assessment, a consultant will be
commissioned to provide flood risk modelling and assessment for Western Link. They will utilise
outputs from a flood model to calculate highways drainage and flood risk associated with Western
Link.
The traffic modelling and design undertaken in WP1 will inform completion of a transport
assessment for the scheme.
Further Public Consultation will be undertaken as part of Work Package 2 in support of a Statement
of Community Involvement for the Planning Application. This will be led by a consultant partner and
take the form of a staged process, giving specific focus to sensitive areas of the scheme.
Preparation of the planning application will require consultation with statutory authorities such as
Natural England and the Environment agency. This will be the responsibility of the planning
advisors, supported by relevant discipline leads and the Project Manager.
The planning application will be submitted for council and third-party review as part of the stage 3
gateway review. Advance discussion will be held with relevant internal council teams to agree the
principles of the assessments formulating the application.
During stage 4 of the project, WP2 will focus on discharge of planning conditions and finalisation of
any outstanding approvals. This will be the responsibility of the design and build contractor except
where conditions need to be specifically discharged by WBC in which they will be the responsibility
of the project manager,
7.5 Work Package 3 - Procurement
Work Package 3 will be led by the Project Manager, with support from the WBC procurement office
and legal team. The procurement team will recommend a procurement route to the project board
and will be responsible for preparing and issuing the necessary procurement documentation,
managing the procurement process and co-ordinating the evaluation of responses.
Procurement will be in two stages, with initial contractor selection undertaken on the basis of stage
3 design information via an OJEU compliant process and final contract award taking place following
a period of detailed design (stage 4).
52
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
7.6 Work Package 4 - Land acquisition, Legal Advice and Public Inquiry
Finalisation of the land required for the scheme will follow from finalisation of the route alignment
undertaken in WP1.
A land consultant will be appointed to provide a full land referencing exercise based on the stage 3
route alignment. This will inform updated land cost estimates and enable the preparation of a
compulsory purchase order and stopping up orders. The CPO and SUOs will be prepared by legal
advisors, appointed by WBC to advise on legal matters related to land, blight and Part 1 claims.
The draft CPO and SUOs will be put forward to the project board and WBC executive board for
approval as part of the stage 3 gateway review. They will also be reviewed with the DfT prior to
being made.
It is anticipated that the project will be subject to a Public Inquiry and WS4 will focus on the
preparation for this. WBC will appoint Legal Counsel to assist with preparation of evidence and
statement of case.
From the point of Council Executive Board resolution on the preferred route in November 2017,
WBC will undertake discussion and negotiation with affected land owners. This will continue during
preparation for Inquiry in order to avoid the need for CPO if possible.
Negotiation over the acquisition of land will be conducted by Officers from Warrington Borough
Council Property and Legal Departments. Officers from the schemes External Partner – Warrington
and Co – will also assist with the negotiation process. This will be considered as the last resort for
the acquisition of the required land.
7.7 Work Package 5 - Business Case
A Consultant will be appointed for the Business Case Development of the Western Link. The work
package will be led by the consultant’s Business Case lead. Drawing on the expertise of an internal
team of transport, economic, social and technical advisors. Financial, Commercial and
Management cases will require direct input from WBC.
Discussion and liaison will be undertaken with the DfT during the OBC review period up to May
2018.
The final business case will be drafted based on the stage 3 design information and presented to
the DfT for an initial review prior to any public Inquiry. Completion of the final business case will be
undertaken following approval of the Target cost by WBC at the end of stage 4, with DfT approval
of the FBC triggering contract award.
7.8 Construction
The construction stage of the project – stage 5 will be led by the appointed design and build
contractor. A nominated Construction Manager and Clerk of Works from the infrastructure Delivery
Service group will oversee the project from the client side
7.9 Key issues for implementation
The table below defines the key issues and risks that have been identified as having the potential
to affect scheme implementation as well as associated mitigation measures to address the
impacts.
53
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Table 15: Key implementation issues
Issue Impact Mitigation
Work Package Management and Co-ordination
The division of tasks into distinct packages has potential to create disconnect between the outputs being produced. This could delay the programme whilst issues are rectified or reduce the overall quality of delivery
The Project Management team will be responsible for co-ordinating work package activities to ensure key interdependencies are managed and the overall programme is maintained. This will be reviewed and discussed at project team meetings.
Resource Management The project is likely to experience peaks in work load and other periods of relative quiet for some teams. The right resource needs to be available consistently throughout the project to ensure quality and delivery to programme.
Resource will be planned in advance by each organisation based on the delivery methodology and scope defined in the project plan. This will be monitored and evaluated each month to reforecast demand as necessary.
Information Management. The vast amount of information that is produced needs to be accessible to the right people at the right time. Failure of this could delay the programme or negatively impact third party communication.
The project Information management plan will set out the procedures to be adopted for production, storage and issue of information both within the project team and externally.
Configuration Management. Failure to ensure a consistent basis of design between disciplines or failure to maintain appropriate version control could result in wasted work or poor-quality outputs.
The information management plan will set out a consistent version control procedure for all teams. A common data environment will be used to progress designs.
Communication and Teamwork The delivery team will be large and drawn from a variety of disciplines, backgrounds and companies. Failure to achieve good communication and a spirit of collaboration will negatively impact the delivery programme and quality.
Each will package will hold specific work package meetings to discuss issues. There will be an overall project meeting to maintain communication access work packages. Official communication protocol will be set out in the communications plans but alongside this team days will be held to encourage collaborative working. Co-location of key team members will be utilised at relative points on the programme.
Health and Safety The Health and Safety of project team members and third parties during design and construction will need to be paramount to prevent injury or harm.
The design team will conduct hazard review meeting during the design process to identify and mitigate potential risks. Hazard reduction will continue on site with the contractor conducting regular H&S reviews. All works will need to be undertaken with an appropriate risk assessment and method statement. Key individuals will be subject to specific risk meetings.
Strategy and Objectives The scheme has been developed to meet specific objectives, defines based on the need for intervention. Should these change, the nature of the scheme would need to be reviewed and the intended outputs altered.
Ensure that scheme objectives are based on sound evidence and continue to review their relevance throughout the project.
54
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
8 Risk management
The management of risk and uncertainty will be key to the successful delivery of the scheme, as it
will identify threats to project delivery and enable effective risk management actions to be
assigned. A risk management strategy will be developed and reviewed at key stages of project
development. An affective risk management strategy should include:
● A continuous approach;
● Thorough identification of risks;
● Provide active risk avoidance and mitigation;
● Effectively communicate the risks to the project team;
● Deliver the scheme objectives to cost, quality and time indicators.
8.1 Risk Management Strategy
An effective risk management strategy for the project will be based on the principles for risk
management contained within the OGC PRINCE2 guidance. The procedure for identifying key
risks should follow as below:
● Identify: complete the risk register (as appropriate to the area of the project and/or the producing
organisation) and identify risks, opportunities, and threats;
● Assess: assess the risks in terms of their probability and impact on the project objectives;
● Plan: prepare the specific response to the threats (e.g., to help reduce or avoid the threat), or
this could also be to plan to maximize the opportunity if the risk happens;
● Implement: carry out the above in response to an identified threat or if one occurs; and
● Communicate: report and communicate the above to relevant project team members and
stakeholders.
Risk management needs to be an ongoing process, shown in Figure 13 below.
Figure 13: Risk Management Process
The overall risk management strategy will be owned by the SRO; however, the day-to-day
management of the strategy and project risk will be managed by the Project Manager as the key
55
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
project officer. As an extension of this, discussion around the risk register will be a standing item on
the monthly Project Board meetings. This should enable active management of the project risks
and wider communication between different members of the project team. This will include a
monthly risk report to document risks and key actions relating to risk.
The process for escalation of risks is outlined below to demonstrate accountability levels within
WBC. Where an individual does not have appropriate accountability, the risk would need to be
escalated and managed at a higher level. Risks may also require escalation if they cannot be
resolved within the Construction or Client team or if the risk has wider impacts beyond Western
Link. The escalation scale is as follows:
● Project Manager;
● Programme Board;
● Senior Responsible Officer;
● Strategic Management Team; and
● Executive Board.
8.2 Current Risk management
There are currently two levels of project based risk management:
● Project Risks: those affecting the cost, scope and timescale for the project; and
● Project Management and Delivery Risks: those presenting wider risks to the client body
These are both discussed below.
8.2.1 Project Risks
Project risks have been assessed as part of the Quantified Risk Assessment (QRA) process
adopted for the Western Link which is discussed further in section 3 of the financial case. In
summary, the QRA process involved the population of risk register by each of the disciplines
involved in delivering the OBC.
The populated risk registers formed the basis of discussion at risk work shops during which the
risks were reviewed, added to/amended and quantified where appropriate. The resultant project
risk register which covers all risks both quantifiable and qualitative risks as well as the full QRA are
contained in Appendix O, but the top ten project risks resulting from this process are:
Table 16: Top Ten Project Risks
Risk Consequence Mitigation
Earthworks - Waste Disposal
Potential for all excavated ground between MSC and St. Helens Canal/Sankey Brook to be contaminated - high cost of disposal to non-hazardous and hazardous landfill
High waste disposal costs; significant truck movements with accompanying H&S and Environmental risks
Where possible minimise excavation into waste deposits - adoption of geocell within design. Increased quantities could be remediation
Vertical alignment tie in difficulties due to existing topography and height restrictions not accurate on OS Mapping and LIDAR
Worst case is the route could not be completed to ensure the safe movement of vehicles and pedestrians and full re-design is required.
Full topographical survey of the preferred route required to confirm horizontal alignment risk can be mitigated. (E.g. through WCML and Walton Viaduct, around electrical grid site)
Utility clashes due to limited corridor for route, including all general stats risks
Costly diversions of high level utilities impacted by the construction of the route. Worst case is multiple high
GPR survey of entire preferred route. Modify alignment of preferred route to minimise diversions
56
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Risk Consequence Mitigation
cost diversions are required to complete route
Cost of acquiring businesses where severance results in whole property being acquired.
Additional Cost of Compensation. Early negotiations with claimants to ascertain likelihood of such a claim being received.
Claims for No Land Taken (where properties have now been avoided through route realignment).
Additional Cost of compensation. Maintain access to all properties during works. Obtain traffic management plans at the earliest opportunity for review.
Weather event, stats diversions delayed, supply chain difficulties
Additional construction activities time and cost.
Robust programme, monitoring and management
Additional Inflationary Effects Additional cost Make allowance in risk register for costs
Poor highway foundation due to Gatewarth Landfill encountered beneath road alignment.
Poor ride quality, high maintenance liability, environmental risk of inducing leachate release from landfill, HSE risk of inducing landfill gas release into drainage runs, potential to destabilise landfill slopes; potential radioactive waste.
Minimise excavation into landfill (after 40+ years, much of the biodegradation should have occurred, hence settlement less of an issue than Arpley) - reinstate capping as required. If earthwork <3m height adopt geocell basal reinforcement; if >3m height adopt pile load platforms to transfer load to either Glacial Soils or Rockhead
Design Scope Changes. Additional time and cost Control and definition of scope by Client and delivery team
Traffic Modelling requires wider WBC network Improvements.
Additional cost of construction work Make cost allowance in capital and risk costs. Assess wider network impacts during stage 3 and design necessary junction improvements.
Source: Warrington Borough Council
8.2.2 Project Management and Delivery Risks
WBC also maintains an active risk register that covers wider risks to the council. The top ten risks
are shown in Table 17.
Table 17: Top Ten Project Management and Delivery Risks
Risk Consequence Mitigation
Modelling – Western Link is the first test of the new Warrington Multi Modal Transport Model (MMTM)
Incorrect or challengeable modelling data Assurance role being provided by WSP. Modelling work has had input and check from both AECOM and Mott MacDonald.
CPO Approach – Council has unclear approach to Blight issues, and/or scheme requires CPO and has been subject to some opposition.
Public objection to scheme, loss of reputation for council, delay to scheme. Precedence for future schemes.
Employ solicitor to provide legal advice. Agree CPO and blight approach with executive board. Hold consultation events ahead of planning. Maintain close dialogue with directly affected land owners.
Public Inquiry – Inspector decides against the progress of scheme.
Scheme incurs delays and is either not developed or goes through the appropriate statutory channels to challenge the decision
Maintain project records, maintain consistent project team. Employ third party for assurance role and maintain a risk register. Engage solicitor to assist with legal processes and ensure clear vision and consistent treatment of scheme across all professional appointments and internally within the Council, meeting the legislative, economic, social and environmental requirements to justify the scheme coming forward
Network Rail approvals delay or increase cost of project.
Increased cost and programme. Hold early dialogue with Network Rail. Include approval processes in programme. Employ consultant with knowledge of Network Rail processes.
57
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Risk Consequence Mitigation
Special Parliamentary Procedure (SPP) – if exchange land cannot be offered for affected Commons/open land, scheme could be subject to SPP
Loss of reputation for the Council, delay to project, possibility of elements of the scheme not being able to be delivered.
Investigate options and provide suitable exchange land to avoid SPP
Stakeholder objection. Loss of reputation for council, delay to project.
Hold consultation events ahead of planning. Maintain close dialogue with directly affected land owners and interested parties.
Utilities – additional diversions required and/or statutory undertaker objection to any required CPO is received and remains unresolvable
Additional cost and time, with potential for two public inquiries
Carry out ground survey of area and engage statutory undertakers in scheme development
Ecological mitigation measures required beyond those allowed for.
Additional cost and time. Carry out necessary ecological surveys and hold dialogue with EA and Natural England
Appropriate delivery team is not available.
Additional time and loss of quality. Appoint delivery team early to secure service for project
Failure to obtain Political Support. DfT do not fund scheme. Hold dialogue with MP, Local Members and neighbouring authorities.
Source: Warrington Borough Council
58
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
9 Contract Management
The Senior Responsible Officer (SRO) is responsible for the execution of parties engaged under
the terms of all contracts relating to Western Link. Three contractual arrangements are proposed
for use in the Western Link, these are listed below:
● SCAPE national Civil Engineering and Infrastructure Framework 2015;
● Transportation and Public Realm Consultancy Services Framework 2013; and
● Competitive Dialogue Process, OJEU, Public Contracts Regulations (NEC4 Option C).
The first two of the above contractual arrangements for commissioning work and engaging
companies are well established. WBC intends to undertake engagements over stage 3 and 4
using the first two of these contractual arrangements. This should allow work to progress prior to,
and during, any announcement of a successful funding award from DfT.
RIBA stage 5 (engaging a contractor to deliver a scheme to a target cost price) will require a 2
stage D&B procurement during stage 4 and stage 5 will require NEC4 contract to be issued and
reviewed between WBC and the contractor chosen at the end of the CDP process. This will be
subject to review and clause changes based on the individual positions of both parties. The NEC4
contract will be reviewed and audited by independent consultants as part of the WBC client
assurance provision. Further detail on contract management is detailed in the Commercial Case
59
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
10 Communication and stakeholder
management
10.1 Introduction
This section outlines the key stakeholders who are involved in Western Link, the communications
strategy for the scheme and the communications and stakeholder management plan. Appendices
B and C detail in full the approach taken to date in respect of stakeholder consultation and the
results of that consultation, as well as a forward plan for future consultation as the scheme
progresses through RIBA work stages 3-5 and a full Major Scheme Business case is prepared.
Western Link is a substantial highways infrastructure project, with the potential to impact various
members of the public. Therefore, it is essential to capture the different view-points and consider
them in scheme design and delivery. A stakeholder management plan has therefore been designed
in order to manage the flow of information between both the project team and key stakeholders.
Good communication between both parties is essential in providing a clear understanding of the
Western Link scheme and its acceptance. The management plan will ensure scheme design,
benefits and delivery is clearly communicated.
10.2 Consultation objectives
A number of objectives have been set for the consultation process:
• Raise awareness and understanding of the scheme
• Understand key stakeholder’s views and preferences for scheme design
• Understand the public and political support and acceptability of the scheme
• Provide several opportunities for the pubic to discuss the scheme
• Ensure feedback of the publics thoughts about the project to the Executive Board
10.3 Key stakeholders
Table 18 presents Warrington Borough Council’s stakeholder management strategy for the
Western Link scheme going forward. Here, the stakeholder interest and strategy for managing
stakeholder expectations is outlined.
60
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Table 18: Key Stakeholders
Stakeholder Interest Influence Strategy Responsible for consultation
Consultation start
Consultation end
Consultation frequency
Department for transport
National government body supporting transport and travel country wide.
Approval and awarding of funding for scheme
Communicate project plans and schedule
Project Manager
Already involved On scheme completion
Set meetings at set project milestones
Warrington Borough Council
Warrington Borough Council are the scheme promoter and take charge for Western Link’s delivery.
They are also responsible for the schemes funding alongside Cheshire and Warrington LEP.
Warrington Borough Council are the Local Planning Authority and will define the planning conditions before and during construction.
Keep informed
Project Manager
Already involved On scheme completion
Ad hoc as required
Cheshire and Warrington Local Enterprise Partnership
Cheshire and Warrington LEP seek to drive economic growth and create housing and jobs across the region.
The C&W LEP Performance and Investment Committee is responsible for approving the Business Case and release of Growth Deal funding to support the
delivery of the scheme.
Keep informed
Project Manager
Already involved On scheme completion
Ad hoc as required
Highways England
Operates, maintains and improves England’s motorways and major A roads.
Western Link will form a addition to the Primary route network in Warrington.
Interest in the schemes locations and integration with current highways network in Warrington.
Communicate project plans and schedule
Project Manager
On business case approval
On scheme completion
Ad hoc as required
Warrington & Co
Warrington & Co is an external partner to the Western Link project. The organisation is a public and private sector growth delivery agency. The Homes Community Agency, Cheshire and Warrington LEP and Warrington Borough Council are long standing members of Warrington &Co.
Direct activities that relate to land acquisitions, strategic regeneration and ensuring Western Link delivers in terms of jobs and growth for Warrington.
Keep informed
Project Manager
Already involved On scheme completion
Ad hoc as required
61
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Stakeholder Interest Influence Strategy Responsible for consultation
Consultation start
Consultation end
Consultation frequency
Transport for the North
The scheme has been ranked as ‘endorsed intervention’ in the TfN northern scheme review11. This means that TfN recognise the contribution that the scheme would make to the regional economy
Transport for the North (TfN) has endorsed the intervention noting its strong contribution to the labour market and business to business links for goods.
Keep informed
Project Manager
On business case approval
On scheme completion
Ad hoc as required
Land Owners
There may be some land take as part of the Western Link Scheme. in this case. consultation and negotiation will be pivotal to the schemes success.
Warrington Borough Council will need to consult relevant land owners once a definitive route has been decided upon.
Public meetings to consult on plans, press releases and website
Press & Communications Officer
On business case approval
On scheme completion
Regular meetings during detailed design, then ad hoc as required.
Local residents and community
Arguably the most important of the Stakeholders, they will be the end user of the Western Link scheme.
The community’s views and feedback on design is paramount to the schemes delivery. Sufficient public consultation is required to gauge the community’s thoughts and views on Western Link.
Public meetings to consult on plans, press releases and website
Press & Communications Officer
On business case approval
On scheme completion
Press and website releases on business case approval, construction start and scheme completion.
Peel Holdings
Peel have had a strong influence in the North West. They look to refurbish and expand the Port of Warrington.
In response to public concerns over increases in port traffic and congestion, Peel are committed to working with regional stakeholders to lobby Government for funding for surface access transport improvements. Expanding bridge crossings and providing improved transport links through Warrington Town Centre is critical to facilitate the desired growth for Port Warrington
Keep informed
Project Manager
On business case approval
On scheme completion
Regular meetings during detailed design, then ad hoc as required.
The Homes and Community Agency (HCA)
The HCA currently own land holdings in the south of Warrington, referred to as ‘Warrington South’ – an area which covers 350ha of land and has the potential to create 6000 new jobs and release land for business equating to 11,000 new jobs.
Homes and Communities Agency support the provision of improved transport access that will enable their land to be developed for housing and employment.
Keep informed
Project Manager
On business case approval
On scheme completion
Ad hoc as required
62
https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Stakeholder Interest Influence Strategy Responsible for consultation
Consultation start
Consultation end
Consultation frequency
Network Rail Network Rail own and maintain the West Coast Mainline, Helsby line and Fiddlers ferry line. All of which the scheme must cross.
Network Rail must approve any works taking place on Network Rail land or assets. Works must be phased and planned to suit rail operations to network rail satisfaction and approval
Communicate project plans and schedule
Project Manager/Design Manager
On business case approval
On scheme completion
Regular meetings during detailed design
Source: Warrington borough Council / Resolve
Mott MacDonald | Warrington Western Link 63 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
10.4 Consultation
Consultation can be split into two parts:
1. Public engagement: delivered through questionnaires and public consultation events across
the Warrington and Cheshire area in two rounds. Initial public consultation as part of project
stage 2A was undertaken during July 2017 and further consultation as part of stage 2B in
September 2017.
2. Stakeholder engagement: A diverse range of stakeholders exist for the Western Link
scheme, as noted in Table 13, for groups that have direct inputs to the Business Case and
scheme design. Consultation with stakeholders was also undertaken in July and again in
September 2017.
10.5 Public Consultation
Public Consultation was conducted in two rounds and delivered through a range of public
consultation events.
The first round of consultation took place during stage 2A in July 2017 and presented 6 route
options for Western Link. The second round of consultation took place during stage 2B in
September 2017 and focussed on the recommended route option.
For both rounds, Warrington Borough Council introduced questionnaires for the public to
answer. This provided an opportunity for the public to first voice their opinion on the six options
presented at stage 2A and then again after a recommended route had been chosen at stage
2B.
10.5.1 First Round Consultation
For the first round of consultation, a booklet containing information on the study area, the alternate
route options for Western Link and the timeline for the Western Link were included. Sixteen-page
booklets with pull out, freepost feedback forms were available at all consultation events and at
local libraries and community hubs to enable people to review the proposals and to have their
say. The booklet explained the proposals in an accessible format and provided a mechanism for
feedback.
The printed document contained the following information: Overview, Aims, Location Context,
Route Options, Yellow Option, Orange Option, Red Option, Pink Option, Purple Option, Green
Option, Route Options Comparison, Timeline and Contact Details. Extracts from the booklet can
be found below in Figures 14 and 15.
Mott MacDonald | Warrington Western Link 64 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Figure 14: Public consultation – Western Link Proposal Booklet
Mott MacDonald | Warrington Western Link 65 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Figure 15: Public consultation – Western Link Proposal Booklet
Source: Warrington Borough Council
18 public consultation events were undertaken in July 2017. The dates of the events and their
attendance can be found in Table 18. The consultations were hosted at a variety of places
within the town centre and across the Borough to give as many Warrington residents and
stakeholders the opportunity to attend an event.
Table 19: Warrington Borough Council Public Consultation Events - July 2017
Date Time Location Attendees
Saturday 1 July 10am – 5pm Golden Square Shopping Centre
Over 500
Monday 3 July 3pm – 8pm Burtonwood Community Centre
38
Tuesday 4 July 3pm – 8pm Orford Neighbourhood Hub 67
Wednesday 5 July 3pm – 8pm Appleton Parish Hall 87
Thursday 6 July 3pm – 8pm Walton Hall, 47
Friday 7 July 3pm – 8pm The Peace Centre 168
Mott MacDonald | Warrington Western Link 66 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Date Time Location Attendees
Saturday 8 July 10am – 5pm Golden Square Shopping Centre
Over 500
Monday 10 July 3pm – 8pm Waterside Inn 112
Tuesday 11 July 3pm – 8pm Winwick Leisure Centre 9
Wednesday 12 July 3pm – 8pm Woolston Neighbourhood Hub
58
Thursday 13 July 3pm – 6pm St John’s Community Church Hall
44
Friday 14 July 5pm – 8.30pm Whittle Hall Community Centre
43
Saturday 15 July 10am – 5pm Golden Square Shopping Centre
Over 500
Monday 17 July 3pm – 8pm Birchwood Leisure Centre 33
Tuesday 18 July 4.30pm – 8.30pm Lymm Village Hall 18
Wednesday 19 July 10am – 5pm Golden Square Shopping Centre
Over 500
Thursday 20 July 3pm – 8pm Kings Community Centre 250
Friday 21 July 10am – 5pm Sainsbury’s, Santa Rosa Boulevard
323
Source: Warrington Borough Council
Overall, 2,236 people provided feedback either via feedback forms left at the public exhibitions,
in the post or online at www.warrington.gov.uk/westernlink.
At the 2011 census, Warrington had a total population of 202,200, of which 49.6% are male and
50.4% are female. In 2016, it was estimated that the current population of Warrington is
208,800. Therefore, this represents an approximate 1% response rate from the population of
the Borough.
1,972 people answered the question “Please indicate what your current view is on the proposal
for a Western Link scheme”
● 43% are supportive of the proposal for a Western Link scheme (846 respondents)
● 52% are not supportive (1,029 respondents)
● 5% had no view (97 respondents)
1,633 full postcodes were received from the 2,236 responses, which shows that 62% (1,018) of
all responses came from within the WA5 1 (Great Sankey, Sankey, Cromwell Avenue, Old
Liverpool Road, Hood Lane) and WA5 2 (Penketh, Cuerdley) postcode areas. These postcodes
cover well populated areas most impacted at the northern end of all six routes. From this
breakdown of the 1,018, 319 out of 451 from WA5 1 and 349 out of 567 from WA5 2 did not
support the Western Link project108 out of 451 from WA5 1 and 165 out of 567 from WA5 2
supported the project. The remainder either held no view or did not answer this question.
A further 210 responses were received from within the WA4 6 (Walton, Higher Walton, Chester
Road, Gainsborough Road) postcode areas. This postcode area is largely affected by the
southern end of all six routes. Of the 210 responses from this postcode area, 103 did not
support the Western Link project and 97 supported the project. The remainder either held no
view or did not answer this question.
1,228 responses came from WA5 1, WA5 2 and WA4 6. 771 responses in these postcode areas
did not support the Western Link project. Overall, responses largely came from postcodes close
to one or more of the proposed routes.
Mott MacDonald | Warrington Western Link 67 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
.
11,907 people answered the question “Which option for the Western Link do you prefer?”
● 16% preferred the Yellow option for the Western Link (309 respondents)
● 6% preferred the Orange option for the Western Link (104 respondents)
● 31% preferred the Red option for the Western Link (593 respondents)
● 6% preferred the Pink option for the Western Link (105 respondents)
● 8% preferred the Purple option for the Western Link (158 respondents)
● 5% preferred the Green option for the Western Link (97 respondents)
● 28% had no preferred option (541 respondents)
Further public consultation events took place in September 2017 on a recommended route. A
further questionnaire was circulated which invited qualitative feedback on the chosen route. A
booklet containing information on the route, results of the previous consultation and
amendments to the route were included. Eight-page recommended route booklets with pull out,
freepost feedback forms were available at all three public exhibitions and at local libraries to
enable people to have their say. The booklet explained the recommended route proposals in an
accessible format and provided a mechanism for feedback.
The printed document contained the following information: Recommended Route, Summary of
Previous Consultation, Overview of Route, Amendments to Route, Timeline and Contact Details
Extracts from the booklet can be found below in Figure 16. A full analysis of the consultation
results is included in Appendix B.
Figure 16: Extracts from the Western Link Proposal Booklet
Mott MacDonald | Warrington Western Link 68 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Source: Warrington Borough Council
10.5.2 Second Round Consultation
The dates and times of the events for stage 2B and their attendance can be found in Table 20.
The consultations were hosted at locations key to the recommended route as well as a town
centre location to allow interested parties an opportunity to attend an event.
Table 20: Warrington Borough Council Public Consultation Events September 2017
Date Time Location Attendees
Saturday 23 September 10am – 5pm St Werburgh’s Community Hub
117
Sunday 24 September 10am – 5pm The Peace Centre 354
Monday 25 September 9am – 5pm Golden Square Shopping Centre
Over 500
Source: Warrington Borough Council
Overall, 758 responses were received either via feedback forms left at the public exhibitions, in
the post or online at www.warrington.gov.uk/westernlink
Mott MacDonald | Warrington Western Link 69 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
However, of these, 196 responses were left blank, therefore 562 people have provided written
feedback on the recommended route. Of the 562:
● 83% responded online (469 respondents)
● 17% responded via feedback forms returned at events or via the freepost address (93
respondents)
Key topics raised in written feedback included:
Table 21: Consultation Feedback
Key Topic Comments Received Scheme Response
Noise, vibration, air quality, light pollution
141 Comments received
‘It won't ease traffic congestion in the long term and will increase air pollution.’
‘Far from alleviating congestion problems in Warrington I think the red route will draw more traffic to Warrington with consequent noise & air pollution and congestion for residents.’
Should funding be approved, the project proposals would be subject to a full Environmental Impact Assessment as part of a planning application.
Impact on community facilities and green spaces e.g. Morley Common, Sankey Valley, Trans Pennine Trail, BMX, Moore Nature Reserve
112 comments received
‘I am totally distraught at the current proposal to build a high-level bridge and road across Morley Common which will have a devastating impact on our views and quality of life.’
‘Concerned with the loss of green space in Sankey Valley.’
The scheme has been designed to have as little impact on community facilities as possible. The Council is sensitive to the fact that Morley Common is a well-used public space with facilities including football pitches,
changing areas and a playground. Should the
scheme receive major scheme funding from Central Government, the Council will replace any facilities affected at Morley Common.
Will invite additional traffic avoiding Mersey Gateway
94 comments received
‘This will cause further problems as people avoiding the Mersey Bridge may use this road.’
‘We need something to stop the Widnes bridge toll-avoiding traffic coming through Warrington instead for free.’
The Mersey Gateway bridge is now open. The Council is currently in ongoing discussion with Halton BC and has an agreed Memorandum of Understanding that if traffic levels in Warrington increase as a consequence of the bridge, then discussions can be entered into with Halton BC regarding mitigation for those impacts.
The Western Link is not being designed with a traffic capacity the same as the Mersey Gateway. It is intended that the
Western Link will connect north and south Warrington but, due to some fixed, physical considerations, will only be designed to cater for local trips across Warrington.
Not needed/waste of money/won’t solve the problem/incorrect solution/move the problem from one area to another
83 comments received
‘There will be greater congestion in and around the surrounding areas affected by the road.’
‘As with most of the proposed routes you are just moving traffic congestion from one area to another.’
Modelling work highlighted that the scheme has a positive impact on traffic congestion at key pinch points within
Warrington. This included both Brian Bevan Island and Bridgefoot Gyratory and also on the A56 and A57 as drivers
choose to use the Western Link for journeys that currently have to negotiate the town centre via Mersey Street and Wilson Patten Street.
The modelling assessments have also shown a significant reduction in the delay experienced at junctions across the town centre and an improvement in north-south and south-north journey times.
Mott MacDonald | Warrington Western Link 70 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Key Topic Comments Received Scheme Response
Further transport modelling work will estimate the wider impacts should the scheme be successful in gaining major
scheme funding.
Building road to bring forward development will neutralise the relief the road brings
77 comments received.
‘The new proposal will not ease any congestion as it comes with 4000 new houses to be built on the route causing more gridlock.’
‘Whichever route you choose the impact on the town’s traffic will not be relieved if you continue build properties at the present rate.’
The Council’s draft Local Plan, with the issue of housing and business site allocations around the borough, proposes areas of housing and employment around the Western Link. The traffic modelling undertaken for Western Link includes proposed development and the road and junction designs take account of the anticipated traffic flows.
Nature conservation/impact on wildlife
70 comments received.
‘Dreadful. A complete blot on the landscape, which will result in destruction of the environment.’
‘This should not be allowed we should keep our green space and not create an urban concrete jungle. We need to save our green spaces, wildlife etc.’
Should funding be approved, the project proposals would be subject to a full Environmental Impact Assessment as part of a planning application.
Most logical/appropriate route choice
62 comments received.
‘I would support this, mainly because it is an option that adds an additional crossing over the Ship Canal to alleviate traffic issues at Bridgefoot and along Chester Road. It will provide better connectivity across Warrington and prevent economic development being stifled by the horrendous traffic.’
‘It is clear Warrington needs something being done about the congestion in Warrington particularly when there is a problem on the M6, M62 and M60 which places Warrington at gridlock particularly in areas such as Bridgefoot and Stockton Heath. I agree the Red Route appears to be the better option.’
The project team has undertaken a number of technical assessments in addition to analysing the feedback from the public consultation. All the routes were appraised in a multi-criteria appraisal known as INSET, which matches the DfT’s appraisal guidance. This considers factors such as design, cost, deliverability, equality, environmental impact, social impact, public consultation response, cost-benefit analysis and other factors. The Red Route performed best based on this appraisal process.
Cromwell Avenue 57 comments received.
‘I understand the need to ease congestion on the town centre but what is not clear is the impact this will have on Cromwell Avenue and the areas surrounding.’
‘Whilst I feel for the residents who are going to have that eyesore foisted on them, my concern is Cromwell Ave. Pity the poor people trying to turn right out of St Greg's/Peace Centre. Cromwell Ave is only single lane, has a number of roundabouts, and is backed up twice a day.’
Further transport modelling work will estimate the wider impacts should the scheme be successful in gaining major
scheme funding.
Mott MacDonald | Warrington Western Link 71 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Key Topic Comments Received Scheme Response
Impact on traffic congestion (e.g. will worsen)
53 comments received.
‘This new road will only result in extra congestion as traffic is brought into the already clogged road system.’
‘Will make traffic in Warrington worse.’
Modelling work highlighted that the scheme has a positive impact on traffic congestion at key pinch points within
Warrington. This included both Brian Bevan Island and Bridgefoot Gyratory and also on the A56 and A57 as drivers
choose to use the Western Link for journeys that currently have to negotiate the town centre via Mersey Street and Wilson Patten Street.
The modelling assessments have also shown a significant reduction in the delay experienced at junctions across the town centre and an improvement in north-south and south-north journey times.
Further transport modelling work will estimate the wider impacts should the scheme be successful in gaining major
scheme funding.
Consultation criticism/ Criticism of Council/ Lack of information
52 comments received.
‘The original questionnaire was designed in a way to support your case for the road. There was no option to state that you completely disagreed with the road, just which is your 'preferred option'. The option was to state an actual route or no preferred option... This statement can be misconstrued on so many levels and I applaud you for your total dishonesty in constructing the questionnaire as you have done.’
‘The way the council has not approached residents about the plans other than via social media is a sham and how can you expect respect for your considerations if you yourselves fail to consider the very people that pay your council tax.’
This Consultation Report outlines the consultation held at both stages of the project.
At each stage, the details displayed were based on the latest information available to the team.
Highway safety e.g. children walking to school
49 comments received.
‘I strongly object to the Western Link it will not ease congestion in Great Sankey it will make matters worse and create dangers for pupils at St Gregory's High School where there will be a large intersection.’
‘Against red route because of the safety issues in relation to the amount of traffic as well as children attending local schools.’
All new roads are built to meet strict safety standards. Crossing points be developed as part of the next stage of design.
Impact on residential and commercial properties/ Compulsory purchase
46 comments received.
‘I think this route is unrealistic and not at all viable, people are going to lose their homes and it's the first dreadful step towards the desecration of our town.’
‘A great option with the minimal impact on local residences.’
The scheme has been designed to affect as few residential and commercial properties as possible. We will continue to work with affected residents and business owners as the scheme progresses.
Mott MacDonald | Warrington Western Link 72 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Source: Resolve
10.6 Future Consultation
Stage 3 consultation to support a planning application will need very careful consideration and
this is covered in detail in Appendix C, ‘Forward Consultation Plan’.
It is proposed that the pre-application consultation for any planning application would be done in
two steps, with a third consultation step post-submission of the planning application. This will
enable us to engage often and regularly, providing the community with ample opportunity to fully
discuss their views and see that comments are being taken on board wherever possible.
Working alongside specialist partners and stakeholders, we will discuss and agree a detailed
strategy to engage with the wider community, as well as those most affected by the project. We
will seek support and, where appropriate, input into the strategy from WBC Elected Members,
local community leaders and groups, including those representing hard to reach groups, to
ensure we reach all those likely to be affected by and interested in the project.
A thorough consultation process will be discussed and agreed, so that issues that arise can be
identified, considered, and as far as possible, seek to reach agreement on those issues.
Three steps are suggested as follows:
Table 22: Proposed consultation process
Application Step and Step aims Strategy Proposed
Pre-application Step 1
This would happen before wider community engagement.
The aim of this step of consultation is to establish a consultation methodology through engagement with key stakeholders. A further aim is to engage with those most affected by the route through workshops – in order to have a detailed discussion about concerns.
Meet with relevant members of the Council Leadership, including Senior Officers, to discuss the strategy for consulting with the community and stakeholders. Meet with the relevant Warrington Borough Council Ward Members to discuss the strategy for consulting the local communities most affected. Brief the Full Council and agree with Members the engagement strategy. Additionally, agree a strategy for working with the affected homeowners/businesses and communities.
Host workshops for communities (residents and businesses) affected by the route. Invitation would also include key community leaders within these areas. Workshops would allow for in-depth discussion of issues.
Hold bespoke events to facilitate discussion with groups to reach agreement on arising matters from the previous consultations such as:
● Access to/from Saxon Park
● Hood Lane
● Baronet Mews garages
Hold face to face meetings with directly affected residents and business owners with support and advice from WBC legal/CPO team.
Meet with the leadership of the neighbouring authorities of St Helens and Halton.
Meet with other senior stakeholders, such as MPs, Statutory Bodies, Cheshire & Warrington LEP, Cheshire Partnership, Warrington Chamber of Commerce, local transport providers and the like to discuss the route and outline the proposed community consultation.
Offer presentations to all Parish Councils affected by the route being taken forward.
Pre-application Step 2
This stage would form the principle element of public and stakeholder consultation.
Launch promotional campaign to publicise consultation events to the wider community:
● Media releases
● Newspaper advertisements
Mott MacDonald | Warrington Western Link 73 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Application Step and Step aims Strategy Proposed
The aim is to reach a broad audience of consultees and stakeholders in order to undertake meaningful consultation which would inform any possible amendments to the proposed route.
● Online advertising
Write to all those previously engaged with at Stages 2a and 2b to advise of upcoming consultation events and/or stakeholder events as appropriate.
A 3D flythrough would help consultees to visualise the route. This should be displayed at the community consultation events and shared via social media and with local media outlets.
Regular media releases and social media posts will be issued to encourage people to view the proposals and comment.
Feedback from the public consultation will be discussed with the project team to ensure that this informs the proposals wherever possible.
Produce Statement of Community Involvement to support the planning application.
Post-application engagement
Step 3
The aim of this step is to continue engagement with consultees and stakeholders and to help manage any issues which arise through the consultation.
Undertake a ‘You Spoke We Listened’ communications exercise post-submission of the planning application. This would catalogue the key amendments made to the scheme as a result of pre-application community consultation. It would also help to maintain dialogue with communities and stakeholders as the planning application progresses through the planning system.
Continual engagement Ongoing engagement with consultees, stakeholders and the community will be managed through media releases and social media posts, direct mailings to affected individuals, local communities and stakeholders.
Source: Resolve
Mott MacDonald | Warrington Western Link 74 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
11 Project reporting
11.1 Delivery reporting
Reporting requirements for the project are aligned with the project hierarchy defined in section
4. These are explained further below.
11.1.1 Work Package Reporting
Each work package lead will be responsible for reporting to the Project Manager. During project
stages this will take the form of a fortnightly ‘snapshot report’ which captures:
● Items progressed in the past 2 weeks;
● Items planned to progress in the next 2 weeks;
● Information required;
● Key Risks; and
● Progress against programme and key deliverable dates.
This report will enable the project manager to assess the most pressing issues and to set the
agenda for fortnightly project team meetings. Project team meetings will serve as a further
opportunity for key issues to be reported and discussed with the Project Manager and for the
Project Manager to disseminate information within the Project team, ensuring that members are
up to date with accurate information.
Work Package leads will be required to submit a formal end of stage report at the conclusion of
each project stage. This will also align with the issue of key deliverables and inform the Project
Manager of their status.
11.1.2 Project Reporting
The Project Manager reports to the Project Executive Board. Reporting will take the form of a
monthly report capturing:
● Items progressed in the past 2 weeks;
● Items planned to progress in the next 2 weeks;
● Information required;
● Key Risks;
● Progress against programme and key deliverable dates; and
● Financial status of the project.
The format of this report is purposefully aligned with the work package reporting format to allow
efficient transfer of information, however only significant risks or issues requiring escalation
beyond the project team will be captured. Escalations are only taken to the Executive Board if
there is a significant spend authority required and/or major policy decisions need to be made.
This is in line with ‘exceptions reporting’ as in Prince2.
Inclusion of financial status allows expenditure to be reviewed as well as any changes to
programme funding.
The Project Manager will attend monthly project executive board meetings to discuss the
contents of the report and to maintain contact with senior officers. Senior officers will be
Mott MacDonald | Warrington Western Link 75 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
expected to feedback any important information to the Project Manager for dissemination to the
project team.
The Senior Responsible Officer will maintain a close working relationship with the Executive
Board and provide progress reports enabling the board to be in a position to provide guidance
on project decisions.
11.1.3 Reporting beyond the project board
The Project Manager and project board have the responsibility to inform the Waterfront
Programme board and Capital investment programme group of any notable project
developments throughout the programme.
However, planned reporting beyond the Project Executive Board will only be at the end of
project stages prior to other major project milestones. In cases where the milestone requires
approval by either Waterfront Programme Board, Capital Investment Programme Group,
Strategic Management Team or Council Executive Board, a report will be produced by the
Project Manager and approved by the Project Executive Board. The report will make a
recommendation on the action to be taken and be supported by the appropriate evidence. The
Project Manager and Senior Responsible officer will attend the necessary meetings to present
and discuss the report.
11.2 DfT Reporting
Reporting to the DfT will take two forms:
● Regular reporting during the delivery programme;
● End of stage reporting tied to milestones.
11.2.1 Regular reporting during the delivery programme
The Project Manager and Senior Responsible Officer will engage the DfT in a quarterly
reporting mechanism to update on progress and raise key issues. This reporting will serve as a
means of maintaining regular contact with the DfT to provide reassurance that the project is
being delivered appropriately. It will also enable both parties to discuss pertinent issues to the
project and identify any actions that need to be undertaken.
11.2.2 End of stage reporting
A formal report will be submitted to the DfT at the end of the key project stages defined in
section 6. These are outlined below.
11.2.2.1 Outline Business Case
The Council is committed to progressing with scheme development whilst the OBC is being
reviewed but recognises the need to respond to DfT comments on the OBC prior to May 2018
and to attend a panel review session. The DfT’s primary point of contact will remain as the
Senior Responsible Officer and Project Manager who will draw on support from the project team
as required.
11.2.2.2 End of Stage 3
At the end of stage 3, in May 2019, the scheme will have progressed to the point where a
planning application can be submitted and there is sufficient certain on route alignment to
commence property acquisition. The end of stage 3 report will therefore include:
Mott MacDonald | Warrington Western Link 76 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
● Update on scheme design and costs;
● Update on scheme and project risks;
● Confirmation of WBC approach to property acquisition; and
● Confirmation of procurement route.
11.2.2.3 End of Stage 4A
Stage 4A will conclude in October 2019 with a decision on planning and selection of a D&B
contractor. A report will be issued to the DfT noting:
● The outcome of planning determination;
● The selected contractor and procurement report.
11.2.2.4 Draft Full Major Scheme Business Case
A draft of the final Major Scheme Business Case (MSBC) will be submitted to the DfT for review
during stage 4B and prior to an anticipated public inquiry. This will allow the DfT to review and
comment on the emerging document and provide both parties with an understand of the
requirements for completing the MSBC. The completed MSBC will be submitted at the end of
stage 4B.
11.2.2.5 End of Stage 4B
Stage 4B concludes in 2021 with a final detailed design, agreed position on cost, final business
case and the outcome of a public inquiry. Reporting to DfT on the following would therefore be
appropriate:
● Final designs;
● Final costs;
● Risk position (including proposed allocation);
● Proposed construction contract;
● Outcome of public inquiry; and
The items above will all be contained in the final business case however, and so the FBC is the
form in which the above will be reported to the DfT.
11.2.2.6 End of Stage 5 - Construction
Whilst the project is on site quarterly reporting to the DfT as 11.2.1 will be maintained. An end of
stage 5 report will be issued to the DfT following completion in 2024. This will include:
● Any changes to the scheme implemented during delivery;
● Final Costs;
● Handover and close out report.
11.2.2.7 Following Completion
Following completion of the scheme on site, reporting will follow the procedures outlined in the
monitoring and evaluation plan contained in Appendix U.
Mott MacDonald | Warrington Western Link 77 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
12 Benefits realisation
This section outlines the approach to managing the realisation of benefits of the Western Link.
Benefits in this context are referred to as ‘a measure of the improvement that will be enjoyed by
the organisation’. The benefits of any transport investment often play a crucial part in the
justification for intervention. Therefore, identification of the benefits of Western link and how they
will be measured is subsequently required.
A detailed benefits realisation plan has been produced and is included as Appendix T, to define
how the benefits of Western link will be identified and measured. Included in the plan are the
key beneficiaries of the scheme, outcomes, baseline measures, responsibility, and timeframes
for each of the key strategic outcomes. The table below provides an overview of the key
benefits.
Mott MacDonald | Warrington Western Link 78 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Table 23: Benefits Realisation plan overview
Scheme Objectives
Enabling Objectives
Scheme outcome
Benefits experienced Who will benefit
Benefit Ownership
Enablers required to realise the benefit
Scheme Objective 1: Relieve congestion and improve air quality in Warrington Town Centre
Reduce volumes of through traffic passing through the town centre
● Reduced traffic flow within the town centre
● Reduction in town centre congestion, delay and queues
● Refreshment of town centre air quality
● Reduction in traffic noise within the town centre
● Safer pedestrian conditions
● Healthier community
● More attractive place for investment and town centre regeneration
● More employment and recreational opportunities
Residents, businesses, and visitors to Warrington.
Warrington Borough Council
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Complementary education and travel demand management programme
● Marketing for future investment and development opportunities
Free up town centre capacity for bus, public realm and active travel improvements
● Reduced traffic flow within the town centre
● Reduction in town centre congestion, delay and queues
● Reduced journey times for town centre public transport services
● More reliable commuter times for employment in the town centre.
● More reliable journey times for leisure trips into the town centre
● More reliable bus travel times and enhancement of bus services.
● Greater accessibility within the town centre and to its many services.
● Raising business and retail occupancy rates within the town centre and supporting Warrington’s redevelopment plans
Residents, businesses, visitors and Warrington Borough Council
Warrington Borough Council
Warrington & Co.
● Completion of Western Link
● Modifications to town centre highways network and public walkways
● Proposals for public realm improvements
● Marketing for future investment and development opportunities
● Aligned business marketing programme to promote development of scheme and economic benefits
● Enhanced cycle and walking infrastructure
Relieve severe pinch points on the network, including Bridgefoot Gyratory and Brian Bevan Roundabout
● Reduced traffic flows at key pinch points and entering the town centre.
● Reduction in town centre congestion, delay and queues at town
● Better journey quality for highways users journeying to the town centre
● Less noise and air pollution at town centre pinch points
● Enhanced living conditions for proximate residential areas
● Enhanced pedestrian and cycling conditions
Residents, businesses, pedestrians and cyclists.
Warrington Borough Council
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Complementary education and travel demand management programme
● Enhanced cycle and walking infrastructure
Mott MacDonald | Warrington Western Link 79 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Enabling Objectives
Scheme outcome
Benefits experienced Who will benefit
Benefit Ownership
Enablers required to realise the benefit
centre pinch points
● Reduced vehicular greenhouse gas emissions in the town centre
● Reduction in travel times travelling to town centre
Contribute to improved air quality in the Warrington town centre Air Quality Management Area
● Reduction in vehicular emissions in the town centre as a result of reduced traffic flows.
● Improved air quality in the town centre.
● More pleasant and safer pedestrian conditions
● Healthier community
● Contribution to meeting national air quality targets
● Helping to refresh the town centre environment and attracting further investment
Residents, businesses, visitors, pedestrians and cyclists.
Warrington Borough Council
● Completion of Western Link
● Landscape remediation works
● Enhanced air quality monitoring programme
● Marketing for future investment and development opportunities
Scheme Objective 2: Improve connectivity between North and South Warrington
Improve local connectivity, by delivering additional route choice and reducing the ‘barrier effect’ caused by the River Mersey, Manchester Ship Canal and railway lines
● Extra capacity added to highways network
● Extra crossings of River Mersey and Manchester ship canal added.
● Increase in vehicle route choice.
● Reduced queues and delays at existing crossing points.
● Improved network resilience against impacts of
● Enhanced journey quality when travelling across Warrington
● Enhanced living conditions for proximate residential areas
● Greater accessibility across Warrington
● More efficient business, freight and commuter movements across Warrington
● Increasing network resilience and prevention of highways degradation
Residents, businesses, Peel holding and visitors to Warrington
Warrington Borough Council
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Complementary education and travel demand management programme
Mott MacDonald | Warrington Western Link 80 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Enabling Objectives
Scheme outcome
Benefits experienced Who will benefit
Benefit Ownership
Enablers required to realise the benefit
uncontrollable bridge swings
Improve strategic connectivity, by making Warrington more resilient in case of incidents on the ‘Motorway Box’
● Reduction in travel times between strategic network and west Warrington and the town centre.
● Increased network resilience with fewer delays and congestion in times of incidents on the wider strategic network
● Enhanced journey quality when travelling across Warrington
● Greater highways resilience and reduced network degradation
● Better connection with the strategic network and improved commercial and freight movements
● Greater opportunities for business growth
Residents, businesses and motorway users
Warrington Borough Council
Highways England
● Completion of Western Link
● Effective signing strategy and dissemination of information relating to diversions along Western Link
● Complementary education and travel demand management programme
Strategic Objective 3: Unlock key development land to support the growth aspirations of ‘Warrington Means Business’ and the Warrington Local Plan
Deliver access to the next phase of the Warrington Waterfront Masterplan
● Construction of Western Link and associated junction to facilitate highways access to Waterfront development.
● Realisation of Warrington Waterfront development.
● Job creation
● Construction of new homes.
● Increased investment in Warrington
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Contribute to meeting local and national housing targets
● Enhanced quality of life for residents
● Growth of the town and contribution to Warrington town’s redevelopment aspirations
Residents, future residents, businesses, developers, investors and WBC
Warrington Borough Council
Warrington & Co
Housing developers
● Completion of Western Link
● Accepted proposal for Warrington Waterfront development
● Marketing for future investment and development opportunities
● Engagement with housing developers
● Aligned business marketing programme to promote development of scheme and economic benefits
Deliver improved access to Port Warrington
● Construction of Western Link and associated junction to facilitate highways
● Enhanced freight operations and distribution with the wider region
● Increased investment in Warrington
Residents, businesses, developers, investors, wider Northern
Warrington Borough Council
Warrington & Co
● Completion of Western Link
● Aligned business marketing programme to promote development of scheme and economic benefits
Mott MacDonald | Warrington Western Link 81 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Enabling Objectives
Scheme outcome
Benefits experienced Who will benefit
Benefit Ownership
Enablers required to realise the benefit
access to Port Warrington development.
● Operation of enhanced intra-modal freight facility at Port Warrington
● Improved access to development
● Job creation
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Warrington established as a destination for logistics and manufacturing
● Growth of the town and contribution to Warrington town’s redevelopment aspirations
● Further establishment of Warrington as a key player within the NPH
economy, and Peel Ports
Peel Ports
TfN
● Engagement with Freight and Logistics Partners on Port Warrington proposals to understand how WL can enhance development options
● Development of Port Warrington intra-modal freight facility
● Engagement with TfN on how freight operations at Port Warrington can benefit wider transport and freight strategy
Deliver access and capacity to support new housing developments
● Construction of Western Link and associated junction to facilitate highways access to Arpley Meadows.
● Construction of new homes.
● Contribute to meeting local and national housing targets
● Enhanced quality of life
● Increased investment in Warrington
● Growth of the town and contribution to Warrington’s redevelopment aspirations
● Tax benefits for Warrington Borough Council
Residents, future residents, developers and WBC
Warrington Borough Council
Warrington & Co
Housing developers
● Completion of Western Link
● Marketing for future investment and development opportunities
● Engagement with housing developers
● Acceptance of Warrington 2017 Draft Local Plan
Deliver access and capacity to support the development of employment land
● Construction of Western Link and associated junction to facilitate highways access to Waterfront development.
● Job creation
● Increased investment in Warrington
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Enhanced quality of life for residents
Residents, businesses, developers, wider Northern economy and investors
Warrington Borough Council
Warrington & Co
● Completion of Western Link
● Effective Integration of Western Link with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
● Aligned business marketing programme to promote development of scheme and economic benefits
● Marketing for future investment and development opportunities
Mott MacDonald | Warrington Western Link 82 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Enabling Objectives
Scheme outcome
Benefits experienced Who will benefit
Benefit Ownership
Enablers required to realise the benefit
● Further establishment of Warrington as a key player within the NPH
Strategic Objective 4: Support the continued growth of Warrington’s economy within the Northern Powerhouse
Deliver journey time savings for commuters travelling into, out of and within Warrington
● Reduced congestion and delays across network
● Reduced journey and commuting times
● Enhanced journey quality for Warrington residents and workforce
● Greater network efficiency
● More efficient freight operations
● Greater access to a wider employment pool
Residents, commuters, businesses and freight operations
Warrington Borough Council
● Completion of Western Link
● Effective Integration with existing highways network – modifications to signage strategy, road markings, footpaths and to road layout
Provide better access to growing employment sites in and around Warrington, including Omega, Lingley Mere, Sci-Tech Daresbury, Warrington town centre and Birchwood
● Improved accessibility to key employment areas in western Warrington
● Journey time savings
● Job growth
● Higher GVA
● Enhanced journey quality for Warrington residents and workforce
● Better linkages between Warrington’s major employment sites and its workforce
● Supporting the growth of Warrington’s key employment sectors and specialist commercial activities
● Further establishment of Warrington as a key player within the NPH
Residents, businesses, Omega, Lingley Mere, Sci-Tech Daresbury, Warrington town centre and Birchwood
Warrington Borough Council
● Completion of Western Link
● Marketing and education plan for use of Western Link and best routing when travelling across Warrington
● Marketing for future investment and development opportunities
● Engagement with TfN over best integration of Warrington’s specialist commercial activities within the NPH
Strategic Objective 5: Make Warrington a more attractive place to live
Provide access to new green and recreational space between the River Mersey and the Manchester Ship Canal
● Increase trips by walking and cycling
● Reduced congestion
● Healthier communities
● Increasing the use of Warrington’s green areas
● Enhanced pedestrian and cycling conditions
● Rise in cycling and walking in Warrington
● Encouragement of less sedentary lifestyles and reducing the burden on local health services
Residents, visitors and local health services
Warrington Borough Council
Mersey forest
● Completion of Western Link
● Successful reclamation of Arpley and Gatewarth landfill sites
● Effective marketing campaigns to encourage the use of Warrington’s redevelopment green areas
● Work with environment and conservation sector partners to develop a complementary recreation strategy for the scheme which unlocks additional benefits
Support the implementation of new public transport and
● New cycle paths constructed
● Healthier communities
● Rise in cycling and walking in Warrington
Bus operators, residents, businesses, pedestrians,
Warrington Borough Council
● Completion of Western Link
● Effective Integration of Western with new highways network associated with Warrington Waterfront development – modifications to
Mott MacDonald | Warrington Western Link 83 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Scheme Objectives
Enabling Objectives
Scheme outcome
Benefits experienced Who will benefit
Benefit Ownership
Enablers required to realise the benefit
active travel routes associated with the Warrington Waterfront development
alongside western link
● Increase trips by walking and cycling
● Reduced congestion
● Increased transport access
● Improved S/T
● Increase in active travel in west Warrington
● Encouragement of less sedentary lifestyles and reducing the burden on local health services
● Increased revenue for bus operators
cyclists and health services
Mersey Forest
signage strategy, road markings, footpaths and to road layout
● Effective marketing campaigns to encourage active travel amongst residents and businesses
Support the Warrington Health and Wellbeing Strategy’s vision to work together for stronger neighbourhoods, healthier people, a vibrant and resilient economy and greater equality across all our communities
● Increased active travel in Warrington
● Increase in business occupancy rates and business start-ups in west Warrington
● Job growth
● Construction of housing
● Reduction in accidents in the town centre
● Healthier communities
● Greater opportunities for employment and business growth
● Increased economic performance and greater economic prosperity within Warrington
● Enhanced quality of life for residents
● Encouragement of less sedentary lifestyles and reducing the burden on local health services
Residents, future residents, businesses, local health services, highways users and investors
Warrington Borough Council
Warrington & Co.
● Completion of Western Link
● Enhanced cycling and walking Infrastructure
● Effective marketing campaigns to encourage active travel amongst residents and businesses
● Aligned business marketing programme to promote development of scheme and economic benefits
● Marketing for future investment and development opportunities
● Work with environment and conservation sector partners to develop a complementary recreation strategy for the scheme which unlocks additional benefits
Source: Mott MacDonald
Mott MacDonald | Warrington Western Link 84 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
The overall benefits plan will be owned by the Senior Responsible Officer. The individual
benefits of the scheme will then be passed to specific staff within Warrington Borough Council
who will then take ownership of the individual benefit. Responsibility then rests with the relevant
party for monitoring and reporting on the delivery of the benefit to the Senior Responsibility
Officer.
Mott MacDonald | Warrington Western Link 85 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
13 Monitoring and evaluation plan
13.1 Introduction
Monitoring and evaluation are essential parts of any infrastructure project. It provides an
opportunity to improve performance by reviewing past and current activities, with the aim of
replicating good practice in the future and eliminating mistakes in future work. This section
outlines the monitoring and evaluation plan for Western Link.
13.2 Monitoring and evaluation
Warrington Borough Council and Cheshire & Warrington LEP have a responsibility to report on
how funding is being utilised for Western Link and how its expenditure represents value for
money to the taxpayer and how spending aligns with Western Link’s main objectives.
DfT guidance ‘Monitoring and Evaluation Framework for Local Authority Major Schemes’ forms
the basis of the monitoring strategy alongside the Cheshire and Warrington LEP Assurance
Framework.
The DfT guidance has been produced to provide a consistent approach to reporting a schemes
value for money and conducting review in a proportionate and targeted approach. The
document sets out the requirements for the monitoring of schemes and outlines three tiers of
monitoring and evaluation, these are:
● Standard monitoring
● Enhanced monitoring
● Fuller evaluation
Western Link follows the enhanced monitoring practice as the scheme is greater than £50m in
value. The scheme will be monitored against a set of standard measures, these can be found in
Table.21. The various monitoring measures are considered in terms of the key stages of the
scheme, these are:
● Inputs (i.e. what is being invested in terms of resources, equipment, skills and activities
undertaken to deliver the scheme).
● Outputs (i.e. what has been delivered and how it is being used, such as roads built, bus
services delivered).
● Outcomes (i.e. intermediate effects, such as changes in traffic flows, modal shifts).
● Impacts (i.e. longer-term effects on wider social and economic outcomes, such as supporting
economic growth).
Table 24: Components of enhanced monitoring
Item Stage Type of information provided Data Collection timing
Rationale
Scheme build
Input ● Programme/project plan assessment
● Stakeholder management approaches
● A review of the risk register and assessment of the impacts
During delivery Knowledge
Mott MacDonald | Warrington Western Link 86 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Item Stage Type of information provided Data Collection timing
Rationale
● Assessment whether the scheme is on track
Delivered scheme
Output ● Full description of scheme outputs
● Identification of the any changes to the scheme since funding approval.
● Identification of any changes to assumptions.
● Assessment of whether the scheme has reached the intended beneficiaries.
● Identification of changes to mitigation measures.
During delivery/post opening
Accountability
Costs Input ● Outturn investment costs.
● Analysis of risk in the elements of investment costs.
● Identification of cost elements with savings.
● Analysis for cost elements with overruns.
● Outturn operating costs.
● Outturn maintenance or other capital costs.
During delivery/post opening
Accountability
Scheme Objectives
● Identification of the main objectives.
Pre or during delivery / post opening (up to 5 years)
Accountability
Travel demand
Outcome ● Road traffic flows on corridors of interest.
● Patronage of the public transport system in the area.
● Counts of pedestrians and cyclists.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Travel times and reliability
Outcome ● Travel times in the corridors of interest.
● Variability in travel times in the corridors of interest.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Impact on the economy
Impact ● Travel times/accountability changes to businesses
● Employment levels and
● Rental values
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Carbon Impact ● Effect of the scheme on carbon in the area of interest.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Noise Impact ● Effect of the scheme on noise levels at important receptor locations.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Local air quality
Impact ● Effect of the scheme on local air quality in the area of interest.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Accidents Impact Effect of the scheme on traffic accidents in the area of interest.
Pre or during delivery / post opening (up to 5 years)
Knowledge/ Accountability
Source: DfT
Mott MacDonald | Warrington Western Link 87 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Aligned with DfT monitoring guidance, Warrington Borough Council will also follow the guidance
for the engagement process. Therefore, Warrington Borough will:
● Submit a detailed monitoring and evaluation plan to DfT within 3-6 months prior full approval
submission.
● Monitoring and evaluation plans will be published on Warrington Borough Council website
and will be available to the public.
● Provide progress reports on the evaluation process to DfT.
● Provide an initial report based on data collection at least once a year following Western Link
opening.
● Provide a final report based on ‘one year after’ data and data collected approximately after
five years of Western Link opening and publish within six years of scheme opening.
This process between Warrington Local Authority and DfT is illustrated below in Figure 17.
Figure 17: Monitoring and evaluation engagement process between Local Authority and DfT
Source: DfT
13.3 Resourcing
A project assurance team has been included within the project structure to ensure that
independent officers/consultants are available to provide scrutiny on project activities. They will
provide expert advice and questioning on key decisions and undertake project auditing activities
on behalf of the Project Board.
Through the WBC Frameworks for consultancy procurement, the council has access to
organizations that provide project auditing service. WSP have been selected for this role. In
addition, WBC contains an in-house organization termed ‘Audit Warrington’ that provides
Mott MacDonald | Warrington Western Link 88 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
assurance services. The assurance team will be responsible for ensuring monitoring and
auditing occurs at key project management stages.
The following budget has been identified for future monitoring and evaluation activity related to
Western Link:
● Data Collection:
– Interim (during construction) process evaluation: £5,000
– Economic evaluation surveys: £5,000
– Trafficmaster data: NA
– ATC counter data: NA
– Land value change assessments: £10,000
– Air quality monitoring: £5,000
– Stakeholder satisfaction survey: £5,000
– Dependant development survey: £5,000
● Analysis and reporting:
– Reporting and management: £20,000
– Baseline report: £10,000
– Annual reports: £5,000
– End of construction report: £10,000
– Plus one year completion report: £20,000
– Four year post completion report: £20,000
The total budget outlined for the monitoring and evaluation activities above is £115,000.
13.4 Reporting
Monitoring and evaluation will be reported in three stages:
• Scheme delivery – reporting on scheme build, scheme delivered and cost measures.
• One year after scheme delivery – primary aim to understand the impact of Western Link on
journey times and travel patterns.
• Up to five years after the scheme – reporting on the longer-term impacts, this includes the
economy (jobs and development), accidents, travel patterns and review in line with the
scheme objectives.
13.5 Evaluation
The delivery and likely benefits of Western Link are demonstrated below in a logic map which
shows causal pathway between the objectives of the scheme to the outcomes and impacts
which will address the objectives. It also shows what inputs are required to deliver the outputs
that are needed to realise those outcomes and impacts.
Mott MacDonald | Warrington Western Link 89 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Figure 18: Western Link logic map
Source: Mott MacDonald
Mott MacDonald | Warrington Western Link 90 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
To evaluate the success of the scheme, and whether the objectives defined for the Western
Link have been met, a structured outline monitoring and evaluation plan has been established
which is included as Appendix U. Monitoring and evaluation has been divided into two parts:
1. Monitoring of project delivery, which focuses on scheme inputs and outputs; and
2. Monitoring of the achievement of the scheme objectives, which focuses on impacts and
outcomes.
The monitoring and evaluation of the project’s construction and delivery is set out in Table 3.
Table 3: Monitoring of project delivery (inputs and outputs)
Aspect of project delivery
Method of monitoring Timeframe Responsibility
Delivery of Western Link to timeframe
● Programme/project plan assessment
● Review of risk register and assessment of impacts
● Project review during scheme design and build.
● Site inspections
Ongoing throughout delivery and construction
Warrington Borough Council
Delivery of Western Link to budget
● Programme/project plan assessment
● Identification of any changes to assumptions.
● Analysis of risk in the elements of costs.
● Project review during scheme design and build.
● Site inspections
Ongoing throughout delivery and construction
Warrington Borough Council
Delivery of Western Link to specification
● Programme/project plan assessment
● Review of risk register and assessment of impacts
● Project review during scheme design and build.
● Site inspections
Ongoing throughout delivery and construction
Warrington Borough Council
Source: Mott MacDonald
Table 4 shows how the scheme objectives and related enabling objectives, (which are
effectively non-target based outcomes) will be measured. Each enabling objective has a
performance indicator which acts as a proxy for the success of the scheme. The methodology
for the associated data collection is also listed.
Mott MacDonald | Warrington Western Link 91 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Table 4: Western Link outline monitoring and evaluation plan: achieving objectives
Objective Enabling objective/outcome
Performance indicator Methodology Timing Responsibility
Relieve congestion and improve air quality in Warrington Town centre
Reduce volumes of through traffic passing through the town centre
● A percentage reduction in traffic flows entering the town centre
● Pre & post implementation ATC counter
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Free-up town centre capacity for bus, public realm and active travel improvements
● Increase in active travel in town centre
● Delivery of town centre regeneration proposals
● Reduction in bus travel times through the town centre
● Non-motorised user counts
● Land value change assessments
● Monitoring of completed regeneration projects
● Traffic master analysis
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Relieve severe pinch points on the network, including Bridgefoot Gyratory and Brian Bevan Roundabout
● A percentage reduction in traffic flows at key town centre pinch points
● A percentage reduction in queue lengths at pinch points
● A percentage reduction in traffic delay at pinch points
● Pre & post implementation ATC counter
● Pre & post implementation queue lengths
● Traffic master data analysis
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Contribute to improved air quality in the Warrington Town centre Air Quality Management Area
● Reduction in vehicular emissions within the town centre and AQMA
● Pre & post air quality monitoring using air quality measurement facilities
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Improve connectivity between North and South Warrington
Improve local connectivity, by delivering additional route choice and reducing the ‘barrier effect’ caused by the River Mersey, Manchester Ship Canal and railway lines
● A percentage reduction in travel times when travelling across Warrington and to the town centre.
● Reduction in queue lengths and delay at existing crossing points.
● Traffic master data analysis
● Pre & post implementation queue lengths
● During delivery/post opening
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Improve strategic connectivity, by making Warrington more resilient in case of incidents within the ‘Motorway Box’
● A percentage reduction in travel times when travelling between west Warrington, Warrington town centre and identified locations on the surrounding motorway network.
● Traffic master data analysis
● Highways England Data analysis
● During delivery/post opening
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Unlock key development land to support the growth
Deliver access to the next phase of the Warrington Waterfront Masterplan
● Number of planning applications submitted as part of the Waterfront development.
● Business surveys & economic evaluation surveys
● During delivery/post opening
● Warrington Borough Council
Mott MacDonald | Warrington Western Link 92 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Objective Enabling objective/outcome
Performance indicator Methodology Timing Responsibility
aspirations of ‘Warrington Means Business’ and the Warrington Local Plan
● Number of jobs created
● Number of business start-ups associated with the Warrington Waterfront development.
● Pre or during delivery / post opening (up to 5 years)
Deliver improved access to Port Warrington
● Number of jobs generated by Port Warrington
● Increase in business occupancy
● Business surveys & economic evaluation surveys
● Ex-post economic impacts study on impact of scheme
● During delivery/post opening
● Warrington Borough Council
Deliver access and capacity to support new housing developments
● Number of houses built ● Land surveys
● Market Analysis study
● During delivery/post opening
● Warrington Borough Council
Deliver access and capacity to support the development of employment land
● Number of jobs created
● Number of business start-ups
● Increase in business occupancy
● Business surveys & economic evaluation surveys
● During delivery/post opening
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Support the continued growth of Warrington’s economy within the Northern Powerhouse
Deliver journey time savings for commuters travelling into, out of and within Warrington
● A percentage reduction in journey times between Warrington’s strategic network and Warrington town centre
● A percentage reduction in travel times when travelling across Warrington
● A percentage reduction in journey times between Warrington and town centre
● Traffic master data analysis ● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Provide better access to growing employment sites in and around Warrington, including Omega, Lingley Mere, Sci-Tech Daresbury, Warrington town centre and Birchwood
● A percentage reduction in journey times from strategic network & across Warrington to the following employment destinations:
– Omega;
– Lingley Mere;
– Sci-Tech Daresbury;
– Warrington town centre; and
– Birchwood.
● Traffic master data analysis ● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Mott MacDonald | Warrington Western Link 93 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
Objective Enabling objective/outcome
Performance indicator Methodology Timing Responsibility
Make Warrington a more attractive place to live
Provide access to new green and recreational space between the River Mersey and the Manchester Ship Canal
● Number of people using redeveloped Arpley and Gatewarth tip areas
● Increase in active travel in Warrington
● Active travel surveys
● Non-motorised user counts
● During delivery/post opening
● Warrington Borough Council
Support the implementation of new public transport and active travel routes associated with the Warrington Waterfront development
● Number of bus services routing to and within Warrington Waterfront
● Increase in cyclists using the Trans Pennine trail
● Increase in active travel in Warrington
● Active travel surveys
● Non-motorised user counts
● During delivery/post opening
● Warrington Borough Council
Support the Warrington Health and Wellbeing Strategy’s vision to work together for stronger neighbourhoods, healthier people, a vibrant and resilient economy and greater equality across all our communities.
● Increased cycling levels and Walking within west Warrington
● Increase in business occupancy rates and business start-ups west Warrington
● Number of houses built
● Reduction in highways accidents in town centre
● Non-motorised user counts
● Active travel surveys
● Business surveys
● Land surveys
● Assessment of road traffic collision
● Pre or during delivery / post opening (up to 5 years)
● Warrington Borough Council
Source: Mott MacDonald
Mott MacDonald | Warrington Western Link 94 Management Case
xx | xx | xx | December 2017 https://mottmac.sharepoint.com/teams/pj-b1092/Shared Documents/06 - Business Case/Documents/OBC/4. Management Case/WL-MMD-07-XX-RP-U-1005 - Management Case DfT submission.docx
14 Contingency Plan
It is important to consider what might happen to the project should there be a threat to delivery.
Given there are a range of risks in the project delivery and management risk registers, it is not
possible to account for every scenario. However, on the basis that one or more risk events
occur that can potentially affect the project deliverability set out in this management case,
contingency measures are outlined below. These relate mostly to ensuring that the impacts of
the project are as close to cost neutral on the Council balance sheet as possible.
In the event the council is unable to construct the highway following the necessary land
acquisition and the project being halted before the beginning of RIBA stage 5 – construction
stage, the council would need to accept that the money spent to date on the pre-construction
and design works would be abortive and need to be halted. The council would have an
obligation to conclude the design works up to the pre-construction point and notify the
contractor that they would not be taking forward the construction contract.
The council would then assess the key land assets acquired as part of the scheme. As CPO
would be the background to land acquisition it is likely that, in the first instance, land belonging
to previous owners would be offered for sale back to the previous incumbent on a ‘first refusal’
basis. If previous owners did not wish to repurchase the land, then WBC would re-market the
properties and holdings to try and cover the potential capital outlay for the land.
In terms of progressing a highways scheme, WBC would continue to investigate low cost alternatives in an attempt to deliver on some of the objectives identified as part of the scheme development.