vr1047 er 1

download vr1047 er 1

of 20

Transcript of vr1047 er 1

  • 7/29/2019 vr1047 er 1

    1/20

    Building Envelope Condition Assessment

    for

    VAS 1047 - Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Presented to:

    Strata Corporation VR 1047

    Prepared by:

    McCuaig &Associates Engineering Ltd.

    File Number: 20110209

    Date: September 30, 2011

  • 7/29/2019 vr1047 er 1

    2/20

    TABLE OF CONTENTS

    EXECUTIVE SUMMARY ........................................................................................................... i!SUMMARYOFOBSERVATIONS............................................................................................ I!SUMMARYOFRECOMMENDATIONS ............................................................................... III!

    1.0! INTRODUCTION .............................................................................................................. 1!1.1! TERMSOFREFERENCE................................................................................................ 2!1.2! BUILDINGDESCRIPTION&HISTORY....................................................................... 2!

    2.0! DOCUMENTS REVIEWED ............................................................................................. 4!3.0! METHODOLOGY ............................................................................................................. 6!4.0! DESCRIPTION OF BUILDING ENVELOPE ASSEMBLIES ...................................... 9!

    4.1! ROOFASSEMBLIES....................................................................................................... 9!4.2! BALCONIES,ROOFDECKS,ANDPLAZADECKS.................................................... 9!4.3! PARKINGGARAGE ..................................................................................................... 12!4.4! LIVINGSPACES ........................................................................................................... 13!4.5! WALLS........................................................................................................................... 14!4.6! WINDOWSANDDOORS ............................................................................................. 19!

    5.0 ! OBSERVATIONS, DISCUSSIONS, AND RECOMMENDATIONS ......................... 22!5.1! OCCUPANTSURVEY .................................................................................................. 22!5.2! ROOFS............................................................................................................................ 23!5.3! BALCONIES,ROOFDECKS,ANDPLAZADECKS.................................................. 25!5.4! PARKINGGARAGE ..................................................................................................... 30!5.5! INTERIORSPACES....................................................................................................... 33!5.6! WALLS........................................................................................................................... 34!5.7! WINDOWSANDDOORS ............................................................................................. 35!

    6.0! FINAL REMARKS........................................................................................................... 38!

    List of Tables

    !"#$%&'&(&)%*+,,%-."/0+-1&2&34.5%/!!!!!!!!!!!!!!!!!! !!!!!!!!!!!!!!!!!!! !!!!!!!!!!!!!!!!!!! !!!!!!!!!!!!!!!!!!! !!!"""!!"#$%&6&(&7-0/1&89%:%&;-/%:0+:&;-1

  • 7/29/2019 vr1047 er 1

    3/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page i 09/30/2011

    EXECUTIVE SUMMARY

    McCuaig and Associates Engineering Ltd. (MAE) was retained by Strata Corporation VR 1047

    to complete an investigation of the performance of the building envelope assemblies that Chelsea

    Terrance. The building is located at 1040 Pacific Street in Vancouver, British Columbia.

    This investigation included an evaluation of parking garage, roofs, balconies, and wall

    assemblies as well as an evaluation of interior conditions as they relate to building envelope

    performance.

    The building, which was constructed in 1981, consists of 112 single-level condominium units.

    The roofs are typically low-slope (flat) roofs comprised of 2-ply SBS membrane. Some areas

    have pitched metal roofing. The exterior walls are either painted concrete or stucco cladding

    over light-gauge steel framing.

    Below grade wall assemblies consist of concrete walls with liquid dampproofing applied to the

    exterior face.

    This investigation consisted of:

    Visual inspections of various building envelope components, both exposed and normallyhidden;

    A perusal of the buildings original construction drawings; Administration and evaluation of an occupant survey; and; Performing invasive testing from the interior side of select exterior walls.

    SUMMARY OF OBSERVATIONS

    Roof Assemblies

    The main roofs were in relatively good condition and have approximately five years of service

    life remaining. The lower roofs were in poorer condition, leaks are occurring, and should be

    replaced.

    Balconies, Roof Decks, and Plaza Decks

    Most of the balconies on the building are protected by the balconies above. It is recommended

    that the balcony membranes on the exposed, high-risk areas be replaced. These balconies have

  • 7/29/2019 vr1047 er 1

    4/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page ii 09/30/2011

    little to no overhang to protect them from the elements and are continuously capturing bulk water

    during precipitation. Additionally, a new rainwater collection system is recommended to

    properly handle the water form the balconies.

    It is recommended that the roof decks be further inspected if any roof work is to proceed at

    Chelsea Terrance and replace these membranes, if required. The plaza deck membrane appearsto be nearing the end of its service life replacement is recommended over the next three to five

    years.

    Parking Garage

    The walls of the parking garage are allowing some water to infiltrate, but this is not seen as a

    structural issue. Various repairs schemes are recommended.

    The suspended slab in the parking garage has had some structural damage. The extent of the

    damage and the repair options are being dealt with independently from this report. It is

    recommended that a traffic coating be installed on the suspended slab to prevent any further

    water migration.

    Living Spaces

    High humidity was noted is some residents suites. The residents can generally manage this

    humidity themselves and recommendations are presented in the report.

    Exterior WallsExterior walls appear to have provided adequate performance to date. Some water ingress has

    been occurring at the base of the wall, which has been attributed to exterior membrane failures.

    Exterior sealant (caulking) should be removed and replaced throughout the building.

    Windows and Doors

    The swing doors at the building are performing as intended. Sliding doors and windows have

    reached their life expectancy but still function. New windows and sliding doors are

    recommended to increase the efficiency and resident comfort within the building.

    Water stains and areas of deteriorated sheathing were observed at several isolated locations in the

    vicinity of windows, providing evidence that windows are leaking. The damage is minor and

    isolated, therefore it is not cause for immediate concern.

  • 7/29/2019 vr1047 er 1

    5/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page iii 09/30/2011

    Building paper lap details in the vicinity of windows are inconsistent. At some locations, laps

    are properly shingled, at some locations laps are reverse shingled, and at some locations gaps

    exist between sheets of building paper.

    SUMMARY OF RECOMMENDATIONS

    Our recommendations, along with order of magnitude budgets to implement our

    recommendations, are summarized in Table 1. Unless noted otherwise, implementation of these

    recommendations need not be considered urgent, but should be completed within the next five

    years.

    Table 1 Recommendations & Budget

    Ref. Recommendation Budget Time Frame

    5.2.r1 Main Roofs The existing membrane should be

    expected to provide approximately five more years of

    reliable service. The Strata should budget in the

    upcoming years to replace the main roofs with a new

    SBS roofing system

    $ 275,000 5 Years

    5.2.r2 Lower Tier Roofs - A roof replacement program for

    these smaller roofs should be implemented within the

    following year. The roofs membranes should be

    replaced with a new SBS system. New rain water

    leader design should be incorporated, where required

    $ 45,000 As soon as feasible

    5.2.r3 All Roof Areas - A qualified tradesman should review

    the low-sloped roofs annually and any required

    maintenance should be performed during this review.

    $ 2,000 Annually

    5.3.1.r1 Suite #813 The existing balcony membrane should be

    removed and replaced with a new SBS system

    including concrete pavers overtop. The corroded steel

    framing members must be replaced with new. This

    work will entail removing the interior finishes and

    stucco and replace with new

    $ 15,000 As soon as

    Possible

  • 7/29/2019 vr1047 er 1

    6/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page iv 09/30/2011

    Ref. Recommendation Budget Time Frame

    5.3.1.r2 Upper Exposed Balconies The existing balcony

    membranes should be removed and replaced with a

    new SBS system, including concrete pavers overtop, as

    soon as feasible for The Strata. The balcony of Suite

    #608 should also have the membrane replaced.

    $ 40,000 As soon as feasible

    5.3.1.r3 Balcony Rain Water Collection System A new rain

    water collection system be installed on the balconies

    (and roof decks where applicable) that collects the

    water, directs it to the ground level, and bypasses all

    balconies beneath.

    $ 30,000 As soon as feasible

    5.3.2.r1 Roof Decks The Strata review the age and condition

    of the roof deck membranes and, if warranted, replace

    them while other roof work is being completed.

    $ 20,000 As soon as feasible

    5.3.3.r1 Plaza Deck Membranes The plaza deck membranes

    should be removes and replaced with new. This work

    could be completed possibly in three phases in the

    coming years. It would be prudent to commence this

    work in approximately three years time and continue

    the remaining two phases one year apart.

    $ 75,000

    X 3 phases =

    $ 225,000

    3 to 5 Years

    5.4.1.r1 Parking Garage Walls - The Strata should inspect

    existing epoxy injection sites annually. Inspectionsshould occur during a prolonged period of wet weather.

    If the leakage occurs through existing sites, re-injection

    should be considered. If leakage begins to occur at

    locations that have not been previously injected The

    Strata should consider implementing one of the above

    note leakage mitigation schemes.

    Dependant on

    repair scheme

    Annually,

    dependant onrepair scheme

    5.4.2.r1 Parking Garage Slabs Apply a traffic coating to the

    suspended slabs in the parking garage to prevent future

    water migration through the slab and subsequent

    concrete decay.

    $ 75,000 As soon as feasible

  • 7/29/2019 vr1047 er 1

    7/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page v 09/30/2011

    Ref. Recommendation Budget Time Frame

    5.5.r1 Interior Spaces The Strata should review the

    operation of the kitchen and bath exhaust fans in the

    suite to ensure they are performing as intended. Any

    non-operational fans should be replaced. The Strata

    should also advise all the residents that humidly levelswithin their suite should be managed by opening

    windows and the use of exhaust fans.

    Negligible As soon as

    possible

    5.6.r1 Exterior Walls The exterior sealant be removed and

    replaced with new and all exterior locations. This

    should include all window/door interfaces, cladding

    interfaces and flashing details.

    $ 50,000 2 Years

    5.7.r1 Windows and Doors If The Strata were looking to

    upgrade the performance of the windows, newlymanufactured windows would provide substantial gains

    with regards to energy savings and resident comfort.

    This upgrade would also eliminate the majority of the

    condensation issues with the windows.

    $ 400,000 At The Stratas

    discretion

    5.7.r2 Entire Building Envelope The building envelope

    should be investigated at regular intervals and a regular

    maintenance program should be established.

    $ 12,000 5 Years

  • 7/29/2019 vr1047 er 1

    8/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 1 09/30/2011

    1.0 INTRODUCTION

    McCuaig & Associates Engineering Limited (MAE) was retained by Strata Corporation VR

    1047 (The Strata) to conduct an evaluation of the building envelope assemblies that enclose the

    building located 1040 Pacific Street in Vancouver, BC. This building is known as Chelsea

    Terrace. Documentation that we have received indicates that the building was constructed in1981.

    This report has been organized into a number of sections and appendices. A description of the

    subject matter of each section and appendix is presented below. Section titles are indicated in

    bold uppercase font.

    The INTRODUCTION provides an overview of the investigation including terms of reference

    and a description of the development.

    The DOCUMENTS REVIEWED section describes the original construction drawings that

    were made available to MAE for this investigation. Relevant information that was obtained from

    the drawings is also described.

    The methods and tools that were used to conduct this investigation are described in the

    METHODOLOGY section of the report.

    The section entitled DESCRIPTION OF BUILDING ENVELOPE ASSEMBLIES describes

    the relevant building envelope assemblies that enclose the buildings that make up the building.

    In the OBSERVATIONS, DISCUSSIONS AND RECOMMENDATIONS section, our field

    observations are described and their relevance to the performance of the building envelope is

    discussed. Photos that illustrate many of our observations are also contained in this section.

    Where applicable, recommendations to correct observed deficiencies are also discussed in this

    section. Order of magnitude budgets are also presented for each of the recommendations.

    Our concluding remarks, including the limitations of this investigation are contained in the

    section entitled FINAL REMARKS.

    Drawings of the various building elevations are presented in APPENDIX A. The locations

    where exploratory openings were conducted are shown on these drawings along with other

    relevant comments.

  • 7/29/2019 vr1047 er 1

    9/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 2 09/30/2011

    APPENDIX B contains a Glossary of Terms referred to throughout this report.

    APPENDIX C contains the completed occupant surveys.

    1.1 TERMS OF REFERENCE

    Briefly, this investigation concerns previous, ongoing, or potential water ingress issues that are

    related to the following building envelope assemblies:

    Roofs; Balcony structures; Plaza decks; Exterior walls below, at, and above grade, and; Exterior windows and doors.The terms of the Client/Engineer agreement specify that upon completion of our field

    evaluations we must prepare a written report that:

    Describes our observations; Provides recommendations to rectify observed building envelope deficiencies; and; Provides an estimate of order of magnitude costs to implement our recommendations.

    1.2 BUILDING DESCRIPTION & HISTORYChelsea Terrace has been constructed in a high-density residential neighborhood on a sloping lot.

    The development is surrounded by mid and high-rise residential buildings and is approximately

    one block north of the ocean. The building consists of 118 units plus one amenities room and a

    common laundry room.

    The building is nine stories high with parking on the first floor and a portion of the second floor.

    Residential units start on the second floor and extend to the top floor. All units have access to

    either private patios or balconies off their suites. Each unit is heated with individual electric

    baseboard heating systems.

    The building structure is constructed from cast-in-place concrete. This concrete makes up the

    structural wall and floor components of the building as well as a large portion of the exterior

    cladding. At some locations the exterior walls are comprised of light-gauge steel stud framing

  • 7/29/2019 vr1047 er 1

    10/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 3 09/30/2011

    with exterior sheathing and stucco as the exterior cladding. The windows and sliding doors in

    the building have double glazing and date back to the original construction.

    The majority of the roofs at Chelsea Terrace are low-slope roofs, commonly referred to as flat

    roofs, and are protected with a 2-ply SBS sheet membrane. Pitched metal roofing exists at

    some location on the building. The low-sloped roofs direct water into internal drains while the

    pitched roofs direct water into external gutters and rain water leaders.

    Detailed descriptions of roof and wall assemblies are found in Section 4.0.

  • 7/29/2019 vr1047 er 1

    11/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 4 09/30/2011

    2.0 DOCUMENTS REVIEWED

    The Strata gave MAE permission to purchase copies of the original construction drawings from

    the City of Vancouver. The drawings that were reviewed and are relevant to this report are

    described below:

    Architectural Drawings:

    Consultant: Hale Architects

    Latest Issue Date: December, 1979

    Purpose of Issue: Proposal to Municipality

    Drawings Provided: A1 to A24

    Structural Drawings:

    Consultant: Read Jones Christoffersen Ltd.

    Latest Issue Date: November, 1979

    Purpose of Issue: Issued for Building Permit

    Drawings Provided: S8 and S9 (other structural drawings were not available)

    For the remainder of this report, the term Construction Drawings shall refer to Drawings A1 to

    A24, S8, and S9, as described above. It should be noted that the Construction Drawings were

    received in a compressed (smaller size) format and, due to their age, are at times difficult to read.

    The structural drawings were incomplete and difficult to read, thus only minimal information

    pertaining to the buildings structural systems was available. MAE acquired additional drawings

    of the building including; Plumbing, Mechanical, and Sprinkler drawings but these were not

    relevant for this investigation. All the drawings listed above will be handed over to The Strata

    for their records when the investigation is complete.

    The Construction Drawings show:

    A site plan; Small scale floor plans including dimensions;

  • 7/29/2019 vr1047 er 1

    12/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 5 09/30/2011

    Building elevations, including a list of exterior finishes; Selected building sections, including dimensions, and; Window and door schedules.The Construction Drawings are also referenced to provide orientation for the project and to

    develop preliminary budgets for repairs or remedial work.

  • 7/29/2019 vr1047 er 1

    13/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 6 09/30/2011

    3.0 METHODOLOGY

    This section describes how this investigation was conducted.

    1. Prior to our site work, an online occupant survey requesting information about knownbuilding envelope issues administered. Some residents, in lieu of the online version,submitted hard copies of the surveys. Copies of the completed surveys can be found in

    Appendix C.

    2. The Construction Drawings were reviewed in order to become familiar with the project.3. Subsequent to reviewing the drawings, visual non-invasive inspections of exposed structural

    components were completed. The purpose of the inspections was to evaluate the condition of

    the exposed structural components that must provide acceptable service levels for the

    remaining life of the building.

    4. Visual inspections of randomly selected building envelope components that are normallyexposed to view were conducted. This included inspections of various roofs, balconies, plaza

    decks, and the exterior face of wall and window assemblies.

    5. Interior conditions within selected units were evaluated. Inspections of interior conditionsfor indications of water ingress from the exterior or excessive condensation, along with

    evidence of broken seals between inner and outer glazing, were conducted.

    6. Selected building envelope components that are normally hidden were visually inspected.The selected areas were dictated by the results given in the occupant surveys and our past

    experience with similar buildings. The inspections were accomplished by removing sections

    of drywall from the interior of the walls and creating an exploratory opening to view the

    insulation, steel studs, and wall sheathing within the assembly.

    Specific units that were inspected are listed in Table 2. For each unit listed in Table 2,

    interior surfaces of exterior walls and windows were inspected and humidity levels were

    checked.

  • 7/29/2019 vr1047 er 1

    14/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 7 09/30/2011

    Table 2 Units Where Interior Inspections Occurred

    Unit Areas Inspected

    204: Exterior wall, skylight, and sliding door area. No exploratory

    openings were conducted.

    306: Exterior wall, bedroom wall, and sliding door area. An

    exploratory opening was conducted.

    308: Exterior walls, bedroom walls, and sliding door area. Four

    exploratory openings were conducted.

    511: Soffit and sliding door area. No exploratory openings were

    conducted.

    608: Soffit, balcony, and sliding door area. No exploratory openings

    were conducted

    810: Exterior wall in living room. An exploratory opening was

    conducted.

    813: Exterior walls and sliding door area. The drywall was previously

    opened up in this area.

    Interior suite inspections were completed on August 29th, 2011. Exterior inspections took place

    on both August 29th and 30th, 2011. The parking garage was reviewed at various times during

    the week of August 29th, 2011. It was generally sunny and warm on the days immediately prior

    to the inspection days.

    Relevant weather data is presented in Table 3. The weather data was obtained from the

    Environment Canada Website. The weather data pertains to the weather station located at the

    Vancouver International Airport, which is the closest weather station to the building that

    provides reasonable historical precipitation data.

  • 7/29/2019 vr1047 er 1

    15/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 8 09/30/2011

    Table 3 Inspection Schedule And Weather Data

    DatePrecipitation at the

    Vancouver AirportHistorical Data

    29 Aug 11 0.0.mm

    30 Aug 11 0.0 mm

    In the 60 days prior to August 29,

    2011, a total of 57.2 mm of rain fell on

    10 days. This is slightly less the

    historical average (1971-2000) of 78.7

    mm for the same period (July and

    August).

    A review of Table 3 indicates that the precipitation that preceded our fieldwork was

    approximately average. This suggests that the invasive inspections occurred at a time when the

    building envelope underwent a reasonable test of its performance in the summer months.

  • 7/29/2019 vr1047 er 1

    16/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 9 09/30/2011

    4.0 DESCRIPTION OF BUILDING ENVELOPE ASSEMBLIES

    Descriptions of the various building envelope assemblies that are the subject of this report are

    provided in this section. The descriptions are based on The Construction Drawings, our

    experience with similar buildings and, in some instances, our invasive visual inspections. There

    has been no attempt to verify the presence of all of the components described herein.

    4.1 ROOF ASSEMBLIES

    The majority of the roofs at Chelsea Terrace are low-slope and are protected with 2-ply SBS

    membranes. There are three small pitched metal roof assemblies on the east on northeast sections

    of the building, one of which has been replaced in the past two years. The pitched metal roofs

    drain by allowing water to flow from their peaks to external gutters at the perimeter of the roof.

    Due to the lack of drawings, we are unable to confirm the presence and the location of all the

    pitched roof components. The low-sloped roofs handle bulk water through interior drains. Thissection will deal primarily with low-sloped roofing.

    The low-sloped roofs are present over the main upper roof area, the mechanical room, the lower

    tiered roofs, and some smaller projections on the north and south elevations. These roofs have

    SBS sheet membrane installed as the waterproofing layer. A good quality SBS roof membrane

    that has been properly installed can be expected to provide approximately 20 years of reliable

    service. Multiple penetrations exist through the membrane including plumbing stacks, exhaust

    vents, turbine vents, and surface drains.

    The SBS membrane is typically applied with two layers; the base sheet is normally mechanically

    fastened to the structure and the cap sheet is torched-on and fully adhered. The cap sheet is

    granulated for UV light resistance. It appears that this membrane has been installed directly to

    the concrete substrate and most likely has a protection board or fibre board between the

    membrane and concrete.

    4.2 BALCONIES, ROOF DECKS, AND PLAZA DECKS

    Roof decks are outdoor living spaces that are situated over living spaces. Balconies are outdoor

    spaces connected to the suites that are not over living spaces. Plaza decks are pedestrian access

    deck areas that are typically overtop of parking areas. Chelsea Terrace has balconies, roof decks,

    and plaza decks all structurally supported by cast-in-place concrete.

  • 7/29/2019 vr1047 er 1

    17/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 10 09/30/2011

    4.2.1 Balconies

    The drawings indicate that water ingress through the balconies is prevented by a liquid

    membrane applied to the cast-in-place concrete; a concrete topping was placed overtop. The

    balconies are serviced by internal drains, which direct water to the balcony floors directly below.

    The soffit area on the underside of the balconies has a strip vent to provide ventilation to the

    soffit cavity.

    In accordance with good water management practices, the balcony floors are generally sloped

    away from the building. It is our understanding that the balcony membranes have not been

    replaced at the building, although some balconies have received isolated repairs.

    The floor layout at Chelsea Terrace is such that most balconies are situated beneath the balconies

    above. Refer to Photo 1. This layout provides substantial protection from precipitation and wind

    driven rain. The upper level balconies are not protected with such a generous overhang and are

    more vulnerable. Rain water freely accumulates on these upper balconies and must be collected

    by the surface drain.

    .

    Photo 1 Typical balcony layout.

    Aluminum and glass guardrails provide balcony fall protection. The guardrails are fastened to

    the balcony upstand wall framing and into the exterior walls. The fastener holes through the

    building exterior provide a water ingress point.

    4.2.2 Roof Decks

    The roof decks are typically located on the uppermost levels and are far fewer than the number

    of balconies on the building. The drawings indicate that water ingress through roof decks is also

  • 7/29/2019 vr1047 er 1

    18/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 11 09/30/2011

    prevented by a liquid membrane, with a concrete topping placed overtop. During the site

    investigation it was noted that some roof decks have had repairs completed, which most likely

    involved a membrane replacement and concrete pavers installed overtop. Refer to Photo 2.

    .

    Photo 2 Roof deck on northeast corner of the building.

    The roof decks are also serviced by internal drains, which either direct water to the balconies

    directly below or the to the internal plumbing system. The guardrails match the design of the

    balcony guardrails.

    4.2.2 Plaza Decks

    The plaza decks are located on thesecond and third levels and are either

    over living space or the parking garage.

    It appears that the plaza deck assembly

    has been updated from the original

    construction, but it still appears to be

    aged. Concrete pavers have been

    placed over drainage matt, which sits

    atop a liquid applied membrane. Refer

    to Photo 3. On the west side of thebuilding, landscaping has been installed

    overtop of the plaza deck membrane..

    Photo 3 Plaza deck area on the south side of the building.

  • 7/29/2019 vr1047 er 1

    19/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    Page 12 09/30/2011

    The plaza decks are typically integrated into the exterior walls to provide the base wall

    waterproofing. Bulk water is directed to internal by-level drains. These drains are connected to

    the buildings plumbing system.

    4.3 PARKING GARAGE

    The parking structure is located on the first and second levels of the building. The first level

    consists of a concrete slab-on-grade while the second level is a suspended concrete slab. It does

    not appear that the parking slabs have been protected with a traffic coating to prevent water

    migration through the slabs. The exterior ramp accessing the parking garage does have a

    waterproof traffic coating, which has been installed in the past year.

    The exposed structural components within the parking garage were reviewed during the

    investigation. The structural components that were inspected included:

    The top surfaces of the level 1 and level 2 slabs; Portions of the underside of the level 3 slab which are visible from level 2. Note that the

    underside of some portions of the level 3 slab are covered with insulation.

    The underside of the suspended portions of the level 2 slab, which are visible from level 1.The majority of the structural components that support this building have been constructed from

    concrete. Typically, structural concrete is reinforced with embedded steel rods (rebar). It

    appears that level 3 and the majority of the upper parking garage floor (level 2) are supported bystandard reinforced concrete slabs. The northeast quadrant of the level 2 floor and the level 1

    floor consist of concrete slabs that are supported by the underlying soil henceforth referred to

    as slabs on grade. It is likely that the slabs on grade are either un-reinforced or lightly

    reinforced.

    When a concrete structure is loaded it deforms and becomes stressed. Certain components of the

    concrete stresses are transferred to the rebar, which often causes cracks to occur in the concrete.

    These cracks, which are necessary to transfer stresses from the concrete to the rebar, are not

    generally a cause for concern, unless they allow water to pass through the structure.

    If water is allowed to continually pass through a section of concrete it will increase the likelihood

    that rebar or other embedded metal components will corrode. The corrosion process causes the

    steel to expand and exert outward pressure on the surrounding concrete. Eventually, the outward

    pressure will cause the concrete to delaminate and spall away. If corrosion occurs in several

  • 7/29/2019 vr1047 er 1

    20/20

    Building Envelope Condition Assessment for Chelsea Terrace

    1040 Pacific Street, Vancouver, British Columbia

    P 13 09/30/2011

    adjacent bars and if it is severe enough the structures load carrying capacity will be reduced.

    Corroded rebar that has been installed purely for crack control will not significantly reduce the

    slabs load carrying capacity, however, the incidence of corroded crack control steel may also

    indicate the presence of corroded main steel. It may take several years of water ingress before

    the level of corrosion is severe enough to become a structural concern.

    Other consequences of ongoing water ingress through concrete include:

    The appearance of rust stains, which often indicate that the corrosion process has started; The appearance of efflorescence, which is a milky liquid that forms when water mixes with

    the lime in the concrete. The appearance of efflorescence is not detrimental to the concrete,

    however if it comes into contact with vehicles, it can damage their finish.

    4.4 LIVING SPACES

    Water vapour is generated inside living spaces by activities such as bathing, cooking, and

    breathing. Warm air can hold more water vapour than cold air. When warm air that is laden

    with water vapour comes into contact with a cold surface, for example a cold aluminum window

    frame, the air cools. When the air cools, it can no longer hold as much vapour, causing the

    vapour to transform to a liquid state. Liquid water then forms against the cold surface. This

    process is referred to as condensation. Condensation generally increases when:

    The number of residents within each unit increases; The resident keeps multiple indoor plants; Windows and doors are inadequately designed to resist heat flow between interior and

    exterior spaces;

    There is an inadequate supply of fresh air.Condensation can be controlled by:

    Eliminating cold interior surfaces; During cold weather, exchanging relatively dry exterior air for relatively moist interior air.

    This can be achieved by ensuring that each unit is adequately ventilated. Suitably designed

    exhaust fans, open windows, or a combination of the two can provide adequate ventilation.