VOLUME 2 - AfDB
Transcript of VOLUME 2 - AfDB
1
AFRICAN DEVELOPMENT BANK (ADB)
OUTFITTING WORKS ON THIRD FLOOR OF
SIERRA LEONE COUNTRY OFFICE OF THE
AFRICAN DEVELOPMENT BANK
BISHOP BUILDING
LAMINA SANKOH STREET, FREETOWN
VOLUME 2
TECHNICAL SPECIFICATIONS
&
BILL OF QUANTITIES
Realini Bader Associates Limited, Sierra Leone
Architects Engineers Planners Quantity Surveyors
72 Wellington Street
Freetown
Sierra Leone
February, 2021
2
SPECIFICATION FOR THE SUPPLY,
INSTALLATION, TESTING AND
COMMISSIONING OF ELECTRICAL SERVICES
ENGINEERING FOR OFFICE BUILDING AT
LAMINA SANKOH STREET, FREETOWN FOR
SIERRA LEONE COUNTRY OFFICE OF THE
AFRICAN DEVELOPMENT BANK (ADB)
3
ELECTRICAL ENGINEERING SERVICE INSTALLATION
4
ELECTRICAL ENGINEERING SERVICE INSTALLATION
CONTENTS
1.0 TENDER CONDITIONS
2.0 DESIGN CRITERIA TENDER SPECIFICATIONS
3.0 ELECTRICAL ENGINEERING SERVICE INSTALLATION
4.0 SCHEDULE OF APPENDICES
5
1.0 TENDER CONDITIONS:
1.1 Introduction
The purpose of this document and supporting drawings/data is to illustrate and
describe the Contract Works associated with the Electrical Engineering Services
(EES) Systems + Applications.
The information contained in the Technical Specification and depicted on the
Drawings is for the purpose of obtaining a competitive Tender for the EES Contract
Works
The Contractor must allow for liaising with other trades to ensure that the EES
Installation is properly coordinated / integrated into the Contract Works / Building
Complex as a whole.
It is recommended that the Contractor visits the site in order to acquaint himself with
the existing site conditions, (access, existing site infrastructure services etc.), that
might affect his Tender.
No claim arising out of any misunderstanding or neglect shall be considered.
1.2 Extent of the Contract Works
The EES Contract Works shall include all the necessary labour and materials and all
construction/building works, together with such tests, adjustments and commissioning
of the electrical engineering services systems and applications as are required to form
a “complete installation”.
The BES Contract Works “Complete Installation” shall mean not only the major items
of plant and equipment detailed in this Document, but all of the incidentals/sundry
components required for the complete execution of the Contract Works.
1.3 Contract Works: Design Development
The Contractor shall be responsible for carrying out the design development work in
connection with the EES Contract Works; this is in addition to that of the fundamental
design of the electrical engineering services systems and applications specified within
this Document and supporting drawings/data.
The Contractor shall allow, within his Tender, for the following particular design
development calculations:
(i) Lighting
To determine the required number of circuits, protection devices and cable sizes,
based upon the completed lighting installation drawings developed.
(ii) Small Power Requirement
To determine the required number of circuits, protection devices and cable sizes,
based the completed small power installation drawings developed.
(iii) Distribution Boards
To determine the required rating of protection devices, cable sizes and
appropriate load balancing illustration, based upon the completed lighting and
small power installation drawings developed.
6
(iv) Incoming Electrical Power Supply (Panel board)
To determine the required rating and size of MCCB’s and associated protection
devices/cable sizes based upon completed installation drawings and electrical
schematic diagram.
The Contractor shall provide the M+E Engineer with the design development
drawings / data for his consideration, prior to the ordering of any capital plant.
The accuracy of such information, as submitted, shall remain the responsibility of
the Contractor.
1.4 Contract Works: Named Plant, Equipment+ Materials
The fundamental design of the EES Systems + Applications has been based upon
the named manufacturers/suppliers of the plant, equipment and materials, as
recorded within this Document.
The operating characteristics, performance and overall quality of the named plant,
equipment and materials have been validated against the design criteria, setting the
minimum standard to be achieved.
The overall space planning of the building complex has taken into account the
physical weight dimensions of the named plant and equipment, together with the
space required around the plant and equipment for maintenance and the future
replacement of the individual components and /or their complete renewal.
Items of plant and equipment, as named, have been sourced from a number of
international manufacturers/suppliers, acknowledged as having had experience in
providing equipment suitable for the intended use/application, with proven longevity
under operation in harsh climatic conditions.
The Contractor shall be at liberty to consider alternative manufacturers / suppliers; in
doing so, the Contractor is required to complete the Tender Declaration Form – Plant
+ Equipment and to submit the latter with his Tender.
In submitting alternative names, the Tenderer shall be expected to have checked that
his proposed manufacturers / suppliers’ plant and equipment satisfies the overall
performance, quality and dimensional requirements when compared to the
manufacturer / supplier as named within this Document.
The Contractor shall be required to provide, at the time of submitting his Tender, full
technical details of any proposed alternative manufacturer / supplier of the following:
(i). Main Electrical LV Panel board, Fused Switch Disconnectors + Distribution
Boards
(ii). Lighting Fittings and Switches
(iii). Small Power Requirement
(iii) Inverter Air Conditioning Units
1.5 Contract Works : Regulations and Standards
The EES Installation shall comply with the Technical Specification (s) set out within
this Document with all relevant British Standards and Codes of Practice and with all
other relevant Statutory Instruments and Regulations current at the time of Tender.
1.6 Contract Works: Materials and Workmanship
All materials must be suitable for their intended use/application and must comply with
the relevant Standards and be installed in accordance with the Codes of Practice and
Manufacturer’s recommendations.
7
All site operatives must be suitable qualified and experienced for the work that they
are assigned to carry out. All workmanship must be of a good standard.
The Project Architect and the M+E Engineer shall reject poor materials and
workmanship and it shall be the contractor’s responsibility to put right such rejected
Contract Works at his own expense.
1.7 Contract Works: Programme
The Contractor shall allow adequate time within his overall Contract Works
Programme for presenting and receiving comments to / from the Project Architect /
M+E Engineer with respect to:
i. Design Development Information
ii. Installation Drawings
iii. Testing and Commissioning Procedures
1.8 Supervision of the Contract Works
The Contractor shall employ a competent, qualified and experienced Principal
Resident Site Engineer, who shall be in charge of the Contract Works during all
working hours and in attendance until the whole of the Contract Works has been
completed and accepted on behalf of the Employer/User.
The Contractor’s appointed representative shall attend meetings on site and be
empowered to answer on behalf of the Contractor.
The Contractor shall appoint a Deputy Site Engineer to cover for periods of absence
of the Principal Residence Site Engineer. Coordination of the Contract Works
The Contractor shall be responsible for the coordination of the all Electrical
Engineering Services Systems, such that each may be installed in a manner which
ensures the correct performance of the system and avoids conflict in the positioning of
the various Building Engineering Services (BES) elements.
The Contractor shall include within his Tender for the detailed development of his
Installation Drawings to contribute to a fully coordinated and integrated BES
Installation.
1.9 Contract Works: Installation Drawings
The Contractor shall prepare and submit to the Project Architect/ M+E Engineer,
Installation Drawings for all of the EES systems to be installed under the Contract
Works, together with such schedules, data, calculations, systems schematics and other
supplementary details necessary to execute the Contract Works.
The Installation Drawings shall be fully detailed, depicting the positions and physical
dimensions of all of the BES Systems Components.
The minimum scale for the production of the coordinated Installation Drawings shall
be:-
LV Panelboard Switch room: 1: 20
Floor Plans 1: 50
Site Services 1: 200
The Contractor shall make due allowance for the preparation of the EES Installation
Drawings within his Tender and within his Overall Contract Works Programme
8
1.10 Contract Works: Fixing of the Services Installation
The Contractor shall be wholly responsible for the sizing, supply and installation of
all supports/fixings for the electrical engineering services.
1.12 Contract Works: Builders Work
Builders Work in connection with (BWIC) the EES Contract Works, such as duct,
holes, basses, chasses etc. shall be detailed by the Contractor as separated drawings.
The Contractor shall inform the Project Architect/M+E Engineer of any BWIC that
may affect the building structure and/or envelope.
The Contractor shall make due allowance for the detailing of the BWIC requirements
within his Tender and within his overall Contract Works Programme
1.13 Contract Works: Testing and Commissioning
The Contractor shall ensure that suitably qualified and experienced personnel,
together with the necessary instrumentation, are available at the time required to set to
work, test and commission the mechanical and electrical engineering services
systems.
The format of the testing and commissioning procedure, together with the details to be
entered on the test sheets, shall be agreed with the M+E Engineer.
The Contractor shall agree with the Project Architect/M+E Engineer a Programme for
the testing and commissioning of the various EES Systems.
The M+E Engineer shall retain a detailed record of all the testing and commissioning
procedures on site for examination.
The testing and commissioning shall demonstrate, amongst other things, that:
(i) All electrical circuits are properly electrically and physically protected and
earthed.
(ii) All electrical switchgears are neatly positioned, levelled and secured.
9
1.14 Contract Works: Record Documentation
The Contractor shall supply to the Project Architect/M+E Engineer, as a prerequisite
to the Practical Completion of the Contract Works, a comprehensive record of the
completed mechanical and electrical engineering services installation. This shall take
the form of:-
i. AutoCAD based disk detailing all INSTALLATION DRAWINGS.
ii. 4 No. Dyeline prints of all INSTALLATION DRAWINGS.
iii. 4 No. Bound A4 copies of the OPERATING + MAINTENANCE MANUALS,
to include:-
a) Copies of all testing and commissioning certificates.
b) Manufacturers/Suppliers technical data for the maintenance and operation of all
plant and equipment, together with a schedule of spares provided.
c) Schedule recording all installation drawings.
The Contractor shall maintain accurate records of all testing and commissioning
procedures throughout the course of the Contract Works for incorporation into the O
+ M Manuals.
The Contractor shall have available a DRAFT COPY of the Record Documentation
for inspection by the Project Architect/M+E Engineer prior to Practical Completion of
the Contract Works.
1.15 Contract Works: Instruction of Employer’s Staff
The Contractor shall include within his tender, under the heading “Record
Documentation”, from the instruction of the Employer’s Appointed Maintenance Staff
on the operation of the EES Systems, to include emergency/breakdown procedures.
The instruction shall take place following the testing and setting to work of the EES
Systems.
A “Draft” copy of the Operating + Maintenance Manual shall be made available for
review by the Employer’s representative during this period.
1.16 Contract Works: Variations
All instructions, variations, additions to the Contract Works are only valid when
agreed to/signed for by the Project Architect (Manager).
Should the Contractor receive, during the progress of the Contract Works, any
instruction for additional work, Which he considers may affect the completion of the
Contract Works within the prescribed Contract Period, he shall be required to
formally notify the Project Architect in writing within seven days of the receipt of
such and instruction.
1.17 Contract Works: Practical Completion
The Contractor shall be responsible for inspecting the EES Installation and shall have
prepared his own defects inspection list and shall duly attend to the same, prior to
offering the completed EES Installation to the Project Architect (Manager) for
inspection and acceptance on behalf of the Employer.
The Project Architect/M+E Engineers’ inspection shall be one of formality and should
not be considered as an inspection for the purposes of forming the Contractor’s final
list scheduling the Outstanding Works.
10
The Contractor shall agree with the Project Architect/M+E Engineer, a suitable date
for the FINAL INSPECTION.
1.18 Maintenance of Services
Any works necessitating interruption or termination of any services required to be
maintained or serving areas outside of the designated works area shall be thoroughly
coordinated and not be initiated until a Programme of works indicating disruption
time scales and/or temporary arrangements has been submitted and agreed fully by all
concerned.
1.19 Contract Works: Defects Liability Period
The Contractor shall be responsible under the Contractor for addressing/correcting all
of the EES Contract Works defects occurring within a period of TWO MONTHS,
commencing from the date of the PRACTICAL COMPLETION CERTIFICATION.
During the Defects Liability Period, the Contractor shall provide prompt and effective
“call back” service to attend to any urgent faults which may develop and which would
affect the day-to-day function of the building complex and facilities.
The Contractor shall retain a written log on site recording the details of the defect – i
e, date notified/date attended, fault identified, action taken, together with any ongoing
investigations/remedial work.
1.20 Contract Works: Provisional Sums
Provisional Sums have been entered on the Electrical Engineering Services
Installation – Tender Breakdown – Form of Tender Document.
These Provisional Sums provide for Works of Costs, which cannot be foreseen,
defined or detailed at the time of preparing the EES Contract Works Tender
Documentation.
The Provisional Sums include for the Contractor’s overheads and profit and therefore
are to be included in the Tender Breakdown as net sums without any further additions.
Instructions as to the deduction of expenditure in whole or in part of the Provisional
Sums shall be instructed by the Project Architect (Manager) during the course of the
Contract Works, as found necessary.
1.21 Contract Works: Schedule of Rates
The Contractor shall submit within his Tender, a priced copy of the Schedule Rates.
Each of the elemental rates shall include for all necessary labour and materials,
together with overheads and profit.
The declared Tender rates shall be used to evaluate all Works added, deleted and/ or
amended against the Contract Works Tender.
The Project Architect (Manager) reserves the right to reject any tender which does not
include the completed Schedule of Rates, returned with the Tender Submission.
11
1.22 Contract Works: Tender Breakdown
The Contractor shall, when submitting his Tender for the Contract Works, enter on
the Tender Breakdown – Form of Tender Document, Lump Sum Costs for each of the
Electrical Engineering Services elements as prescribed.
The Project Architect reserves the right to reject any Tender, which does not include
the completed Tender Breakdown.
12
2.0 TENDER SPECIFICATIONS:
2.1 Introduction:
2.2 General:
The Power Distribution System (PDS) for the Third Floor for the Office Building at
Lamina Sankoh Street, Freetown for Sierra Leone Country Office of the African
Development BANK (ADB) is to be supplied from a 160A, 4-way MCCB LV Panel
board located in the LV Panel board Switch room. The entire electrical system shall be
based on a 230/400V, 3 phase and neutral, 50 Hz, Terra Neutral- Separate (TN-S)
system.
2.3 Regulations and standards
The complete installation shall comply with all relevant British Standard and, where
indicated, with other standards and specifications and all amendments thereto. A
Certificate of compliance shall be provided for the Project Architect, to be included in
the handover.
2.4 Design parameters
Division of installations:
The installation shall be divided into circuits as necessary to:
a. Avoid danger and minimize inconvenience in the event of a fault
b. Facilitate safe inspection, testing and maintenance
c. Take account of hazards that may arise from the failure of a single circuit such as
a lighting circuit
d. Reduce the possibility of unwanted tripping of Residual Current Devices (RCD)
due to excessive protective conductor current not due to fault
e. Mitigate the effect of electro-magnetic disturbances
f. Prevent the indirect energizing of a circuit intended to be isolated
3.0 Prospective fault current (Pfc)
If a protective device is to operate safety, its rated short-circuit capacity must be not less
than the prospective fault current at the point where it is installed.
The distributor needs to be consulted as to the prospective fault current at the origin of
the installation.
4.0 Earth loop impedance external (Ze)
The Ze is to comply with British Standards.
5.0 Voltage droop
The voltage drop between the origin of the installation and a lighting point should not
exceed 3% of the nominal voltage and for other current using equipment or socket
outlets should not exceed 5%
6.0 Electrical installation:
6.1 General.
The contractor shall procure, install, inspect, test and commission the entire electrical
system within the Third Floor as stated within this Specification and associated
drawings.
13
6.2 Main supply.
The main supply should comprise of a TN-S system at 400V, 50 Hz. The incoming
supply cable from the Main 200A, TP&N LV Busbar located within the Generator
House should be run via the existing service duct system and connect and terminated to
2Nr. 8-way TP&N LV Raw Power Distribution Boards located on the Third Floor
Electrical Switch Room as shown on the drawing.
7.0 Electrical service ducts
7.1 Service duct detail.
The supply cable is to be laid or drawn through the existing services duct
.
7.2 Trenching:
No work shall commence until the Contractor has taken all reasonable steps to ensure
that the area is free of all cable, drains and other services. A cable Avoidance Tool
(CAT0 and Signal Generator (Genny) or any other equivalent cable detector tool is to
be used to detect services. Unless otherwise indicate the following is required:
8.0 LV electrical equipment
8.1 General:
All intake equipment is to be installed indoors. The main supply is to be installed via a
lockable isolator before entering the distribution board.
8.2 Main intake isolator:
The main intake isolator will be installed directly below the distribution board. The
isolator is to have the ability to be locked off in the OFF position.
8.3 Distribution board:
The distribution board shall comply with the relevant British Standards as well as the
follow:
A It shall be suitable for surface mounting or concealed in blockworks, have
lockable doors (supplier with two keys) and be controlled by an on-load integral
disconnector.
Keys shall be labelled and handed to the Project Architect/M&E Engineer at practical
completion.
B Where spare ways are provided they shall be fitted with blanking pieces
C All neutral and earth connections shall be made to bars within the distribution
board each connection having an individual terminal. The neutral shall have a
removable link to facilitate testing.
D The connections to the neutral and earth bar shall be made to correspond with the
order of the phase connection.
E All conductors terminated at the board shall be appropriately marked with cable
ring markers indicating the circuit number and phase connection.
F All covers, doors and access plates into the distribution board shall be gasketed to
achieve a minimum protection of IP 32.
14
G Access for cabling shall be from the front only. Shrouding to IP2X shall be fitted
to prevent accidental contact with live parts. Warning labels shall be provided and
fixed.
H There shall be a circuit schedule identifying each circuit giving reference,
description, rating of protective device and connected load located inside the
distribution board
I The circuit schedule shall be typed on an A4 sheet laminated and securely fixed to
the inside of the distribution board door.
8.4 Protection. Protection against electric shock for the electrical installation will be by
means of automatic disconnection of supply. Each protective device is to be identified.
Identification on neutral bus bar and protective conductor bar shall clearly relate each
terminal to its respective device. Overload protection will be provided by the use of the
following devices.
A. Miniature Circuit Breakers (MCBs) MCB shall comply with BSEN61008-1:2012
and have the following characteristic:
(i) Doors shall have a locking system or shall require a special tool for the opening
and have a minimum rated short circuit capacity (1cn) of 10kA unless otherwise
specified.
(ii) MCBs shall be capable of withstanding calculated operational and fault currents
as well as calculated power frequency stress voltages.
(iii) Three phase MCB shall trip all phases on any fault condition.
(iv) Provision shall be made to enable the operating mechanism to be padlocked in
the OFF position.
B. Residual Current Breaker with Overload Protection (RCBO’s).
All 13A socket outlets within the Office Building at Bishop Building Lamina
Sankoh Street, Freetown for Sierra Leone Field Office at the African
Development Bank (ADB) shall be connected through Residual Current Breaker
with Overload Protection (RCBO’s).
All RCBO’s shall comply with BS EN 61009-1:2004+14:2012 and have the
following characteristics:
(i) RCBOs shall be capable of withstanding calculated operational and fault
currents as well as calculated power frequency stress voltages.
(ii) The units shall be double or triple pole as required and mounted enclosed
within the distribution board.
(iii) The RCBO shall automatically open the protected circuit on an earth leakage
fault between phase and earth equal to or greater than the fault current
sensitivity rating of the device.
(iv) The operating mechanism shall be independent trip- free and shall not be
able to be held closed against an earth fault. The units shall be complete with
a test button and trip re- set device.
(v) The RCBO shall have position contact indication whereby the opening of the
device is clearly indicated by a mechanical indicator. This indicator shall be
linked to the device main contacts to show the positive opening of poles.
15
8.5 The ratings and type of protective devices can be found in the Electrical Distribution
Board schedules.
8.6 Labelling:
The Contractor shall ensure they label the following:
a. Lighting and Emergency Exit lighting.
All emergency test key switches shall be labelled EMERGENCY LIGHT.
b. Switches and outlets.
All switches, socket outlets and isolators are to be labelled with their associated
circuit numbers i.e. DB1/1/L1.
8.9. Circuit diagram:
On completion of the electrical system installation, as built drawings of the circuit
layouts are to be produced and be included in the Health and Safety File and issued to
the Authorities at the Sierra Leone Field Office at the African Development Bank
(ADB) during the handover.
9.0 Final circuits
9.1. General:
All fixtures and fittings shall be securely fixed and checked before and after Installation
for defects and damage. All defective fittings shall be replaced. All socket outlets shall
be run as ring final circuit.
9.2 Sockets:
Socket outlets shall comply with the relevant British Standard for the type of outlet
indicated. Socket outlets shall be of the type and rating as indicated. PVC and metal
sockets are to be selected dependent on the room function. All other areas are to be
fitted with PVC and store areas are to be fitted with metal outlets (PVC conduit, back
box and faceplate).
9.3 Mounting heights:
Socket outlets shall be mounted at a height of 400mm above FFL and located in
positions shown on the associated drawings.
9.4 Fixed power circuits:
All fixed power shall be supplied by redials. The split Air Conditioning Units ACU’s
are to be supplied via individual radial circuits dedicated to each ACU. The split Unit
ACU’s are to have lockable rotary isolator switches for the external condenser.
9.5 General. Lux levels are to be achieved as specified. The light fittings are to be of a
sufficient IP rating to protect against dust and insect ingress. The lights to be used are
detailed in the lighting drawings, capable of achieving the light levels as design.
9.6 Emergency lighting:
Emergency lighting systems and equipment shall comply with BS 5266-1:2011. The
emergency lighting should be integral to the entire lighting system. The emergency
lighting shall have the following:
a) Emergency escape lighting:
16
Emergency escape lighting shall provide illumination for the safety of personnel
leaving a location or attempting to terminate a potentially dangerous process before
doing so. In the event of power failure a minimum of 1 LUX level is to be
maintained at floor level for duration of 3 hours. The emergency escape lighting is
to be provided by maintained emergency luminaires that shall have their lamps
energized during normal use or in the event of power failure. The battery backup
shall be permanently connected to a circuit supply via a temper proof test switch,
without interruption by local functional switching.
b) Emergency escape route lighting:
The emergency escape route lighting shall ensure that the means of escape can be
effectively identified and safety used when the premises are occupied. The
emergency escape route lighting is to be provided by non-maintained emergency
luminaires with pictogram and shall energize their lamps during the event of a
power failure. The battery backup shall be permanently connected to a circuit
supply, via a tamper proof test switch, without any functional switching.
Fluorescent Emergency Exit signs are to be located over each external access
doors. The area immediately external of the door is to be illuminated to a distance
of 10m at a level of 1 Lux.
9.7 Switches:
Switches shall comply with the relevant British Standard for the type of switch
indicated. Switches shall be single pole for single phase circuits and the current rating
shall be the room. All other areas are to be in PVC and store in metal clad fittings.
Switches are to be mounted at 1400mm above FFL.
10.0 Cable containment
10.1 General:
The size of the containment shall be calculated in accordance with BS 7671+A2:2013.
Conduit, including flexible and pliable conduits shall be non-metallic and comply
with the relevant British Standards. When circuits are run in containment the
following shall apply:
a. Trucking shall comply with BS 4678-4; 1982 and be 50 x50mm in size
b. PVC Conduit shall comply with BS EN 50086-2-1:1996 and BS 4568-1; 1970 and
be 20mm and 50mm in diameter.
10.2 Trunking general:
Where trunking is required to pass through wall fabrics it shall be fitted with suitable
and approved flame proof fire barriers.
10.3 Supports and joints:
The trunking shall be installed in the ceiling void and secured to the trusses and in
vertical service ducts and secured to the wall surface. Expansion couplings shall be
protective where trunking crosses any expansion joints within the building fabric.
10.4 Bonding:
The metallic trunking must be bonded to earth and tested for continuity but must not
be used as a means of providing the protective conductor
17
10.5 Access and covers:
Trunking and fittings shall have removable lids along its entire length. The lids shall
be of the same material, thickness and finish as that of the trunking.
10.6 Conduit general:
Metallic conduit shall have screw threads for jointing length to length and for the
attachment of accessories, PVC conduit shall use female couplers. Conduit and
fittings shall be screwed to the building fabric unless indicated and approved by the
Project Architect/M&E Engineer. High impact areas shall have galvanized steel
conduit and all other areas shall be PVC. Adequate protection against corrosion shall
be provided to steel conduit.
a Supports, Junction boxes and back boxes installed in conduit runs needs to be
separately fixed to underlying surface and not rely on the efficient saddling of
conduit for their support. A spacer bar saddle shall be fixed 150mm adjacent to
any junction or back box. Fixing saddles shall be positioned at a maximum of
1200mm apart or 300mm from conduit outlet boxes or changes in direction.
b Bends. Steel conduit shall be bent on site to the required shape to allow the
conduit to run around obstacles and corners. All conduit bends shall be achieved
without distorting the diameter of the conduit. Conduit bending shall be by means
of a good quality conduit bending machine, in good condition and any poor or
damaged conduit bends shall be rejected.
c Couplers, bushes ad glands. Bushes and glands used in conjunction with conduits
and conduit accessories shall be appropriate to the type used. Conduit connected
to galvanize steel trunking, back boxes and fluorescent fittings shall utilize a
coupler and male brass bush. The male bush is to be fitted by the appropriate
methods.
d Saddles, Spacer bar saddles shall be used for fixing conduits to surface walls and
ceilings. In all cases the conduit is to be run parallel to the building lines and shall
be fixed in position at intervals of not more than 120mm by means of spacer bar
saddles and these saddles shall be fixed by the appropriate methods.
e Access and covers. Covers for conduit boxes shall be appropriate to the type
used.
11.0 Cable
11.1 General:
All cable types shall be certified and marked in accordance with the British Approvals
Services for Electrical Cables (BASEC) or equivalent. Cables shall be segregated
from other services and shall comply with IEE Specification 034.
11.3 Cable routes:
Cables installed on the surface shall be parallel with the lines of the building
construction and properly aligned. Cables buried below ground shall, as far as is
practicable, follow the features of the site such as building lines.
18
19
11.4 Cable segregation:
A minimum clearance in accordance with IEE Specification 034 shall be allowed
from any equipment, pipework or ductwork. In the event of difficulty in achieving
these requirements the M& Engineer shall be consulted. Adequate space shall be left
between cable runs building fabric and other services to allow for the future removal
or installation of cables.
11.5 Cable Cleats:
Cable cleats shall be made from materials that are resistant to corrosion without the
need for treatment or special finish. Plastic materials shall be non-brittle. Cable cleats
shall be of a suitable size such that they can be tightened down to grip the cables
without exerting undue pressure. The spacing of cable cleats shall comply with
BS7671+A2:2013. On each side of a bend, cable cleats shall be used to secure the
cable.
12.0 Protective conductors and bonding
12.1 General:
Automatic disconnection of the supply is the method of protection utilized for basic
and fault protection. Therefore, all protective conductors and supplementary bonding
is to ensure that, in the event of a fault, sufficient current flows to operate the
protective devices i.e. MCBs or RCD/RCBOs
12.2 Earth conductor:
In accordance with BS 7671+A2:2013, the minimum cross sectional area of the
protective conductor shall be half the cross sectional area of the line conductors.
12.3 Supplementary bonding:
Supplementary bonding conductors shall be installed to all exposed metal conductive
parts. In any part of the installation where the earthed metalwork of the electrical
system comes into contact with the metalwork of any other services, structure or
equipment a permanent earth bond shall be formed as close as is practicable to the
point of contact.
13.0 Inspection testing and commissioning
13.1 General:
During erection, on completion and before being put into services the electrical
installation shall be inspected, tested and verified, so far as is reasonable practicable
that the requirement of BS 7671 + A2 :2013 have been met. The verification shall be
made by a competent person and shall include comparison of the results with the
relevant criteria and regulations. On completion of the verification all relevant
documentation shall be prepared.
13.2 Inspection:
The inspection shall precede any testing of the installation and shall be carried out by
a competent person with that part of the installation being disconnected from the
electrical supply
20
13.3 Live testing:
Live testing shall only be undertaken once suitable precautions have been put in place.
Calibrated equipment and suitable personnel protective equipment must be used.
Although live testing is a recognized method, under no circumstances is any
rectification to be carried out live.
13.4 Safety:
It is the responsibility of the test engineer to ensure their own safety and the safety of
others whilst working through the test procedure. Prior to testing the installation the
test engineer is to ensure the following precaution, are taken:
a. Equipment.
The tester must have knowledge and experience of the correct application and
use of the test instrumentation, leads, probes and accessories.
b. Standards.
All test equipment must meet the safety measures and procedures laid out in
Health and Safety Executive Guidance Note GS 38 for all instruments, leads,
probes and accessories.
13.5 Inspection and test procedure.
The inspection and testing of the new installation shall include the following:
a. Prior to energizing. Before energizing the following procedure is to be followed:
(1) Visual inspection as laid down within the current edition of BS 7671 +A2:2013
(2) Continuity of protective conductors, including main and supplementary bonding
(3) Continuity of ring final circuit conductors, including protective conductors
(4) Insulation resistance
(5) Polarity (by continuity method)
b. During energizing. With the supply connected and energized the following
procedure is to take place:
(1) Check polarity of the supply, using an approved voltage indicator
(2) Earth fault impedance
(3) Prospective fault current measurement
14.0 Certification and forms of completion
14.1 General:
The Contractor is to prepare all forms of completion. Current editions of forms are to
be used from BS 7671+A2:2013
14.2 Commissioning:
The Contractor shall be responsible for carrying out all inspection and testing of the
installation in accordance with BS 7671+A2:2013. The Contractor is to complete their
requirement sections of the commission forms and present them to the Project
Architect/Engineer for submission to the Bank.
14.3 Results.
21
All results obtained during the test procedure are to be recorded on the Schedule of
Test Results for the distribution board for future reference and checked for
acceptability against the prescribed criteria. All failed measurements are to be
highlighted to the Engineer/Bank at the earliest prepared to accompany the Schedule
of Test Results. All documents are to be included in the Health and Safety File and
issued to the Bank during the handover board.
14.4 Emergency lighting.
All emergency lighting is to be tested and certified in accordance with BS 5266-
1:2011. All test results are to be presented as part of the H&S File. The emergency
lighting system is to have the following certificates completed and presented as part
of the Health &Safety File:
a. Emergency lighting completion certificate:
To BS 5266-1:2011 Annex C emergency lighting completion certificated by the
Contractor’s Engineer
b. Design declaration of conformity:
To BS5266-1:2011 Annex C declaration of conformity to be completed by the
Contractor’s Engineer
c. Installation declaration of conformity:
To BS 5266-1:2011 Annex C installation declaration of conformity to be
completed by Contractor’s Engineer
d. Verification- declaration of conformity:
To BS 5266-1:2011 Annex C verification of conformity to be completed by the
Contractor’s Engineer
e. Periodic inspection and test certificate:
To BS 5266-1:2011 Annex D periodic inspection and test certificate to be
completed by the Contractor’s Engineer with assistance from the Bank Facility
Manager.
22
3.0 ELECTRICAL ENGINEERING SERVICE INSTALLATION
3.1 Incoming Electrical Power supply
3.2 Low Voltage Panel board
3.3 Low Voltage Distribution Boards
3.4 3-Compartment Dado Skirting System
3.5 Earthing + Bonding
3.6 Structured Cable Management System (SCMS)
23
3.1 Incoming Electrical Power Supply
System Description
System Drawings + Data
SL/ADB/E-1: Block Schematic Layout Power Supply & Distribution
Network
SL/ADB/E-2: Line Schematic Layout Primary / Secondary LV Distribution
Network
Appendix 1: Schedule of Incoming Electrical Raw Power Supply from the 200A,
TP&N LV Busbar located on the Ground Floor in the Main Switchroom.
System Plant, Equipment + Materials
3.2 Low Voltage TP&N Busbar:
The existing Low Voltage 200A, TP&N Busbar is located in the Main LV
Switchroom on the Basement Floor.
▪ Busbar chamber produced in 200A rating
▪ Nominal lengths 610mm
▪ Twin copper busbars are located in the same positions throughout the range
▪ Twin bar design for easy positioning of cables
▪ Fully rated Neutral
▪ win bar design to 200A
▪ One set of 4 clamps supplied with each chamber as standard
Specification:
Busbar Rating: 200A
Colour: Grey
Current Rating: 200A
Depth: 190mm
Dimensions: (H) 400 mm x (W) 1220 mm x (D) 190 mm
Finish: Epoxy Powder Coated Paint
Height: 400mm
IP Rating: IP31
Material: Full Cold Rolled Steel
Mounting: Wall
Number of Poles: 4 Pole
Packaging Types: Each
Product Range: Busbar Chambers
Size: 1220 mm
Standards: BS EN 61439-1
Unspsc: 39121320
Voltage Rating: 400V
Width: 1220mm
3.2.2 Fault Rating
The Busbar shall be constructed and type tested to withstand a fault level of 50KA for
1 second in accordance with BSEN 60439-1
24
3.2.3 Construction General
The Busbar shall be modular sheet steel, minimum 2mm thickness, cubicle built on a
rigid,
Self-supporting framework with compartments separated by barriers of a minimum
1.6mm thickness
Overall external Ingress Protection (IP) rating for the Panelboard shall not be less than
IP31 as defined in BSEN60529.
All internal live parts shall be protected to IP2X.
All parts of the Busbar both internal and external shall be free of sharp edges and
sharp corners.
3.2.4 Construction Form Type
The Busbar shall be Form 4, Type 2 as defined in BS 60439.
Busbars shall be separated from functional units.
Terminations to functional units shall be separated from each other.
Busbar separation shall be achieved by metallic or non-metallic rigid barriers or
partitions.
3.2.5 Busbars and Cabling
The busbar system shall comply with BS 159 and shall be:-
1. HDHC copper bar.
2. Fully rated allowing for any reduction in CSA where bars are drilled.
3 Inaccessible from equipment compartments and protected by sheet steel
barriers or shutters.
4. Clearly and indelibly colour identified as red, yellow, blue and black
respectively.
5. Tested in accordance with BS 7767
Connections between the busbars and the connected components shall have a current
rating not less than the nominal rating of the component and shall be of adequate
cross section for the specified fault level. Connections to functional units from the
main busbars shall be suitably rated copper busbars to a minimum of 250 Amps and
below this rating shall be in appropriately sized single core black PVC insulated, tri
rated, copper stranded cable.
All connections shall be marked with the requisite colour identification.
All connections from busbars to control and instrumentation equipment shall be
protected by fuses. The fuses shall be mounted on or as close as possible to the
busbars. Further fusing within the equipment’s compartment shall be provided if
necessary to ensure adequate discrimination.
Neutrals shall be full size for all busbars and cabling.
3.2.6 Earth Bar
A continuous, horizontally mounted earth bar shall be provided throughout the length
of the Panel board of minimum size 50mm x 6mm, suitable for extension and with
25
provision for bonding all metalwork with bolted connections. A minimum of two
connections shall be provided to the Panel board framework.
A minimum of two earth connections shall be provided for connection to the external
main earth ring.
Earthing shall comply with BS 7430, Code of Practice for Earthing.
Vertical earth bars shall be provided in each of the wiring chambers linked to the
main earth bar drilled out and fitted with suitable fixings for the appropriate number
of functional unit earth connections.
All earth bars shall be clearly identified within each wiring chamber.
Bolted copper links shall be provided to enable the switchboard earth system to be
isolated from the main earth ring for testing.
3.2.7 Wiring and Cabling
All internal wiring and cabling shall be:-
1 Terminated with suitable copper tube lugs, insulated end sleeves or PVC
insulated crimp terminals.
2. Fully insulated, PVC tri-rated grade cable to BS 6231.
3. Protected by grommets, bushes or glands where it passes through metal
enclosures.
4. Protected against heat and mechanical damage.
5. Labelled at both terminations. These reference numbers shall appear on the
wiring diagrams.
All power cabling shall be securely clamped to remain in place under the worst fault
conditions, and they shall not be supported by their terminations.
Small wiring shall be enclosed in trunking or other cable management system and
shall be numbered at both ends with the terminal number and wire number shown on
circuit drawings.
Cable terminations at 230VAC shall be fitted with a suitable removable shroud or
barrier to IP2X.
Panelboard to comply with BS 5486: Part 1, Form 4 with IP 54 degree of protection,
cable mounted. Circuit details as indicated in Appendices-1
System Plant, Equipment + Materials
3.3 Distribution Boards
Distribution Boards to be of totally enclosed type (IP 31) to provide protection in
compliance with BS 5420 IEC 144. The location of distribution boards to be as
recorded within Appendices 1a &b, 2a.
A multi-terminal Earthing bar shall be provided for circuit protective conductors of
the insulated metal cased boards, with one terminal for each outgoing circuit. These
26
will be connected directly to Earthing terminal without dependence on exposed
conductive parts of enclosure.
Distribution Boards shall be labelled showing the area and services which are to be
fed from them, and where not otherwise immediately obvious, their source of supply.
The engraving to be in white 10mm high letters on red plastic sheet or equal and fixed
external to the lids of apparatus by screw or rivets.
Low voltage Switchgear:
(i) Moulded Case Circuit Breakers (MCCB’s)
Moulded Case Circuit Breaker ratings shall be as stated within Appendix -1.
They are to be of the 500V totally enclosed metal clad type, complying with
BS 4752 (IEC 157-1) ASTA Certified P1 or P2 rating (50/35KV, 415V).
(ii) Miniature Circuit Breakers (MCB’s)
Miniature circuit breakers for incorporation in distribution boards to comply
with the requirements of BS 3871 (IEC 898)
(iii) Switch Fuses and Isolators
Switch fuses to be of the 500V totally enclosed metal clad type, complying
with BS 5414 (IEC 408) AC22 and AC23 rating. All switch fuses to be fitted
with HRC fuse cartridges and to be SP + N / TP + N, as required and as rated
in Appendix 12.
(iv) Residual Current-Operated Circuit Breakers
Residual current-operated circuit breakers to comply with BS 4293 (IEC 755)
(v) Isolators
Local isolator shall be supplied and installed for the control of each power
consuming fixed appliance which is solidly connected. It is necessary to
ensure that the means of isolation and the appliance are in the same room and
in direct line of vision and not more than 6 meters apart.
(vi) PVC Insulated Armoured Cables
These cables shall be of 600/1000V grade in compliance with BS 6346. The
conductors to be insulated with PVC or XLPE insulated, PVC bedded,
armoured with a single layer of galvanized steel wire or tape, and sheathed
overall with PVC.
Unless specifically indicated otherwise, all cables shall have copper
conductors.
Where cables enter switchgear and other apparatus, they are to be made off
with suitable brass glands which shall incorporate both a cone grip armour
clamp with positive armour locking and a resilient compression gland to
firmly grip the outer PVC Sheath of the cable. A brass earth tag to be fitted
between the gland and the apparatus. A secure earthing connection to be made
between the earth tag and the main earthing terminal of the apparatus, using a
suitable copper conductor
27
(vii) PVC Insulated Single Core Cables
These cable to be of 600/1000V grade to BS 6004 and, unless specifically
indicated otherwise, to have copper conductors. Cable for all services shall be
in accordance with the Appendix 11 and the latest IEE Regulations. Cables to
be coloured in accordance with Table: 52A of the IEE Regulations.
(viii) Wiring Installation
PVC Conduit (Concealed)
PVC conduit and fittings to be high impact type, heavy gauge, BS 4607
Compliant, AH grade.
No conduit to be less than 20mm dia.
PVC conduit to be concealed within walls
(ix) Flexible Metallic Conduit (Plant)
Flexible metallic conduit to be of the overlapping helically wound flexible
steel type, with a PVC outer cover in accordance with BS 731. The conduit to
be fitted with heavy duty couplers and connections and to include a bush to
protect cables when drawn-in
Flexible metallic conduits on Plant and Equipment final connections
(x) Cable Trunking
Cable Trunking to be installed in floor ducts and plant rooms on routes as
shown on drawings.
(xi) Cable Trunking Plastics
The cable Trunking to be constructed of heavy gauge extruded high impact
PVC.
(xii) Cable trays
Cable trays to be galvanized punched metal.
Cable trays to be installed in ground floor ducts, service risers, plant room and
switch rooms.
3.4 3-Compartments Dado Trunking
The PVC Dado Trunking system has been designed to prevent communication
interference, with its 3 compartments designed to separate data communication /
telephone and mains 240V cables.
The 2 outer compartments are designated to the data communication and telephone
cables; the center compartment is for use with 240V mains cable.
The product is ideal for re-routing cables from horizontal position to vertical with no
visible joints.
28
3.5 Earthing + Bonding
System Description
Earthing and Bonding to be undertaken in compliance with IEE Wiring Regulations
and BS 7430.
Equipotential bonding to be applied to all exposed metal parts and in particular:-
Metal cable trunking and trays
3.6 Structured Cable Management System (SCMS)
System Description
A fully integrated / coordinated SCMS to be supplied / installed, arranged to
accommodate cabling system in the vertical service ducts
System Plant, Equipment + Materials
(i) Vertical Service Ducts
400mm wide x 25mm deep, galvanized, punched metal cable trays, fixed to
the building structure with support brackets.
(ii) Ceiling Voids (Basement Floor, Ground Floor and First Floor
Type A – 400mm wide x 50mm deep,
Type B – 300mm wide x 50mm deep,
Type C – 2mm wide x 50mm deep, high strength, electro-plated zinc,
galvanized
Steel rod wire basket cable tray, fixed to ceiling with support brackets.
Wire baskets and fittings to be as manufactured / supplied by Wiremould
Cables to be secured within cable trays / baskets employing “VELCRO” type
quick release fasteners.
Dado/Skirting Trunking (Reception Area, Conference Room, Server Switch
Room, Store,, and Offices.
Type D – 135mm x 50mm deep, white finished chamfered high impact PVC
manufactured in accordance with BS 4678. Part 4 (1982)
Tender Drawings/Figure Nos
Drawing
Number
System Drawing Type Detail
SL/ADB/E-1 Low Voltage
Distribution
Block Schematic
Layout
Incoming Power Supply and Low Voltage
Distribution
SL/ADB/E-2 Low Voltage
Distribution
Line Schematic
Diagram
Panelboard locations, Incoming/Outgoing LV Cable
Routing, Fire Alarm, Door Access Control and
CCTV Camera Locations
Structured Cable
Management System
Cabling Systems in vertical service duct
TO BE READ IN CONJUNCTION WITH ARCHITECTURAL AND STRUCTURAL ENGINEERING
DRAWINGS
29
Contract Works: Named Plant, Equipment + Materials.
The Contractor shall enter below the names of the Manufacturers / Suppliers of the Plant,
Equipment and Materials included within his Tender Price, either by confirming his use of
the ‘As Named’ Manufacturer/Supplier or by defining his proposed alternative.
4.0 SCHEDULE OF APPENDICES:
Appendix DETAIL
1 Incoming Raw Power Electrical Supply: Schedule of Existing LV Busbar Panel
2a Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 1 – Third Floor
2b Low Voltage Power Distribution: Schedule – Raw Power Distribution Board 2 – Third Floor
3 Low Voltage Power Distribution: Schedule – UPS Distribution Board 1 – Server Room Third Floor
4 Low Voltage Power Distribution: Schedule – Small Power Requirements – Third Floor
5 Schedule of Light Fittings - Internal / External Areas Third Floor
6 Incoming Electrical Power Supply: Schedule of Cables – Third Floor
7 Technical Specification – Electrical Services Installation
8 Technical Specification – Inverter Single Split Air Conditioning Unit Services Installation.
Plant, Equipment, Materials As Named Manufacturer/Supplier
in this Document
Proposed Alternative
Manufacturer/Supplier
(Country of Origin)
1. Panelboard PROTEUS
2. Distribution Boards PROTEUS
3. Fused Switch Disconnectors PROTEUS
4. Luminaries Thorn Lighting Ltd +DESIGNPLAN
5. Small Power Accessories MK Ltd Legrand
6. 3-Compartments Dado Trunking
7. Structured Cable Management System Wiremould Ackermann Centaur
30
APPENDIX 2 – SCHEDULE OF RAW POWER DISTRIBUTION BOARDS THIRD
FLOOR
2a Raw Power Distribution Board 1 – Third Floor
Location: Third Floor
Reference: Raw Power DB-1
Type: 1 x 8Way 125A TP + N
Fed From: 200A, TP&N 4-Pole Busbar
Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc
Cct
No
Circuit MCB Cable Size
(mm sq.)
Load in Watts
R Y B
1 Outdoor Passage Area - Lighting 10A 1.5-2c + E
2 Male / Female Toilets- Lighting 10A 1.5-2c + E
3 Store & Switchgear Area - Lighting 10A 1.5-2c + E
4 Reception/ Passage/ Lobby Area - Lighting 10A 1.5-2c + E
5 Server Room - Lighting 10A 1.5-2c + E
6 Office - Lighting 10A 1.5-2c + E
7 Conference Room - Lighting 10A 1.5-2c + E
8 Emergency Exit Lightning - Lighting 10A 1.5-2c + E
9 Office- Lighting 10A 1.5-2c + E
10 Canteen - Lighting 10A 1.5-2c + E
11 Servery/Kitchen Areas - Lighting 10A 1.5-2c + E
12 Male / Female Toilets- Lighting 10A 1.5-2c + E
13 Store existing- Lighting 10A 1.5-2c + E
14 Reception – A/C Unit - 1- Radial 40A 4.0-2c + E
15 Server Room – A/C Unit - 1- Radial 40A 4.0-2c + E
16 Server Room – A/C Unit - 1- Radial 40A 4.0-2c + E
17 Office – A/C Unit - 1- Radial 40A 4.0-2c + E
18 Office – A/C Unit - 1- Radial 40A 4.0-2c + E
19 Lobby – A/C Unit - 1- Radial 40A 4.0-2c + E
20 Canteen -– A/C Unit - 1- Radial 40A 4.0-2c + E
21 Hand Dryer - 1- Radial 20A 4.0-2c + E
22 Hand Dryer - 1- Radial 20A 4.0-2c + E
23 SPARE
24 SPARE
Phase Total (Watts)
Total Load (kVA)
[p.f = 0.85]
Imax (A)
Io = Imax x 0.85
NOTE: All 13A Raw Socket Outlets within the Third Floor to the RCBO protected
31
2b Raw Power Distribution Board 2 – Third Floor
Location: Third Floor
Reference: Raw Power DB-2
Type: 1 x 8Way 125A TP + N
Fed From: 200A, TP&N 4-Pole Busbar
Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc
Cct
No Circuit MCB
Cable Size
(mm sq.)
Load in Watts
R Y B
1 Conference Room Office – A/C Unit - 1- Radial 40A 4.0-2c + E
2 Conference Room Office – A/C Unit - 1- Radial 40A 4.0-2c + E
3 Conference Room Office – A/C Unit - 1- Radial 40A 4.0-2c + E
4 Conference Room Office – A/C Unit - 1- Radial 40A 4.0-2c + E
5 Hand Dryer - 1- Radial 20A 4.0-2c + E
6 Hand Dryer - 1- Radial 20A 4.0-2c + E
7 Reception – Radial - 2 Sockets 40A 4.0-2c + E
8 Server Room – Radial - 3 Sockets 40A 4.0-2c + E
9 Office -– Radial - 2 Sockets 40A 4.0-2c + E
10 Conference Room-– Radial - 2 Sockets 40A 4.0-2c + E
11 Office-– Radial - 2 Sockets 40A 4.0-2c + E
12 Canteen -– Ring - 3 Sockets 20A 42.5-2c + E
13 Servery/Kitchen Areas– Ring - 2 Sockets 20A 2.5-2c + E
14 Store existing– Ring - 2 Sockets 20A 2.5-2c + E
15
16
17
18
19
20
21
22
23
24
Phase Total (Watts)
Total Load (KVA)
[p.f = 0.85]
Imax (A)
Io = Imax x 0.85
NOTE: All 13A Raw Socket Outlets within the Third Floor to the RCBO protected
32
APPENDIX 3 – SCHEDULE OF UPS POWER DISTRIBUTION BOARDS THIRD
FLOOR
3a UPS Power Distribution Board 1 – Third Floor
Location: Third Floor
Reference: UPS DB-1
Type: 1 x 8Way 125A TP + N
Fed From: 20kVA New UPS
Feed Cable: 1 x 4C x 25mmsq XLPE/SWA/PVC; 10mmsq cpc
Cct
No
Circuit MCB Cable Size
(mm sq.)
Load in Watts
L N E
1 CCTV Multiplexer – Radial 10A 2.5-2c + E
2 Addressable Fire Alarm Panel – Radial 10A 2.5-2c + E
3 Door Access Control Panel – Radial 10A 2.5-2c + E
4 Reception – Radial - 2 Sockets 40A 4.0-2c + E
5 Server Room – Radial - 3 Sockets 40A 4.0-2c + E
6 Office -– Radial - 2 Sockets 40A 4.0-2c + E
7 Conference Room-– Radial - 2 Sockets 40A 4.0-2c + E
8 Office-– Radial - 2 Sockets 40A 4.0-2c + E
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23 SPARE
24 SPARE
Phase Total (Watts)
Total Load (kVA)
[p.f = 0.85]
Imax (A)
Io = Imax x 0.85
33
APPENDIX 4 - SCHEDULE OF SMALL POWER REQUIREMENTS- THIRD
FLOOR
THIRD FLOOR
NUMBER OF SMALL
ELECTRICAL POWER
OUTLETS
TYPE / RATING COMMENTS
TYPE A TYPE B
Server Switch Room TYPE B
MK Logic Plus, Legrand
13Amp Double Switch
Socket Outlets
Power points fitted to 3
compartment high impact PVC
dado trunking installed at skirting
level
Reception Area
TYPE B
MK Logic Plus, Legrand
13Amp Double Switch
Socket Outlets
As Above
Server Room TYPE B As Above As Above
Office TYPE B As Above
Power points fitted to 3
compartment high impact PVC
dado trunking installed at skirting
level
Conference Room TYPE B As Above As Above
Lobby TYPE A As Above As Above
Office TYPE B As Above
Power points fitted to 3
compartment high impact PVC
dado trunking installed at skirting
level
Canteen TYPE A
MK Logic Plus, Legrand
13Amp Single Switch
Socket Outlets
Servery TYPE A As Above
Kitchen TYPE A As Above
Store existing TYPE A TYPE B
MK Logic Plus, Legrand
13Amp Single Switch
Socket Outlets
Door Access Control TYPE A
MK 13 Amp Legrand
Switched Fused Spur
with Neon Indicator
UPS Power points located on wall
at high level adjacent to each door
under Access Control
Alarm Systems TYPE A
MK 13 Amp Legrand
Metalclad Plus Switch
Socket Outlets
UPS Outlet points fitted to
galvanized metal conduits within
Reception Area
CCTV TYPE A
MK 13 Amp Legrand
Switched Fused Spur
with Neon Indicator
UPS power points located on wall
at high level adjacent to each door
under Access Control
Notes: TYPE A – Single Switched Socket Outlet
TYPE B – Double Switched Socket Outlet
Radial Circuit – 2Nr. Socket Outlets to 1Nr. 40A MCB
34
APPENDIX 5: SCHEDULE OF LIGHT FITTINGS - INTERNAL / EXTERNAL
AREAS
S/N AREA REF. TYPE OF FITTING/SWITCHING QTY
A Third Floor:
1 Passage 32W, THORN CETUS 240 Downlight c/w
Bezel
3
2 Male / Female Toilets
13W GX24-Q-2 Lamp - BEGA TYPE No.
2543 - Impact Resistant Ceiling Light, Low
Voltage Fluorescent Lights
4
3 Store by Switchgears As Above 1
4 Switchgear Area As Above 1
5 Reception 600 x 600mm 40W LED Ceiling Panel
Lighting IP44
2
6 Server Room As Above 2
7 Office As Above 2
8 Conference Room As Above 12
9 Passage Area As Above 2
10 Emergency Exit
Lightning
8Watts Emergency Illuminated Exit Sign-
3Hrs. Maintain
4
11 Lobby 600 x 600mm 40W LED Ceiling Panel
Lighting IP44
2
12 Office 18W LED Ceiling Downlight 4
13 Canteen 600 x 600mm 40W LED Ceiling Panel
Lighting IP44
6
14 Servery 1200mm x 36W LED Emergency Fluorescent
fittings.
1
15 Kitchen 1200mm x 36W LED Emergency Fluorescent
fittings.
1
16 Male / Female Toilets
13W GX24-Q-2 Lamp - BEGA TYPE No.
2543 - Impact Resistant Ceiling Light, Low
Voltage Fluorescent Lights
3
17 Store existing 1200mm x 36W LED Normal Fluorescent
fittings.
1
Note: 1. All light fittings to be manually switched.
2. MK Metalclad Plus type switches/switch plates..
3. MK Logic Plus type switches/switch plates.
4 All light fitting wiring to be contained within enclosed PVC conduit pipes and
accessories.
35
APPENDIX 6: SCHEDULE OF CABLE
S/N FROM TO CABLE DESCRIPTION
RAW POWER
A 200A Busbar in Main
Electrical Switchgear
125A, 8-way TP&N LV Raw
Power Distribution Board-1 4C x 35mm2 XLPE/SWA/PVC Cable + 16mm2 cpc
B 200A Busbar in Main
Electrical Switchgear
125A, 8-way TP&N LV Raw
Power Distribution Board-2 4C x 35mm2 XLPE/SWA/PVC Cable + 16mm2 cpc
UPS POWER
A 20kVA 3Ph High
Frequency Online UPS
125A, 8-way TP&N LV UPS
Power Distribution Board-1
4C x 25mm2 XLPE/SWA/PVC Cable + 16mm2 cpc
36
PROPOSED ELECTRICAL SWITCHGEARS
1. 250Amps, 12way Energy Management Panelboard with increasing emphasis
on
energy conservation, we have offers the Proteus Switchgear range of
intrinsic energy management, varying from time switch and relay logic to
electronic microprocessor control*of lighting, heating and ventilation and
fire/security systems.
To meet these changing requirements in commercial and industrial
applications, Proteus Switchgear manufactures custom-designed energy
management panels, typically incorporating the following options:
1. Main incoming isolation / protection up to 800 amps
2. 24 hour essential services distribution•
3. Point of entry / exit key switch controlled services
4. Fire alarm interlocking•
5. Signage control / extended hours manual override
6. Emergency lighting test / battery discharge facility
7. Panels built to specification or in conjunction with Proteus Technical
Department.
2. 3 Pole MOULDED CASE CIRCUIT BREAKERS TO IEC/EN 60947-2’
for use as outgoing devices within and Panelboard.
3. THREE PHASE POWER DISTRIBUTION BOARD
TO 10kA, MCB’s up to 63A (17.5mm Module) 10kA MCB’s 10 amps to
125A
(26.3mm Module) Unique busbar arrangement to accept MCB’s up to 125A
maximum outgoing*
10kA MCB’s 125 amps (26.3mm Module)
Unique busbar arrangement to accept MCB’s up to 125 amps maximum
outgoing
4. THREE PHASE SWITCH DISCONNECTORS WITH FUSES
FEATURES
Specification as Switch Disconnectors above, plus:
Internal switching mechanism also padlockable in off
position
Maximum rated fuses fitted
Fully rated at AC23A category of duty (inductive
load)
Screened terminals
37
5. THREE COMPARTMENT PVC DADO SKIRTING TRUNKING 3 METRE
LENGTHS
3 Metre Lengths, Three Compartments 3 Compartment Dado Flat
Angle
PVC Dado Trunking
3 Compartment Dado Flat Tee 3 Compartment Dado External
Angle
The PVC Dado Trunking system has been designed to prevent communication interference,
with its 3 compartments designed to separate data communication / telephone and mains
240V cables.
The 2 outer compartments are designated to the data communication and telephone cables;
the center compartment is for use with 240V mains cable.
The product is ideal for re-routing cables from horizontal position to vertical with no visible
joints.
38
TECHNICAL SPECIFICATIONS FOR THE
SUPPLY, INSTALLATION AND
COMMISSIONING OF WALL MOUNTED
INVERTER AIR CONDITIONG UNITS ON
THE AT THIRD FLLOR FOR OFFICE
BUILDING AT LAMINA SANKOH STREET,
FREETOWN FOR SIERRA LEONE
COUNTRY OFFICE OF THE AFRICAN
DEVELOPMENT BANK (ADB)
39
AIR CONDITIONING (HVAC) UNITS:
A. Scope Of Specification
1. Installation to Comply with this Specification
The Inverter Air-Conditioning and Control system installation shall comply with
this Specification which details the intrinsic properties (including materials and
workmanship) of the installation in so far as it is not overridden by the Conditions
of Contract, Special Conditions of Contract, and Particular Specification for the
Works, Drawings and/or written instructions of the Project Architect.
2 SCOPE OF THE WORKS
This Specification, Particular Specification, Tender Equipment Schedule and
Drawings detail the performance requirements of the Works. The Works to be
carried out in accordance with this Specification shall include the installation and
supply of all materials necessary to form a complete installation including any
necessary tests, adjustments, commissioning and maintenance as prescribed and
all other incidental sundry components together with the necessary labour for
installing such components, for the proper operation of the installation.
B Statutory Obligations and Other Regulations
1 The Air-Conditioning and Control System installation shall comply with the
followings:-
1.1 Statutory Obligations
(a) Building (Ventilating System) Regulation under Buildings Ordinance (Sierra
Leone);
(b) Electricity Ordinance and other subsidiary legislation made under the
Ordinance;
(c) Fire Service (Installations and Equipment) Regulations, Fire Services
Ordinance and other subsidiary legislation made under the Ordinance;
(d) Noise Control Ordinance, and other subsidiary legislation made under the
Ordinance;
(e) Air Pollution Ordinance, and other subsidiary legislation made under the
Ordinance;
(f) Ozone Layer Protection, and other subsidiary legislation made under the
Ordinance;
(g) Environmental Impact Assessment Ordinance, and others made under the
Ordinance;
(h) Places of work Public Ordinance and other subsidiary legislation made under
the Ordinance.
1.2 Other Requirements
(a) Code of Practice for the Electricity (Wiring) Regulations published by
Electrical Distribution and Services Authority (EDSA) and Mechanical
Services Department, Ministry of Works, Government of Sierra Leone;
(b) Code of Practice for Energy Efficiency of Electrical Services Installations and
Air Conditioning Services Installations issued by Electrical & Mechanical
Services Department, Government of Sierra Leone;
40
C Execution of Works:
1 International System of Units (SI)
The International System of Units (System International Unites) of weights and
measures shall be used for all materials, equipment and measurements.
2 Programme of Works
The Contractor shall submit to the Project Architect a detailed programme of the
Works within 7days from the acceptance of his tender showing the intended
method, stages and order of work execution in coordination with the building
construction programme, together with the duration he estimated for each and
every stage of the Works. The programme shall include at least the following:-
(a) Dates for the placement of orders for equipment and materials;
(b) Expected completion dates for builder’s work requirements, i.e. when work
site needs to be ready;
(c) Delivery dates of equipment and materials to Site;
(d) Dates of commencement and completion of every stage of the Works in line
with the building construction programme, i.e. each floor level and/or zone
area;
(e) Dates of documents/drawings submissions to Project Architect to obtain the
necessary approvals;
(f) Dates of requirement of temporary facilities necessary for testing &
commissioning, e.g. electricity supply and town gas;
(g) Dates of completion, testing and commissioning; and
(h) Short term programme showing the detailed work schedules of coming weeks
and months shall also be provided to the Project Architect. Programme shall
be regularly updated to reflect the actual progress and to meet the
Contractors’ obligations under the Contract.
In addition, detailed submission schedules for installation drawings, equipment
and testing and commissioning shall be submitted to the Architect for approval.
The formats and information to be included in the schedules shall be as required
by the Project Architect.
3 Builder’s Work
All builder’s work including openings or holes through building structure or
partition walls; trenches, ducts and cutting; and all plinths, concrete bases,
supports, ducts, etc. required for the installation will be carried out as part of the
building works by the building contractor at the expense of the Employer provided
that the Contractor has submitted full details of such requirements within a
reasonable time to the Project Architect for approval, so that due consideration
may be given before the building contractor commences the building works in
accordance with the building programme in the areas concerned. After obtaining
the said approval of the Project Architect, the Contractor is required to mark out at
the relevant locations of the Site the exact positions and sizes of all such works
and to provide detailed information of such works to the building contractor to
facilitate him to carry out the builder’s works as the works proceed.
All "cutting-away" and "making-good" as required to facilitate the Contractor’s
works will be carried out by the building contractor, except for minor provisions
required for the fixing of screws, raw plugs, redhead bolts, etc. which shall be
41
carried out by the Contractor. The Contractor shall mark out on Site and/or supply
drawings of all "cutting-away" to the building contractor within a reasonable time.
All expenses properly incurred and losses suffered by the Employer as a result of
the Contractor’s failure to comply with the above requirements are recoverable by
the Employer from the Contractor.
The Contractor shall ensure that such works are essential for the execution of the
Works. In the event that any of such works is proved to be non-essential,
unnecessary and/or abortive, the Contractor shall bear the full cost of such works
including but not limited to any unnecessary or incorrect cutting-away and
making-good and shall reimburse the Employer for all cost incurred in this
connection.
Upon completion of the builder’s works by the building contractor, the Contractor
shall forthwith check and examine that all builder’s works so executed have been
completed in accordance with his requirements. If at any time it becomes apparent
to the Contractor that any builder’s works completed by the building contractor
does not comply with his requirements in any respect whatsoever, the Contractor
shall forthwith give notice in writing to the Project Architect and specify in details
the extents and effects of such non-compliance in that notice. The Contractor is
deemed to have satisfied with the builder’s works after a period of 7 days from the
date of completion of the builder’s works if the above notice is not served to the
Project Architect within such period. All additional expenditure properly incurred
and all loss suffered in this connection by the Employer in having such works re-
executed and rectified shall be recoverable by the Employer from the Contractor.
4 Protection of Materials and Equipment
Unless the responsibility is clearly defined in the Contract that the protection on
Site for delivered equipment, materials and installation is solely by other
contractors, the Contractor shall be responsible for the safe custody of all
materials and equipment as stored or installed by him until finally inspected,
tested and accepted. In addition, the Contractor shall protect all work against theft,
fire, damage or inclement weather and carefully store all materials and equipment
received on Site but not yet installed in a safe and secure place unless otherwise
specified.
All cases of theft and fire must immediately be reported to the police, the building
contractor, the Project Architect and the representatives on Site with full details.
Where necessary the Contractor shall provide lockable steel container or other
equally secure enclosures placed within a securely fenced-in compound provided
by the Building Contractor on Site for the storage of materials and equipment.
The Contractor shall co-ordinate and arrange with the Building Contractor who
shall provide clean, reasonably finished and lockable secure accommodation for
the storage of sensitive and/or expensive items before installation.
If there is no Building Contractor, all the storage facilities and spaces shall be
provided by the Contractor.
42
5 SERVICE CONDITION
The following service conditions shall apply to materials and equipment’s:
Building Location
Freetown, Sierra Leone
08o30’N, 13o14’W, Altitude 11m
Design Criteria
1. External Environmental Conditions
High temperatures, high humidity, saline atmosphere, presence of airborne
dust particles during Harmattan, periods of high precipitation
2. External Ambient Design Conditions
33o C db. 27oC wb. Average max/min daytime temperatures 30oC.db /
24oC.wb (Diurnal Range 6oC)
References: CIGSE Design Guide
BBC Weather Data, based on readings at location for 14 years
3. Internal Environmental Design Conditions
Refer Schedules 1-3 for internal temperatures, occupancy levels and fresh air
requirements.
4. Internal Noise Criteria
5. IEE Wiring Regulations
6. CIBSE Commissioning Codes
6 VOLTAGE COVERED BY THIS SPECIFICATION
Unless otherwise specified, all apparatus, equipment, materials and wiring shall be
suitable for use with a 3-phase and neutral, 4-wire, 400/230 V ±6%, 50 Hz ±2%.
7 HVAC System for use in Hash Environments:
Remove and replace all the existing Single Split Wall Mounted HVAC Systems to
an efficiency and energy-savings at lower costs with the Inverter technology in
HVAC Systems.
This will greatly reduce the energy requirements to run the HVAC units and save
diesel cost when the system is used when the Generator Set is use.
a) Inverter Air Conditioning
The inverter air conditioning is the latest technology in the HVAC field that is
becoming more popular due to its environmental friendly and energy savings
approach. Providing comfort to the users is another big advantage of this kind
of system.
Traditionally, the compressor that is used in an air conditioning system is an
ON or OFF type in that it either works at the maximum capacity or none at all.
It ON when the room thermostat calls for cooling and OFF when the desired
temperature has been achieved. This cycle is repeated with the change of load
in the room.
The advancement in power electronics has enabled the inverter technology to
thrive by the use of microcontroller and IGBT modules to drive the
43
compressor DC or AC motor. The speed of the compressor motor can be
varied by using the variable frequency drive.
These is done by converting the incoming AC supply to DC voltage and then
modulate it by changing the voltage, current and frequency of the power to the
compressor. Changing the frequency changes the speed of the compressor by
using a more complicated electronics control circuitry.
b) Advantages of using Inverter Technology
Keeping abreast with the latest technology has more advantages than
remaining status quo. Here are some of the reasons why you should consider
buying an inverter air conditioning system.
• Energy Savings is one of the most important factors to consider when
buying equipment. In the long run, the benefit outweighs the initial cost.
The inverter technology uses less energy compared to the traditional
system.
ON/OFF type of compressor has large starting current, sometimes 6 times
more than the running current. This causes flicker to lights and the energy
consumed is greater. Typically, there is a 20% to 30% savings in power
consumption.
• Comfort to the users is another advantage of this system. During start-up,
the compressor can run full speed to provide quick cooling to the room.
After the desired room temperature has been achieved, the speed of the
compressor is regulated using the variable frequency drive based on the
required cooling load of the room.
The fluctuation of temperature is minimum compared to the ON/OFF type
of compressor. This provides a comfortable environment for the occupants
at all times.
• Ozone Friendly refrigerant such as R410a is used in most inverter system.
This refrigerant contains only HFC compared to R22 which contains
HCFC, an additional chlorine component that destroys the ozone layer of
the earth.
Always enquire the kind of refrigerant which is in used as some installers
prefer to continue using R22 as it is cheaper compared to R410a and hence
lower their cost.
• Quiet Operation is another feature that inverter technology offers. The
outdoor unit which contains the inverter compressor is much quieter
compared to the non-inverter compressor. Hence, you do not have to
worry about noise when you sleep.
• Cost Saving: Highly efficient, energy saving, and cost saving operation is
realized with HVAC inverter and heat pump technologies.
• Durability: Anti-corrosion treatment is provided for installation in harsh
environmental conditions.
44
• Custom-built Installation: Custom-built installation and flexibility in
power supply provide solutions to precisely meet customer requirements
• High Reliability: The addition of various advanced features ensures
reliable and stable system operation.
45
Temperature Control by Inverter/Non-Inverter Compressors (Cooling)
G SCHEDULE OF PROPOSED CONFORT COOLING INVERTER SINGLE
SPLIT WALL MOUNTED AIR-CONDITIONING UNITS TO BE INSTALL
ON THE THIRD FLOOR ADB COUNTRY OFFICE FOR FREETOWN,
SIERRA LEONE
No Room Schedule Qty. Type of Unit Cooling
Capacity
Total
Cooling
Third Floor
1 Server Room 1 Wall Mounted 1 x 9,000BTU 9,000BTU
2 Main Entrance Reception 1 Wall Mounted 1 x 12,000BTU 9,000BTU
3 Office 1 Wall Mounted 1 x 12,000BTU 12,000BTU
4 Office 1 Wall Mounted 1 x 18,000BTU 18,000BTU
5 Conference Hall 4 Wall Mounted 4 x 18,000BTU 72,000BTU
6 Office 1 Wall Mounted 1 x 18,000BTU 18,000BTU
7 Lobby Area) 1 Wall Mounted 1 x 12,000BTU 12,000BTU
8 Store 1 Wall Mounted 1 x 9,000BTU 9,000BTU
9 Canteen 1 Wall Mounted 1 x 24,000 BTU 24,000BTU
46
TECHNICAL SPECIFICATION FOR THE
SUPPLY AND INSTALLATION OF A 20KVA,
3-PHASE 400V~, 50HZ, HIGH FREQUENCY
ONLINE UPS WITH INTERNAL
MAINTENANCE BYPASS & PARALLEL
CAPABILITY
47
PRODUCT OVERVIEW:
20KVA, 3-PHASE 400V~, 50HZ, HIGH FREQUENCY ONLINE UPS
Key Features:
▪ Run time for load 16000W
▪ Max. Capacity Used 100%
▪ Output power capacity 16.0kWatts / 20.0kVA
▪ Nominal Output Voltage 230V, 400V 3PH
▪ Nominal Input Voltage 400V 3PH
▪ Input Connections Hard Wire 5-wire (3PH + N + G)
▪ Maximum Input Current 27.0A
20kVA 400V, with Internal Maintenance Bypass & Parallel Capability
Effective 20kVA, 3 Phase UPS power protection against downtime and data loss for mission
critical applications
Includes:-Bolt Down Brackets, CD with software, Installation Guide, Power modules ship
installed, User Manual, and Web/SNMP Management Card
• Parallel-capacity capable: Increases total power capacity by using multiple
uninterruptible power supplies
simultaneously.
• Parallel-redundant capable: Power the connected equipment with multiple
uninterruptible power supplies to
increase system redundancy
FEATURES & BENEFITS:
Marketing features
Hot-swappable batteries Ensures clean, uninterrupted power to protected equipment while
batteries are being replaced
Manageability
Network manageable: Provides remote power management of the UPS over
the network.
LED status indicators: Quickly understand unit and power status with visual
indicators.
SmartSlot: Customize UPS capabilities with management cards.
Programmable frequency: Ensures compatibility with different input frequencies
LCD display: Alpha-Numeric Display which displays system
parameters and alarms.
InfraStruXure Manager Compatible: Enables centralized management via the APC
InfraStruXure Manager.
48
Audible alarms Provides notification of changing utility power and UPS
power conditions
PROTECTION:
Cold-start capable: Provides temporary battery power when the utility
power is out.
Safety-agency approved: Ensures the product has been tested and approved to
work safely with the connected service provider
equipment and within the specified environment.
Frequency and voltage regulation: Gives higher application availability by correcting poor
frequency and voltage conditions without using the
battery.
TOTAL COST OF OWNERSHIP:
Manual maintenance bypass: Reduces installation costs by eliminating the
need for an external mechanical bypass.
Temperature-compensated battery charging: Prolongs battery life by regulating the charge
voltage according to battery temperature.
Input Power Factor Correction: Minimizes installation costs by enabling the
use of smaller generators and cabling.
Intelligent battery management: Maximizes battery performance, life, and
reliability through intelligent, precision
charging.
SUSTAINABILITY:
EU CoC for UPS: Ensures that UPSs sold in the EU are highly efficient
AVAILABILITY:
Automatic internal bypass: Supplies utility power to the connected loads in the
event of a UPS power overload or fault.
Scalable runtime: Allows additional run time to be quickly added as
needed.
Generator compatible: Ensures clean, uninterrupted power to protected
equipment when generator power is used.
Dual mains input: Increases availability by allowing the UPS to be
connected to two separate power sources.
Battery modules connected in parallel Delivers higher availability through redundant
batteries.
SERVICEABILITY:
Shippable with modules installed: Enables pre-installation UPS staging and testing and
faster installation.
Automatic self-test: Periodic batteries self-test ensures early detection of a
battery that needs to be replaced.
Battery replacement without tools: Enables fast battery replacement, lowering Mean Time
to Repair (MTTR).
Modular design: Provides scalability, N+1 redundancy, fast
serviceability, and reduced maintenance requirements
via self-diagnosing, hot-swappable, and field-
replaceable modules.
49
TECHNICAL SPECIFICATIONS:
Output
Max Configurable Power (Watts): 16.0kWatts /20.0kVA
Neutral Output Current: 50A
Output Voltage Note: Configurable for 380, 400 or 415 V 3 Phase nominal
output voltage
Output Voltage Distortion: Less than 5% at full load
Output Frequency (sync to mains): 47 - 53 Hz for 50 Hz nominal
Output Frequency (not synced): 50Hz +/- 0.1% for 50Hz nominal
Other Output Voltages: 380, 415
Load Crest Factor: Unlimited
Topology: Double Conversion Online
Waveform type: Sine wave
Overload Operation: 10 minutes @ 125% and 60 seconds @ 150%
Maximum Output Current: 32
Output Voltage THD: < 2% for 0 to 100% linear load and < 5% for full non
linear load
Output Voltage Tolerance: +/-1% static and +/- 5% at 100% load step
Bypass: Built-in Maintenance Bypass, Built-in Static Bypass
Input
Input frequency: 47 - 70 Hz (auto sensing)
Input voltage range for main operations: 304 - 477V
Input Total Harmonic Distortion: Less than 5% for full load
Type of Input Protection Required: 3-pole breaker
Other Input Voltages: 380, 415
Maximum Short Circuit Withstand (Icw): 30.0kAmps
Input Power Factor at Full Load: 0.98
BATTERIES & RUNTIME:
Battery type: No internal battery - uses external battery system
Replacement Battery: SYBT4
Efficiency: View Efficiency Graph
COMMUNICATIONS & MANAGEMENT:
Interface Port(s): DB-9 RS-232, SmartSlot, SUVTPCOM
Control panel: Multi-function LCD status and control console
Audible Alarm: Audible and visible alarms prioritized by severity
Emergency Power Off (EPO): Yes
PHYSICAL:
Maximum Height: 823MM, 82.3CM
Maximum Width: 352MM, 35.2CM
Maximum Depth: 838MM, 83.8CM
Net Weight: 134.0KG
Shipping weight: 173.0KG
Shipping Height: 1290MM, 129.0CM
Shipping Width: 720MM, 72.0CM
Shipping Depth: 1110MM, 111.0CM
Color: Black
Units per Pallet: 1.0
50
ENVIRONMENTAL:
Operating Temperature: 0 - 40 °C
Operating Relative Humidity: 0 - 95 %
Operating Elevation: 0-999.9meters
Storage Temperature: -35 - 60 °C
Storage Relative Humidity: 0 - 95 %
Storage Elevation: 0-15000meters
Audible noise at 1 meter from surface of unit: 54.0dBA
Online thermal dissipation: 3112.0BTU/hr.
Protection Class: IP 20
CONFORMANCE:
Approvals: C-tick, EN 50091-2, EN/IEC 62040-3, IEC 61000-3-2, IEC 61000-3-3,
ISO 14001, ISO 9001, VFI-SS-112
Standard warranty: 1 year on-site repair or replace with factory authorized Start-UP
GENERAL:
Bypass Connection: 5 wire (3PH + N + G)
DOCUMENTATION:
Manuals and Warranties
51
SYSTEM WIRING DIAGRAM
52
ACCESSORIES MUST BE INCLUDED
UPS Communications Cable Smart Signaling UPS VT Battery Temperature Sensor for
External Battery Cabinet
UPS Cables that provide dedicated connections Accessory solutions to tailor the UPS to
meet your
between UPSs and servers desktops, workstations, specific needs
UPS Communications Cable Smart Signaling UPS VT Parallel
Communication Kit
6'/2m - DB9 to RJ45 Accessory solutions to tailor the
Smart-UPS to meet your UPS Cables that provide dedicated connections specific
needs
between UPSs and desktops, workstations, and
servers
UPS Communications Cable Smart Signaling 15' / 4.5m UPS Signaling Offer for IBM
AS/400 and IBMi (IBM Power
UPS Cables that provide dedicated connections between Systems)
UPSs and desktops, workstations, and servers UPS Cables that provide dedicated
connections between UPSs and
desktops, workstations, and servers
53
DOCUMENTATION:
Manuals and Warranties
Operation manual containing information on operation, maintenance and troubleshooting for
the user of the UPS system
DESIGN/CONFIGURATION: Providing information on technical data, facility planning, drawings, and options
AGENCY APPROVALS:
Certificate of Origin UPS 3-Phase, 20 kVA, 400 V, 50 Hz (Sheet)
DRAWINGS:
Smart-UPS VT Parallel, With Battery, System Wiring Diagrams
54
PRELIMINARIES
55
PRELIMINARIES AMOUNT (US $)
PRELIMINARIES
A POSITION OF THE WORKS
The position of the works on the site will be on the 3rd Floor of
Bishop Building at Lamina Sankoh Street, Freetown and as
indicated in the Contract Document, and as shown on the drawings.
The contractor’s operative including those of all Sub-Contractors are
limited to the use of only those areas of the site, which is essential,
they should use or enter for the execution of the works or for access.
Entry to all other areas shall be prohibited. Plants, temporary
buildings, spoil heaps etc., shall be placed only in areas or position
previously agreed with the Consultants and the African
Development Bank.
B EXISTING SERVICES
The services that may exist on or over the site and within the
building include electricity cable lines, telephone distribution
lines and water supply pipes
C SITE VISIT
The tenderer is strongly recommended to visit the site and
ascertain for himself site accessibility, the nature of the
ground, the circumstances under which the works will be executed and all local conditions and restrictions likely to affect the execution of the works. No claims on the grounds
of want of knowledge will be entertained. The site may be visited at any time during normal working hours
D DRAWINGS The drawings used in the preparation of these Bills of
Quantities are numbered:
C/F
56
PRELIMINARIES
AMOUNT (US $)
B/F
A MEASUREMENT These Bills of Quantities have been prepared in accordance
with the PRINCIPLES of the Standard Method of Measurement
of Building Works, Seventh Edition, (Metric), simplified to accord local practice. All items have been measured and billed in metric in accordance with clause 3 of the General
Rules of the Standard Method of Measurement of Building Works (7th Edition) .
B EXECUTION The works throughout shall be executed to drawings prepared
by and under the direction of the Consultant. Figured
dimensions should always be preferred to scale dimensions. Otherwise working and detailed drawings are to be taken in
preference to small-scale plans. Where there is a case of doubt or dispute the Consultant’s decision will be binding and failure to comply with the foregoing will not form the basis of
any claim.
GENERAL MATTERS
C AVAILABILITY OF MATERIALS The contractor shall make full enquires to satisfy himself that
all materials; in particular cement, sand, coarse aggregates, and water which are described in these Bills of Quantities and to which his prices relate will be available in sufficient
quantities to enable him to complete the whole of the works in contract time and no claim will be entertained on the grounds of non- availability of materials and that the
contractor had to resort to alternative sources of supply for materials specified.
D AVAILABILITY OF LABOUR
The Contractor will be held to have made all enquires to the sources of his labour and to have made all provisions in his tender for every cost to him of providing and maintaining the
labour force necessary to complete the contract including all supervisory costs associated therewith. No claims will be entertained on grounds associated with the failure by the
Contractor to observe these recommendations.
57
C/F
PRELIMINARIES AMOUNT (US $)
B/F A DUTY –FREE CONCESSION
The Contractor will not be exempted from the payment of customs duties and other such Government levies normally imposed on imports on any equipment, plant Vehicles and
materials, which he may wish to import for the execution of contract.
B INSURANCE A provisional sum is included in the main summary to cover
the following for which the Contractor will be required to take out polices.
(a) For insuring against all risk of personal injury to or death of any person whomsoever the contractor is responsible
(b) For insuring against all risk of injury or damage to existing property and new works.
(c) For maintaining in the joint names of the employer and the contractor insurance in respect of all risk of injury or damage to property other than the works as
defined in the conditions of contract. (d) For insuring in the joint names of the employer and
the
contractor against loss and damage by fire etc. as defined
in the conditions of contract
The limit of third-party risks shall not be less than Twenty thousand US Dollars (US$ 20,000.00) in respect of any one incident
Notwithstanding the minimum cover specified before the
Contractor shall indemnify the employer against all third-party
claims.
The contractor’s attention is drawn to the advisability of ensuring that the provisions of his insurance policy are adequate to cover the actual cost of replacement or repair at
any time during the currency of the contractual commitment.
58
C/F
PRELIMINARIES AMOUNT (US $)
B/F
CONTRACTOR’S LIABILITY A DAMAGE AND THEFT
The Contractor will be solely responsible for safeguarding the works, materials and plant against damage and theft and he
is advised to effect such additional insurance as is necessary to adequately cover such risks.
OBLIGATIONS AND RESTRICTIONS IMPOSED BY THE EMPLOYER
MATERIALS B The whole of the materials (except where otherwise
described) goods and equipment required for the full
performance of the contract by the Contractor must be provided through normal trade channels and shall include for the payment of all necessary bank charges, opening letters of
credit, postage, cables, telex, e-mails port charges, handling charges, agents fees and other similar charges, and delivery to site.
The contractor shall keep on the site a storekeeper who shall
keep records of all materials brought on to the site and taken
from the site, which documents shall be made available for inspection by the Consultants.
On the date of the signing of the contract the Contractor is to
make a review of the materials he will require for the
execution of the works and he is to place orders for such materials without delay in order that materials are delivered to the site, as they are required. All materials which can be
stored on site with the approval of the Consultant without deterioration or damage are to be purchased and stored as soon as possible.
C WORKING SPACE
Provide for taking all precautions to prevent workmen including those employed by sub-contractors from trespassing on adjoining owner’s property and any parts of the premises
not affected by the works.
59
Provide also for taking reasonable precaution to keep all unauthorized persons off the site.
C/F
PRELIMINARIES AMOUNT (US $)
B/F A WORKING HOURS
Working hours are limited to the normal working hours of the building industry. Overtime shall not be worked by operatives
on the site without the prior express permission in writing from the Consultant.
B MATERIALS FOUND ON SITE Any materials other than earth filling which are discovered
upon the site during the course of legitimate excavation or demolition work and the like and which are suitable for incorporation in the permanent work may only be used for
permanent work with the prior written consent of the Consultant. The quality and value of any such materials authorized to be used in the permanent works will be
assessed by the Quantity Surveyor and the total value thereof deducted from the contract sum. The contractor is expressly prohibited from executing any excavation work and the like
for the sole purpose of obtaining building materials.
C NOTICE BOARD AND ADVERTISING
The contractor shall erect or display a notice of advertising in
an approved manner and position a single board of an approximate size (1200 x 2400mm) high overall containing the name, address and description of the project, Employer,
Consultants, Contractor, Donor and authorized sub – contractors. Allow here for providing the same
D MAINTENANCE OF PUBLIC AND PRIVATE SERVICES Establish the position of, protect, uphold and maintain all
pipes, ducts, sewers, service mains, overhead cables, etc. during the execution of the works. The contractor shall make good any damage due to any cause within his control at his
own expense or pay all costs and charges in connection therewith, Where it is necessary to interrupt any such mains or services, permission shall be obtained from the Consultant
and, where appropriate, from the local authority or public undertaking and the duration of any interruption kept to a
60
minimum
C/F
PRELIMINARIES AMOUNT (US $)
B/F A PROGRAMME
The contractor upon acceptance of his offer shall proceed immediately with the preparation of a programme or statement, which shall clearly set forth the sequence of all operations and the
time limit within which it is proposed that each operation shall be commenced and completed. The Contractor shall be held to have coordinated the whole of the works embraced in this contract
including the work of nominated sub-contractors, local authorities and public undertaking whether engaged by him or engaged directly by the Employer.
The consultant will supply the contractor with adequate details of
all works to be carried out by others directly engaged by the
employer where such work is to be integrated with the work under his contract. Upon the agreement or negotiated amendment of the programme by the consultant the contractor shall be responsible for
executing the works in conformity therewith
Six reproducible copies of the agreed programme are to be supplied
to the consultants within seven days of agreement being reached. At the same time the contractor shall issue to the consultant a statement setting out the latest dates by which drawings and other
instructions are required by him for the implementation of the agreed programme.
Allow here also for updating the programme on a weekly basis to reflect the actual progress achieved on site
B PROGRESS PHOTOGRAPHS Allow for providing monthly two sets of progress photographs of
postcard size, as directed by the Consultant to a minimum of four
shots per set of the works to clearly indicate the progress of the work.
Allow also for providing the client with 2 Nr approved photographic albums of the self- adhesive type each approximately 250mm x 300mm with hard wearing covers and at least 18 Nr pages each
covered with a transparent film
C SAMPLES
Allow here for submitting samples of all materials and for executing small specimen of works as directed by the Consultants
61
C/F
PRELIMINARIES
AMOUNT (US $)
B/F
A TESTING MATERIALS The Contractor will be required to carry out test of materials
on site and to prepare, pack and dispatch materials and
goods to a nominated testing laboratory in connection therewith (including the making of concrete test cubes). The Contractor’s attention is drawn particularly to the
requirements in the concrete work section of the specifications.
B CERTIFICATE VALUATION
The contractor will be required to submit a detailed approximately priced statement of work executed and materials supplied in support for each application for interim
payment. He shall, at the same time, provide any necessary applications for payments from nominated sub-contractors.
C INFORMATION FOR CLERK OF WORKS Allow here for furnishing to the clerk of works such
information as he shall require in connection with the works including a statement showing the number of men employed in all trades daily and delivery notes for all materials received
on the site
D. TEMPORARY ACCOMODATION AND FACILILTIES FOR
EMPLOYER
Provide and maintain a secure weatherproof office for the
clerk of works with floor area not less than 20m2 and no part of the ceiling less than 2250mm high. Provide desk or tables with lockable drawers, sufficient plan bench, and chairs
lockable equipment cupboard. Provide artificial lighting, attendance and cleaning.
Provide and maintain separate temporary toilet accommodation for the use of the clerk of works and other Employer’s representatives and maintain in a clean and
odour free condition. Such accommodation shall be flushing
62
type and be temporarily connected to a suitable septic tank. Provide washbasin with water supply together with an
adequate supply of soap, toilet roll and clean towels.
C/F
PRELIMINARIES
AMOUNT (US $)
B/F A TEMPORARY ACCOMMODATION AND FACILITIES
FOR EMPLOYER (CONTD.)
Alter, shift and adapt the foregoing temporary buildings
from time to time as may be necessary and finally clear away and make good all surfaces, services, disturbed etc
B TEMPORARY TELEPHONE FOR EMPLOYER Allow here for the installation in the office of Clerk of works
of a separate telephone or mobile cell phone for the use of the Employer and the cost of telephone calls made on his behalf
C SITE MEETINGS
Allow here for all expenses in accommodating and attending regular progress site meetings under the chairmanship and
direction of the Consultant.
D WORKS BY NOMINATED SUB-CONTRACTORS
The word “attendance” or “attend upon” where used
throughout these Bills of Quantities in connection with
nominated sub –contractors shall mean:
1. General attendance on nominated sub-contractors as
defined in Clause A51 (3) of the standard method of measurement of building works.
2. Providing free use of erected hoisting facilities, scaffolding, etc.
3. Providing free use of electric power.
63
C/F
PRELIMINARIES
AMOUNT (US $)
B/F A WORKS BY NOMINATED SUB-CONTRACTORS
(CONTD.)
Special attendance on nominated sub-contractors where required have been described in the relevant sections of
these Bills of Quantities.
Builder’s work in connection therewith has been measured
separately unless otherwise stated, but the Contractor must obtain particulars of the position in which chases, holes, mortices, etc. will be required so as to avoid unnecessary
cutting away. No claim will be considered for the extra cost of cutting away work already built as a result of the contractor’s neglecting to obtain sufficient particulars before
hand
B
GOODS AND MATERIALS FROM NOMINATED SUPPLIERS
The words “fix” or “ fixing” or” fix only” where used
throughout these Bills of Quantities in connection with goods and materials to be obtained from nominated suppliers or supplied by the Employer shall mean fixing goods and
materials as defined in Clause A 52 of the Standard method of Measurement of Building works
C SECURITY FOR DUE PERFORMANCE The Contractor shall enter into a written contract and shall
together with his sureties execute a performance bond payable on demand and equal to 10% of the Contract Sum. The sureties shall be a reputable financial institution such as
a bank, an insurance company or finance company acceptable to the Employer.
The Employer may release up to 75% of the performance bond after practical completion of the works and the remaining 25% at the end of the defects liability period or
the satisfactory making good of defects whichever is the
64
latest.
D PLANT, TOOLS AND VEHICLES Provide all necessary plant, tools and vehicles for the proper
execution and completion of the whole of the works
C/F
PRELIMINARIES
AMOUNT (US$)
B/F
A SCAFFOLIDING Provide all necessary temporary scaffolding for the proper
execution of the works, Alter and adapt as necessary and
clear away on completion.
B SITE ASMINISTRATION AND SECURITY
Provide for all site administration costs including cost for
general foreman in charge.
Safeguard the works, materials, plant etc against damage or
theft including providing all necessary watching and lighting.
C TRANSPORT FOR WORK PEOPLE
Provide for all costs in respect of all necessary transport for work people.
D PROTECTING THE WORK FROM INCLEMENT WEATHER
Provide for carefully covering up and protecting the works
including those by nominated sub-contractors or any adjoining property exposed by these works from inclement weather.
The Contractor should note particularly that no concrete
work, or other work liable to become damaged by rain, may
be carried out during rainy weather except with the express permission of the consultant and that all such work must be covered up at night and adequately protected from rain.
The Contractor shall avail himself of all reasonable means
and aids to building in inclement weather, which are
65
currently available and use his best endeavours to prevent or to minimize delays, which might result from bad weather.
The Consultant will not grant an extension of time for delays, which have been incurred through failure to comply with these recommendations.
C/F
PRELIMINARIES
AMOUNT (US$)
B/F A
WATER FOR THE WORKS
Provide clean fresh water for use on the works, pay all charges in connection therewith, provide all temporary
storage, plumbing services, connections, etc. and clear away and make good works disturbed on completion
B LIGHTING AND POWER FOR THE WORKS
Provide all necessary temporary electric and power for the works including all necessary flood lighting where work after dark is involved including that required by nominated sub-
contractors and pay all fees and charges. Where electricity is available adjacent to the site the Contractor must allow here
or in his prices for a metered connection and pay all fees and charges in connection therewith and for current consumed.
TEMPORARY ROADS, HARDSTANDING, CROSSING ETC.
C Provide and maintain in good condition all necessary
temporary roads, hard standing, crossing, etc. that may be required and clear away and make good on completion.
TEMPORARY ACCOMMODATION FOR THE USE OF THE CONTRACTOR
Provide and maintain temporary office accommodation for
the Contractor’s staff and watertight sheds for the storage and protection of materials, tools, and tackle for the use of workmen employed upon the site and a watchman’s hut in
positions to be agreed with the Consultant.
Provide and maintain in a clean and odour free condition
66
where directed temporary toilet accommodation for the use of all workmen. Whenever possible such accommodation
shall be of the flushing type and be temporarily connected to a suitable septic tank.
Alter, shift and adapt temporary buildings from time to time as may be necessary and finally clear away and make good all surfaces, etc disturbed.
C/F
PRELIMINARIES
AMOUNT (US $)
B/F A TEMPORARY TELEPHONES OF THE USE FOR THE
CONTRACTOR
Provide and maintain a temporary telephone or mobile cell phone service to the office of the foreman in charge and to the office of such other of the Contractor’s site staff as may
be necessary for the full period of works and pay all charges and expenses in connection therewith
B TRAFFIC REGULATIONS
Comply with all vehicular and air control traffic regulations particularly those relating to unloading and loading of
Vehicles and provide any necessary traffic control.
C SAFTEY, HEALTH AND WELFARE OF WORK
PEOPLE
Provide for costs incurred and comply with all safety, health
and welfare regulations appertaining to all work people (including those employed by any sub-contractor) employed on the site
Provide adequate First Aid equipment, which shall be
available for the use of all workmen during working hours.
D DISBURSMENT ARISING FROM THE EMPLOYMENT OF
WORK PEOPLE
Provide for all costs in respect of all work people for:
a) Workmen compensation liability b) Redundancy Pay c) Annual and public holidays
d) Traveling time, expense, fares and subsistence (see
67
item C page 10 for transport for work people) e) Non – productive time and other expenses in
connection with overtime f) Any incentive time and bonus payments g) Any other disbursements arising from employment of
work people.
C/F US$
PRELIMINARIES
AMOUNT (US $)
B/F
A MAINTENANCE OF PUBLIC AND PRIVATE ROADS
Maintain public and private roads, footpaths, kerbs etc. in
good condition and keep the approaches to the site clear of mud and dirt. The Contractor shall clear and make good any damage caused by his own or any sub-contractor s or
supplier’s transport at his own expenses and pay any costs and charges in connection therewith.
B REMOVE RUBBISH, PROTECTIVE CASINGS AND COVERING AND CLELANING THE WORK ON COMPLETION
Provide for removing all rubbish from the site to an approved dumping site both as it accumulates from time to time and at
completion.
Provide for removing all protective casings and covering and
leave the whole of the works clean to the satisfaction of the Consultant on completion and prior to handing over.
C DRYING THE WORKS Provide for adequate drying out of the works both for the
Contractor’s own work and the work of all nominated sub-contractors and allow for providing all necessary labour, appliances and fuel required therefore.
D TEMPORARY FENCING, HOARDING, SCREENS,
PLANKED FOOTWAYS GUARD RAILS, GANTRIES ETC.
Provide and maintain all necessary temporary fencing, hoarding, screens, planked footways, guard rails, gantries and the like for the proper execution of the work. Allow for
68
protection of the public and the occupants of adjoining premises and for meeting the requirements of any local or
other authority and alter, shift and adapt from time to time as necessary and finally clear away when no longer required and reinstate all surfaces, services etc disturbed.
C/F US$
PRELIMINARIES
AMOUNT (US $)
B/F
A PROTECTION OF SITE
Allow for protecting the site including the provision of temporary barrow runs, etc. and for reinstating on
completion including filling in all depressions caused by Vehicular traffic and making good where huts etc. have been removed (excluding seeding and turfing).
B
ALLOW OTHER STATUTORY OBLIGATIONS
Provide for complying with all other statutory obligation not herein-before mentioned.
C
DAYWORKS
Where work cannot properly be measured and valued the contractor shall be reimbursed on a day work basis in
accordance with the conditions of contract
The Prime Cost of such will be calculated in accordance with the “Definition of Prime Cost of Daywork carried out under a Building Contract” published by the Royal Institution of
Chartered Surveyors, December, 1975 Edition together with additions to each of the Prime cost at the rate to be inserted hereunder by the Contractor
The Contractor shall give to the Consultant reasonable notice
of the commencement of any work which he considers
should be paid for as daywork and in respect of such shall submit to the Consultant for Verification Vouchers in triplicate in the manner and at the time stated in the conditions of
contract. The basis of payment will be decided by the Quantity Surveyor
69
The daywork shall be recorded on properly laid out and
numbered Vouchers specifying the time daily spent upon the work and the materials and plants employed; the voucher shall also state the date on which the works were executed
and give a detailed description of and a reference to the instruction authorizing the work.
C/F
PRELIMINARIES
AMOUNT (US $)
B/F
A DAY WORKS (CONTD.)
The signature of the Consultant or his representative shall only confirm the scope of the work and that it has been carried out and not acceptance that the work shall be paid for as daywork, if
at all.
The Quantity Surveyor may reject any daywork sheets, if in his
opinion the work could properly be measured and valued within the terms of the contract.
Provide the sum of US$ 500.00 for labour as defined 500.00 Add for incidental costs, overheads and profit
as defined. %
Provide the sum of US$ 1,000.00 for materials
and goods as defined
1,000.00
Add for incidental costs, overheads and profit as defined %
Provide the sum of US$ 1,500.00 for plants as defined
1,500.00
Add for incidental costs, overheads and profits as defined %
TOTAL OF PRELIMINARIES CARRIED TO MAIN SUMMARY
70
OUTFITTING WORKS
71
Item No Description
Qty Unit Rate US$ Amount US$
DEMOLITION
Please refer to Clause C20 of the Standard
Method of Measurement (Seventh Edition)
(SMM7) of the Building Works to ensure
that all requirements for demolition are fully
met by the Bidder
A Carefully demolish existing glazed aluminum
partitions including doors within the thickness
of partitions and store away off-site in Client’s
approved location (Approx. 130m2)
Item
B Carefully pull-down existing ceiling tiles and
hangers and set aside in Client’s approved store
off-site (Approx. 240m2)
Item
DEMOLITION Carried
To Summary US$
72
Item No Description
Qty Unit Rate US$ Amount US$
B/F
NEW OUTFITTING WORKS
NEW PARTITIONS
A 3600mm high bronze anodized high-quality
double-glazed aluminum partitions with shatter
and sound proof tinted glass completes with
fixing accessories and fully secured doors
within thickness of partition walls in
Conference Room
63
M2
B Ditto but single glazed in offices and canteen
areas
53
M2
C 1500mm high built in Plexiglas aluminum
partition with worktop for Receptionist overall
size 1700mm long by 1200mm wide complete
with access door and window
1
Nr
D Allow for providing raised timber floor to make
room for electrical and Data cables in
conference room using well-seasoned and
treated timber well polished with ronseal polish
(Provisional)
32
M2
E Allow for making good floor tiles where
partitions have been removed (Approx. 3m2)
Item
NEW CEILINGS
F Provide and fix 600 x 600 x 12mm thick
acoustic ceiling tiles under concrete slab
complete with aluminum hangers and all
necessary support and fixing accessories
240
M2
NEW PARTITIONS AND CEILING Carried
To Summary US$
73
Item No Description
Qty Unit Rate US$ Amount US$
ROOF REPAIRS
A Carefully remove all cracked concrete to
underside of roof slab, prepare surface and
apply cement mortar (1:3) to conceal
reinforcement in roof slab (Approx. 40m2)
Item
B Provide and fix steel Acro props to underside of
roof slabs as medium-term support to structure
24
Nr
C 50 x 150mm treated sawn hardwood fixed to
underside of slab on top of Acro props
36
M
ROOF REPAIRS Carried
To Summary US$
74
Item
No
Description
Qty Unit Rate
US$
Amount US$
ELECTRICAL INSTALLATION
DEMOLITION
A Remove all existing electrical fixtures on the third-
floor complete including cabling, lights and
switches, socket fixtures and old Electrical
switchgears and put aside as directed by the Bank
Item
ELECTRICAL INSTALLATION (FIRST FIX)
Supply and install electrical ‘’first fix’’ for the
following generally in concealed plastic conduits
and 3-Compartments Dado Trunkings (Small Power
Requirements and Voice/Data Outlets), fittings,
including chasing, building in conduits and
trunkings and floor, through walls and ceiling with
circular boxes plugged for fixing and fitting MK
boxes
Light Points:
B Ceiling Mounted Light Points 40 Nr.
C Emergency Exit Light Points 4 Nr.
D 10Amp Light Switch Point 15 Nr.
E Circular Boxes 40 Nr.
ITC Network Installation
F Voice/Data Socket Outlet Point 50 Nr
G CCTV Camera Point 3 Nr
H Television/Satellite Socket Outlet Point 4 Nr
IP Addressable Fire Alarm System Points:
J Smoke/Heat Detector Point
12 Nr
K Break Glass Point 7 Nr
L Electronic Sounder Point 2 Nr
M 5-Zone IP Addressable Fire Alarm System Control
and Monitoring Panel
1
Nr
C/F US$
75
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
Switched Socket Outlet Point:
A 13A, Double Socket Outlet (Raw Power) 80 Nr
B 13A, Double Socket Outlet (UPS Power) 80 Nr
C
13A, Single Socket Outlet 6
Nr
D 20A Hand Dryer Outlet 3 Nr.
E 30A, A/C Switch 12 Nr.
F 45A Cooker Outlet 2 Nr
Switchgear Point:
G 125A, 8-way TP&N MCB Distribution Board (DB-
Raw Power)
2
Nr.
H 125A, 8-way TP&N MCB Distribution Board (DB-
UPS Power)
1
Nr.
2 ELECTRICAL WIRING (SECOND FIX)
Supply and erect 1.5mm2 3-core pvc insulated cable
and pvc sheathed cables in concealed 20mm
diameter pvc conduit and circular boxes in circuit
wiring from Distribution Board, to Light Switch to
Light Point:
J Ceiling Lights Points 40 Nr
K Emergency Exit Light Points 4 Nr
Supply and erect 4.0mm2 3-core pvc insulated cable
and pvc sheathed cables in concealed 20mm
diameter pvc conduit in radial circuit wiring from
raw power socket outlets (3 sockets per circuit) to
Raw Power Distribution Boards
L 13Amp Double Socket (Raw Power)
80 Nr
M 13Amps Single Socket (Raw Power) 6 Nr
C/F US$
76
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
ELECTRICAL WIRING (SECOND FIX)
CONT.:
Supply and erect 4.0mm2 3-core pvc insulated cable
and pvc sheathed cables in concealed 20mm
diameter pvc conduit in radial circuit wiring from
UPS power socket outlets (3 sockets per circuit) to
the TP&N LV UPS Power Distribution Boards
A 13Amp Double Socket (UPS Power) 80 Nr
Supply and erect 4.0mm2 3-core pvc insulated cable
and pvc sheathed cables in concealed 20mm
diameter pvc conduit in radial circuit wiring from
A/C Units Switch to the Raw Power TP&N LV
Distribution Board:
B 30Amps A/C Switch Point 12 Nr
Supply and erect 6.0mm2 3-core pvc insulated cable
and pvc sheathed cables in concealed 20mm
diameter pvc conduit in radial circuit wiring from
Cooker Outlet Point to Distribution Board:
C
45Amps Cooker Outlet Point 2
Nr
Supply and erect 4-core 35mm2 XLPE/PVC/SWA
armoured cable in concealed 50mm diameter pvc
pipe in radial circuit wiring complete with cable
glands and accessories from existing 200A TP&N
LV Busbar located on the Basement Floor in the
Main Electrical Switchroom to 3 x 125A, 8-way
TP&N LV Raw Power Distribution Boards located
on the third floor as shown on the drawing.
D 3 x 125A, 8-way TP&N LV MCB Distribution
Boards-Rea Power Supply
30
Nr.
Supply and erect 4-core 25mm2 XLPE/PVC/SWA
armoured cable in concealed 50mm diameter pvc
pipe in radial circuit wiring complete with cable
glands and accessories from New 20KVA UPS
located in the UPS Room on the Fifth Floor to 1 x
125A, 8-way TP&N LV UPS Power Distribution
Boards located in the Server Switchroom on the
third floor as shown on the drawing,.
E 3 x 125Amps 8-way TP&N LV MCB Distribution
Board-UPS Power Supply
45
Nr
C/F US$
77
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
3 FITTINGS AND ACCESSORIES (THIRD
FIX)
3-COMPARTMENTS DADO TRUNKING
Supply and install 3-Compartments Dado
Trunking complete with fittings and accessories
for Small Power Requirements, Voice & Data
Outlets
A 3 Metre Lengths, Three Compartments PVC Dado
Trunking
30
Length
B 3 Compartment Dado Flat Angle 10 Nr
C 3 Compartment Dado Flat Tee 12 Nr
D 3 Compartment Dado External Angle 15 Nr
E
3 Compartment Dado End Cover 15
Nr
10Amp Light Switches:
F 1 gang 1-way switch – Legrand 8 Nr.
G 1 gang 2-way switch - Legrand 2 Nr
H 2 gang 1-way switch – Legrand 5 Nr
Switched Socket Outlets:
J 13Amps, Double Sockets Legrand 7300 - 70 80 Nr
K 13Amps, Single Sockets Legrand 7300 - 70 6 Nr
L 13Amps Double sockets - UPS Sockets Legrand
7301 -61. The Socket must carry a Red Rocker
switching control to identify all UPS Socket
outlets.
80
Nr
M 20A Hand Dryer Outlet 3 Nr
N 30A, A/C Switch complete with Neon Indicator -
Legrand
12
Nr
O 45A Cooker Socket 2 Nr
C/F US$
78
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
FITTINGS AND ACCESSORIES (THIRD
FIX) CONT
Light Fixtures:
A 600 x 600mm 40W LED Low Energy Lightning-
IP44 Normal Light Fixtures
14
Nr
B 600 x 600mm 40W LED Low Energy Lightning-
IP44 Emergency Light Fixtures (3 Hours Non-
Maintained)
13
Nr
TOILET CEILING LIGHTS - BEGA TYPE No.
2543 - Impact Resistant Ceiling Light, Low
Voltage Fluorescent Lights, 13watts 900 Lumen, 1
TC-D. Protection Class IP 65 BEGA TYPE
C BEGA Round Shaped, c/w TC-TEL 13W GX24-
Q-2 Lamp
6
Nr
D 18W Low Energy LED Ceiling Downlight
Fixtures in store and switch room areas
2
Nr
E THORN AQUAFORCE-II – 1 x 36Watts
Fluorescent fittings. Body and diffuser made of
sturdy polycarbonate for impact resistance-High
Frequency and Emergency control gear. Rapid
installation with Quick-fix bracket installed in
ceiling. High performance in tough IP65
environments. Fluorescent fittings AQUAF2 - 1 x
36W T26
1
Nr
F
THORN AQUAFORCE-II – 1 x 18Watts
Fluorescent fittings. Body and diffuser made of
sturdy polycarbonate for impact resistance-High
Frequency and Emergency control gear. Rapid
installation with Quick-fix bracket installed in
ceiling. High performance in tough IP65
environments. Fluorescent fittings AQUAF2-1 x
18W T26
2
Nr
G 8-Watt Emergency Illuminated Exit Sign Box (3
Hours Non-Maintained) made from powder coated
steel and has 20mm entries and BESA Box
Fitting. Width: 390mm, Height: 190mm, Depth:
60mm Lamp Type: 1 x 8W T5 tube (included).
4
Nr
C/F US$
79
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
HAND DRYER:
A Hygienic' Automatic Chrome hand dryers suitable
for damp environments and resistant to corrosion
for applications where aesthetics is the highest
priority plus the fact our chrome hand dryers are
also vandal resistant and high powered.
3
Nr
ELECTRIC WATER COOLER
B Supply and install 230V, 50Hz, Electric Water
Cooler that cools and dispenses the water to be
located in the reception area.
2
Nr
Sub-Mains Switchgears-Third Floor: Supply and
install the following boards, approved Sub-Mains
Switchgears, fuse etc.and including 25mm²
diameter concealed in pvc conduits and wiring
between to:
Supply, install and connect PROTEUS BX TYPE
B or Equal and Approved, 400/230V, 50Hz,
125Amps 8-way TP&N LV Distribution Boards
(Raw Power Sockets and Light Circuits) or Equal
and Approved as shown in Line Schematic for the
Third Floor.
Distribution Board shall comply with the
following features:
C 1. Bus bar shall be rated at 200A and are of a
one-piece construction
2. Clean line overall hinged door (key
operated lockable door optional) over
MCB's
3. Removable end plates, top and bottom
4. Easily removable interior for ease of
installation
5. All boards shall accept MCB’s and HRC
carriers
6. All boards shall accept 100A SP, DP, TP
modular isolation in out-going ways
7. Isolators shall be locked in ON or OFF
position
2
Nr
C/F US$
80
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
FITTINGS AND ACCESSORIES (THIRD
FIX) CONT
Sub-Mains Switchgears-Third Floor: Supply and
install the following boards, approved Sub-Mains
Switchgears, fuse etc.and including 25mm²
diameter concealed in pvc conduits and wiring
between to:
Supply, install and connect PROTEUS BX TYPE
B or Equal and Approved, 400/230V, 50Hz,
125Amps 8-way TP&N LV Distribution Boards
(Raw Power Sockets and Light Circuits) or Equal
and Approved as shown in Line Schematic for the
Third Floor.
Distribution Board shall comply with the
following features:
A 1. Bus bar shall be rated at 200A and are of a
one-piece construction
2. Cleanline overall hinged door (key
operated lockable door ptional) over
MCB's
3. Removable end plates, top and bottom
4. Easily removable interior for ease of
installation
5. All boards shall accept MCB’s and HRC
carriers
6. All boards shall accept 100A SP, DP, TP
modular isolation in out-going ways
7. Isolators shall be locked in ON or OFF
position
1
Nr
B Supply, install and connect PROTEUS RANGE
100A, TP&N Switch Disconnector in the UPS
Room designed to provide compact wall mounted
installation with ample space for ease of
installation. Fully rated BS88 fuses fitted.
Manufactured to BSEN60947-3, 100A,
PROTEUS RANGE TP&N Fused Switch
Disconnect -UPS Room
1
Nr
C/F US$
81
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
TESTING & COMMISSIONING
D Allow for Testing and Commissioning the
complete Electrical Services Installation for the
Third Floor to the satisfaction of the Engineer,
including labour which comprises the whole of the
labour associated with the rewiring and
replacement and installation of new fixtures and
making good all disturbed surfaces necessary to
form a complete installation and such tests,
adjustments as may otherwise be required to give
an effective working installation. Isolators shall be
locked in ON or OFF position
Item
Total Electrical Installation Carried
To Summary US$
82
Item
No
Description
Qty Unit Rate
US$
Amount US$
WALL MOUNTED INVERTER SINGLE
SPLIT AIR CONDITIONING UNIT.
DEMOLITION
A Remove all existing old Wall Mounted Single
Split Air Conditioning Units on the third floor
complete with fittings and put aside as directed by
the Bank
Item
Supply and install new Wall-Mounted Inverter Air
Conditioning Units with fast Cooling Energy
Efficient Inverter split Air Conditioner Units
complete with environment friendly refrigerant R-
410a and accessories including controllers and
anchoring brackets for the Outdoor Units as
specified on the drawing for the Third Floor
B 9,000BTU 2 Nr
C 12,000BTU 3 Nr
D 18,000BTU 6 Nr
E 24,000BTU 1 Nr
F Supply and install liquid and gas copper pipes
complete with pipe insulation and all necessary
accessories to complete the installation.
Item
G Supply and install 63A, 4Pole, IP65 Rotary
Isolator, manufactured to BSEN 60947 Parts 1 &
3. IP65 polycarbonate enclosure with padlockable
operating handle for security complete with Earth
& Neutral terminals fitted to terminate power
supply cable to A/C Outdoor Unit.
12
Nr
H Supply and install condensate drain pipes in
25mm pvc pipe complete with elbows, T-Pieces,
pipe solvent and all necessary materials to
complete the installation
Item
C/F US$
83
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
WALL MOUNTED INVERTER SINGLE
SPLIT AIR CONDITIONING UNIT (CONT)
TESTING & COMMISSIONING
A Allow for Testing and Commissioning the complete
replacement of the Air Conditioning System
installation for the Third Floor to the satisfaction of
the Engineer, including labour which comprises the
whole of the labour associated with the installation
of new replacement units and making good all
disturbed surfaces necessary to form a complete
installation and such tests, adjustments as may
otherwise be required to give an effective working
installation.
Item
Total of Air Conditioning Unit Installation Carried
To Summary US$
84
Item
No
Description
Qty Unit Rate
US$
Amount US$
20kVA, 3-PHASE 400V~, 50HZ, HIGH
FREQUENCY ONLINE UPS
DEMOLITION
A Remove existing old 10kVA UPS's complete with
fittings and put aside as directed by the Bank
Item
B Supply, position and install 20kVA 3-Phase 400V~,
50 Hz, High Frequency Online UPS with Internal
Maintenance Bypass & Parallel Capability as
specified for the ADB Office Country complete with
battery packs, connecting battery cables and
accessories.
2
Nr
C Supply, install and connect 16mm2 4-core
Cu/XLPE/PVC Flexible cable &1 x 10mm2 single
core Yellow / Green CPC cable in radial circuit
wiring from UPS Units outputs to 63A Switch Board
located on the Fifth Floor complete with cable
glands, booths, lugs and all necessary accessories to
complete the installation
10
M
D Supply, install and connect 16mm2 4-core
Cu/XLPE/PVC Flexible cable &1 x 10mm2 single
core Yellow / Green CPC cable in radial circuit
wiring from Main Raw Power Electrical Switchgear
located on the Fifth Floor to New UPS Units
complete with cable glands, booths, lugs and all
necessary accessories to complete the installation.
30
M
Testing & Commissioning:
E Allow for testing and commissioning the complete
20kVA 3-Phase 400V~, 50 Hz, High Frequency
Online UPS with Internal Maintenance Bypass &
Parallel Capability Equipment’s complete with
battery packs and connecting battery cables as
specified for the ADB Office requirement for
performance
Item
Total New UPS Equipment’s Installation Carried
To Summary US$
85
Item
No
Description
Qty Unit Rate
US$
Amount US$
SUPPLY, DELIVERY, INSTALLATION &
COMMISSIONING OF ICT NETWORK,
CCTV, FIRE ALARM SYSTEM AND ACCESS
DOOR CONTROL SYSTEM FOR ADB
SIERRA LEONE OFFICE, 3RD FLOOR
BISHOP BUILDING
Networking/Data Points wiring
A Supply, delivery, wiring, conduit laying of computer
networking points with cat 6 cable (from switch to
individual points) through 16 / 20mm dia. HDP pipe
concealed in ceilings, walls and floors including
heavy type metal box and all necessary connecting,
fixing, insulation all complete.
(From IT Room on 5TH floor to the 3RD floor)
RJ-45 plugs to be included
600
M
Single Gang Face Plate with Information Outlet
B
Supply and installation of Computer Outlets RJ 45,
CAT 6, single, with required facia plate.
45
Nr
Category 6 Patch Panel
C Supply and Installation of 48-ports, rack mounted,
High impact, flame retardant, thermoplastic or
Powder coated steel, 22/24 AWG, CAT 6 RJ-45
patch panel for Data
1
Nr
Wall Mount Rack with Fan
D Supply, installation, testing and commissioning of
9U rack with fan designed to integrate wall-
mounting, easy equipment access, and cable
management in IT network. Adjustable rack rails
with square mounting holes to accommodate up to
12U of standard 19" rackmount equipment;
adjustable front and rear vertical rackmount rails;
Locking, reversible Plexiglass front door (2.7mm
thick) and locking, removable side panels.
1
Nr
E Supply and installation of:
Cisco nexus 9200L-48P-4X switch including smart
net
2
Nr
86
C/F US$
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F
SECURITY SYSTEM A Supplying and laying of CAT-6 UTP cable made of Cu
with 23/60 twin dc wire inside 20/25 mm. dia. HDP
materials including labour charge for laying CCTV
cables with pull boxes, metal box all complete and concealed wiring through ceiling, false ceiling, wall,
table whichever applicable including cable shoes/sockets
cable clamps and necessary connecting, fixing, chiselling of existing wall / ceiling and redoing the chiselled area
with cement and sand mortar as per the drawings, site
conditions, specifications and instructions All point wiring from each CCTV (IP cameras) to be
terminated to HUB switch.
(From IT Room on 5TH floor to specified locations on
the 3RD floor)
350
M
CCTV cameras to integrate with existing NVR
B
Model: alhua 3 Nr
FIRE ALARM SYSTEM
C Supply, installation, testing and commissioning of
Optical smoke detectors with base; auto compensation; digital processing algorithm; protected area - up to 120
sq. m.; low profile design; LED indication with 360
visibility; sensor status indication every 8 seconds.
16
Nr
D Supply & delivery of Fire alarm call points
Model type: C-TEC
3
Nr
E Supplying and laying of CAT-6 UTP cable made of Cu
with 23/60 twin dc wire inside 20/25 mm. dia. HDP
materials including labour charge for laying fire alarm cables with pull boxes, metal box all complete and
concealed wiring through ceiling, false ceiling, wall,
table whichever applicable including cable shoes/sockets
cable clamps and necessary connecting, fixing, chiselling of existing wall / ceiling and redoing the chiselled area
with cement and sand mortar as per the drawings, site
conditions, specifications and instructions All point wiring from each fire alarm to be terminated to
HUB switch. (From IT
Room on 5TH floor to specified locations on the 3RD floor)
300
M
87
C/F US$
Item
No
Description
Qty Unit Rate
US$
Amount US$
B/F FIRE ALARM SYSTEM (CONT)
DOOR ACCESS CONTROL SYSTEM
A
B
Supply, installation, testing and commissioning of
RFID door access control system with Electric
Magnetic lock (220 – 240V AC and 12V DC).
USB Reader capable to keep logs of access and
denial for at least 90days with a
Minimum 30 cards per lock to be supplied
Supply and Installation of IP Video Phon7 inches
screen size system with touch free sensor for
Gesture activated calling at main entrance and to be
integrated seamlessly with the door access control
3
3
Nr
Nr
WIRELESS ACCESS
C
Supply, install and test Wireless MIMO Access
Points as indicated in the diagram with the following
specifications:
Category – 806.11n
Band – dual band (2.4/5 GHz)
Note: Connection will be from IT Room on 3rd
Floor on the Nexus Switch to specified locations on
the 3RD floor.
Model: Cisco Air
2
Nr
.
88
Total ICT Network, CCTV, Fire Alarm System and Access Door Control
System Installation Carried To Summary US$
ITEM NO DESCRIPTION
AMOUNT US$
SUMMARY (OUTTING WORKS)
DEMOLITION
NEW PARTITIONS/CEILING
ROOF REPAIRS
ELECTRICAL SERVICES INSTALLATION
WALL MOUNTED INVERTER SINGLE SPILT AIR
CONDITIONING UNIT
20KVA. 3-PHASE 400V -, 50HZ, HIGH FREQUENCY
ONLINE UPS
ICT NETWORK, CCTV, FIRE ALARM SYSTEM AND
ACCESS DOOR CONTROL SYSTEM
TOTAL OF OUTFITTING WORKS Carried
To MAIN SUMMARY US$
89
MAIN SUMMARY
90
AMOUNT US$
MAIN SUMMARY
PRELIMINARIES
OUTFITTING WORKS
SUB-TOTAL US$
ADD
• INSURANCES (P.S) 1,500.00
• CONTINGENCIES – 5% OF SUB-TOTAL
GRAND TOTAL Carried To
CONTRACTOR’S BID US$
91