Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
Transcript of Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
1/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 1 of 52 WAPCOS LIMITED
CHAPTER - 1
GUIDELINES OF DESIGN PRINCIPLE AND SPECIFICATIONS FOR MATERIALS
AND WORKS
1.1 INTRODUCTION
This chapter provides broad guidelines for designing the different components
of the work and also covers the specifications for material used for civil,
structural building and architectural work. The bidder has to follow the relevant
Indian Standard specification while designing the different components of the
works. Wherever Indian Standard specifications are not available the bidder
has to quote proper authority (or) code for the assumption made and method
adopted and the bidder has to enclose the authority (or) code. Similarly for the
procurement of material used for testing of materials unless specified in the
tender the relevant provision of the appropriate bureau of Indian Standard
(BIS) shall apply for all materials and workmanship. Where the relevant BIS
do not exists; the latest version of the relevant British Standard specification
(or) standard of the American society for testing material shall apply.
1.2 SCOPE OF WORKS
The work contemplated covers the design, manufacture, assembly, testing,
supply, construction of shore based intake through open channel with two
groynes, Stone protection works for groynes, dredging of offshore channel
construction of approach channel (onshore and offshore channel),
construction of desilting basin, Construction of forebay, Construction of pump
house including sump, Laying and assembly of Intake and Outfall pipeline,
Construction of approach road of single lane (Sectional drawing enclosed)
along the pipeline route upto pump house, Construction of MCC room,
chlorination room, Outfall Structure including diffuser, civil, structural,
Mechanical, Electrical, Control & Instrumentation and architectural works as
specified / required for safe and trouble-free operation of Sea water Intake and
Outfall system for 2 X 800 MW Units and for future 1 X 800 MW Unit of
SDSTPS at Nellore, Andhra Pradesh, India, including One (1) year Operation
and maintenance of the commissioned plant with personnel, spares &
consumables and imparting training to APPDCL/APGENCO staff on O&M of
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
2/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 2 of 52 WAPCOS LIMITED
entire system. The major scope of works involved are the following but not
limited to the same for civil and mechanical works of sea water intake and
outfall system.
Design, Construction of groynes, offshore channel of suitable
size including stone protection works for groynes, dredging of
offshore channel etc.
Design, construction of onshore channel, desilting basin.
Design, construction of forebay including counterfort retaining
wall/RCC Diaphragm wall etc.
Design, construction of Pump house including sump etc.
Design, supply & installation of three (3) numbers Vertical
Turbine pumps with all necessary electrical, mechanical
accessories and provision of two (2) numbers future pumps
Design, procuring, jointing and laying of factory made 2200 mm
diameter and minimum 16 mm thick delivery/intake pipeline
including 2 mm thick PU coating from pump house to terminal
point (TP1) inside the plant with all necessary butterfly valves,
air valves, sluice valves, thrust block ,anchor blocks, valve
chambers, expansion joints etc.
Design, procuring, jointing and laying of factory made 1800 mm
diameter and minimum 14 mm thick Return/Outfall pipeline
including 2 mm thick PU coating from terminal point (TP1) to
diffuser point as specified with necessary butterfly valves, air
valves, sluice valves, thrust block ,anchor blocks, valve
chambers, expansion joints etc.
Design, construction of approach road from plant boundary to
pump house along the pipeline route.
Design, supply & installation of three (3) nos. traveling water
screens, coarse screens.
Design, supply & installation of six (6) nos stop log gates and
provision of two (2) numbers future requirement.
Design, supply & installation of Cranes and Hoists as per
requirement.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
3/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 3 of 52 WAPCOS LIMITED
Design, supply & installation of Electro chlorination system for
sea water to avoid biofouling in Intake pipeline with all necessary
accessories etc.
Surface preparation and necessary corrosion resistance painting
for all equipment, piping, valves, structures, buildings, tanks,
walls, platforms etc.
One (1) year Operation and maintenance of the commissioned
plant with personnel, spares & consumables and imparting
training to APPDCL/APGENCO staff on O&M of system.
Scope of works specified above is tentative and Bidder has to execute
complete works for satisfactory functioning of entire Sea water intake & Outfall
System. The Bidder shall quote for the Base scheme and can suggest
alternative options with separate price which will not be considered for
evaluation.
The preliminary geotechnical investigation, hydrographic survey, topographic
survey and oceanographic studies were conducted by the purchaser and
preliminary report is available with Purchaser and will be furnished to the
successful bidder for reference. However for detailed engineering and
construction Bidder has to carry out necessary geotechnical investigation,
hydrographic survey, topographic survey and oceanographic studies etc. as
required.
Any discrepancies or lack of inconsistency data found at a later date in
Purchasers investigation shall not form the basis of any extra claim or time
extension. Bidder shall take special care to assess exact nature and quantum
of work involved both on shore and off shore area.
The system design & construction shall be proven to meet all functional
requirements and perform accurately and safely under the prevailing
environmental and operating conditions without undue heating, vibration,
wear, corrosion, aging, malfunction or other operating problems.
All equipment, materials and instruments shall be supplied from reputed
manufacturer and approved vendors of APPDCL/APGENCO and shall
conform to relevant latest national / international standards.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
4/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 4 of 52 WAPCOS LIMITED
The description of work given in the document is for broad understanding of
the nature of the work. The bidder should acquaint himself with nature of
work to be performed for continuous trouble-free operation.
The details of civil, structural, architectural work involved that require design,
drawing, material for construction are given below.
Design and construction of groynes, dredging of Intake channel in the
sea and desilting basin with proper embedment and other protective
works ,concrete lining from onshore open channel to forebay, including
Mechanical Components
Design of Intake Pump House and associated Switchgear& control room
and Electro Chlorination Plant room.
Laying of partly underground, partly over ground and over Buckingham
canal the intake pipeline up to the terminal point (TP1) which is at a
distance of around 5.3 km from the proposed pump House.
Laying of partly underground, partly over ground and over Buckingham
canal the return flow water pipeline on land and off shore submarine pipe
up to a Diffuser section as specified.
The work to be performed shall also include all labour, consumables,
equipment, temporary works, temporary storage sheds, temporary labour and
staff colony, temporary site offices, construction plant, fuel supply, power,
transportation including making arrangement of power where required and all
incidental items not shown or specified but reasonably implied or necessary for
the completion of civil works, all in strict accordance with the specifications,
Latest codal requirements and including revisions and amendments there to as
may be required during the execution of the work.All materials including cement, reinforcement steel, structural steel, etc. shall be
arranged / procured by the Bidder.
The work shall include setting up a complete testing laboratory in the field to
carry out all relevant tests required for the civil works.
The Contractor shall setup a quality control laboratory with all facilities to carry
out the testing of all construction materials and field quality tests as per field
quality plan (FQP)/ Specifications/relevant IS Codes. The contractor shall
provide sufficient qualified and competent manpower for carrying out Lab testing
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
5/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 5 of 52 WAPCOS LIMITED
and field quality control. The Contractor shall provide all facilities to carry out the
test desired by the PURCHASER. If the contractor does not have facility for
some tests, these tests should be got done from reputed third party Labs. All
costs for testing will be borne by the Contractor for Quality Assurance (QA) &
Quality Control (QC). The test certificates/lab reports of different construction
materials shall be submitted by the contractor for PURCHASERs review and
approval before incorporating the material in the work. The contractor shall also
submit the Test reports of various tests of the works to the PURCHASER for
review/Approval.
All the documents (Soft & Hard Copy) shall be properly maintained and easily
retrievable.
The Contractor shall submit field quality plan (FQP) 15 days in advance for
approval of the PURCHASER before commencement of the works.
The work shall be carried out in accordance with the design / drawings to be
developed by the Bidder and approved by the PURCHASER. For all onshore
and offshore constructions and foundations, etc., necessary layout details are to
be developed by the Bidder keeping in view the statutory & functional
requirements of the system & facilities sufficient space and access shall be
provided in the layout. Certain minimum requirements are indicated in this
specification for guidance purpose only. However, the Bidders offer shall cover
the complete requirements as per the best prevailing practices and to the
complete satisfaction of the PURCHASER.
All the standards and other technical requirements as covered in this
specification and relevant code of practice shall be strictly adhered to by the
Bidder in order to achieve the quality of work.
The Bidder should fully apprise himself of the prevailing conditions at the
proposed site, meteorological conditions like climate, rainfall, relative humidity,
wind, storm and cyclones, visibility, oceanographic conditions, local conditions,
site specific parameters and shall include for all such conditions, contingent
measures in the bid, including those which may not have been specifically
brought out in the specifications. The PURCHASER has carried out
environmental parameter by engaging outside agency and the same may be
availed if required for reference.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
6/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 6 of 52 WAPCOS LIMITED
The bidder has to carry out all survey works such as bathymetry, topography
and hydrographic survey in order to assess the bed profile of the sea and also
to assess the quantum of dredging and also to decide the depth of founding for
structural component.
1.3 SUBMISSIONS OF DOCUMENTS
The following documents are to be submitted for the approval of the
PURCHASER, prior to commencement of fabrication. All drawings shall be of
standard sizes (Metric System) and shall be made on AutoCAD format. Editable
soft copies of Design calculations and design basis in original format and
drawings in AutoCAD format shall be submitted. This will be addition to the hard
copies that have to be submitted for the above items.
Layout drawing of various facilities at onshore and offshore location, all
pipeline routing drawings with coordinates, showing roads, bridges,
culverts etc.
Drawing showing underground facilities with co-ordinates of these
facilities like buried pipes, buried cable, trenches, ducts, sewer, drains,
sumps, pits, culverts, foundations, etc. along pipe routes.
Architectural floor plans, elevations, cross-sections and perspective view
of all buildings.
Site leveling, area filling drawings indicating final grade levels of various
areas along with survey drawings indicating the natural contours and
spot levels of the natural ground, permanent features, etc.
Basis of design of all buildings, facilities, services and structures. The
Contractor shall get the design basis report approved by
PURCHASER/Consultant prior to undertaking any detailed engineering
works.
Design calculations and drawings for foundations / sub-structure and
superstructure of all buildings including pump houses and other all
structures.
Bidders reports on Hydraulic model studies on Intake Pump sump
including forebay Numerical model studies on discharge water
recirculation, quantity of littoral drift, hydrodynamics and sedimentation
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
7/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 7 of 52 WAPCOS LIMITED
and Flume studies for gryones trunk section and round head section
from reputed laboratory like IIT/CWPRS.
Drawings of all architectural works including finish schedule, colour
scheme (Both internal and external), doors & windows, flooring and false
ceiling, etc.
Design calculations and drawings for plumbing and building drainage.
Write-up on various statutory requirements and their compliance for
various buildings and facilities.
Copy of all studies / investigations report carried out by the Bidder as per
scope.
Fabrication drawings all structural steel works (only for reference) &design calculations for important joint connections.
Marking scheme identifying the equipment / pump lay down areas.
All other designs, details / drawings or any other submission as indicated
elsewhere in this specification and as required by the PURCHASER.
Details of corrosion protection and anti-bio-fouling measures for all
structures.
All construction drawings shall include total quantity of concrete (grade
wise), reinforcement steel (diameter wise) and structural steel (section
wise).
Type of dredger proposed to be engaged for dredging the sea bed to
facilitate for intake channel.
Report on the detail methodology for laying and anchoring offshore
outfall pipeline.
Report on the detailed methodology of construction of onshore pump
house, forebay, desilting Basin, open channel and de-watering.
Report on design and laying of onshore and offshore pipelines.
1.4 LOCATION OF WORK
1.4.1 LOCATION OF SHORE BASED INTAKE
A tentative location and dimensions of Groynes has been shown in the
tender drawing for drawing intake sea water. These drawings of groynes are
for guidelines only; Bidder shall design groynes section as per requirement.
The Intake channel will be protected by groynes to protect from siltation.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
8/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 8 of 52 WAPCOS LIMITED
These groynes are rubble mound type structure with approximate length of
185m. The intake channel of 30 m width and dredged up to -3.0 m CD contour
in between two gryones one on south side and other on north side and sea
water will be carried out on land by open channel excavated up to -3.0 m
below CD and bottom width will be 5 m. This channel will be connected to
desilting basin of bottom width 12m and excavated up to -4.0 m below CD and
stone protection also provide to two groynes from scouring.
1.4.2 INTAKE PUMP HOUSE AND FOREBAY
Pump house structure shall be founded at a location shown tentatively at the
tender drawing. A forebay will be provided in front of pump house to receive
water from open channel. Functional requirement of the pump house is toreceive water and pumping it to main plant area through intake pipe line.
A maintenance bay shall be provided with heavy vehicle entry facilities for
erection and maintenance. A screen and gate handling bay shall be provided
in the pump house for storing gates/screens whenever they are not in use.
The storage bay shall be provided with crane access for hauling gates/screen
and also with structures supporting and stacking them for.
The foundation of Pump house including sump portion shall be designed on
pile keeping in view of the soil conditions. The super structure of the pump
house shall comprise of RCC design mix, construction the pump house will be
provided with heavy duty EOT crane travelling over crane runway girders
spanning between brackets. Suitable access and platform / walkway shall be
provided for crane operation. The side cladding shall be of brick wall laid, and
jointed in cement mortar as per specification. The roof shall have parapet and
water proofing as per specification. The ground floor shall have heavy-duty
floor finish. Adequate door /windows/ ventilators shall be provided as per
specification. Vertical turbine pumps will be placed on RCC pump operating
floor. Suitable hatch shall be kept on the floor to access the pump sumps by
ladder.
Forebay is located on the shore line side of the pump house as shown in
tender drawings. The fore bay receives seawater through an onshore
channel. The side walls and base slab shall be of RCC and foundation shall
be based on soil conditions, Hand rails all along the side walls as per
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
9/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 9 of 52 WAPCOS LIMITED
specification shall be provided for safety. The layout of forebay shall conform
to the stipulation of Manual of Hydraulic Institute and BHRA.
Annexed to the pump house there will be chlorination plant room, Electrical
switchgear and control room. The building will be a RCC framed structure
with brick wall side cladding. Minimum clear height under the roof of building
shall be 4.50 m or more if required for adequate clearance. The building shall
have toilet facilities. Adequate door/window / ventilators / louvers shall be
provided in the above building. The MCC room and Chlorination room shall
have vitrified tiles flooring with provision AC and false ceiling.
1.4.3 INTAKE CHANNEL / OFFSHORE CHANNEL
Intake / Offshore channel is proposed to be provided at sea side and it is to beprotected with two groynes. Intake channel will have 30 m width and dredged
upto -3.0 m contour below CD. This channel will be extended up to 180 m in
to the sea from High Tide Line and will be taken through open channel or
onshore channel on land and connected to desilting basin.
A desilting basin will be formed at appropriate location before Pump house
as shown in the tender drawing. Size and depth of basin will be ascertained
by hydraulic model study. Sludge removal facilities will provided in the
desilting basin so that it can be cleaned without interrupting the water flow to
the pump house or generation at power plant.
[
1.4.4 BRIDGE OVER BUCKINGHAM CANAL WITH APPROACH RAMP &CROSS OVER BRIDGE
The cross over structure for laying / taking the Intake & Outfall pipelines and
roadway wherever required shall be RCC of mix design concrete. The
minimum height shall 8 m keeping in view of navigation under the bridge. The
width of bridge shall fix considering diameter of Intake and outfall pipeline,
sufficient space for inspection and walking and approach road etc. The
foundation of bridge shall be designed on pile keeping view of soil conditions
for further details refer drawing enclosed
1.4.5 LAYING OF INTAKE PIPELINE
Intake pipeline from Pump house shall be laid up to the terminal point (TP1)
and these pipeline is partially over ground and partially buried below ground
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
10/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 10 of 52 WAPCOS LIMITED
level and minimum 1m to be maintained between top of pipeline and existing
RL of ground. The work shall include construction of valve chambers/manhole
chambers/sludge pits and sub base layer etc. The Intake pipeline shall be
anchored properly for the exposed pipeline and wherever necessary at bend
and level difference shall be provided with thrust blocks. The backfilling shall
be done by the excavated soil to the maximum extent possible and it shall be
properly consolidated / compacted.
1.4.6 LAYING OF RETURN FLOW / OUTFALL PIPELINE UP TO DIFFUSERPOIN
A tentative location of return flow / Outfall pipeline is shown in the tender
drawing. The outfall pipeline is to be laid partially over ground and partially
buried below ground level and minimum 1m to be maintained between top of
pipeline and existing RL of ground and to be taken upto the diffuser point in
sea as specified and thereafter it shall be taken by suitable means depending
upon the sea bed level.
The outfall pipeline shall terminate at the diffuser section, designed to
promote rapid mixing and dilution with surrounding sea water. A multi port
diffuser system shall discharge the reject water into the sea. The diffuser portshall consist of riser pipes projecting up from the diffuser pipeline that is
buried beneath the sea and shall be properly anchored. The diffuser head will
be encased in concrete for protection against ship anchors and suitable case
should be also provided. The diffuser structure shall be firmly founded in the
seabed below the scour depth. Additional concrete collar blocks shall be
placed over the diffuser to increase the stability. Marker buoys shall be
located around the diffuser head if needed.
The design and construction of offshore concrete and other type of structure
like diffuser shall conform to the followings
Recommendation for the design and construction of concrete marine
structures
Relevant Indian Codes of practices IS 4651 Part I to Part V, IS 9556, 9527
and other latest codes etc.
1.5 GEOTECHNICAL INVESTIGATION AND FOUNDATION SYSTEM
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
11/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 11 of 52 WAPCOS LIMITED
The Bidder shall carry out his own geotechnical investigation in all works before
commencing detailed design and working drawings for finding out the allowable
bearing pressures, expected settlements, type of foundations, etc. as per the
relevant Bureau of Indian Standard. The soil investigation report shall be
submitted to the PURCHASER for approval and the approved report shall
become the basis for design of sub-structure. Approval of the PURCHASER
shall in no way relieve the contractor of his sole responsibility in regard to
stability and safety of the structure.
1.6 REQUIREMENT OF FOUNDATIONS DESIGN
All foundation system shall be as per the recommendation of soil investigation
report furnished by Bidder. The foundation system will comprise both Pilefoundations as well as isolated / strip / raft foundations depending on Intensity
of loading and settlement criteria and based on the bearing capacity of the
soil.
For design of foundations, net allowable bearing capacity in different strata
shall be considered based on the soil investigation report.
The foundation shall be designed for the maximum bending moment that
arrived from various combinations of loading.
In case of presence of high water table, necessary dewatering shall have to
be made in order to carry out the excavation without any side collapse. In
case, deep well point system is required, the same shall also be provided. In
addition to above, at certain places sheet piling to support sides of
excavations may also be required. Scheme for dewatering and design with all
computations and back-up data of dewatering and sheet piling shall be
submitted for PURCHASERs information.
The founding level shall be decided as per functional requirement. The bottom
of excavation shall be properly compacted prior to casting of bottom slab of
trenches. The depth of foundation shall be fixed based on Safe bearing
capacity of soil.
Backfilling around foundations shall be carried out with excavated materials in
layers not exceeding 20 cm thickness and each layer shall be compacted to
95% standard proctor density for cohesive soil and to 85% of relative density
for non-cohesive soils.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
12/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 12 of 52 WAPCOS LIMITED
For open foundations, the total permissible settlement and differential
settlement will be as per latest code of practice and from functional
requirements whichever is more stringent. However total settlements of
foundation resting on soil will be restricted to following:
a) Isolated/ Strip footing of width up to 6.0m : 25 mm
b) Footing of width greater than 6.0m (raft) : 50 mm
1.6.1 CODES AND STANDARDS
a) Internationally accepted design Codes and Standards where Indian
Codes are not available and which are equivalent to Indian Standards.
b) National Building Code of India.
c) "Accepted Standards" and "Good Practice" listed in the appendix to
National Building Code of India.
d) IS-1200: Method of measurement of Building and Civil Engineering
Works.
e) IS-1256: Code of Practice for Building By laws.
f) IS-456 : Code of Practice for Plain and reinforced concrete.
In addition to the above, the stipulation in the relevant code for each item of
work shall be followed.
1.6.2 FOUNDATIONS
a) IS-1904 : Code of practice for design and construction of
foundations & soils.
b) IS-2950 : Code of practice for design and construction of raft
foundations.
c) IS-2974 : Code of practice for design and construction of
Machine foundations (all parts).
d) IS 2911 : Code of practice for Design and Construction of Pile
Foundation. (All parts)
1.6.3 LOADING
a) IS-875 : Code of practice for design loads for buildings and
structures - loading standards (all parts).
b) IRC 6 : I.R.C loading classification.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
13/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 13 of 52 WAPCOS LIMITED
1.6.4 ROOF AND FLOORING
a) IS-2204 : Code of practice for construction of reinforced
concrete shell roof.
b) IS-3201 : Criteria for the design and construction of precast
concrete trusses and purlins.
c) IS-809 : Rubber flooring materials for general purposes.
e) IS-1195 : Bitumen mastic for flooring.
f) IS-1196 : Code of practice for laying bitumen mastic flooring.
h) IS-1237 : Cement concrete flooring tiles.
i) IS-1443 : Code of practice for laying and finishing of cement
concrete flooring tiles.
j) IS-2114 : Code of practice for laying in situ terrazzo floor finish.
k) IS-2571 : Code of practice for laying in situ cement concrete
flooring.
l) IS-5491 : Code of practice for laying in situ granolithic concrete
floor topping.
m) IS-5766 : Code of practice for laying burnt clay brick flooring.
n) IS-1197 : Code of practice for laying of rubber floors.
o) IS-2441 : Code of practice for fixing ceiling coverings.
1.6.5 WATER PROOFING
a) IS-1322 : Bitumen felts for waterproofing and damp proofing.
b) IS-1346 : Code of practice for waterproofing of roofs with bitumen
felts.
c) IS-1609 : Code of practice for laying damp proof treatment using
bituminous felts.
d) IS-3036 : Code of practice for laying lime concrete for a
waterproofed roof finish.
e) IS-3037 : Bitumen mastic for use in waterproofing of roofs.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
14/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 14 of 52 WAPCOS LIMITED
f) IS-3067 : Code of practice for general design, details and
preparatory work for damp proofing and water proofing
of buildings.
g) IS-3384 : Bitumen primer for use in water proofing and damp
proofing.
h) IS-4365 : Code of practice for application of bitumen mastic for
waterproofing of roofs.
1.6.6 EARTHQUAKE RESISTANT DESIGN
a) IS-1893 : Criteria for earthquake resistant design of
structures.
b) IS-4326 : Code of practice for earthquake resistant design
1.6.7 STRUCTURAL STEELWORK
a) IS-800 : Code of practice for general construction in steel.
Part-I: Load and permissible stresses.
Part-II: Fabrication, Galvanising, Inspection and
Packing.
c) IS-806 : Code of practice for use of steel tubes in general
building construction.
d) IS-808 : Rolled steel beams, channels and angle sections.
e) IS-813 : Scheme of symbols for welding.
f) IS-814 : Covered electrodes for manual metal arc welding of
carbon and carbon manganese steel.
g) IS-816 : Code of practice for use of metal arc welding for
general construction in mild steel.
h) IS-817 : Code of practice for training and testing of metal arc
welders.
i) IS-818 : Code of practice for safety and health requirements in
electric and gas welding and cutting operation.
j) IS-819 : Code of practice for Resistance spot welding for light
assemblies in Mild Steel.
k) IS-919 : Recommendations for limits and fits for engineering.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
15/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 15 of 52 WAPCOS LIMITED
l) IS-1024 : Code of practice for use of welding in Bridges and
Structures subjected to Dynamic loading.
m) IS-1161 : Steel tubes for structural purposes.
n) IS-1182 : Recommended practice for Radiographic Examinationof Fusion Welded Butt joints in steel plates.
1.7 ENVIRONMENTAL PROTECTION
Chapter on Corporate Responsibility for Environmental Protection (CREP)
published in Gazette of India dated 27.08.2003.
1.8 LOADING ON STRUCTURES AND FOUNDATIONS
1.8.1 GENERAL
All structures and buildings including Pump House, Water Retaining
structures, desilting basin and various other works including Site leveling,
Approach roads, Drains, Sewers, etc., are covered in this specification. In
case of marine structures, environmental forces due to wave, current &
sediment loads, etc. shall also be considered and latest design standard
practices shall be followed.
Structures shall be designed for the most critical combinations of loads, as
stipulated in IS 456 2000 and other latest code as applicable for marinestructure.
1.8.2 DEAD LOADS
Dead loads shall include the weight of structure complete with finishes,
fixtures and partitions.
1.8.3 IMPOSED LOADS
The imposed load to be considered for the design of various structures shall
be based on IS 875 all parts of latest edition and IS 456-2000 with latest
editions.
In addition to the imposed load as prescribed in the relevant IS equipment
load, erection, operation and maintenance load shall be considered for
designing the structure.
1.8.4 EQUIPMENT LOADS
Loads of all equipment like Pumps, Pump Motor, Cooling Equipment,
Electrical Control and Relay Panels, Cable load, Pipe load (static and
dynamic), stop log gates, trash racks, traveling water screen, Tanks etc., shall
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
16/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 16 of 52 WAPCOS LIMITED
be considered over and above the imposed loads as per the manufacturers
recommendations. Loads due to thermal expansion and hydraulic thrust of
pipes shall also be considered.
1.8.5 CRANE LOADSFor crane loads, an impact factor of 25% and lateral crane surge of 10% (of
lifted weight + trolley weight) shall be considered in the analysis of frame
according to the provisions of IS : 875. The longitudinal crane surge shall be
5% of the static wheel load.
1.8.6 WIND LOADS (WL)
Wind loading will be in accordance with latest edition of Indian Standard Code
IS: 875 (Part-3) for a basic wind speed of 50 m/sec (or) for prevailing andobserved wind speed at site.
1.8.7 EARTHQUAKE LOADS (EL)
The lateral forces will be established in accordance with the recommendations
of IS-1893. The site falls in Zone-III as per the classification of earthquake
zone.
The various site specific seismic parameters for the design
1) Peak ground horizontal acceleration (PGA)MCE : 0.09g
2) Peak ground horizontal acceleration (PGA)DBE : 0.05g
3)Reduction factor (R) is to be applied to the site specificdesign horizontal acceleration spectral coefficients toobtain the design acceleration spectra
a)For ordinary moment resisting steel frames withconcentric braces designed and detailed as per IS : 800
: 4.0
b)For ordinary moment resisting steel frames designed withconcentric braces and detailed as per IS : 800
: 4.0
c) For special moment resisting RC frames designed anddetailed as per IS: 456 and IS: 13920. : 5.0
d) for steel chimney : 2.0
e)For design of equipment resting on ground, reductionfactor should be taken as per IS code:1893 (Part 4) :2005
Note: g = Acceleration due to gravity1.8.8 CONSTRUCTION LOADS
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
17/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 17 of 52 WAPCOS LIMITED
The integrity of the structures shall be maintained without use of temporary
framing, struts or ties and cable bracing, so far as possible. However,
construction or crane access considerations may dictate the use of temporary
structural systems. Special studies shall be made and documented to ensure
the stability and integrity of the structures during any periods involving use of
temporary bracing systems.
1.8.9 TAMPERATURE LOADS
For temperature loading, the total temperature variation shall be considered
as 2/3 of the average maximum annual variation in temperature. The average
maximum annual variation in temperature for this purpose shall be taken as
the difference between the mean of the daily minimum ambient temperatureduring the coldest month of the year and mean of daily maximum ambient
temperature during the hottest month of the year. The structure shall be
designed to withstand stresses due to 50% of the total temperature variation.
Suitable expansion joints shall be provided in the longitudinal direction
wherever necessary
The maximum distance of the expansion joints shall be as per the provisions
of IS: 800 and IS: 456 for steel and concrete structures respectively.
1.8.10 WAVE LOADS
The wind load shall be as per IS 4651Part I to Part V shall be referred.
LOAD COMBINATION
The structure has to be analyzed for various combination of loading as
prescribed in the latest relevant code.
1.9 ANALYSIS METHODOLOGY
Analysis of building / structure shall be carried out by 3D (Space frame
method) or by 2D depending on the type of structure and load details.
For analysis of structure, software like STAAD Pro of latest version shall be
used. For design of various structural elements like foundations, columns,
beams, slab etc. in-house developed software or STAAD Pro shall be used
wherever applicable / possible.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
18/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 18 of 52 WAPCOS LIMITED
1.10 DESIGN CRITERIA
The underground Intake water sumps are RCC water retaining structures and
shall be designed according to IS- 3370. In addition to design of structural
elements as uncracked section, limitation on crack width of 0.10 mm on bothfaces, considering severe exposer condition, shall be checked as per IS-456.
All components of the structure are to be designed for hydrostatic pressure,
earth pressure and also by following various loading condition as given below
i) Inside empty, but at outside, ground water is at FGL surcharge
load.
ii) Inside filled up with water up to full height of the basin and no
lateral pressure from outside of wall.
The dividing wall of the reservoir shall be designed considering one
compartment is empty and other being filled up with water.
iii) The base slab shall be checked against full hydrostatic uplift of
ground water without taking consideration of pressure release
valve. However in fore bay of the pump house they may be
provided subject to approval by the PURCHASER.
The RCC floor slab supporting pumps shall be checked for induced dynamic
load during sudden pump shut off condition. The pump floor shall also be
checked against resonance during normal operating condition.
STABILITY OF STRUCTURES
Design shall be checked against buoyancy due to the ground water during
construction and maintenance stages for structure like underground storage
tanks, pits, trenches, basements, etc. Minimum factor of safety of 1.5 against
buoyancy shall be ensured considering empty condition inside and ignoring
the superimposed loading. for purpose of calculating downward load due to
any overburden, the mass located vertically above and the inclined portion
depending on the angle of soil. The projected area of the base slab shall be
taken into consideration.
All building sub structure including pump houses shall be checked for sliding
and overturning stability during both construction and operating conditions for
various combinations of loads. Factor of safety for these cases shall be taken
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
19/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 19 of 52 WAPCOS LIMITED
as mentioned in IS: 456 and other relevant IS codes. However following
minimum factor of safety shall be followed.
a) Factor of safety against overturning due to wind, seismic or other
lateral load shall be as per clause 20.1 of IS: 456.
b) Factor of safety against sliding shall be 1.5 minimum.
c) Factor of safety against uplift due to hydrostatic forces shall be 1.2 and
due to any other loads shall be 1.5.
Stability of the structure shall also be investigated for loading conditions
during construction, repair or other temporary measures. Lower factor of
safety may be used for such loading conditions as per relevant IS codes.
1.11 ARCHITECTURAL CONCEPTS
Intake Pump House shall be architecturally treated in such a way that it will be
aesthetically pleasing and satisfying all functional requirements. The
architectural treatment shall be compatible with the surroundings, taking full
consideration of climatic conditions and building orientation.
1.12 SITE VISIT AND SURVEY
The Bidder shall visit the site and assess the site conditions and to ascertain
the incidental work required to be carried out to commence the main work &
accordingly the cost is to be considered in his offer.
CONTRACTOR shall carry out the survey of the site before excavation and set
properly all lines and establish levels for various works such as earthwork in
excavation for grading, basement, foundations, plinth filling, roads, drains,
cable trenches, pipelines, etc. Such survey shall be carried out by taking
accurate cross sections of the area perpendicular to established reference /
grid lines at 5m intervals or as determined by ENGINEER based on ground
profile. These shall be checked by ENGINEER and thereafter properly
recorded.
1.13 SITE CLEARING
The area to be excavated / filled shall be cleared of fences, trees, plants, logs,
stumps, and bush vegetation, rubbish, slush, etc. and other objectionable
matter. If any root or stumps of trees are met during excavation, they shall also
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
20/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 20 of 52 WAPCOS LIMITED
be removed. The material so removed shall be burnt or disposed off as
directed by ENGINEER. Where earth fill is intended, the area shall be stripped
of all loose/soft patches, top soil containing objectionable matter/materials
before fill commence.
The CONTRACTOR shall have to clean the site before the work is
commenced and after completion. The rates quoted shall be inclusive of all
charges likely to be incurred in carrying out the work of site clearance, initial &
final and shall also hold good under all conditions of weather.
Any minerals of any description whatsoever and all precious stones, treasures,
relics, antiques and other similar things that may be found discovered on the
site shall remain the property of Government and the CONTRACTOR shall
duly intimate the PURCHASER or any person duly authorized by him to
receive such property.
After completion of the work and before handing over the completed work to
the PURCHASER, the CONTRACTOR shall remove all unused and waste
material, remove temporary structures, ramps, platforms, etc., lying in the
vicinity of completed work and dispose off as directed by the PURCHASER.
Further, temporary structures for storing water etc., labour sheds or any other
sheds put up by the CONTRACTOR for facility of his work, shall be
demolished completely and waste materials disposed. The work site and other
areas, which were in his possession in connection with the execution of work,
should not present any unsightly or ugly appearance. The completed work will
not be taken over by the Engineer-in-charge, unless the final clearance of the
site is done as mentioned above.
1.14 EARTH EXCAVATION
Excavation shall be carried out as specified in the specification. Filling and
compaction shall also be carried out as specified.
Excavation for permanent work shall be taken out to such widths, lengths,
depths and profiles as are shown on the drawings or such other lines and
grades as may be specified by ENGINEER. Rough excavation shall be carried
out to a depth of 150 mm above the final level. The balance shall be
excavated with special care. Soft pockets shall be removed even below the
final level and extra excavation filled up as directed by ENGINEER. The final
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
21/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 21 of 52 WAPCOS LIMITED
excavation, if so instructed by ENGINEER, should be carried out just prior to
laying the mud-mat.
CONTRACTOR may, for facility of work or similar other reasons excavate, and
also backfill later, if so approved by ENGINEER, at his own cost, outside the
lines shown on the drawings or directed by ENGINEER. Should any
excavation be taken below the specified elevations, CONTRACTOR shall fill it
up with concrete of the same class as in the foundation resting thereon, up to
the required elevation. No extra payment shall be claimed by CONTRACTOR
on this account.
All excavations shall be done to the minimum dimensions as required for
safety and working facility. Prior approval of ENGINEER shall be obtained by
CONTRACTOR in each individual case, for the method he proposes to adopt
for the excavation, including dimensions, side slopes, dewatering, disposal,
etc. The approval, however, shall not any way relieve CONTRACTOR of his
responsibility for any consequent loss or damage. The excavation must be
earned out in the most expeditious and efficient manner. Side slopes shall be
as steep as will stand safely for the actual soil conditions encountered. Every
precaution shall be taken to prevent slips. Should slips occur, the slipped
material shall be removed and the slope dressed to a modified stable slope.
Removal of the slipped earth will not be paid for.
In case any rock is obtained from excavation may be used for filling and
leveling to indicate grades without further breaking. In such an event, filling
shall be done in layers not exceeding 50 cm approximately. After rock filling to
the approximate level indicated above has been carried out, the voids in the
rocks shall be filled with finer materials such as earth, broken stone, etc. and
the area flooded so that finer materials fill up the voids. Care shall be taken to
ensure the finer fill material does not get washed out. Over the layer so filled, a
100 mm thick mixed layer of broken material and earth shall be laid and
consolidation carried out.
Excavation shall be carried out with such tools, tackles and equipment as
described.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
22/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 22 of 52 WAPCOS LIMITED
For all foundations below ground water table, excavation shall be done first
just up to ground water level and further excavation to founding level shall be
done just before concreting. As soon as founding strata is reached, lean
concrete mud mat shall be placed and concreting of foundation shall be
carried out with minimum loss of time. During entire operation, excavation
shall be kept dry by dewatering. CONTRACTOR shall programme his work to
ensure that the above procedure is strictly followed including providing
facilities for pumping of water to drain out the water and also to avoid any side
collapse.
APPLICABLE CODES
The following Indian Standard codes unless otherwise specified herein, shall
be applicable. In all case, the latest revision of the codes shall be referredto.
(a) IS:783 Code of practice for laying of concrete pipes
(b) IS:1200 Method of Measurement of Building works. (Parts 1 to 28)
(c) IS:2720 Method of test for soils
Part-2 Determination of Water Content
Part-7 Determination of Water content-Dry Density relation usingLight compaction
Part-8Determination of Water Content-Dry Density relation usingHeavy Compaction
Part-28Determination of Dry Density of Soils in-place, by the Sandreplacement Method
Part-29Determination of Dry Density of Soils in-place, by the CoreCutter Method.
(d) IS:3764 Safety code for excavation work
1.15 REFILLING AND COMPACTION
For filling the trench excavated material including the grabbed materials may
be used with the approval of Engineer / Consultant. The sand used for this
purpose shall free from boulders, rubbish, clay, silt etc., If good quality sand is
not available for the above purpose in full or part, required quantity of sea
sand shall be quarried and transported to the site of work. The payment for
such transportation shall be made under relevant item. The contractor shall
quarry the required quantity of sea sand from the nearby area.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
23/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 23 of 52 WAPCOS LIMITED
The sand required for filling shall be dumped and consolidated by approved
means. Payment shall be made only for the completed profile based on levels
taken before and after construction.
In case the sea sand is used for filling it should be thoroughly washed before
use.
Filling in trenches above pipes and drains shall be commenced as soon as the
joints of pipes and drains have been tested and passed. The back-filling
material shall be properly consolidated by watering and ramming, taking due
care that no damage is caused to the pipes.
Where the trenches are excavated in soil, the filling from the bottom of the
trench to the level of the centre line of the pipe shall be done by hand
compaction with approved earth in layers not exceeding 8 cm. Backfilling
above the level of the centre line of the pipes shall be done with approved
earth by hand compaction or other approved means in layers not exceeding
20 cm.
To ensure that the fill has been compacted as specified, field test shall be
carried out by the CONTRACTOR. The cost of the tests shall be borne by the
Contractor.
Field compaction test shall be carried out in difference stages of filling and
also after the fill to the entire height has been completed.
1.15.1 PLINTH FILLING
Plinth filling shall be carried out with approved material as described herein
before in layers, and compacted with mechanical compactor ENGINEER my
however permit manual compaction by hand tampers in case he is satisfied
that mechanical compaction is not possible. When filling reaches the finished
level, the surface shall be flooded with water, unless otherwise directed, for at
least 24 hours, allowed to dry and then the surface again compacted as
specified above to avoid settlements at a later stage. The finished level of the
filling shall be trimmed to the level / slope specified.
A compaction / road roller may be used only if permitted by ENGINEER. As
rolling proceeds, water sprinkling shall be done to assist consolidation. Water
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
24/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 24 of 52 WAPCOS LIMITED
shall not be sprinkled in case of sandy fill.
The compacted surface shall be properly shaped, trimmed and consolidated to
an even and uniform gradient. All soft spots shall be excavated and filled and
consolidated.
At some locations/areas, it may not be possible to use rollers because of
space restrictions, etc., CONTRACTOR will then be permitted to use
pneumatic tampers, rammers, etc. and he shall ensure proper compaction.
1.16 MATERIAL FOR THE WORK
1.16.1 CEMENT
The cement shall be procured from the approved Vendors of
AGENCO/APPDCL. Cement shall be Sulphate resistant cement conforming to
latest relevant IS codes. Changing of brands or type of cement within the
same structure or portions thereof shall be permitted only with approval of
PURCHASER.
CONTRACTOR will have to make his own arrangements at his cost for the
storage of adequate quantity of cement. Cement bags shall be stored in a dry
enclosed shed (storage under tarpaulins will not be permitted), well away fromthe outer walls and insulated from the floor to avoid contact with moisture from
ground and so arranged as to provide ready access. Damaged or reclaimed
or partly set cement will not be permitted to be used and shall be removed
from the site. Storage arrangements shall be such that there is no dead
storage. Not more than 12 bags shall be stacked in any tier. The storage
arrangement shall be approved by PURCHASER. Consignments of cement
shall be stored as received and shall be consumed in the order of their
delivery. The Engineer-in-Charge will issue OK Cards to Cement stacks and
that cement which is 'Okayed only shall be used. The stacking arrangement
and issue system will be approved by PURCHASER.
Cement held in storage for a period of ninety (90) days or longer from the date
of manufacture shall be tested for normal consistency, fineness, setting time
and compressive strength. Should at any time PURCHASER have reasons to
consider that any cement is defective, then irrespective of its origin, date ofmanufacture and/or manufacture's test, such cement shall be tested again
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
25/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 25 of 52 WAPCOS LIMITED
immediately as per Engineers instruction at reputed third party laboratory
and charges of the test to be borne by the contractor and until the results of
such tests are found satisfactory, it shall not be used in any work.
CONTRACTOR shall not be entitled to any claim of any nature on this
account.
TRANSPORTATION OF CEMENT
The Contractor shall make his own arrangement at his cost for transporting the
cement to his store and to the work spot and for handling, re-handling and
storing cement in good condition.
1.16.2 AGGREGATES
(a) "Aggregate" in general designates both fine and coarse inert materials
used in the manufacture of concrete.
(b) "Fine Aggregate" is aggregate most of which passes through 4.75 mm IS
sieve
(c) "Coarse Aggregate" is aggregate most of which is retained on 4.75 mm IS
sieve.
All fine and coarse aggregate proposed for use in the work shall be subjectedto the PURCHASER'S approval and after specified materials have been
accepted the source of supply of such materials shall not be changed without
prior approval of PURCHASER.
The materials shall be brought by the CONTRACTOR from the quarries
approved by the PURCHASER. For materials collected from quarries either
owned or controlled by the Government of Andhra Pradesh (or from private
bodies) or obtained from excavation for foundation and used in the work
covered by these specifications.
General approval of source of material or portion thereof shall not be
constructed that all materials taken form the source or portion thereof and the
CONTRACTOR will be held responsible for the specified quality of all such are
approved materials used in the work.
Aggregates shall except as noted above, consist of natural sands, crushed
stone and gravel from a source known to produce satisfactory aggregate for
concrete and shall be chemically inert, strong, hard, durable against
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
26/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 26 of 52 WAPCOS LIMITED
weathering, of limited porosity and free from deleterious materials that may
cause corrosion of the reinforcement or may impair the strength and/or
durability of concrete. The grading of aggregates shall be such as to produce a
dense concrete of specified strength and consistency that will work readily into
position without segregation and shall be based on the 'mix'' designs and
preliminary tests on concrete specified later.
SAMPLING AND TESTING
All sampling and tests of fine aggregate shall be in accordance with the
recommended Indian Standard Specifications. All tests shall be made by
contractor under the supervision of PURCHASER at contractor's expense.
Routine control tests of fine aggregate at various stages in aggregate
processing plant will be made by the contractor. The CONTRACTOR shall
provide such facilities as PURCHASER may consider necessary for the ready
procurement of representative test samples and testing. Samples of the
aggregate for mix design and determination of suitability shall be taken under
the supervision of PURCHASER and tested by the CONTRACTOR in
presence of Purchaser well in advance of the scheduled placing of concrete at
no extra cost.
STORAGE OF AGGREGATES
All coarse and fine aggregates shall be stacked separately in stock piles in the
material yard near the work site properly to avoid inter mixing of different
aggregates. Contamination with foreign materials shall be avoided. The
aggregates must be of specific quality not only at the time of unloading at site
but more so at the time of lading into mixer. Rakers shall be used for lifting, the
coarse aggregates. Coarse aggregates shall be piles in layers not exceeding
1.2 meters height to prevent coning or segregation. Each layer shall cover the
entire area of the stock pile before succeeding layers are stacked. Aggregates
that have become segregated shall be rejected. Rejected material after
remixing may be accepted, if subsequent tests demonstrate conformance with
required gradation.
SPECIFIC GRAVITY
Coarse aggregates having a specific gravity below 2.5 t/m3 (saturated surface
dry basis) shall not be used without special permission of PURCHASER.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
27/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 27 of 52 WAPCOS LIMITED
1.16.3 FINE AGGREGATE
Fine aggregate except as noted above, and for other than light weight
concrete shall consist of clean natural river sand conforming to IS: 383. The
sand shall be clean, sharp, hard, strong and durable and shall be free from
dust, vegetable substances, adherent coating, clay, alkali, organic matter,
mica, salt, or other deleterious substances, which can be injurious to the
setting qualities, strength/durability of concrete.The grading of fine aggregate
for concrete shall be within the limits of either zone I or zone II of the IS 383,
table 4.
SCREENING AND WASHING
Sand shall be prepared for use by such screening or washing, or both, as
necessary, to remove all objectionable foreign matter while separating the
sand grains to the required size fractions.
GRADATION
Unless otherwise directed or approved, the grading of sand shall be within the
limits indicated here under:
PERCENTAGE PASSING FOR
IS Sieve Grading Grading Grading GradingDesignation Zone I Zone II Zone III Zone IV10 mm 100 100 100 1004.75 mm 90-100 90-100 90-100 95-1002.36 mm 60-95 75-100 85-100 95-100
1.18mm 30-70 55-90 75-100 90-100
600 micron 15-34 35-59 60-79 80-100300 micron 5-20 8-30 12-40 15-50150 micron 0-10 0-10 0-10 0-15
Where the grading falls outside the limits of any particular grading zone of
sieves, other than 600 microns I.S. Sieve, by total amount not exceeding 5
percent, it shall be regarded as falling within that grading zone. This tolerance
shall not be applied to percentage passing the 600 micron I.S. Sieve or to
percentage passing any other sieve size on the coarse limit of Grading Zone I
or the finer limit of Grading zone IV Fine aggregates conforming to Grading
Zone IV shall not be used unless mix designs and preliminary tests have
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
28/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 28 of 52 WAPCOS LIMITED
shown its suitability for producing concrete of specified strength arid
workability.
FINENESS MODULUS
Sand shall conform to IS 383 Zone I or Zone II The fineness modulus is
determined by adding the cumulative percentages retained on the following IS
sieve sizes (4.75 mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron and 150
micron) and dividing the sum by 100.
SOUNDNESS
The average loss of weight of sand after 5 cycles of sodium sulphate
accelerated soundness test as specified in IS.2386 (part 5) shall not be more
than 10% and shall not be more than 15 % when magnesium sulphate solution
is used.
The Grading and fineness modulus of sand may be altered by PURCHASER
depending upon the requirements, suitability and availability. The contractor
shall procure process and supply the required sand at no extra cost.
1.16.4 COARSE AGGREGATE
Coarse aggregate for concrete, except as noted above and for other than light
weight concrete shall conform to IS: 383. This shall be of crushed stone and
shall be cleaned, and free form elongated flaky or laminated pieces, adhering
coatings, clay lumps, coal residue, clinkers, slag, alkali, mica, organic matter
or other deleterious matter.
It shall be roughly cubical in shape. The overall grading of the coarse
aggregate, viz., graded aggregate of nominal size 20mm shall conform to the
requirements specified in IS 383. The contractor shall, if required by the
engineer, obtain the specified grading by combining single aggregates in
proportions to give the specified grading.
SCREENING AND WASHING
Natural gravel and crushed rock shall be screened and/or washed for the
removal of dirt or dust coating, if so demanded by ENGINEER-IN-CHARGE.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
29/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 29 of 52 WAPCOS LIMITED
IS. Sieve Percentage passing for single sized aggregate of nominal size
Designation
63 mm 40 mm 20mm 16 mm 12.5 mm 10 mm
80mm 100 - - - - -
63 mm 85-100 100 - - - -40mm 0-30 85-100 100 - - -
20mm 0-5 0-20 85-100 100 - -
16 mm - - - 85-100 100-100 -
12.5 mm - - - - 85-100 100 ^
10 mm 0-5 0-5 0-20 0-30 0-45 85-100
4.75 mm - - 0-5 0-5 0-10 0-20
2.36mm - - - - - ' - 0-5
I.S. Sieve Percentage passing for graded aggregate of nominal size
Designation
40 mm 20mm 16 mm 12.5 mm
80mm 100 - - -
63 mm - - - -
40mm 95-100 100 - -
20mm 30-70- 95-100 100 100
16 mm - 90-100 -
12.5 mm ' - - - 90-100
10 mm 10-35 25-55 30-70 40-85
4.75 mm 0-5 0-10 0-10 0-10
2.36 mm - - - .
The Grading of coarse aggregate shall in general conform to the Grading as
given in IS.-383. The exact Grading of coarse aggregate for different items of
cement concrete works shall be approved by PURCHASER from time to time,
based on the laboratory tests. Such changes in the Grading shall be carried
out by CONTRACTOR at no extra cost.
The pieces shall be angular in shape and shall have granular or crystalline
surfaces. Friable, flaky and laminated pieces, mica and shale if present, shall
be only in such quantities that will not, in the opinion of the PURCHASER,
affect adversely the strength and/or durability of concrete. The maximum size
of coarse aggregate shall be the maximum size specified above but in no case
greater than 1/4th of the minimum thickness of the member, provided that the
concrete shall be placed without difficulty so as to surround all reinforcement
thoroughly and fill the corners of the form. For heavily reinforced concrete
members, the nominal maximum size of the aggregate shall be 5 mm less
than the clear distance between the main bar or 5mm less than the minimum
cover to the reinforcement whichever is smaller. The amount of fine particles
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
30/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 30 of 52 WAPCOS LIMITED
occurring in the free state or as loose adherent shall not exceed 1% when
determined by laboratory sedimentation tests as per IS:238
The limits for flakiness and elongation tests will be specified by PURCHASER
based on tests from time to time and the CONTRACTOR shall procure the
aggregates as per requirements without claiming for any extra rate.
After 24 hours immersion in water, a previously dried sample shall not have
gained more than 1% of its oven-dried weight in air as determined by IS 2386
WORKS TESTS ON AGGREGATES
During the course of the Contract, fine and coarse aggregates shall be tested
at site as often as required by the Engineer and at the Contractors expense.Tests shall be carried out in accordance with the methods specified in as
below, unless otherwise ordered by the purchaser.
WORKS TEST ON AGGREGATES
Particle size IS 2386 Part I
Silt content by field settling test IS 2386 Part I
Moisture content IS 2386 Part III
Organic impurities content IS 2386 Part II
1.16.5 WATER
Water used for concreting production and curing shall be as per IS 456 -2000
requirement. Water used for both mixing and curing shall be clean and free
from injurious amounts of oils, acids, alkalis, salts, sugar, organic materials or
other substances that may be deleterious to concrete or steel. Potable water is
generally considered satisfactory for mixing and curing of concrete.
The sample of water taken for testing shall represent the water proposed to be
used for concreting, due account being paid to seasonal variation. The sample
shall not receive any treatment before testing other than that envisaged in the
regular supply of water proposed for use in concrete. The sample shall be
stored in a clean container previously rinsed out with similar water.
The initial setting time of test block made with the appropriate cement and the
water proposed to be used shall not be less than 30 minutes and shall not
differ by more than +/-30 minutes from the initial setting time of control test
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
31/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 31 of 52 WAPCOS LIMITED
block, prepared with the same cement and distilled water. The test blocks shall
be prepared and tested in accordance with the requirements of IS: 4031.
1.16.6 REINFORCEMENT STEEL
REINFORCEMENT
All reinforcement bars for concrete structure shall be of CRS steel, grade Fe
500 with fusion epoxy coating of Minimum 175-300 microns conforming to
latest relevant IS codes. All reinforcement shall be corrosion resistant bar. The
bidder shall clearly indicate the coating system suggested on the
reinforcement or alternate system for corrosion resistance of reinforcement
and structure with proper technical specification.
STORAGE
The reinforcement bars shall not be kept in direct contact with the ground but
stacked on top of an arrangement of timber sleepers or the like.
If the reinforcing rods have to be stored for long duration, where storage for
more than three months is envisaged, they shall be coated with cement wash
before stacking and/or be kept under cover or stored as directed by
PURCHASER.
Fabricated rods shall be carefully stored to prevent the damage, distortion,
corrosion and deterioration.
LAPS
Laps and splices for reinforcement shall be shown on the drawings. Splices in
adjacent bars shall be staggered and the locations of all splices, except those
specified on the drawings, shall be approved by PURCHASER. The bars shall
not be lapped unless the length required exceeds the maximum available
lengths of bars at site.
BENDING
Reinforcing bars procured by the Contractor bent or in coils, shall be
straightened before they are cut to size. Straightening of bars shall be done in
cold and without damaging the bars. This is considered as the part of
reinforcement bending/fabrication work.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
32/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 32 of 52 WAPCOS LIMITED
All bars shall be accurately bent according to the sizes and shapes shown on
the detailed working drawings / bar bending schedules. They shall be bent
gradually by machine or other approved means. Reinforcing bars shall not be
straightened and rebent in a manner that will injure the material; bars
containing cracks or splits shall be rejected. They shall be bent cold, except
bars of over 25 mm in diameter which may be bent hot if specifically approved
by PURCHASER. Bars incorrectly bent shall be used only if the means used
for straightening and rebinding be such as shall not, in the opinion of
PURCHASER, injure the material. No reinforcement bars shall be bent when
in position in the work without approval, whether or not it is partially embedded
in hardened concrete. Bars having kinks or bends other than those requiredby design shall not be used.
FIXING
Reinforcement bars shall be accurately fixed by any approval means and
maintained in correct position shown in the drawings by the use of blocks,
spacers and chairs as per IS 2502 to prevent displacement during placing and
compaction of concrete. Bars intended to be in contact at crossing points shall
be securely bound together at all such points with 1.25 mm diameter soft
annealed steel wire. The vertical distances required between successive
layers of bars in beams or similar members shall be maintained by the
provision of mild steel spacer bars at such intervals that the main bars do not
perceptibly sag between adjacent spacer bars.
COVER
The cover for reinforcement bars shall be provided for the extremely exposure
condition as indicated in IS 456-2000.
INSPECTION
Erected and secured reinforcement bars shall be inspected and approved by
PURCHASER prior to placement of concrete.
1.17 SPECIFICATION FOR CONCRETE
1.17.1 MIX DESIGN
The concrete for all RCC works shall be as per specifications mentioned in
the Indian Standard and also to conform the design requirements.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
33/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 33 of 52 WAPCOS LIMITED
a) All the calculations relevant to the design of class of concrete mix.
b) The sieve analysis of aggregates which they proposed to use in the
works.
c) Full details of preliminary tests on concrete and
d) The weight of cement, sand and coarse aggregate to be adopted for
mixing.
Mix design shall be carried out as per IS: 10262 and IS: 456-2000. All the
preliminary tests and mix designs for all concrete works envisaged in the
contract shall be carried out by the contractor under the supervision of
Purchaser or a reputed third party concrete lab approved by the Purchaser.
The Contractor shall arrange all the materials, equipments, lab setup and
other resources required for mix design. Only those materials which are to be
used for Concrete production shall be used in mix design. PURCHASER shall
have powers to vary the proportions, water cement ratio and slump for the
specified work or works based on laboratory tests and the CONTRACTOR is
bound to adopt these changes on works without any extra cost.
The Contractor shall further note that the requirements of providing concrete of
specified quality in the field shall be his sole responsibility and he shall not be
eligible for any compensation in case the strengths obtained in the field do not
satisfy the criteria laid down, the work will be liable to rejection by
PURCHASER or a suitable reduction in the rate for concrete shall be effected
at the direction of the PURCHASER. The mix design shall be carried out with
approved state or Central Government Institute for the specified mix.
1.17.2 CONCRETE WORK
CONCRETE
The quality of concrete shall be of design mix specified in the drawing and
schedule of quantities.
The ingredients of the concrete such as fine and coarse aggregate shall be
measured by weight by means of an approved Batching Machine. Due
allowance shall be made to weight of water carried by the aggregate. The
actual amount added to the mixer being reduced as necessary. The decision
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
34/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 34 of 52 WAPCOS LIMITED
of the Engineer / Consultant in this regard shall be final and binding on the
contractor.
The water cement ratio shall be the minimum possible having regard to proper
compaction by the respective means specified. The Concrete shall be mixed
in the Batch mixing machine of approved type and capacity. Where coarse
aggregate is over 20 mm, the concrete shall be mixed only in non-tilting type
of mixers. The resulting concrete shall be a uniform workable mixture of the
specified.
The batching, mixing, placing in position of concrete shall be as per the
guidelines stipulated in ISI 456-2000.
1.17.3 SAMPLING AND TESTING OF CONCRETE
Sampling of concrete shall be done as per the provision made in the relevant
IS or as directed by the PURCHASER or his representative. The additional
test if ordered shall also be carried out as per the direction.
All water retaining structures shall be tested for water tightness as per the
provisions of IS: 3370
If RCC floor / roof are assumed to act as diaphragm transmitting lateral loads
to braced bays it shall be provided with shear connectors. However,
whenever large / number of cut-outs are provided in the floor slab, horizontal
floor bracings shall be provided below slab to transfer horizontal force to
columns without considering diaphragm action from slab.
The minimum frequency of sampling of concrete of each class/grade shall be
in accordance with Clause 15.2 of IS 456-2000. Such samples shall be drawn
on each day for each type of concrete. Sampling, testing and acceptance
criteria shall be as per IS 456-2000.
CONSISTENCY
Slumps tests shall be carried out as often as demanded by PURCHASER and
invariably from the same batch of concrete from which the test cubes are
made. Slump tests shall be done immediately after sampling.
Test cubes shall be made and tested in accordance with IS 456 - 2000. If the
concrete test cubes do not give the stipulated strengths, PURCHASERreserves the right to ask CONTRACTOR to dismantle such portions of the
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
35/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 35 of 52 WAPCOS LIMITED
work, which in his opinion are unacceptable and re-do the work to the
standard stipulated at CONTRACTOR'S cost.
The inspection and testing of concrete structures shall be done of IS: 456-
2000.
1.18 CURING
All concrete shall be cured by keeping it continuously damp for the period of
time required for complete hydration and hardening to take place. Preference
shall be given to the use of continuous sprays or ponded water, continuously
saturated coverings of sacking, canvas, hessian or other absorbent materials,
or approved effective curing compounds applied with spraying equipment
capable of producing a smooth, even-textured coat. Extra precautions shall be
exercised in curing concrete during cold and hot weather as outlined
hereinafter. The quality of curing water shall be the same as that used for
mixing concrete.
Certain types of finish or preparation for overlaying concrete must be done at
certain stages of the curing process and special treatment may be required for
specific concrete surface finish.
Curing of concrete made of high alumina cement and super-sulphated cement
shall be carried out as directed by ENGINEER-IN-CHARGE.
CURING WITH WATER
Fresh concrete shall be kept continuously wet for a minimum period of 10.
days from the date of placing of concrete, following a lapse of 12 to 14 hours
after laying concrete. The curing of horizontal surfaces exposed to the drying
winds shall however begin immediately after the concrete has hardened.
Water shall be applied to unformed concrete surfaces within 1 hour after
concrete has set. Water shall be applied to formed surface immediately upon
removal of forms. Quantity of water applied shall be controlled so as to prevent
erosion of freshly placed concrete.
CONTINUOUS SPRAYING
Curing shall be assured by use of an ample water supply under pressure in
pipes, with all necessary appliances of hose, sprinklers and spraying devices.
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
36/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 36 of 52 WAPCOS LIMITED
Continues fine mist spraying or sprinkling shall be used, unless otherwise
specified or approved by PURCHASER.
ALTERNATE CURING METHODS
Whenever, in the judgment of PURCHASER, it may be necessary to omit the
continuous spray method, a covering of clean sand or other approved means
such as wet gunny bags which will prevent loss of moisture from the concrete
may be used. No type of covering will be approved which would stain or
damage the concrete during or after the curing period. Covering shall be kept
continuously wet during the curing period.
For curing of concrete in pavements, side-wall, floors, flat roof or other level
surfaces, the ponding method of curing is preferred. The method of containing
the ponded water shall be approved by PURCHASER. Special attention shall
be given to edges and comers of the slabs to ensure proper protection to
these areas. The ponded areas shall be kept continuously filled with water
during the curing period.
CURING COMPOUNDS
Surface coating type curing compounds shall be used only under special
permission of PURCHASER. Curing compounds shall be liquid type white
pigmented, conforming to U.S. Bureau of Reclamation specification. No curing
compound shall be used on surfaces where future blending with concrete,
water or acid proof membrane, or painting is specified.
CURING EQUIPMENT
All equipment and materials required for curing shall be on hand and ready for
use before concrete is placed.
1.19 SPECIFICATION FOR CONSTRUCTION AND KEY JOINTS
Concrete shall be placed without interruption until completion of the part of the
work between predetermined construction joints, as specified hereinafter.
Time lapse between the pouring of adjoining units shall be as specified on the
drawings or as directed by PURCHASER.
If Stopping of concreting becomes unavoidable anywhere, a properly formed
construction joint shall be made where the work is stopped. Joints shall be
either vertical or horizontal, unless otherwise shown on drawings. In case of
-
7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..
37/52
APPDCLTechnical Specification
For
Sea Water Intake System
Sri Damodaram Sanjeevaiah
Thermal Power Station
2X800 MW
Tender DocumentVolume II_Book I_Chapter 1 Page 37 of 52 WAPCOS LIMITED
an inclined or curved member, the joint shall be at right angles to the axis of
the member. Vertical joints in walls shall be kept to minimum. Vertical joints
shall be formed against a stop Board; horizontal joints shall be level and
wherever possible, arranged so that the joint lines coincide with the
architectural features of the finished work. Battens shall be nailed to the form
work to ensure a horizontal line and if directed, shall also be used to form a
grooved joint. For tank walls and similar work, joints shall be formed as per IS:
3370. Concrete that is in the process of setting shall not be disturbed or
shaken by traffic either on the concrete itself or upon the shuttering. Horizontal
and vertical construction joints and shear keys shall be located and shall
conform in detail to the requirements of the plans unless otherwise directed byPURCHASER. Where not described, the joint shall be in accordance with the
following:
COLUMN JOINT
In a column, the joint shall be formed 75 mm below the lowest soffit of the
beams including haunches if any. In flat slab construction, the joints shall be
75 mm below the soffit of column capital. At least 2 hours shall elapse after
depositing concrete in columns, piers or walls, before depositing in beams,
girders or slabs supported thereon.
BEAMS AND SLABS JOINTS
Concrete in a beam shall be placed throughout without a joint but if the
p