Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

download Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

of 52

Transcript of Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    1/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 1 of 52 WAPCOS LIMITED

    CHAPTER - 1

    GUIDELINES OF DESIGN PRINCIPLE AND SPECIFICATIONS FOR MATERIALS

    AND WORKS

    1.1 INTRODUCTION

    This chapter provides broad guidelines for designing the different components

    of the work and also covers the specifications for material used for civil,

    structural building and architectural work. The bidder has to follow the relevant

    Indian Standard specification while designing the different components of the

    works. Wherever Indian Standard specifications are not available the bidder

    has to quote proper authority (or) code for the assumption made and method

    adopted and the bidder has to enclose the authority (or) code. Similarly for the

    procurement of material used for testing of materials unless specified in the

    tender the relevant provision of the appropriate bureau of Indian Standard

    (BIS) shall apply for all materials and workmanship. Where the relevant BIS

    do not exists; the latest version of the relevant British Standard specification

    (or) standard of the American society for testing material shall apply.

    1.2 SCOPE OF WORKS

    The work contemplated covers the design, manufacture, assembly, testing,

    supply, construction of shore based intake through open channel with two

    groynes, Stone protection works for groynes, dredging of offshore channel

    construction of approach channel (onshore and offshore channel),

    construction of desilting basin, Construction of forebay, Construction of pump

    house including sump, Laying and assembly of Intake and Outfall pipeline,

    Construction of approach road of single lane (Sectional drawing enclosed)

    along the pipeline route upto pump house, Construction of MCC room,

    chlorination room, Outfall Structure including diffuser, civil, structural,

    Mechanical, Electrical, Control & Instrumentation and architectural works as

    specified / required for safe and trouble-free operation of Sea water Intake and

    Outfall system for 2 X 800 MW Units and for future 1 X 800 MW Unit of

    SDSTPS at Nellore, Andhra Pradesh, India, including One (1) year Operation

    and maintenance of the commissioned plant with personnel, spares &

    consumables and imparting training to APPDCL/APGENCO staff on O&M of

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    2/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 2 of 52 WAPCOS LIMITED

    entire system. The major scope of works involved are the following but not

    limited to the same for civil and mechanical works of sea water intake and

    outfall system.

    Design, Construction of groynes, offshore channel of suitable

    size including stone protection works for groynes, dredging of

    offshore channel etc.

    Design, construction of onshore channel, desilting basin.

    Design, construction of forebay including counterfort retaining

    wall/RCC Diaphragm wall etc.

    Design, construction of Pump house including sump etc.

    Design, supply & installation of three (3) numbers Vertical

    Turbine pumps with all necessary electrical, mechanical

    accessories and provision of two (2) numbers future pumps

    Design, procuring, jointing and laying of factory made 2200 mm

    diameter and minimum 16 mm thick delivery/intake pipeline

    including 2 mm thick PU coating from pump house to terminal

    point (TP1) inside the plant with all necessary butterfly valves,

    air valves, sluice valves, thrust block ,anchor blocks, valve

    chambers, expansion joints etc.

    Design, procuring, jointing and laying of factory made 1800 mm

    diameter and minimum 14 mm thick Return/Outfall pipeline

    including 2 mm thick PU coating from terminal point (TP1) to

    diffuser point as specified with necessary butterfly valves, air

    valves, sluice valves, thrust block ,anchor blocks, valve

    chambers, expansion joints etc.

    Design, construction of approach road from plant boundary to

    pump house along the pipeline route.

    Design, supply & installation of three (3) nos. traveling water

    screens, coarse screens.

    Design, supply & installation of six (6) nos stop log gates and

    provision of two (2) numbers future requirement.

    Design, supply & installation of Cranes and Hoists as per

    requirement.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    3/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 3 of 52 WAPCOS LIMITED

    Design, supply & installation of Electro chlorination system for

    sea water to avoid biofouling in Intake pipeline with all necessary

    accessories etc.

    Surface preparation and necessary corrosion resistance painting

    for all equipment, piping, valves, structures, buildings, tanks,

    walls, platforms etc.

    One (1) year Operation and maintenance of the commissioned

    plant with personnel, spares & consumables and imparting

    training to APPDCL/APGENCO staff on O&M of system.

    Scope of works specified above is tentative and Bidder has to execute

    complete works for satisfactory functioning of entire Sea water intake & Outfall

    System. The Bidder shall quote for the Base scheme and can suggest

    alternative options with separate price which will not be considered for

    evaluation.

    The preliminary geotechnical investigation, hydrographic survey, topographic

    survey and oceanographic studies were conducted by the purchaser and

    preliminary report is available with Purchaser and will be furnished to the

    successful bidder for reference. However for detailed engineering and

    construction Bidder has to carry out necessary geotechnical investigation,

    hydrographic survey, topographic survey and oceanographic studies etc. as

    required.

    Any discrepancies or lack of inconsistency data found at a later date in

    Purchasers investigation shall not form the basis of any extra claim or time

    extension. Bidder shall take special care to assess exact nature and quantum

    of work involved both on shore and off shore area.

    The system design & construction shall be proven to meet all functional

    requirements and perform accurately and safely under the prevailing

    environmental and operating conditions without undue heating, vibration,

    wear, corrosion, aging, malfunction or other operating problems.

    All equipment, materials and instruments shall be supplied from reputed

    manufacturer and approved vendors of APPDCL/APGENCO and shall

    conform to relevant latest national / international standards.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    4/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 4 of 52 WAPCOS LIMITED

    The description of work given in the document is for broad understanding of

    the nature of the work. The bidder should acquaint himself with nature of

    work to be performed for continuous trouble-free operation.

    The details of civil, structural, architectural work involved that require design,

    drawing, material for construction are given below.

    Design and construction of groynes, dredging of Intake channel in the

    sea and desilting basin with proper embedment and other protective

    works ,concrete lining from onshore open channel to forebay, including

    Mechanical Components

    Design of Intake Pump House and associated Switchgear& control room

    and Electro Chlorination Plant room.

    Laying of partly underground, partly over ground and over Buckingham

    canal the intake pipeline up to the terminal point (TP1) which is at a

    distance of around 5.3 km from the proposed pump House.

    Laying of partly underground, partly over ground and over Buckingham

    canal the return flow water pipeline on land and off shore submarine pipe

    up to a Diffuser section as specified.

    The work to be performed shall also include all labour, consumables,

    equipment, temporary works, temporary storage sheds, temporary labour and

    staff colony, temporary site offices, construction plant, fuel supply, power,

    transportation including making arrangement of power where required and all

    incidental items not shown or specified but reasonably implied or necessary for

    the completion of civil works, all in strict accordance with the specifications,

    Latest codal requirements and including revisions and amendments there to as

    may be required during the execution of the work.All materials including cement, reinforcement steel, structural steel, etc. shall be

    arranged / procured by the Bidder.

    The work shall include setting up a complete testing laboratory in the field to

    carry out all relevant tests required for the civil works.

    The Contractor shall setup a quality control laboratory with all facilities to carry

    out the testing of all construction materials and field quality tests as per field

    quality plan (FQP)/ Specifications/relevant IS Codes. The contractor shall

    provide sufficient qualified and competent manpower for carrying out Lab testing

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    5/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 5 of 52 WAPCOS LIMITED

    and field quality control. The Contractor shall provide all facilities to carry out the

    test desired by the PURCHASER. If the contractor does not have facility for

    some tests, these tests should be got done from reputed third party Labs. All

    costs for testing will be borne by the Contractor for Quality Assurance (QA) &

    Quality Control (QC). The test certificates/lab reports of different construction

    materials shall be submitted by the contractor for PURCHASERs review and

    approval before incorporating the material in the work. The contractor shall also

    submit the Test reports of various tests of the works to the PURCHASER for

    review/Approval.

    All the documents (Soft & Hard Copy) shall be properly maintained and easily

    retrievable.

    The Contractor shall submit field quality plan (FQP) 15 days in advance for

    approval of the PURCHASER before commencement of the works.

    The work shall be carried out in accordance with the design / drawings to be

    developed by the Bidder and approved by the PURCHASER. For all onshore

    and offshore constructions and foundations, etc., necessary layout details are to

    be developed by the Bidder keeping in view the statutory & functional

    requirements of the system & facilities sufficient space and access shall be

    provided in the layout. Certain minimum requirements are indicated in this

    specification for guidance purpose only. However, the Bidders offer shall cover

    the complete requirements as per the best prevailing practices and to the

    complete satisfaction of the PURCHASER.

    All the standards and other technical requirements as covered in this

    specification and relevant code of practice shall be strictly adhered to by the

    Bidder in order to achieve the quality of work.

    The Bidder should fully apprise himself of the prevailing conditions at the

    proposed site, meteorological conditions like climate, rainfall, relative humidity,

    wind, storm and cyclones, visibility, oceanographic conditions, local conditions,

    site specific parameters and shall include for all such conditions, contingent

    measures in the bid, including those which may not have been specifically

    brought out in the specifications. The PURCHASER has carried out

    environmental parameter by engaging outside agency and the same may be

    availed if required for reference.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    6/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 6 of 52 WAPCOS LIMITED

    The bidder has to carry out all survey works such as bathymetry, topography

    and hydrographic survey in order to assess the bed profile of the sea and also

    to assess the quantum of dredging and also to decide the depth of founding for

    structural component.

    1.3 SUBMISSIONS OF DOCUMENTS

    The following documents are to be submitted for the approval of the

    PURCHASER, prior to commencement of fabrication. All drawings shall be of

    standard sizes (Metric System) and shall be made on AutoCAD format. Editable

    soft copies of Design calculations and design basis in original format and

    drawings in AutoCAD format shall be submitted. This will be addition to the hard

    copies that have to be submitted for the above items.

    Layout drawing of various facilities at onshore and offshore location, all

    pipeline routing drawings with coordinates, showing roads, bridges,

    culverts etc.

    Drawing showing underground facilities with co-ordinates of these

    facilities like buried pipes, buried cable, trenches, ducts, sewer, drains,

    sumps, pits, culverts, foundations, etc. along pipe routes.

    Architectural floor plans, elevations, cross-sections and perspective view

    of all buildings.

    Site leveling, area filling drawings indicating final grade levels of various

    areas along with survey drawings indicating the natural contours and

    spot levels of the natural ground, permanent features, etc.

    Basis of design of all buildings, facilities, services and structures. The

    Contractor shall get the design basis report approved by

    PURCHASER/Consultant prior to undertaking any detailed engineering

    works.

    Design calculations and drawings for foundations / sub-structure and

    superstructure of all buildings including pump houses and other all

    structures.

    Bidders reports on Hydraulic model studies on Intake Pump sump

    including forebay Numerical model studies on discharge water

    recirculation, quantity of littoral drift, hydrodynamics and sedimentation

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    7/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 7 of 52 WAPCOS LIMITED

    and Flume studies for gryones trunk section and round head section

    from reputed laboratory like IIT/CWPRS.

    Drawings of all architectural works including finish schedule, colour

    scheme (Both internal and external), doors & windows, flooring and false

    ceiling, etc.

    Design calculations and drawings for plumbing and building drainage.

    Write-up on various statutory requirements and their compliance for

    various buildings and facilities.

    Copy of all studies / investigations report carried out by the Bidder as per

    scope.

    Fabrication drawings all structural steel works (only for reference) &design calculations for important joint connections.

    Marking scheme identifying the equipment / pump lay down areas.

    All other designs, details / drawings or any other submission as indicated

    elsewhere in this specification and as required by the PURCHASER.

    Details of corrosion protection and anti-bio-fouling measures for all

    structures.

    All construction drawings shall include total quantity of concrete (grade

    wise), reinforcement steel (diameter wise) and structural steel (section

    wise).

    Type of dredger proposed to be engaged for dredging the sea bed to

    facilitate for intake channel.

    Report on the detail methodology for laying and anchoring offshore

    outfall pipeline.

    Report on the detailed methodology of construction of onshore pump

    house, forebay, desilting Basin, open channel and de-watering.

    Report on design and laying of onshore and offshore pipelines.

    1.4 LOCATION OF WORK

    1.4.1 LOCATION OF SHORE BASED INTAKE

    A tentative location and dimensions of Groynes has been shown in the

    tender drawing for drawing intake sea water. These drawings of groynes are

    for guidelines only; Bidder shall design groynes section as per requirement.

    The Intake channel will be protected by groynes to protect from siltation.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    8/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 8 of 52 WAPCOS LIMITED

    These groynes are rubble mound type structure with approximate length of

    185m. The intake channel of 30 m width and dredged up to -3.0 m CD contour

    in between two gryones one on south side and other on north side and sea

    water will be carried out on land by open channel excavated up to -3.0 m

    below CD and bottom width will be 5 m. This channel will be connected to

    desilting basin of bottom width 12m and excavated up to -4.0 m below CD and

    stone protection also provide to two groynes from scouring.

    1.4.2 INTAKE PUMP HOUSE AND FOREBAY

    Pump house structure shall be founded at a location shown tentatively at the

    tender drawing. A forebay will be provided in front of pump house to receive

    water from open channel. Functional requirement of the pump house is toreceive water and pumping it to main plant area through intake pipe line.

    A maintenance bay shall be provided with heavy vehicle entry facilities for

    erection and maintenance. A screen and gate handling bay shall be provided

    in the pump house for storing gates/screens whenever they are not in use.

    The storage bay shall be provided with crane access for hauling gates/screen

    and also with structures supporting and stacking them for.

    The foundation of Pump house including sump portion shall be designed on

    pile keeping in view of the soil conditions. The super structure of the pump

    house shall comprise of RCC design mix, construction the pump house will be

    provided with heavy duty EOT crane travelling over crane runway girders

    spanning between brackets. Suitable access and platform / walkway shall be

    provided for crane operation. The side cladding shall be of brick wall laid, and

    jointed in cement mortar as per specification. The roof shall have parapet and

    water proofing as per specification. The ground floor shall have heavy-duty

    floor finish. Adequate door /windows/ ventilators shall be provided as per

    specification. Vertical turbine pumps will be placed on RCC pump operating

    floor. Suitable hatch shall be kept on the floor to access the pump sumps by

    ladder.

    Forebay is located on the shore line side of the pump house as shown in

    tender drawings. The fore bay receives seawater through an onshore

    channel. The side walls and base slab shall be of RCC and foundation shall

    be based on soil conditions, Hand rails all along the side walls as per

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    9/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 9 of 52 WAPCOS LIMITED

    specification shall be provided for safety. The layout of forebay shall conform

    to the stipulation of Manual of Hydraulic Institute and BHRA.

    Annexed to the pump house there will be chlorination plant room, Electrical

    switchgear and control room. The building will be a RCC framed structure

    with brick wall side cladding. Minimum clear height under the roof of building

    shall be 4.50 m or more if required for adequate clearance. The building shall

    have toilet facilities. Adequate door/window / ventilators / louvers shall be

    provided in the above building. The MCC room and Chlorination room shall

    have vitrified tiles flooring with provision AC and false ceiling.

    1.4.3 INTAKE CHANNEL / OFFSHORE CHANNEL

    Intake / Offshore channel is proposed to be provided at sea side and it is to beprotected with two groynes. Intake channel will have 30 m width and dredged

    upto -3.0 m contour below CD. This channel will be extended up to 180 m in

    to the sea from High Tide Line and will be taken through open channel or

    onshore channel on land and connected to desilting basin.

    A desilting basin will be formed at appropriate location before Pump house

    as shown in the tender drawing. Size and depth of basin will be ascertained

    by hydraulic model study. Sludge removal facilities will provided in the

    desilting basin so that it can be cleaned without interrupting the water flow to

    the pump house or generation at power plant.

    [

    1.4.4 BRIDGE OVER BUCKINGHAM CANAL WITH APPROACH RAMP &CROSS OVER BRIDGE

    The cross over structure for laying / taking the Intake & Outfall pipelines and

    roadway wherever required shall be RCC of mix design concrete. The

    minimum height shall 8 m keeping in view of navigation under the bridge. The

    width of bridge shall fix considering diameter of Intake and outfall pipeline,

    sufficient space for inspection and walking and approach road etc. The

    foundation of bridge shall be designed on pile keeping view of soil conditions

    for further details refer drawing enclosed

    1.4.5 LAYING OF INTAKE PIPELINE

    Intake pipeline from Pump house shall be laid up to the terminal point (TP1)

    and these pipeline is partially over ground and partially buried below ground

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    10/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 10 of 52 WAPCOS LIMITED

    level and minimum 1m to be maintained between top of pipeline and existing

    RL of ground. The work shall include construction of valve chambers/manhole

    chambers/sludge pits and sub base layer etc. The Intake pipeline shall be

    anchored properly for the exposed pipeline and wherever necessary at bend

    and level difference shall be provided with thrust blocks. The backfilling shall

    be done by the excavated soil to the maximum extent possible and it shall be

    properly consolidated / compacted.

    1.4.6 LAYING OF RETURN FLOW / OUTFALL PIPELINE UP TO DIFFUSERPOIN

    A tentative location of return flow / Outfall pipeline is shown in the tender

    drawing. The outfall pipeline is to be laid partially over ground and partially

    buried below ground level and minimum 1m to be maintained between top of

    pipeline and existing RL of ground and to be taken upto the diffuser point in

    sea as specified and thereafter it shall be taken by suitable means depending

    upon the sea bed level.

    The outfall pipeline shall terminate at the diffuser section, designed to

    promote rapid mixing and dilution with surrounding sea water. A multi port

    diffuser system shall discharge the reject water into the sea. The diffuser portshall consist of riser pipes projecting up from the diffuser pipeline that is

    buried beneath the sea and shall be properly anchored. The diffuser head will

    be encased in concrete for protection against ship anchors and suitable case

    should be also provided. The diffuser structure shall be firmly founded in the

    seabed below the scour depth. Additional concrete collar blocks shall be

    placed over the diffuser to increase the stability. Marker buoys shall be

    located around the diffuser head if needed.

    The design and construction of offshore concrete and other type of structure

    like diffuser shall conform to the followings

    Recommendation for the design and construction of concrete marine

    structures

    Relevant Indian Codes of practices IS 4651 Part I to Part V, IS 9556, 9527

    and other latest codes etc.

    1.5 GEOTECHNICAL INVESTIGATION AND FOUNDATION SYSTEM

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    11/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 11 of 52 WAPCOS LIMITED

    The Bidder shall carry out his own geotechnical investigation in all works before

    commencing detailed design and working drawings for finding out the allowable

    bearing pressures, expected settlements, type of foundations, etc. as per the

    relevant Bureau of Indian Standard. The soil investigation report shall be

    submitted to the PURCHASER for approval and the approved report shall

    become the basis for design of sub-structure. Approval of the PURCHASER

    shall in no way relieve the contractor of his sole responsibility in regard to

    stability and safety of the structure.

    1.6 REQUIREMENT OF FOUNDATIONS DESIGN

    All foundation system shall be as per the recommendation of soil investigation

    report furnished by Bidder. The foundation system will comprise both Pilefoundations as well as isolated / strip / raft foundations depending on Intensity

    of loading and settlement criteria and based on the bearing capacity of the

    soil.

    For design of foundations, net allowable bearing capacity in different strata

    shall be considered based on the soil investigation report.

    The foundation shall be designed for the maximum bending moment that

    arrived from various combinations of loading.

    In case of presence of high water table, necessary dewatering shall have to

    be made in order to carry out the excavation without any side collapse. In

    case, deep well point system is required, the same shall also be provided. In

    addition to above, at certain places sheet piling to support sides of

    excavations may also be required. Scheme for dewatering and design with all

    computations and back-up data of dewatering and sheet piling shall be

    submitted for PURCHASERs information.

    The founding level shall be decided as per functional requirement. The bottom

    of excavation shall be properly compacted prior to casting of bottom slab of

    trenches. The depth of foundation shall be fixed based on Safe bearing

    capacity of soil.

    Backfilling around foundations shall be carried out with excavated materials in

    layers not exceeding 20 cm thickness and each layer shall be compacted to

    95% standard proctor density for cohesive soil and to 85% of relative density

    for non-cohesive soils.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    12/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 12 of 52 WAPCOS LIMITED

    For open foundations, the total permissible settlement and differential

    settlement will be as per latest code of practice and from functional

    requirements whichever is more stringent. However total settlements of

    foundation resting on soil will be restricted to following:

    a) Isolated/ Strip footing of width up to 6.0m : 25 mm

    b) Footing of width greater than 6.0m (raft) : 50 mm

    1.6.1 CODES AND STANDARDS

    a) Internationally accepted design Codes and Standards where Indian

    Codes are not available and which are equivalent to Indian Standards.

    b) National Building Code of India.

    c) "Accepted Standards" and "Good Practice" listed in the appendix to

    National Building Code of India.

    d) IS-1200: Method of measurement of Building and Civil Engineering

    Works.

    e) IS-1256: Code of Practice for Building By laws.

    f) IS-456 : Code of Practice for Plain and reinforced concrete.

    In addition to the above, the stipulation in the relevant code for each item of

    work shall be followed.

    1.6.2 FOUNDATIONS

    a) IS-1904 : Code of practice for design and construction of

    foundations & soils.

    b) IS-2950 : Code of practice for design and construction of raft

    foundations.

    c) IS-2974 : Code of practice for design and construction of

    Machine foundations (all parts).

    d) IS 2911 : Code of practice for Design and Construction of Pile

    Foundation. (All parts)

    1.6.3 LOADING

    a) IS-875 : Code of practice for design loads for buildings and

    structures - loading standards (all parts).

    b) IRC 6 : I.R.C loading classification.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    13/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 13 of 52 WAPCOS LIMITED

    1.6.4 ROOF AND FLOORING

    a) IS-2204 : Code of practice for construction of reinforced

    concrete shell roof.

    b) IS-3201 : Criteria for the design and construction of precast

    concrete trusses and purlins.

    c) IS-809 : Rubber flooring materials for general purposes.

    e) IS-1195 : Bitumen mastic for flooring.

    f) IS-1196 : Code of practice for laying bitumen mastic flooring.

    h) IS-1237 : Cement concrete flooring tiles.

    i) IS-1443 : Code of practice for laying and finishing of cement

    concrete flooring tiles.

    j) IS-2114 : Code of practice for laying in situ terrazzo floor finish.

    k) IS-2571 : Code of practice for laying in situ cement concrete

    flooring.

    l) IS-5491 : Code of practice for laying in situ granolithic concrete

    floor topping.

    m) IS-5766 : Code of practice for laying burnt clay brick flooring.

    n) IS-1197 : Code of practice for laying of rubber floors.

    o) IS-2441 : Code of practice for fixing ceiling coverings.

    1.6.5 WATER PROOFING

    a) IS-1322 : Bitumen felts for waterproofing and damp proofing.

    b) IS-1346 : Code of practice for waterproofing of roofs with bitumen

    felts.

    c) IS-1609 : Code of practice for laying damp proof treatment using

    bituminous felts.

    d) IS-3036 : Code of practice for laying lime concrete for a

    waterproofed roof finish.

    e) IS-3037 : Bitumen mastic for use in waterproofing of roofs.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    14/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 14 of 52 WAPCOS LIMITED

    f) IS-3067 : Code of practice for general design, details and

    preparatory work for damp proofing and water proofing

    of buildings.

    g) IS-3384 : Bitumen primer for use in water proofing and damp

    proofing.

    h) IS-4365 : Code of practice for application of bitumen mastic for

    waterproofing of roofs.

    1.6.6 EARTHQUAKE RESISTANT DESIGN

    a) IS-1893 : Criteria for earthquake resistant design of

    structures.

    b) IS-4326 : Code of practice for earthquake resistant design

    1.6.7 STRUCTURAL STEELWORK

    a) IS-800 : Code of practice for general construction in steel.

    Part-I: Load and permissible stresses.

    Part-II: Fabrication, Galvanising, Inspection and

    Packing.

    c) IS-806 : Code of practice for use of steel tubes in general

    building construction.

    d) IS-808 : Rolled steel beams, channels and angle sections.

    e) IS-813 : Scheme of symbols for welding.

    f) IS-814 : Covered electrodes for manual metal arc welding of

    carbon and carbon manganese steel.

    g) IS-816 : Code of practice for use of metal arc welding for

    general construction in mild steel.

    h) IS-817 : Code of practice for training and testing of metal arc

    welders.

    i) IS-818 : Code of practice for safety and health requirements in

    electric and gas welding and cutting operation.

    j) IS-819 : Code of practice for Resistance spot welding for light

    assemblies in Mild Steel.

    k) IS-919 : Recommendations for limits and fits for engineering.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    15/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 15 of 52 WAPCOS LIMITED

    l) IS-1024 : Code of practice for use of welding in Bridges and

    Structures subjected to Dynamic loading.

    m) IS-1161 : Steel tubes for structural purposes.

    n) IS-1182 : Recommended practice for Radiographic Examinationof Fusion Welded Butt joints in steel plates.

    1.7 ENVIRONMENTAL PROTECTION

    Chapter on Corporate Responsibility for Environmental Protection (CREP)

    published in Gazette of India dated 27.08.2003.

    1.8 LOADING ON STRUCTURES AND FOUNDATIONS

    1.8.1 GENERAL

    All structures and buildings including Pump House, Water Retaining

    structures, desilting basin and various other works including Site leveling,

    Approach roads, Drains, Sewers, etc., are covered in this specification. In

    case of marine structures, environmental forces due to wave, current &

    sediment loads, etc. shall also be considered and latest design standard

    practices shall be followed.

    Structures shall be designed for the most critical combinations of loads, as

    stipulated in IS 456 2000 and other latest code as applicable for marinestructure.

    1.8.2 DEAD LOADS

    Dead loads shall include the weight of structure complete with finishes,

    fixtures and partitions.

    1.8.3 IMPOSED LOADS

    The imposed load to be considered for the design of various structures shall

    be based on IS 875 all parts of latest edition and IS 456-2000 with latest

    editions.

    In addition to the imposed load as prescribed in the relevant IS equipment

    load, erection, operation and maintenance load shall be considered for

    designing the structure.

    1.8.4 EQUIPMENT LOADS

    Loads of all equipment like Pumps, Pump Motor, Cooling Equipment,

    Electrical Control and Relay Panels, Cable load, Pipe load (static and

    dynamic), stop log gates, trash racks, traveling water screen, Tanks etc., shall

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    16/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 16 of 52 WAPCOS LIMITED

    be considered over and above the imposed loads as per the manufacturers

    recommendations. Loads due to thermal expansion and hydraulic thrust of

    pipes shall also be considered.

    1.8.5 CRANE LOADSFor crane loads, an impact factor of 25% and lateral crane surge of 10% (of

    lifted weight + trolley weight) shall be considered in the analysis of frame

    according to the provisions of IS : 875. The longitudinal crane surge shall be

    5% of the static wheel load.

    1.8.6 WIND LOADS (WL)

    Wind loading will be in accordance with latest edition of Indian Standard Code

    IS: 875 (Part-3) for a basic wind speed of 50 m/sec (or) for prevailing andobserved wind speed at site.

    1.8.7 EARTHQUAKE LOADS (EL)

    The lateral forces will be established in accordance with the recommendations

    of IS-1893. The site falls in Zone-III as per the classification of earthquake

    zone.

    The various site specific seismic parameters for the design

    1) Peak ground horizontal acceleration (PGA)MCE : 0.09g

    2) Peak ground horizontal acceleration (PGA)DBE : 0.05g

    3)Reduction factor (R) is to be applied to the site specificdesign horizontal acceleration spectral coefficients toobtain the design acceleration spectra

    a)For ordinary moment resisting steel frames withconcentric braces designed and detailed as per IS : 800

    : 4.0

    b)For ordinary moment resisting steel frames designed withconcentric braces and detailed as per IS : 800

    : 4.0

    c) For special moment resisting RC frames designed anddetailed as per IS: 456 and IS: 13920. : 5.0

    d) for steel chimney : 2.0

    e)For design of equipment resting on ground, reductionfactor should be taken as per IS code:1893 (Part 4) :2005

    Note: g = Acceleration due to gravity1.8.8 CONSTRUCTION LOADS

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    17/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 17 of 52 WAPCOS LIMITED

    The integrity of the structures shall be maintained without use of temporary

    framing, struts or ties and cable bracing, so far as possible. However,

    construction or crane access considerations may dictate the use of temporary

    structural systems. Special studies shall be made and documented to ensure

    the stability and integrity of the structures during any periods involving use of

    temporary bracing systems.

    1.8.9 TAMPERATURE LOADS

    For temperature loading, the total temperature variation shall be considered

    as 2/3 of the average maximum annual variation in temperature. The average

    maximum annual variation in temperature for this purpose shall be taken as

    the difference between the mean of the daily minimum ambient temperatureduring the coldest month of the year and mean of daily maximum ambient

    temperature during the hottest month of the year. The structure shall be

    designed to withstand stresses due to 50% of the total temperature variation.

    Suitable expansion joints shall be provided in the longitudinal direction

    wherever necessary

    The maximum distance of the expansion joints shall be as per the provisions

    of IS: 800 and IS: 456 for steel and concrete structures respectively.

    1.8.10 WAVE LOADS

    The wind load shall be as per IS 4651Part I to Part V shall be referred.

    LOAD COMBINATION

    The structure has to be analyzed for various combination of loading as

    prescribed in the latest relevant code.

    1.9 ANALYSIS METHODOLOGY

    Analysis of building / structure shall be carried out by 3D (Space frame

    method) or by 2D depending on the type of structure and load details.

    For analysis of structure, software like STAAD Pro of latest version shall be

    used. For design of various structural elements like foundations, columns,

    beams, slab etc. in-house developed software or STAAD Pro shall be used

    wherever applicable / possible.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    18/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 18 of 52 WAPCOS LIMITED

    1.10 DESIGN CRITERIA

    The underground Intake water sumps are RCC water retaining structures and

    shall be designed according to IS- 3370. In addition to design of structural

    elements as uncracked section, limitation on crack width of 0.10 mm on bothfaces, considering severe exposer condition, shall be checked as per IS-456.

    All components of the structure are to be designed for hydrostatic pressure,

    earth pressure and also by following various loading condition as given below

    i) Inside empty, but at outside, ground water is at FGL surcharge

    load.

    ii) Inside filled up with water up to full height of the basin and no

    lateral pressure from outside of wall.

    The dividing wall of the reservoir shall be designed considering one

    compartment is empty and other being filled up with water.

    iii) The base slab shall be checked against full hydrostatic uplift of

    ground water without taking consideration of pressure release

    valve. However in fore bay of the pump house they may be

    provided subject to approval by the PURCHASER.

    The RCC floor slab supporting pumps shall be checked for induced dynamic

    load during sudden pump shut off condition. The pump floor shall also be

    checked against resonance during normal operating condition.

    STABILITY OF STRUCTURES

    Design shall be checked against buoyancy due to the ground water during

    construction and maintenance stages for structure like underground storage

    tanks, pits, trenches, basements, etc. Minimum factor of safety of 1.5 against

    buoyancy shall be ensured considering empty condition inside and ignoring

    the superimposed loading. for purpose of calculating downward load due to

    any overburden, the mass located vertically above and the inclined portion

    depending on the angle of soil. The projected area of the base slab shall be

    taken into consideration.

    All building sub structure including pump houses shall be checked for sliding

    and overturning stability during both construction and operating conditions for

    various combinations of loads. Factor of safety for these cases shall be taken

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    19/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 19 of 52 WAPCOS LIMITED

    as mentioned in IS: 456 and other relevant IS codes. However following

    minimum factor of safety shall be followed.

    a) Factor of safety against overturning due to wind, seismic or other

    lateral load shall be as per clause 20.1 of IS: 456.

    b) Factor of safety against sliding shall be 1.5 minimum.

    c) Factor of safety against uplift due to hydrostatic forces shall be 1.2 and

    due to any other loads shall be 1.5.

    Stability of the structure shall also be investigated for loading conditions

    during construction, repair or other temporary measures. Lower factor of

    safety may be used for such loading conditions as per relevant IS codes.

    1.11 ARCHITECTURAL CONCEPTS

    Intake Pump House shall be architecturally treated in such a way that it will be

    aesthetically pleasing and satisfying all functional requirements. The

    architectural treatment shall be compatible with the surroundings, taking full

    consideration of climatic conditions and building orientation.

    1.12 SITE VISIT AND SURVEY

    The Bidder shall visit the site and assess the site conditions and to ascertain

    the incidental work required to be carried out to commence the main work &

    accordingly the cost is to be considered in his offer.

    CONTRACTOR shall carry out the survey of the site before excavation and set

    properly all lines and establish levels for various works such as earthwork in

    excavation for grading, basement, foundations, plinth filling, roads, drains,

    cable trenches, pipelines, etc. Such survey shall be carried out by taking

    accurate cross sections of the area perpendicular to established reference /

    grid lines at 5m intervals or as determined by ENGINEER based on ground

    profile. These shall be checked by ENGINEER and thereafter properly

    recorded.

    1.13 SITE CLEARING

    The area to be excavated / filled shall be cleared of fences, trees, plants, logs,

    stumps, and bush vegetation, rubbish, slush, etc. and other objectionable

    matter. If any root or stumps of trees are met during excavation, they shall also

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    20/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 20 of 52 WAPCOS LIMITED

    be removed. The material so removed shall be burnt or disposed off as

    directed by ENGINEER. Where earth fill is intended, the area shall be stripped

    of all loose/soft patches, top soil containing objectionable matter/materials

    before fill commence.

    The CONTRACTOR shall have to clean the site before the work is

    commenced and after completion. The rates quoted shall be inclusive of all

    charges likely to be incurred in carrying out the work of site clearance, initial &

    final and shall also hold good under all conditions of weather.

    Any minerals of any description whatsoever and all precious stones, treasures,

    relics, antiques and other similar things that may be found discovered on the

    site shall remain the property of Government and the CONTRACTOR shall

    duly intimate the PURCHASER or any person duly authorized by him to

    receive such property.

    After completion of the work and before handing over the completed work to

    the PURCHASER, the CONTRACTOR shall remove all unused and waste

    material, remove temporary structures, ramps, platforms, etc., lying in the

    vicinity of completed work and dispose off as directed by the PURCHASER.

    Further, temporary structures for storing water etc., labour sheds or any other

    sheds put up by the CONTRACTOR for facility of his work, shall be

    demolished completely and waste materials disposed. The work site and other

    areas, which were in his possession in connection with the execution of work,

    should not present any unsightly or ugly appearance. The completed work will

    not be taken over by the Engineer-in-charge, unless the final clearance of the

    site is done as mentioned above.

    1.14 EARTH EXCAVATION

    Excavation shall be carried out as specified in the specification. Filling and

    compaction shall also be carried out as specified.

    Excavation for permanent work shall be taken out to such widths, lengths,

    depths and profiles as are shown on the drawings or such other lines and

    grades as may be specified by ENGINEER. Rough excavation shall be carried

    out to a depth of 150 mm above the final level. The balance shall be

    excavated with special care. Soft pockets shall be removed even below the

    final level and extra excavation filled up as directed by ENGINEER. The final

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    21/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 21 of 52 WAPCOS LIMITED

    excavation, if so instructed by ENGINEER, should be carried out just prior to

    laying the mud-mat.

    CONTRACTOR may, for facility of work or similar other reasons excavate, and

    also backfill later, if so approved by ENGINEER, at his own cost, outside the

    lines shown on the drawings or directed by ENGINEER. Should any

    excavation be taken below the specified elevations, CONTRACTOR shall fill it

    up with concrete of the same class as in the foundation resting thereon, up to

    the required elevation. No extra payment shall be claimed by CONTRACTOR

    on this account.

    All excavations shall be done to the minimum dimensions as required for

    safety and working facility. Prior approval of ENGINEER shall be obtained by

    CONTRACTOR in each individual case, for the method he proposes to adopt

    for the excavation, including dimensions, side slopes, dewatering, disposal,

    etc. The approval, however, shall not any way relieve CONTRACTOR of his

    responsibility for any consequent loss or damage. The excavation must be

    earned out in the most expeditious and efficient manner. Side slopes shall be

    as steep as will stand safely for the actual soil conditions encountered. Every

    precaution shall be taken to prevent slips. Should slips occur, the slipped

    material shall be removed and the slope dressed to a modified stable slope.

    Removal of the slipped earth will not be paid for.

    In case any rock is obtained from excavation may be used for filling and

    leveling to indicate grades without further breaking. In such an event, filling

    shall be done in layers not exceeding 50 cm approximately. After rock filling to

    the approximate level indicated above has been carried out, the voids in the

    rocks shall be filled with finer materials such as earth, broken stone, etc. and

    the area flooded so that finer materials fill up the voids. Care shall be taken to

    ensure the finer fill material does not get washed out. Over the layer so filled, a

    100 mm thick mixed layer of broken material and earth shall be laid and

    consolidation carried out.

    Excavation shall be carried out with such tools, tackles and equipment as

    described.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    22/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 22 of 52 WAPCOS LIMITED

    For all foundations below ground water table, excavation shall be done first

    just up to ground water level and further excavation to founding level shall be

    done just before concreting. As soon as founding strata is reached, lean

    concrete mud mat shall be placed and concreting of foundation shall be

    carried out with minimum loss of time. During entire operation, excavation

    shall be kept dry by dewatering. CONTRACTOR shall programme his work to

    ensure that the above procedure is strictly followed including providing

    facilities for pumping of water to drain out the water and also to avoid any side

    collapse.

    APPLICABLE CODES

    The following Indian Standard codes unless otherwise specified herein, shall

    be applicable. In all case, the latest revision of the codes shall be referredto.

    (a) IS:783 Code of practice for laying of concrete pipes

    (b) IS:1200 Method of Measurement of Building works. (Parts 1 to 28)

    (c) IS:2720 Method of test for soils

    Part-2 Determination of Water Content

    Part-7 Determination of Water content-Dry Density relation usingLight compaction

    Part-8Determination of Water Content-Dry Density relation usingHeavy Compaction

    Part-28Determination of Dry Density of Soils in-place, by the Sandreplacement Method

    Part-29Determination of Dry Density of Soils in-place, by the CoreCutter Method.

    (d) IS:3764 Safety code for excavation work

    1.15 REFILLING AND COMPACTION

    For filling the trench excavated material including the grabbed materials may

    be used with the approval of Engineer / Consultant. The sand used for this

    purpose shall free from boulders, rubbish, clay, silt etc., If good quality sand is

    not available for the above purpose in full or part, required quantity of sea

    sand shall be quarried and transported to the site of work. The payment for

    such transportation shall be made under relevant item. The contractor shall

    quarry the required quantity of sea sand from the nearby area.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    23/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 23 of 52 WAPCOS LIMITED

    The sand required for filling shall be dumped and consolidated by approved

    means. Payment shall be made only for the completed profile based on levels

    taken before and after construction.

    In case the sea sand is used for filling it should be thoroughly washed before

    use.

    Filling in trenches above pipes and drains shall be commenced as soon as the

    joints of pipes and drains have been tested and passed. The back-filling

    material shall be properly consolidated by watering and ramming, taking due

    care that no damage is caused to the pipes.

    Where the trenches are excavated in soil, the filling from the bottom of the

    trench to the level of the centre line of the pipe shall be done by hand

    compaction with approved earth in layers not exceeding 8 cm. Backfilling

    above the level of the centre line of the pipes shall be done with approved

    earth by hand compaction or other approved means in layers not exceeding

    20 cm.

    To ensure that the fill has been compacted as specified, field test shall be

    carried out by the CONTRACTOR. The cost of the tests shall be borne by the

    Contractor.

    Field compaction test shall be carried out in difference stages of filling and

    also after the fill to the entire height has been completed.

    1.15.1 PLINTH FILLING

    Plinth filling shall be carried out with approved material as described herein

    before in layers, and compacted with mechanical compactor ENGINEER my

    however permit manual compaction by hand tampers in case he is satisfied

    that mechanical compaction is not possible. When filling reaches the finished

    level, the surface shall be flooded with water, unless otherwise directed, for at

    least 24 hours, allowed to dry and then the surface again compacted as

    specified above to avoid settlements at a later stage. The finished level of the

    filling shall be trimmed to the level / slope specified.

    A compaction / road roller may be used only if permitted by ENGINEER. As

    rolling proceeds, water sprinkling shall be done to assist consolidation. Water

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    24/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 24 of 52 WAPCOS LIMITED

    shall not be sprinkled in case of sandy fill.

    The compacted surface shall be properly shaped, trimmed and consolidated to

    an even and uniform gradient. All soft spots shall be excavated and filled and

    consolidated.

    At some locations/areas, it may not be possible to use rollers because of

    space restrictions, etc., CONTRACTOR will then be permitted to use

    pneumatic tampers, rammers, etc. and he shall ensure proper compaction.

    1.16 MATERIAL FOR THE WORK

    1.16.1 CEMENT

    The cement shall be procured from the approved Vendors of

    AGENCO/APPDCL. Cement shall be Sulphate resistant cement conforming to

    latest relevant IS codes. Changing of brands or type of cement within the

    same structure or portions thereof shall be permitted only with approval of

    PURCHASER.

    CONTRACTOR will have to make his own arrangements at his cost for the

    storage of adequate quantity of cement. Cement bags shall be stored in a dry

    enclosed shed (storage under tarpaulins will not be permitted), well away fromthe outer walls and insulated from the floor to avoid contact with moisture from

    ground and so arranged as to provide ready access. Damaged or reclaimed

    or partly set cement will not be permitted to be used and shall be removed

    from the site. Storage arrangements shall be such that there is no dead

    storage. Not more than 12 bags shall be stacked in any tier. The storage

    arrangement shall be approved by PURCHASER. Consignments of cement

    shall be stored as received and shall be consumed in the order of their

    delivery. The Engineer-in-Charge will issue OK Cards to Cement stacks and

    that cement which is 'Okayed only shall be used. The stacking arrangement

    and issue system will be approved by PURCHASER.

    Cement held in storage for a period of ninety (90) days or longer from the date

    of manufacture shall be tested for normal consistency, fineness, setting time

    and compressive strength. Should at any time PURCHASER have reasons to

    consider that any cement is defective, then irrespective of its origin, date ofmanufacture and/or manufacture's test, such cement shall be tested again

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    25/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 25 of 52 WAPCOS LIMITED

    immediately as per Engineers instruction at reputed third party laboratory

    and charges of the test to be borne by the contractor and until the results of

    such tests are found satisfactory, it shall not be used in any work.

    CONTRACTOR shall not be entitled to any claim of any nature on this

    account.

    TRANSPORTATION OF CEMENT

    The Contractor shall make his own arrangement at his cost for transporting the

    cement to his store and to the work spot and for handling, re-handling and

    storing cement in good condition.

    1.16.2 AGGREGATES

    (a) "Aggregate" in general designates both fine and coarse inert materials

    used in the manufacture of concrete.

    (b) "Fine Aggregate" is aggregate most of which passes through 4.75 mm IS

    sieve

    (c) "Coarse Aggregate" is aggregate most of which is retained on 4.75 mm IS

    sieve.

    All fine and coarse aggregate proposed for use in the work shall be subjectedto the PURCHASER'S approval and after specified materials have been

    accepted the source of supply of such materials shall not be changed without

    prior approval of PURCHASER.

    The materials shall be brought by the CONTRACTOR from the quarries

    approved by the PURCHASER. For materials collected from quarries either

    owned or controlled by the Government of Andhra Pradesh (or from private

    bodies) or obtained from excavation for foundation and used in the work

    covered by these specifications.

    General approval of source of material or portion thereof shall not be

    constructed that all materials taken form the source or portion thereof and the

    CONTRACTOR will be held responsible for the specified quality of all such are

    approved materials used in the work.

    Aggregates shall except as noted above, consist of natural sands, crushed

    stone and gravel from a source known to produce satisfactory aggregate for

    concrete and shall be chemically inert, strong, hard, durable against

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    26/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 26 of 52 WAPCOS LIMITED

    weathering, of limited porosity and free from deleterious materials that may

    cause corrosion of the reinforcement or may impair the strength and/or

    durability of concrete. The grading of aggregates shall be such as to produce a

    dense concrete of specified strength and consistency that will work readily into

    position without segregation and shall be based on the 'mix'' designs and

    preliminary tests on concrete specified later.

    SAMPLING AND TESTING

    All sampling and tests of fine aggregate shall be in accordance with the

    recommended Indian Standard Specifications. All tests shall be made by

    contractor under the supervision of PURCHASER at contractor's expense.

    Routine control tests of fine aggregate at various stages in aggregate

    processing plant will be made by the contractor. The CONTRACTOR shall

    provide such facilities as PURCHASER may consider necessary for the ready

    procurement of representative test samples and testing. Samples of the

    aggregate for mix design and determination of suitability shall be taken under

    the supervision of PURCHASER and tested by the CONTRACTOR in

    presence of Purchaser well in advance of the scheduled placing of concrete at

    no extra cost.

    STORAGE OF AGGREGATES

    All coarse and fine aggregates shall be stacked separately in stock piles in the

    material yard near the work site properly to avoid inter mixing of different

    aggregates. Contamination with foreign materials shall be avoided. The

    aggregates must be of specific quality not only at the time of unloading at site

    but more so at the time of lading into mixer. Rakers shall be used for lifting, the

    coarse aggregates. Coarse aggregates shall be piles in layers not exceeding

    1.2 meters height to prevent coning or segregation. Each layer shall cover the

    entire area of the stock pile before succeeding layers are stacked. Aggregates

    that have become segregated shall be rejected. Rejected material after

    remixing may be accepted, if subsequent tests demonstrate conformance with

    required gradation.

    SPECIFIC GRAVITY

    Coarse aggregates having a specific gravity below 2.5 t/m3 (saturated surface

    dry basis) shall not be used without special permission of PURCHASER.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    27/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 27 of 52 WAPCOS LIMITED

    1.16.3 FINE AGGREGATE

    Fine aggregate except as noted above, and for other than light weight

    concrete shall consist of clean natural river sand conforming to IS: 383. The

    sand shall be clean, sharp, hard, strong and durable and shall be free from

    dust, vegetable substances, adherent coating, clay, alkali, organic matter,

    mica, salt, or other deleterious substances, which can be injurious to the

    setting qualities, strength/durability of concrete.The grading of fine aggregate

    for concrete shall be within the limits of either zone I or zone II of the IS 383,

    table 4.

    SCREENING AND WASHING

    Sand shall be prepared for use by such screening or washing, or both, as

    necessary, to remove all objectionable foreign matter while separating the

    sand grains to the required size fractions.

    GRADATION

    Unless otherwise directed or approved, the grading of sand shall be within the

    limits indicated here under:

    PERCENTAGE PASSING FOR

    IS Sieve Grading Grading Grading GradingDesignation Zone I Zone II Zone III Zone IV10 mm 100 100 100 1004.75 mm 90-100 90-100 90-100 95-1002.36 mm 60-95 75-100 85-100 95-100

    1.18mm 30-70 55-90 75-100 90-100

    600 micron 15-34 35-59 60-79 80-100300 micron 5-20 8-30 12-40 15-50150 micron 0-10 0-10 0-10 0-15

    Where the grading falls outside the limits of any particular grading zone of

    sieves, other than 600 microns I.S. Sieve, by total amount not exceeding 5

    percent, it shall be regarded as falling within that grading zone. This tolerance

    shall not be applied to percentage passing the 600 micron I.S. Sieve or to

    percentage passing any other sieve size on the coarse limit of Grading Zone I

    or the finer limit of Grading zone IV Fine aggregates conforming to Grading

    Zone IV shall not be used unless mix designs and preliminary tests have

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    28/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 28 of 52 WAPCOS LIMITED

    shown its suitability for producing concrete of specified strength arid

    workability.

    FINENESS MODULUS

    Sand shall conform to IS 383 Zone I or Zone II The fineness modulus is

    determined by adding the cumulative percentages retained on the following IS

    sieve sizes (4.75 mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron and 150

    micron) and dividing the sum by 100.

    SOUNDNESS

    The average loss of weight of sand after 5 cycles of sodium sulphate

    accelerated soundness test as specified in IS.2386 (part 5) shall not be more

    than 10% and shall not be more than 15 % when magnesium sulphate solution

    is used.

    The Grading and fineness modulus of sand may be altered by PURCHASER

    depending upon the requirements, suitability and availability. The contractor

    shall procure process and supply the required sand at no extra cost.

    1.16.4 COARSE AGGREGATE

    Coarse aggregate for concrete, except as noted above and for other than light

    weight concrete shall conform to IS: 383. This shall be of crushed stone and

    shall be cleaned, and free form elongated flaky or laminated pieces, adhering

    coatings, clay lumps, coal residue, clinkers, slag, alkali, mica, organic matter

    or other deleterious matter.

    It shall be roughly cubical in shape. The overall grading of the coarse

    aggregate, viz., graded aggregate of nominal size 20mm shall conform to the

    requirements specified in IS 383. The contractor shall, if required by the

    engineer, obtain the specified grading by combining single aggregates in

    proportions to give the specified grading.

    SCREENING AND WASHING

    Natural gravel and crushed rock shall be screened and/or washed for the

    removal of dirt or dust coating, if so demanded by ENGINEER-IN-CHARGE.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    29/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 29 of 52 WAPCOS LIMITED

    IS. Sieve Percentage passing for single sized aggregate of nominal size

    Designation

    63 mm 40 mm 20mm 16 mm 12.5 mm 10 mm

    80mm 100 - - - - -

    63 mm 85-100 100 - - - -40mm 0-30 85-100 100 - - -

    20mm 0-5 0-20 85-100 100 - -

    16 mm - - - 85-100 100-100 -

    12.5 mm - - - - 85-100 100 ^

    10 mm 0-5 0-5 0-20 0-30 0-45 85-100

    4.75 mm - - 0-5 0-5 0-10 0-20

    2.36mm - - - - - ' - 0-5

    I.S. Sieve Percentage passing for graded aggregate of nominal size

    Designation

    40 mm 20mm 16 mm 12.5 mm

    80mm 100 - - -

    63 mm - - - -

    40mm 95-100 100 - -

    20mm 30-70- 95-100 100 100

    16 mm - 90-100 -

    12.5 mm ' - - - 90-100

    10 mm 10-35 25-55 30-70 40-85

    4.75 mm 0-5 0-10 0-10 0-10

    2.36 mm - - - .

    The Grading of coarse aggregate shall in general conform to the Grading as

    given in IS.-383. The exact Grading of coarse aggregate for different items of

    cement concrete works shall be approved by PURCHASER from time to time,

    based on the laboratory tests. Such changes in the Grading shall be carried

    out by CONTRACTOR at no extra cost.

    The pieces shall be angular in shape and shall have granular or crystalline

    surfaces. Friable, flaky and laminated pieces, mica and shale if present, shall

    be only in such quantities that will not, in the opinion of the PURCHASER,

    affect adversely the strength and/or durability of concrete. The maximum size

    of coarse aggregate shall be the maximum size specified above but in no case

    greater than 1/4th of the minimum thickness of the member, provided that the

    concrete shall be placed without difficulty so as to surround all reinforcement

    thoroughly and fill the corners of the form. For heavily reinforced concrete

    members, the nominal maximum size of the aggregate shall be 5 mm less

    than the clear distance between the main bar or 5mm less than the minimum

    cover to the reinforcement whichever is smaller. The amount of fine particles

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    30/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 30 of 52 WAPCOS LIMITED

    occurring in the free state or as loose adherent shall not exceed 1% when

    determined by laboratory sedimentation tests as per IS:238

    The limits for flakiness and elongation tests will be specified by PURCHASER

    based on tests from time to time and the CONTRACTOR shall procure the

    aggregates as per requirements without claiming for any extra rate.

    After 24 hours immersion in water, a previously dried sample shall not have

    gained more than 1% of its oven-dried weight in air as determined by IS 2386

    WORKS TESTS ON AGGREGATES

    During the course of the Contract, fine and coarse aggregates shall be tested

    at site as often as required by the Engineer and at the Contractors expense.Tests shall be carried out in accordance with the methods specified in as

    below, unless otherwise ordered by the purchaser.

    WORKS TEST ON AGGREGATES

    Particle size IS 2386 Part I

    Silt content by field settling test IS 2386 Part I

    Moisture content IS 2386 Part III

    Organic impurities content IS 2386 Part II

    1.16.5 WATER

    Water used for concreting production and curing shall be as per IS 456 -2000

    requirement. Water used for both mixing and curing shall be clean and free

    from injurious amounts of oils, acids, alkalis, salts, sugar, organic materials or

    other substances that may be deleterious to concrete or steel. Potable water is

    generally considered satisfactory for mixing and curing of concrete.

    The sample of water taken for testing shall represent the water proposed to be

    used for concreting, due account being paid to seasonal variation. The sample

    shall not receive any treatment before testing other than that envisaged in the

    regular supply of water proposed for use in concrete. The sample shall be

    stored in a clean container previously rinsed out with similar water.

    The initial setting time of test block made with the appropriate cement and the

    water proposed to be used shall not be less than 30 minutes and shall not

    differ by more than +/-30 minutes from the initial setting time of control test

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    31/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 31 of 52 WAPCOS LIMITED

    block, prepared with the same cement and distilled water. The test blocks shall

    be prepared and tested in accordance with the requirements of IS: 4031.

    1.16.6 REINFORCEMENT STEEL

    REINFORCEMENT

    All reinforcement bars for concrete structure shall be of CRS steel, grade Fe

    500 with fusion epoxy coating of Minimum 175-300 microns conforming to

    latest relevant IS codes. All reinforcement shall be corrosion resistant bar. The

    bidder shall clearly indicate the coating system suggested on the

    reinforcement or alternate system for corrosion resistance of reinforcement

    and structure with proper technical specification.

    STORAGE

    The reinforcement bars shall not be kept in direct contact with the ground but

    stacked on top of an arrangement of timber sleepers or the like.

    If the reinforcing rods have to be stored for long duration, where storage for

    more than three months is envisaged, they shall be coated with cement wash

    before stacking and/or be kept under cover or stored as directed by

    PURCHASER.

    Fabricated rods shall be carefully stored to prevent the damage, distortion,

    corrosion and deterioration.

    LAPS

    Laps and splices for reinforcement shall be shown on the drawings. Splices in

    adjacent bars shall be staggered and the locations of all splices, except those

    specified on the drawings, shall be approved by PURCHASER. The bars shall

    not be lapped unless the length required exceeds the maximum available

    lengths of bars at site.

    BENDING

    Reinforcing bars procured by the Contractor bent or in coils, shall be

    straightened before they are cut to size. Straightening of bars shall be done in

    cold and without damaging the bars. This is considered as the part of

    reinforcement bending/fabrication work.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    32/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 32 of 52 WAPCOS LIMITED

    All bars shall be accurately bent according to the sizes and shapes shown on

    the detailed working drawings / bar bending schedules. They shall be bent

    gradually by machine or other approved means. Reinforcing bars shall not be

    straightened and rebent in a manner that will injure the material; bars

    containing cracks or splits shall be rejected. They shall be bent cold, except

    bars of over 25 mm in diameter which may be bent hot if specifically approved

    by PURCHASER. Bars incorrectly bent shall be used only if the means used

    for straightening and rebinding be such as shall not, in the opinion of

    PURCHASER, injure the material. No reinforcement bars shall be bent when

    in position in the work without approval, whether or not it is partially embedded

    in hardened concrete. Bars having kinks or bends other than those requiredby design shall not be used.

    FIXING

    Reinforcement bars shall be accurately fixed by any approval means and

    maintained in correct position shown in the drawings by the use of blocks,

    spacers and chairs as per IS 2502 to prevent displacement during placing and

    compaction of concrete. Bars intended to be in contact at crossing points shall

    be securely bound together at all such points with 1.25 mm diameter soft

    annealed steel wire. The vertical distances required between successive

    layers of bars in beams or similar members shall be maintained by the

    provision of mild steel spacer bars at such intervals that the main bars do not

    perceptibly sag between adjacent spacer bars.

    COVER

    The cover for reinforcement bars shall be provided for the extremely exposure

    condition as indicated in IS 456-2000.

    INSPECTION

    Erected and secured reinforcement bars shall be inspected and approved by

    PURCHASER prior to placement of concrete.

    1.17 SPECIFICATION FOR CONCRETE

    1.17.1 MIX DESIGN

    The concrete for all RCC works shall be as per specifications mentioned in

    the Indian Standard and also to conform the design requirements.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    33/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 33 of 52 WAPCOS LIMITED

    a) All the calculations relevant to the design of class of concrete mix.

    b) The sieve analysis of aggregates which they proposed to use in the

    works.

    c) Full details of preliminary tests on concrete and

    d) The weight of cement, sand and coarse aggregate to be adopted for

    mixing.

    Mix design shall be carried out as per IS: 10262 and IS: 456-2000. All the

    preliminary tests and mix designs for all concrete works envisaged in the

    contract shall be carried out by the contractor under the supervision of

    Purchaser or a reputed third party concrete lab approved by the Purchaser.

    The Contractor shall arrange all the materials, equipments, lab setup and

    other resources required for mix design. Only those materials which are to be

    used for Concrete production shall be used in mix design. PURCHASER shall

    have powers to vary the proportions, water cement ratio and slump for the

    specified work or works based on laboratory tests and the CONTRACTOR is

    bound to adopt these changes on works without any extra cost.

    The Contractor shall further note that the requirements of providing concrete of

    specified quality in the field shall be his sole responsibility and he shall not be

    eligible for any compensation in case the strengths obtained in the field do not

    satisfy the criteria laid down, the work will be liable to rejection by

    PURCHASER or a suitable reduction in the rate for concrete shall be effected

    at the direction of the PURCHASER. The mix design shall be carried out with

    approved state or Central Government Institute for the specified mix.

    1.17.2 CONCRETE WORK

    CONCRETE

    The quality of concrete shall be of design mix specified in the drawing and

    schedule of quantities.

    The ingredients of the concrete such as fine and coarse aggregate shall be

    measured by weight by means of an approved Batching Machine. Due

    allowance shall be made to weight of water carried by the aggregate. The

    actual amount added to the mixer being reduced as necessary. The decision

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    34/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 34 of 52 WAPCOS LIMITED

    of the Engineer / Consultant in this regard shall be final and binding on the

    contractor.

    The water cement ratio shall be the minimum possible having regard to proper

    compaction by the respective means specified. The Concrete shall be mixed

    in the Batch mixing machine of approved type and capacity. Where coarse

    aggregate is over 20 mm, the concrete shall be mixed only in non-tilting type

    of mixers. The resulting concrete shall be a uniform workable mixture of the

    specified.

    The batching, mixing, placing in position of concrete shall be as per the

    guidelines stipulated in ISI 456-2000.

    1.17.3 SAMPLING AND TESTING OF CONCRETE

    Sampling of concrete shall be done as per the provision made in the relevant

    IS or as directed by the PURCHASER or his representative. The additional

    test if ordered shall also be carried out as per the direction.

    All water retaining structures shall be tested for water tightness as per the

    provisions of IS: 3370

    If RCC floor / roof are assumed to act as diaphragm transmitting lateral loads

    to braced bays it shall be provided with shear connectors. However,

    whenever large / number of cut-outs are provided in the floor slab, horizontal

    floor bracings shall be provided below slab to transfer horizontal force to

    columns without considering diaphragm action from slab.

    The minimum frequency of sampling of concrete of each class/grade shall be

    in accordance with Clause 15.2 of IS 456-2000. Such samples shall be drawn

    on each day for each type of concrete. Sampling, testing and acceptance

    criteria shall be as per IS 456-2000.

    CONSISTENCY

    Slumps tests shall be carried out as often as demanded by PURCHASER and

    invariably from the same batch of concrete from which the test cubes are

    made. Slump tests shall be done immediately after sampling.

    Test cubes shall be made and tested in accordance with IS 456 - 2000. If the

    concrete test cubes do not give the stipulated strengths, PURCHASERreserves the right to ask CONTRACTOR to dismantle such portions of the

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    35/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 35 of 52 WAPCOS LIMITED

    work, which in his opinion are unacceptable and re-do the work to the

    standard stipulated at CONTRACTOR'S cost.

    The inspection and testing of concrete structures shall be done of IS: 456-

    2000.

    1.18 CURING

    All concrete shall be cured by keeping it continuously damp for the period of

    time required for complete hydration and hardening to take place. Preference

    shall be given to the use of continuous sprays or ponded water, continuously

    saturated coverings of sacking, canvas, hessian or other absorbent materials,

    or approved effective curing compounds applied with spraying equipment

    capable of producing a smooth, even-textured coat. Extra precautions shall be

    exercised in curing concrete during cold and hot weather as outlined

    hereinafter. The quality of curing water shall be the same as that used for

    mixing concrete.

    Certain types of finish or preparation for overlaying concrete must be done at

    certain stages of the curing process and special treatment may be required for

    specific concrete surface finish.

    Curing of concrete made of high alumina cement and super-sulphated cement

    shall be carried out as directed by ENGINEER-IN-CHARGE.

    CURING WITH WATER

    Fresh concrete shall be kept continuously wet for a minimum period of 10.

    days from the date of placing of concrete, following a lapse of 12 to 14 hours

    after laying concrete. The curing of horizontal surfaces exposed to the drying

    winds shall however begin immediately after the concrete has hardened.

    Water shall be applied to unformed concrete surfaces within 1 hour after

    concrete has set. Water shall be applied to formed surface immediately upon

    removal of forms. Quantity of water applied shall be controlled so as to prevent

    erosion of freshly placed concrete.

    CONTINUOUS SPRAYING

    Curing shall be assured by use of an ample water supply under pressure in

    pipes, with all necessary appliances of hose, sprinklers and spraying devices.

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    36/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 36 of 52 WAPCOS LIMITED

    Continues fine mist spraying or sprinkling shall be used, unless otherwise

    specified or approved by PURCHASER.

    ALTERNATE CURING METHODS

    Whenever, in the judgment of PURCHASER, it may be necessary to omit the

    continuous spray method, a covering of clean sand or other approved means

    such as wet gunny bags which will prevent loss of moisture from the concrete

    may be used. No type of covering will be approved which would stain or

    damage the concrete during or after the curing period. Covering shall be kept

    continuously wet during the curing period.

    For curing of concrete in pavements, side-wall, floors, flat roof or other level

    surfaces, the ponding method of curing is preferred. The method of containing

    the ponded water shall be approved by PURCHASER. Special attention shall

    be given to edges and comers of the slabs to ensure proper protection to

    these areas. The ponded areas shall be kept continuously filled with water

    during the curing period.

    CURING COMPOUNDS

    Surface coating type curing compounds shall be used only under special

    permission of PURCHASER. Curing compounds shall be liquid type white

    pigmented, conforming to U.S. Bureau of Reclamation specification. No curing

    compound shall be used on surfaces where future blending with concrete,

    water or acid proof membrane, or painting is specified.

    CURING EQUIPMENT

    All equipment and materials required for curing shall be on hand and ready for

    use before concrete is placed.

    1.19 SPECIFICATION FOR CONSTRUCTION AND KEY JOINTS

    Concrete shall be placed without interruption until completion of the part of the

    work between predetermined construction joints, as specified hereinafter.

    Time lapse between the pouring of adjoining units shall be as specified on the

    drawings or as directed by PURCHASER.

    If Stopping of concreting becomes unavoidable anywhere, a properly formed

    construction joint shall be made where the work is stopped. Joints shall be

    either vertical or horizontal, unless otherwise shown on drawings. In case of

  • 7/29/2019 Vol II_Book I_CH1_G_Guidelines of Design Principle and Spec..

    37/52

    APPDCLTechnical Specification

    For

    Sea Water Intake System

    Sri Damodaram Sanjeevaiah

    Thermal Power Station

    2X800 MW

    Tender DocumentVolume II_Book I_Chapter 1 Page 37 of 52 WAPCOS LIMITED

    an inclined or curved member, the joint shall be at right angles to the axis of

    the member. Vertical joints in walls shall be kept to minimum. Vertical joints

    shall be formed against a stop Board; horizontal joints shall be level and

    wherever possible, arranged so that the joint lines coincide with the

    architectural features of the finished work. Battens shall be nailed to the form

    work to ensure a horizontal line and if directed, shall also be used to form a

    grooved joint. For tank walls and similar work, joints shall be formed as per IS:

    3370. Concrete that is in the process of setting shall not be disturbed or

    shaken by traffic either on the concrete itself or upon the shuttering. Horizontal

    and vertical construction joints and shear keys shall be located and shall

    conform in detail to the requirements of the plans unless otherwise directed byPURCHASER. Where not described, the joint shall be in accordance with the

    following:

    COLUMN JOINT

    In a column, the joint shall be formed 75 mm below the lowest soffit of the

    beams including haunches if any. In flat slab construction, the joints shall be

    75 mm below the soffit of column capital. At least 2 hours shall elapse after

    depositing concrete in columns, piers or walls, before depositing in beams,

    girders or slabs supported thereon.

    BEAMS AND SLABS JOINTS

    Concrete in a beam shall be placed throughout without a joint but if the

    p