Viet Nam: Sustainable Rural Infrastructure Development ...1.2 Subproject type Rural road...
Transcript of Viet Nam: Sustainable Rural Infrastructure Development ...1.2 Subproject type Rural road...
Initial Environmental Examination
February 2013
Viet Nam: Sustainable Rural Infrastructure Development Project in the Northern Mountain Provinces Subproject 34: Improving Linh Nham – Deo Nhau Road and Upgrading Van Han Market, Dong Hy District, Thai Nguyen Province Prepared by the Ministry of Agriculture and Rural Development for the Asian Development Bank
ABBREVIATIONS
ADB - Asian Development Bank
AH - Affected Households
AP - Affected Persons
CPC - Commune People’s Committee
CSB - Commune Supervision Board
CSC - Construction Supervision Consultant
CPMU - Central project management unit
DARD - Department of Agriculture and Rural Development
DIA - Direct Impact Area
DONRE - Department of Natural Resources and Environment
DPC - District People’s Committee
EM - Ethnic Minority
ESC - Environmental Supervision Consultant
EMP - Environmental Management Plan
IEE - Initial Environmental Examination
IIA - Indirect Impact Area
MONRE - Ministry of Natural Resources and Environment
PPC - Province People’s Committee
PPMU - Provincial Project Management Unit
SIA - Secondary Impact Area
SRIDP - Sustainable Rural Infrastructure Development Project in the
Northern Mountain Provinces
UXO - Unexploded Ordinance
This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
TABLE OF CONTENTS
ABBREVIATIONS ............................................................................................................................... ii
TABLE OF CONTENTS ..................................................................................................................... iii
LIST OF TABLES ............................................................................................................................... iv
I. INTRODUCTION ..............................................................................................................................1
II. DESCRIPTION OF PROJECT ........................................................................................................2
a. Description of Linh Nham – Deo Nhau road .......................................................2
b. Describe the subproject: Van Han market ..........................................................3
III. DESCRIPTION OF EXISTING ENVIRONMENT ...........................................................................9
IV. ENVIRONMENTAL IMPACT SCREENING ................................................................................ 12
V. OUTLINE OF ENVIRONMENT MANAGEMENT PLAN (EMP) ................................................... 27
A. Environmental impact mitigation plan .............................................................................. 27
B. Environment monitoring plan ........................................................................................... 33
C. Environmental Compliance Monitoring ............................................................................ 35
D. Assign tasks in implementation of EMP ........................................................................... 39
E. Monitoring and reporting system ...................................................................................... 41
F. Budget for EMP implementation ...................................................................................... 42
VI. COMMUNITY CONSULTATION AND PROJECT INFORMATION DISCLOSURE ................... 43
A. Description of activities to date ........................................................................................ 43
B. The results of community consultation up to reporting time............................................. 44
C. Community consultation activities in the future ................................................................ 45
VII. GRIEVANCE REDRESS MECHANISM .................................................................................... 46
VIII. CONCLUSIONS AND RECOMMENDATIONS ........................................................................ 46
Appendix 1: Cost for EMP implementation ...................................................................................... 50
Appendix 2: Minutes of agreement to get soil for leveling fields and minute of exploitation borrow
pits between households and PMU.................................................................................................. 52
Appendix 3: Some pictures on the environment status of Linh Nham – Deo Nhau road and Van
Han market ....................................................................................................................................... 61
Appendix 4. Consultation activities .................................................................................................. 67
Appendix 5: Consultation and participation document ..................................................................... 68
Appendix 6: Documentation of public consultation .......................................................................... 81
Appendix 7: Source of data used in the reporting process ............................................................ 80
Appendix 8: Sample Complaint Form ............................................................................................ 81
LIST OF TABLES
***
Table 1: General data of the subproject ..............................................................................................2
Table 2: Description of background environment of the study area for the subproject ......................9
Table 3.1: Environmental impact Screening of Linh Nham - Deo Nhau road .................................. 12
Table 3.2: Environmental impact screening of Van Han market upgrading..................................... 22
Table 41: Environmental impact mitigation plan for Linh Nham - Deo Nhau road ........................... 27
Table4.2: Environment management plan for Van Han market upgrading project .......................... 31
Table 5: Environment impact monitoring plan .................................................................................. 33
Table 6.1: Environmental compliance monitoring plan for Linh Nham - Deo Nhau road ................. 35
Table 6.2: Plan for environmental regulation compliance monitoring for Van Han market .............. 38
Table 7: EMP Implementation Plan.................................................................................................. 39
Table 8: Monitoring and reporting system ........................................................................................ 41
Table 9: Budget for EMP implementation ........................................................................................ 42
Table 10: Community consultation and information disclosure ....................................................... 43
Table 11: The results of community consultation ............................................................................. 44
Table 12: Proposed community consultation activities .................................................................... 45
Table 13: Estimated for disclosure information activities ................................................................. 50
Table 14: Cost estimation for implementation of capacity building and training .............................. 51
Table 15: Attendance in consultation meetings ............................................................................... 81
Table 16: Matrix of issues and concerns ......................................................................................... 82
1
I. INTRODUCTION
A. Subproject rationale
1. Sustainable Rural Infrastructure Development Project in Northern Mountain provinces (SRIDP) is being
implemented through a sector loan from Asian Development Bank (ADB). Ministry of Agriculture and Rural
Development (MARD) is the Executing Agency for the sector loan. SRIDP coverage are 15 mountainous
provinces in Northern Vietnam (Bac Giang, Bac Kan, Cao Bang, Dien Bien, Ha Giang, Hoa Binh, Lai Chau,
Lang Sơn, Lao Cai, Phu Tho, Son La, Thai Nguyen, Tuyen Quang, Vinh Phuc, Yen Bai).
2. While the poverty levels throughout the country had been significantly reduced as a result of
development efforts; the statistics in mountain provinces above had indicate rather slow improvement during
the last decade (47% in 2002, 32.3% in 2006 and 27% in 2008)1. Part of the problem is due to the
inadequate access facilities, social services, and commercial opportunities. It is for this reason that GOV and
ADB had pursued the SRIDP to provide sustainable access facilities in these poverty stricken mountain
provinces. These infrastructures include rural roads, public markets, irrigation and water supply facilities. As
a part of the SRIDP, the Subproject “ Road improvement Linh Nham – Deo Nhau and Van Han market,” will
be implemented at Dong Hy district, Thai Nguyen Province.
B. Subproject Objectives
3. The Subproject aims to improve the rural road linking two poverty strike agricultural communes in the
Dong Hy District that serves as access to social services centers and upgrade common market Van Han,
facilitate agricultural production exchange in locality.
C. Project Alternatives
4. Efforts to minimize the adverse social impacts of the Subproject include the shifting of the proposed
road alignment at various points to avoid human settlements, public facilities, water bodies, and hilly areas.
In addition, impacts on business disruption and income loss during construction of upgrading Van Han
market are unavoidable however efforts can be made to minimize these adverse impacts. Likewise, the
need for borrow pits in the construction of embankments will be minimized and the Subproject will, whenever
feasible, use materials from cuttings in the construction of embankments.
5. Initial Environmental Examination (IEE) has been prepared to meet the Social Policy Safeguards
requirements of ADB2 and GOV
3. The IEE contains the following contents:
(i) Section II: Description of the project
(ii) Section III: Description of the existing environment
(iii) Section IV: Environmental impact screening
(iv) Section V: Outline environmental management plan
(v) Section VI: Public consultation and disclosure activities
(vi) Section VII: Grievance Redress Mechanism
(vii) Section VIII: Conclusion and Recommendations
1 Report and Recommendation of the President to the Board of Directors, ADB, September 2010
2 Environmental guideline (2003)
3 Law on environmental protection approved by the National Assembly of Socialist of Vietnam on 29 November, 2005
2
II. DESCRIPTION OF PROJECT
Table 1: General data of the subproject
Description Subproject data
1. General information
1.1 Subproject name Road improvement Linh Nham-Deo Nhau and Van Han market,
Dong Hy district
1.2 Subproject type Rural road improvement, common market upgrading
1.3 ADB Environment Category Category B
1.4 Project employer Management Board for SRIDP -Thai Nguyen province
1.5 Address of project Owner Group 28 Hoang Van Thu ward - Thai Nguyen city
1.6 Name and title of Head of Subproject
Owner Bui Tien Chinh, position: Director of PPMU
1.7 Telephone, fax and email address of
Subproject Owner
0280.385.5484.
1.8 Name of Environmental Officer of PPMU Le Quang Hieu
1.9 Telephone, fax and email address of
PPMU Environment Officer 0972.477.087 [email protected]
2. Description of subproject
a. Description of LinhNham – Deo Nhau road
2.1 New project or rehabilitation project Rural road improvement
2.2 Grade of road (Technical Standards) Grade V-mountain road
2.3 Designed speed (km/h) 30 km/h
2.4 Length and width of road (km)
- Current status: 19,44Km; Width=5-6m
-Design: Length 19,44Km; embankment =6.5m;
Pavement=3.5m; shoulder=2x1.5m
2.5 Road surface (asphalt pavement,
concrete, gravel, etc.)
- Current status: Earth fill road
- Design: 2 layer asphalt pavement
2. 6 Bridge number and length - Current status: 01 Khe Mo bridge, bridge slab: L=13.5m at
station: Km1+147;
- Design: The spillway is designed as combining overflow
crossing through Cau Mai spring (Km12+876) with round culvert
D100.
2.7 Number and size of culvert - Total: 64 culverts
- Current status: 28 culverts are available, including pipe culvert
D50, D75, D70, D100, D80, D60, D30.
- Design 36 new culverts, with typical diameter is 100cm
2.8 The length of the drainage works - Current status: Earthwork drainage system on the route is
mainly degraded and filled by soil or grass, transmission capacity
is low, rainwater damages pavement seriously.
- Design: Trapezoidal cross-section earth canal, size
3
(40x40x120) cm. Inclined slope sections is ≥ 6%, the bed of the
ditch is reinforced by boulders and cement mortar which is 25 cm
thick.
2.9 Extent of land acquisition: The current width of the road ranges from 5.0 to 6.5m, while the
design of the road width is 6.5m. Therefore, the width of the site
clearance is estimated at 0-1.5m along the route. However, for
the positions of cut slope and embankment slope, it needs to be
wider for ground clearance. Total of permanently acquired land is
of 80,456 m2
No branch road is upgraded under this subproject
2.10 Number of other major and minor
roads crossing the subproject alignment
The project road starts at the junction with National Highway 379
and Linh Nham - Deo Nhau road, the road ends at the boundary
between two districts of Dong Hy and Vo Nhai.
2.11 Number of water ways crossing the
road
- Khe Mo spring, Ngon Cat spring and Cau Mai spring cross
through the project road
2.12 Number of hills and mountains cut
across by the road
The subproject road running along the foothills. Cutting through
Lau Ha mountain in Nhau pass
b. Describe the subproject: Van Han market
2.13 New project or rehabilitation project Road Upgrading and construction of market structure
2.14 Total upgraded market area 2,448.6 m2
2.15 Market structure
Area: 431.4 m2, the structure is built with bearing steel structural
frame roof, and iron steel sheets roofing.
Two gables and the lobby are built with concrete and masonry
bricks
2.16 Toilet
Area: 40,2 m2,Brick wall and reinforced concrete roof.
Thai Nguyen PPMU had officially confirms to add aseptic tank as
an important part of rural market in the Construction documents.
The drainage system of the market will also be built. The waste
water of this facility will be discharged into the drainage system
of Van Han commune.
The drainage system of the commune exists as drainage canals
flow around the commune without treatment process, diseases
and odor problems may arise as a result of it. Water used within
the subproject area is from dug wells.
2.17 Paths in the market, yard Reinforced concrete structure, grade 200, 20cm thick
2.18 Water supply Installation of pumps and wells
2.19 Drainage system
Drainage ditches are connected to the drainage system of
residential sites. The drainage system of the commune exists as
drainage canals flow around the commune without treatment
process, diseases and odor problems may arise as a result of it.
2.20 Solid Waste treatment Concentration landfill is built in accordance with general plan of
commune. Waste is transported and disposed at the landfill.
2.21 Lighting system Connection to the existing electricity distribution system of the
commune
4
3. Construction activities
3.1 Commencement date (month/year) 7/2013
3.2 Completion date (month/year) 1/2015
3.3 Number of workers Estimated about 100 workers
3.4 Construction camps required (Yes/No) Yes, 3 workers camps/tents will be built
3.5 Construction in rainy season (Yes/No) Yes (in favorable weather conditions) or just some preparations
for constructions
3.6 Concrete or asphalt mixing plant/s
(Yes/no) Yes, 3-4 mobile plants
3.7 Location and extent of borrow area and
description of material source/s
Source of materials
+ Soil for construction will be exploited at the hills of the
communes of Khe Mo and Van Han where vegetations are
mainly shrubs and weeds, not located near waterways nor
houses of local people. The hills for soil exploitation is not high,
therefore the risk of landslide occurring during exploitation
process is likely to not happen. Utilizing of these borrow pits are
in agreement for exploiting hill’s soil of the owners and in
accordance with local government (see enclosed documents)Soil
is exploited the most from 5 borrow pits at Km5+100, Km8+600,
Km10+800, Km12+200, Km18+50. The surveyed estimate of the
reserves is sufficient to upgrade the route (37,000 m3), average
distance of transport is 1 km.
+Cement, steel: Supplied from Chua Hang town, average
distance of transport is 15 km
+Stones of all types are exploited from Nui Voi quarry in Dong Hy
district, average distance of transport is 12 - 15 km
Temporary yards for construction materials will be determined
by the Contractors. Materials can be temporarily stored in the
yard of CPC’s office, other public offices or temporary rented
land.
3.8 Method on management of excess
excavated/surplus soil
The survey and interview of landowners were implemented by
PPMU and engineering design consultants, through which, the
landowners have been informed of the impacts to their lands by
these construction activities. It is planned that redundant soil will
be used to elevate field level along the road owned by farmer
households who have agreed and have expressed their desire
for such land filling.
After being filled, it is expected that these raised lowlands will
have an improve productivity and other land use potentials, due
to its resultant low flooding potential during the rainy season. On
the other hand, elevation of the lands is not higher than the road
that ensures drainage capacity both sides of the road. There are
6 main dumpsites along the road at Km8+200; Km9+600;
Km14+100; Km15+400; Km17+600; Km19+400 which are low
lands the owners of which desire them to be elevated. Other low
lying lands to be leveled with excavated soil along the road are
owned by the local government.
3.9 Type and approximate quantity of Preliminary estimates:
5
construction materials + Volume of excavated soil :430 599 m3
+ Volume of filling soil27 973 m3
+ Steel: 28 tons
+ Macadam of all sizes 35,000 m3
+ Boulder 1,000 m3
3.10 Quantity of solid waste generated from
construction (monthly in terms of m3)
+ Soil and broken stones is estimated at about 400m3/month.
+Domestic wastes per head is calculated at about
0.3kg/person/day. Total about 900kg/month for 100 workers
3.11 Number and conditions estimate of
vehicles and construction machines
There are of about 22 units of vehicles and construction
machines planned to be used during construction phase, include
bulldozers, lifts, graders, rollers, trucks.
4. Operation and maintenance activities
4.1 Maximum allowable speed 30km/h (limited conditions)
4.2 Expectedload (tons) 10 tons
4.3 Expected traffic volumes Traffic volume growth: 10%/year
4.4 Descriptions of maintenance activities
- Linh Nham – Deo Nhau route:
Activities on route maintenance will be carried out by the Road
Management Board (RMB) of Dong Hy district. The maintenance
activities include road-side repair, painting and replacing the sign
noards, clearing soil and weeds in the drains and sluices,
clearing trees and shrubs on either road side, repair the crack
positions and potholes and other minor damages
Operation and maintenance of mountain road Grade V are
conducted by Communal People Committees (CPCs) of Khe
Mo,Van Han in coordination of RMB of Dong Hy district
The routine maintenances will be done on the basis of approved
technical-economic reports. The maintenance activities for the
works will be implemented once every five years and costs
account for approximately 30% of total investment
- Van Han
Van Han CPC will be the recipient of the Van Han market. The
CPC is responsible for establishing a Market Management Unit.
The market fixed fee tariff to be collected from the market
locators, will be based on the state regulations. The fee
collection will be used to pay for the services of the Market
Management Unit and other necessary services. The unit will
also be responsible for maintenance of the facility.
5. Resettlement and land acquisition 4
5.1 Number of affected households 601 households
5.2 AHs loosing > 10% productive land or
livelihood source
0
5.3 Number of APs that must relocate 0
5.4 Total land area to be acquired (m2) Temporary = 0 m
2 Permanent = 80,456 m
2
5.5 Total government land to be acquired Temporary = 0 m2 Permanent = 0 m
2
4 This data is taken from Resettlement Plan
5.6 Agricultural land area to be acquired(m
5.7 Forest land to be acquired (m2)
5.8 Aquaculture land to be acquired (m
5.9 Residential land to be acquired (m
5.10 Garden land to be acquired (m2)
5.11 Other land to be acquired (m2)
6. Subproject cost
6.1 Total cost of subproject
Figure 1: Vicinity map of subproject area and
Van Han market
5.6 Agricultural land area to be acquired(m2) Temporary = 0 m
2 Permanent = 14,728 m
Temporary = 0 m2 Permanent = 14,723 m
5.8 Aquaculture land to be acquired (m2) Temporary = 0 m
2 Permanent = 360 m
5.9 Residential land to be acquired (m2) Temporary = 0 m
2 Permanent = 13,392 m
Temporary = 0 m2 Permanent = 37,113 m
Temporary = 0 m2 Permanent = 0 m
VND 82,844,935,000 equivalent to 3,971,473 USD
Figure 1: Vicinity map of subproject area and surrounding areas
Rural road
LinhNham – DeoNhau
Van Han market at
Km10+310
6
Permanent = 14,728 m2
Permanent = 14,723 m2
Permanent = 360 m2
Permanent = 13,392 m2
Permanent = 37,113 m2
Permanent = 0 m2
VND 82,844,935,000 equivalent to 3,971,473 USD
7
Figure 2: Map of subproject and locations of borrow pits, disposal sites
1
2
3
4
5
1
2
3
4
5
6
3
2 1
: Worker’s tents at 3 location at Km2+094; Km7+730;
Km16+730
: Borrow pits at 5 locations at Km5+100, Km8+600,
Km10+800, Km12+200, Km18+500
: Dump sites at 6 locations at Km8+200; Km9+600;
Km14+100; Km15+400; Km17+600; Km19+400
1
1
1
Van Han market at
Km10+310
9
III. DESCRIPTION OF EXISTING ENVIRONMENT
6. The Direct Impact Area (DIA) covers the existing 19.44 km long and 6 m wide road (measured from
embankment toe) and 2,448.6 m2
and Van Han market site adjacent to the alignment road in Van Han
commune..The Secondary Impact Area (SIA) is the strip of land 100 m to each side of the DIA. The Indirect
Impact Area (IIA) covers the subproject beneficiary area corresponding to the 2 communes traversed by the
road which includes: Khe Mo and Van Han.
Table 2: Description of background environment of the study area for the subproject
Description Subproject data
1. Subproject location
1.1 Communes: Khe Mo, Van Han
1.2 District: Dong Hy
1.3 Province: Thai Nguyen
1.4 Geographical
location:
21038’00-21
0 42’00 N
1050 52’00-106
0 02’00 E
2. Natural environmental conditions
2.1 Air quality There is no sign of high level of re-suspended dust in the subproject due to:
(a) The project is located in the rural area where there are no industrial zones, factories
or large scale construction works for a long time
(b) Prevailing livelihood activities in the subproject area are mainly agriculture, some
services which pose almost no possibility of high level of dust re-suspension.
(c) Gaseous emissions are mainly from transport such as motorbikes and few 4 wheel
vehicles.
2.2 Noise and vibration - The noise level in the area is low, typical of rural areas. Main noise source comes from
transport such as motorbikes and few 4 wheel vehicles.
2.3 Climate and natural
disasters
- Rainy season lasts from May to October with the rainfall making up 70-80% of the
annual rainfall.
- Dry season lasts from November to April. Less rains and more sunshine with rainfall
making up only 20-30% of the total annual rainfall. The average rainfall during many
years is 2,000mmm, average temperature is 23.1 0C
- In general, the subproject area is less prone to inundation due to flood.
2.4 Topography and soil - The project road is located in the low hilly and cleavage terrain, alternating terraced
fields and some small villages of Khe Mo and Van Han communes. Overall, the terrain
elevation on the route does not change a lot, from 2m to 8m (except section goes through
Nhau Pass).
- Van Han market is adjacent to Linh Nham – Deo Nhau road at Km10+320.69 on the left
side in Pha Ly hamlet of Van Han commune.
- Land use in the subproject study area is mainly agricultural land for green tea and
timber trees.
2.5 Water bodies - The road to be upgraded crosses 3 streams of Cau Mai, Khe Mo and Ngon Cat
2.6 Ground water - It is observed that deep well having depth of 7-10m compared to natural ground level,
therefore it can be concluded that ground water in the area is deep. The groundwater
dynamics is seasonal based.
- At present, groundwater is mainly used for domestic use at households and small
business scale. Groundwater has not been used for irrigation.
10
2.7 Water Quality Ground water: it is observed in the dug wells of households that there is no sign of
external pollution such as oil, organic residues or garbage leach.
- The surface water of the area is mainly used for agriculture production; there is no sign
of surface water pollution because there is no industrial factory or significant pollution
source in the study area
2.8 Natural Hazards - The subproject area runs along hilly foot so it will not be affected by inundation. Only
some lowly embanked roads along the streams are often flooded during rainy season,
particularly in section of overflow building through Cau Mai stream at K12+876
2.9 Terrestrial flora and
fauna
- Terrestrial flora: These are mainly green tea and planted timber trees.
- Fauna: Mostly domestic animals that include cattle, pigs, goats, poultry and others.
- Wildlife: Mostly insects (i.e. mosquito, snails, etc.), common birds, amphibians, and
reptiles.
- There is no wildlife found that are listed in Red Book.
2.10 Aquatic flora and
fauna
- Aquatic flora and fauna include common fishes (i.e. carp, anabas, mullets and popular
ones in rivers and streams in delta area of Thai Nguyen) and crustacean species: such
as shrimps, crabs (Somanithelphusma),
- Aquaculture:
+ There are farmed fish such as carp, anabas, mullet, pike in household ponds for
household consumption.
- There are no aquatic species found in the subproject study area that are listed in Red
Book.
2.11 Protected areas
Protected area The subproject will not affect any historic or cultural heritage.
3. Environmental and social conditions
3.1 UXO The subproject route and Van Han market are existing structures regularly used by the
local residents and traders, so there is no possibility of any UXO.
3.2 Land use The communes Van Han and Khe Mo that has jurisdiction over the subproject(rural road
and market), have a total natural area of 9,563.58 ha. The area has the following land
uses: agricultural land (4,131.28 ha), forest land(4,963.85 ha); aquaculture land (39.5 ha);
residential land (160.43 ha); and unused land area (268.52 ha). (Source: Statistical
yearbook of Dong Hy district, 2011).
3.3 Residential lands
traversed Residential areas are built along and adjacent to the subproject road
3.4 Rural infrastructure During construction, some electricity poles will have to be moved as these are located
within the road corridor. Arrangement will be made for the transfer and restoration of this
facility to ensure the continuity of electric power service to the local residents..
3.5 Agriculture - Agriculture: mainly green tea and paddy rice. Other crops include sugarcane, bean and
planted timber trees (i.e. eucalyptus)
- Aquaculture: fish farming of common popular freshwater fishes
3.6 Population (direct and
indirect beneficiaries)
- Van Han commune has 9,822 people (2,365 households), population density is at 150
persons/km2;
- Khe Mo commune has 6,952 people (1,792 households), density of 230 persons/km2.
(Source: Statistical yearbook of Dong Hy district, 2011).
3.7 Ethnic minorities In the study area, the Kinh is majority, ethnic group accounts for only approximately 40%,
of which the Tay (17%) is the most numerous followed by the Nung (13%). Income of
100% of ethnic minority households is from agriculture. Due to low degree of cultivation,
11
the percentage of ethnic minorities which are classified as poor households is very high.
Of the 602 affected households, 139 (23%) are ethnic minorities.
3.8 Livelihood - The main livelihood of the community is agricultural production, making up 99% of the
local population in the area.
- Poverty incidence (in accordance with poverty line of the Government): the overall
poverty rate of the two communes Khe Mo and Van Han in 2011 are, 7.4% and 21%
respectively. The poor households are mainly policy preferential households, households
with members having disabilities, or female-headed households without support.
3.9 National/ Cultural
heritage
There is no cultural heritage in the project area.
3.10. Public health - Some coetaneous diseases or eye diseases due to unsafe water sources for domestic
use; or yellow teeth as Fluorine concentration exceeds the allowable threshold in
domestic water.
- Common diseases in the summer are: diarrhea, fever, dengue, typhoid, etc.
- Upper respiratory track infection such as sinusitis, sore throats, etc.
3.11 Traffic and
Transportation
characteristics
- The present motorized transport volume is not great, mainly serving agriculture
production, domestic use and part of small scale construction activities
- Prevailing forms of transport aside from walking are bicycles, motorbikes and small size
cars.
12
IV.ENVIRONMENTAL IMPACT SCREENING
7. An environmental impact assessment (EIA) is an evaluation on the possible positive or negative impact
that a proposed project may have on the environment, together consisting of physical, biological and social-
economic aspects. To identify and evaluate the impacts of any one project, there are various methods
commonly used for environmental impact assessment such as check-list method; matrix method; the Battelle
environmental evaluation system; and cost-benefit analysis method.
8. In this part of the report, the consultant used the check-list method, which is widely used and generally
sufficient for small scale projects having Category B classification.
Table 3.1: Environmental impact Screening of Linh Nham – Deo Nhau road
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
1. Impacts in pre-construction stage
1.1 Impact on
households,
causing living
land or
agricultural land
loss
Yes Minor Negative Temporary
The subproject entails the upgrading of the existing
road with minor widening and adjustments made to
some sections to conform to the technical
requirements of Mountain road Type V. The
Subproject will acquire about 13,392 m2 of
residential land, 37,113 m2 of garden land, 14,728
m2 of annual crop land, 360 m
2 of aquaculture
land, and 14,723 m2 of forest land. The impact is
judge to be not significant since there are no HH to
be relocated and none of the APs will lose more
than 10% of their productive land or livelihood
source.
However, loss of forest lands which are mainly
productive forest owned by local people, will lead
to loss of asset and income of people. Moreover,
some of common animals (birds, rodents…), may
be displaced, however, these can transfer to other
wilderness areas nearby..
2. Impacts in construction stage
2.1 Possibility of
filling up
cultivation areas
along the route
Yes Minor Negative Temporary
Location: Cultivation areas belonging to 2
communes of Khe Mo, Van Han that are located
along the road and at lower elevation as compared
to the current road surface.
Scope: during the construction, soil erosion and
soil and stone falling into creeks or fields may
happen causing filling or sedimentation of fields for
streams. The subproject also has impacts on
agriculture production as non-fertile soil from
excavated embankments may cover farmlands and
silt waterways causing reduced water conveyance
13
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
capacity. While a portion of the excavated
materials can be used as backfill, this only
accounts for about 6% of the redundant materials,
and therefore most of the spoils will have to be
disposed properly. However, since part of the
subproject scheme is to use the redundant soil as
backfill materials for elevating selected adjacent (to
the road) low-lying agricultural lands, then the
impact would have been reduced to medium.
Efforts will have to be done by the contractor to
avoid disposing soil near water ways such as
streams and irrigation canals. Also, the rich organic
top soil would need to be removed first prior to
backfilling, as this will need to be placed on the top
of the leveled farmland to ensure no loss to
agricultural productivity.
2.2 Obstruction
of local
travelling
Yes Minor Negative Temporary
Scope: Limited mobility of local people is a
problem during the harvest time of agricultural
products (green tea, paddy rice, cash crops) during
the months of May and October. Moreover, the
travelling of pupils, farmers and traders at Van Han
markets is also affected by the construction
activities most especially along road sections
undergoing upgrading.
If the temporary stockpiles along the road are not
well managed, the small transport such as
bicycles, motorcycles, and wagons will be placed
at risk, especially during night time and low light
periods such as dawn and sunset.
However, as the construction is prescribed to be
done on individual section by section basis, the
movement of local people using the road is still
possible with a few difficulties through the portion
under construction. Likewise, the difficult period is
only during two months of the year, so proper
scheduling of works that avoid these heavy vehicle
traffic conditions can be easily done. The impact is
assessed to be negative but minor,
Location: Residential areas in 2 communes (Khe
Mo, Van Han) alongside the road;
The Khe Mo secondary school of Khe Mo
commune.
Van Han market of Van Han commune.
2.3 Social
disorders at
residential
Yes Minor Negative/
Positive Temporary
Scope:
- Positive: Migrant workers from other provinces
living in the project area may facilitate cultural
14
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
areas near
upgrading roads
due to presence
of migrant
workers
exchange and promote service trade activities in
the locality.
- Negative: May cause conflicts between migrant
workers and local people due to cultural
differences, may rise to social evils such as theft,
robbery, prostitution, and spread of infectious
diseases (i.e. HIV/AIDS) etc. However, the
residence time of worker in worker’s camp/tents is
short due to requirement of construction on each
route section. Moreover, “In-house rules” for
workers to be enforced by the contractor may help
minimize the negative impacts. The impact is
assessed as minor, both positive and negative,
and will be felt only during the construction period.
Location: Residential areas in Khe Mo and Van
Han communes.
2.4 Risks of
health and
safety of
workers and
local people
Yes Minor Negative Temporary
Scope: Following problems can happen during the
construction:
- The transport of construction materials and
wastes through residential areas of communes
may affect the traffic safety of commuters and
pedestrians.
- Stockpiles and machineries gathered along the
road can serve as traffic hazards to motorist and
pedestrians most especially at night when there
are minimal to no lighting at all..
- Construction vehicles and equipment, have
direct impact on health and safety of workers and
local people that are exposed over long periods
tore-suspended dust, excessive noise, vibrations
and exhaust gases emitted during the transport of
materials and operations of construction
equipment. Domestic waste and sewage from
workers camp will have adverse impacts on the
quality of water, land and air found within the
subproject area.
- The critical areas however are the two
sparsely populated built-up areas along the road
alignment. Negatively effecting these areas is
remote considering the location of the 3 workers
camp, 5 borrow pits and is 6 soil disposal sites are
outside of these settlement areas. Similarly, the
public health risk will only be present during the
construction period which is temporary. These
conditions support the assessment that this
adverse impact is minor and temporary.
15
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
Location: The Khe Mo secondary school of Khe
Mo commune
Van Han market of Van Han commune
Residential areas along roads of 2 communes of
Khe Mo and Van Han
Intersection with National Road No. 379
2.5 Risk of
natural
disasters
Yes
Minor Negative Temporary
Scope: Some lowly embanked section of the road
that crosses streams are often flood during rainy
season, particularly in section of the overflow
bridge crossing Cau Mai stream at K12+876. If
flash flooding occurs during the construction of the
upgraded spillway, such event may cause accident
to construction workers, motorist or pedestrians
who are at this section at the time of the natural
calamity occurrence.
The impact however is avoidable considering
proper scheduling of construction works thru this
single critical stream crossing, during dry season.
The risk is also only felt during the construction of
the spillway, and such threat will disappear upon
completion of such works. The impact is therefore
considered negative but minor, and temporary
Location: Crossing Cau Mai stream and alignment
road, low lands along the road
2.6 Wastes and
sewage
generated from
construction
tents
Yes
Minor Negative Temporary
Scope: solid wastes generated are mainly organic
wastes and redundant food from workers tent. It is
estimated 100 workers for whole construction will
generate 30kg of organic wastes and redundant
food per day. In the mountain area with high
demands of livestock, the redundant foods and
edible organic waste can be used for cattle feed.
Therefore, wastes generated from worker’s tents
are insignificant.
Domestic waste water from the 3 workers tents
may contain pathogenic bacteria among others,
which if not properly treated, can pollute the
receiving waters, and if ingested by local people
can cause gastro-intestinal diseases. Following
good construction practices, that are to be
integrated into the TOR, the contractor is required
to install sanitary field toilets that have septic tanks
and sufficient water supply. Only effluent from
these septic tanks can be allowed to flow into
streams and other water bodies.
Location: the 3 temporary worker’s tents
alongside the subproject road for upgrading.
16
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
2.7 Impacts of
excessive noise
on residential
areas
Yes Medium Negative Temporary
Scope: at each road section, 01 shoveller and 01
concrete mixer will be mobilized for construction
together with 10 ton trucks to transport
construction materials.
The noise from construction activities at the
construction site can affect the Khe Mo Secondary
School with its teachers and pupils during class
time.
Moreover, vehicles transporting construction
materials can have impact on the residential areas
(during their sleep) if they transport during night;
However, the sensitive areas are two built-up rural
areas where sparse residences and limited number
of public institutional facilities have been built. The
general terrain in the subproject area is open
valley, with low hills that are well ventilated. Any
gaseous pollutants, dust, noise and vibrations can
easily be dissipated. Similarly, the site being
vegetated with common grasses, paddy rice and
cash crops; can easily absorb the noise and
vibration generated from construction activities
Noise generated by construction vehicles and
equipment can easily be dissipated. Similarly, the
few units of construction equipment operating
during daytime don’t make significantly noise to
cause much alarm for local residents. Finally, the
construction time of each road section is not too
long, therefore, the impact of noise and vibration is
negative, minor and temporary to last only during
the construction of each segment.
Location: The Khe Mo secondary school of Khe
Mo commune.
Residential areas, Khe Mo secondary school of
Khe Mo commune., CPCs, Van Han market of Van
Han Commune, health centers along the road in
the 2 communes of Khe Mo and Van Han
2.8 Air pollution
because of dust
or construction
vehicular
exhaust (CO,
NOx, SOx, etc.)
Yes
Minor Negative Temporary
Scope: Operation of construction transport
vehicles and equipment are sources of emissions,
and its movement thru unpaved roads causes re-
suspension of dust particles,
Burning asphalt and garbage generates also
significant amount of emission.
The terrain on which the subproject road alignment
is located is wide, open and well ventilated, so
emissions and dust generated can easily be
dissipated by wind. Impacts are to be felt only
17
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
during the construction phase and the effects are
reversible.
The impact of dust re-suspension can last only
during construction time (17 months); and will be
relevant only at the section traversing the 2
commune built-up areas. The impact therefore is
considered not significant.
Location: The Khe Mo secondary school of Khe
Mo commune.
Residential areas along roads of 2 communes of
Khe Mo and Van Han
Van Han market of Van Han Commune
2.9 Soil is
polluted by oil
leaked from
construction
vehicles and
equipment
Yes Minor Negative Temporary
Scope: These petroleum-based hazardous
substances can leak from construction vehicles
and equipment during their operation, and/or
during maintenance work, and the pollutant can
spread to cultivation lands adjacent to the route,
causing negative effects to plants. However, the
estimated number of construction vehicles and
equipment are few, so the probable amount of
petroleum leakage may not be significant to affect
the adjacent lands. Asphalt wastes are those found
in batching plants and containers that are regularly
washed for maintenance purposes. Asphalt is an
expensive material that comes in drums or other
seal containers to avoid spillages. With proper
management of asphalt preparation and
application in the road works, waste bitumen that
are washed from the containers are minimal The
impact is to be felt only during the construction
phase. . Therefore, the possibility of soil pollution
is small. The contractors have to regularly check
their equipment to make sure these work
efficiently.
Location: Location of cultivation areas alongside
the road.
2.10 Impact on
quality of
surface water,
and aquatic
environment,
due to
introduction of
contaminants
into the
waterways such
Yes Minor Negative Temporary
Scope: Contaminants during subproject
construction could be carried away by rain and
surface-water to flow into the existing waterways
and cause the deterioration of its water quality and
affect the aquatic environment in it. Similar to soil
contamination in item #2.9, surface water such as
the Cau Mai, Khe Mo and Ngon Cat streams may
be affected by contaminants from the construction
works. However, the total number of construction
equipment and vehicles are small whose combined
18
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
as soil
droppings,
leakage of
motor oil, and
lubricants,
construction
chemical waste
and/or domestic
waste water
oil leakages may not be significant to impact the
water of these natural drainage assuming the
waste does reach the river/streams.
Also, amounts of asphalt and construction
chemical waste coming from washed water of
containers/batching plants (during maintenance
work) may not also be significant to affect these
water ways, as maintenance work is done a few
times and normally during the time when asphalt is
already being laid on the road alignment.
Domestic wastes on the other hand are confined to
the 3 possible areas where temporary construction
workers camp/tent are to installed. These camps
are provided with garbage collection facilities, and
temporary water closet to contain and treat the
domestic waste of 100 (estimate) workers.
Likewise soil contamination of the water meantime
earth works are being conducted in the 3 water
crossings is very possible. However, the proper
timing of these works preferably during the
summer may minimize the impact, which is
temporary and only to be felt during the
construction phase. Soil sediments will eventually
settle to the bottom of the waterway even without
intervention, however, the amount needs to be
minimized in order that these do not reduce the
water conveying capacity of the stream.
The impact is temporary to be felt only during the
construction period, and soil contamination of
surface water is reversible.
Location: Khe Mo, Ngon Cat and Cau Mai
streams along the subproject road.
2.11 Impacts on
infrastructure
system such as
communication,
information,
electricity etc.
Yes Minor Negative Temporary
Scope: Construction activities can affect the
existing electricity network. A number of these
found within the road corridor will have to be
transferred and restored. The final number of poles
to be moved and length of power cables to be
restored will depend on the final road dimensions
and alignment contained in the detailed
engineering design. The said report is still being
prepared as of this report preparation. The
relocation and restoration of electric power will
have negative but minor impacts as restoration
work is not long (temporary impact) and it is
19
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
standard that the local electric power company
takes care of the work so long as they are informed
well in advance by the subproject owner.
Location: along the road
2.12Impacts on
surrounding
environment of
the borrow pits
Yes Minor Negative Temporary
Soil used in construction is exploited by the
contractors from earth hills in Khe Mo and Van Han
communes along the subproject road. The
exploitation has been agreed and permitted by
local governments of Khe Mo, Van Han and the
owners of the hills. However, following
environmental impacts should be taken into
account:
- Dust, noise caused by shovels, excavators and
the transport of exploited soil will affect the lives of
households living near these hills;
- Collapsed and erode slopes can present a risk to
safety of local people who cultivates nearby and of
workers involving in the exploitation of materials;
waste soil also can fill in nearby fields;
- Rainy water and soil overflowing on hilly slope
can cause to fill drainage canals near the hills.
Each earth hill has soil deposit of 2,000 – 4,000 m3
which will be exploited for the construction of 2 -
6km of road.
The impact is negative, however this may only be
minor as the total amount of filling materials is at
27,930 m3. This amount can be well provided from
a part of the excavation soil from the existing
alignment of 430,599 m3 because it is likely that
not all of the excavated materials could be suitable
as filling materials, So there will be a need to
exploit other soil from the borrow pits. The
contractor, in this case, shall take measures to
ensure safety at the borrow pits. The strict control
of environmental safety and the monitoring
coordination from CSC, CSB and local
governments could help reduce impacts at these
areas.
Location: Hills listed in the Annex
2.14 Benefit of
work or
livelihood by
hiring local
workers
Yes Significant Positive Temporary
+ Location: 2 communes in the subproject area
(Khe Mo, and Van Han) and surrounding
communes.
+ Hiring of local labor force is given priority,
especially qualified members of poor households,
policy preferential households, and female headed
households. This local hiring workers will increase
20
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
local HH income, and promote poverty reduction in
local community. When local people are employed
in construction works, this will solve short-term
employment for the 100 directly-hired workers.
3. Impacts in operation stage
3.1 Increase
abilities of
accessibility to
markets,
schools, jobs,
health center
and other
services
Yes Significa
nt Positive Long-term
Location: Communes of Khe Mo, Van Han of
Dong Hy district
Scope: the subproject road will enhance the
accessibility to services and public facilities such
as markets and district health clinics, reducing
traveling time, transport costs .
In the subproject area, there are 05 schools, 04
health stations and 04 local markets in the line
connected to the district administration center by
National Highway 379
Reduction of transport cost for local agricultural
products to the market will result in the increase of
farm incomes, better access to social services, and
therefore improvement of local socio-economic
conditions, and reduction in poverty levels.
3.2 Changes in
terms of traffic
safety Yes Significant Negative Long-term
Location: on the subproject road, especially at the
intersections.
Scope:
The route had been designed following GOV road
quality standard. These standards take into
consideration technical as well as safety of
motorist using the road. Similarly, environmental
nuisance such as dust level is reduced, road
surface is smooth and warning signs installed.
These are intended to make motoring convenient,
comfortable and safe.
- Negative: The improved road condition is
expected to favor an increase in the vehicular
traffic volume. While the improve road will favor
more motorist, it will also encourage over-speeding
which may cause accidents. The traffic projections
in the future had estimated at 10% increase in
vehicles using the route daily.
The positive impact is significant since it already
addresses a chronic access problem in the thru the
improvement of subproject road, thereby making
travel convenient, reduced transport maintenance
cost and reduction in accidents related to poor
roads. However, excesses such as drunk driving
and over speeding are most possible, but are
21
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
controllable with the support of local authorities.
3.3 Increased
noise and
vibrations level
due to
increased traffic
volume
Yes Minor Negative Long-term
Location: The residential area along the road
Scope: Growth of vehicular traffic volume (10%
per year) is expected to result in the increase noise
levels and vibration along the road. Ambient noise
created by the increase in traffic may affect local
residents, institutions (i.e. hospital, health centers,
schools, etc.) that are located within the SIA.
The effects of noise and vibration are insignificant
as (a) the population density is low, (b) local terrain
and vegetative cover can easily dissipate these
nuisances; and (c) the traffic volume is not high
(the traffic volume increase is as small as 10%.
3.4Changes in
levels of dust,
air quality, due
to traffic volume
increase.
Yes Minor Negative Long-term
Location: Residential areas of communes located
alongside the road
Scope: Growth of vehicular traffic volume (10%
per year) is expected to result in the increase in
vehicular emissions which include Particulate
Matter (PM10) which are find dust particles made
of hydrocarbons that are created during engine
combustion. Dust particles from fine soil, however
had been almost removed since the upgraded road
is already paved with asphalt. PM10 (large
quantities) created by the increase in vehicular
traffic may affect local residents, institutions (i.e.
hospital, health centers, schools, etc.) that are
located within the SIA.
However, the impact is small as the (a) the
population density is low, (b) local terrain and
vegetative cover can easily dissipate these
nuisances; and (c) the traffic volume is not high.
3.5 Changes of
land use
patterns in
areas next to
subproject area
Yes Significant Positive Long-term
Location: Cultivation areas and residential areas
along the road
Scope:
- Positive: In the SIA, once the subproject road is
improved, local entrepreneurs may be encouraged
to expand their current business, as well as invite
investors to establish commercial ventures which
can create new jobs, increase economic
development in the area, and improve the life of
the local residents.
- In view of the positive developments within the
subproject area, it is most possible that the land
use of the area along the SIA may shift from
agricultural to commercial and residential. The
change is significant since it is long term, covers
22
IMPACT
Potential impact
BRIEF DESCRIPTION OF IMPACT LOCATION
AND SCOPE
yes/no
minor/si
gnifican
t
negative/
positive
temporary/
permanent
initially the direct beneficiary areas but can expand
to adjacent areas.
- Negative: Without proper land use planning and
enforcement of this approved plan, spontaneous
and uncontrolled establishment of residential and
commercial structures along the road leads to
other environmental issues (i.e. untreated
wastewater, uncollected solid waste generation,
social disturbance, inadequate delivery of basic
services, etc.).
3.6 Changes to
the value of
natural
landscape/visibl
e
Yes Significa
nt Positive Long-term
Location: Along the road
Scope: Among the benefits of the subproject is the
all-weather conditions of the upgraded road that is
not be affected by flooding, stable slopes not
affected by landslides, and improved landscape
resulting from restoration of temporarily used
lands. This condition may encourage local people
improve their houses and garden, and others.
These improvements contribute to the betterment
of the area’s aesthetics.
3.7 Creating
employment for
local community
Yes Minor Positive Long-term
Scope: In the SIA, once the subproject road is
improved, local entrepreneurs may be encouraged
to expand their current business, as well as invite
investors to establish commercial ventures which
can create new jobs, increase economic
development in the area, and improve the life of
the local residents.
Location: Along the entire subproject road
Table 3.2: Environmental impact screening of Van Han market upgrading
IMPACT
POTENTIAL IMPACT
BRIEF DESCRIPTION OF IMPACT LOCATI\N
AND SCALE yes/no
minor/
significant
negative/
positive
temporary/
permanent
1. Impacts in pre-construction stage
1.1 Increased
waste materials
from the
dismantlement of
old structures
Yes Minor Negative Temporary
Location: Van Han market and adjacent areas
Scope: Materials from the existing market that
should be dismantled include bamboo pile,
plastic roof, cement, concrete and broken
bricks. The irresponsible dumping of waste
materials in wrong place will affect the
neighboring areas most especially if these are
productive agricultural lands or waterways.
23
The volume of waste materials is not significant,
and some of these can even be reused by local
people. Proper coordination with local
authorities or concerned persons for the reuse
and disposal of inert materials is required. This
adverse impact is minor, and to be felt only
once.
1.2 Increased
noise, and dust
level
Yes Minor Negative Temporary
Location: the neighboring areas of Van Han
market
Scope: increased noise level due to the
operation of workers and equipment to
dismantle structures, especially jack hammers
and bulldozers will affect the daily activities and
sleep of local people living nearby the route in
hamlets of Khe Mo 2, Tien Phong, Ao Rom 1,
Ao Rom 2, Ao Dau, Hai Ha, Cau Mai, Van Han,
Pha Ly, La Dum, Ap Che, Lang Hoa, Thai Hung
in Khe Mo commune and Van Han commune.
The type and make of the existing market will
not require heavy equipment and noisy jack
hammers to dismantle. Manual labor may be
more appropriate to deploy and at the same
time provide livelihood for the local people. By
using manual labor, it is most possible that the
debris may still be reused by local people, in
contrast to heavy equipment which will definitely
demolish the structures and its components.
Manual labor will not generate as much noise
as heavy equipment, and they will only operate
in the morning where there is light. Dust is
inevitable, but can be minimized. The impact is
therefore adverse, but minor and temporary to
last only during the dismantling period.
2. Impacts in construction stage
2.1 Disruption in
the trading
activities and
commercial
transactions in the
area
Yes Small Negative Temporary
Location: Van Han market
Scope: The market is to be built on the existing
one, so land acquisition is not necessary.
Currently there are about 80 people doing small
businesses in the market. The average revenue
is about 6 mill. VND/person. But during the
construction of the new market, the existing
locators/traders may have to move to a
temporary market situated along the road near
the subproject market for upgrading. It is
possible that a reduction in revenue may
happen during the 18 months of construction,
since the space provided in the temporary
market may not be enough (the temporary
market is located 500 m far from the old market,
with an area of 2,000 m2
compare to total
upgraded market area of 2,448.6 m2
for traders
to store their goods for sale, or the support
facilities such as sufficient clean water, electric
power, solid waste collection and disposal, and
24
sewage are not adequate; such that buyers opt
to do their marketing elsewhere.
The disruptions and temporary relocation of
trading activities will affect: (i) income of
households (ii) hindering movement of transport
thru the temporary facility; (iii) may attract more
social evils such as petty thief; (iv) solid wastes
collection and disposal; (v) sanitation problem
due to possible inadequate toilet and water
supply, which may lead to public health issues.
The impact is small considering that the loss
income (if any) can be reimbursed as part of the
REMDP allowances, the market fees collected
by the local government from vendors will be
reduced, temporary utility facilities (i.e. water
supply, electric power, garbage collection,
drainage, etc.) will be provided by the contractor
as part their contract, and impact period is only
limited to a year, and these effects are
reversible.
2.2 Increased dust
level Yes Small Negative Temporary
Location: Van Han commune
Scope: Construction activities (transporting
materials, soil excavation and shoveling) in the
market area may cause dust re-suspension
especially during the dry months. The dust
particles once it is blown by wind towards the
temporary market stall will have impact on food
quality and other merchandizes displayed and
sold uncovered in the market. Therefore,
sanitation and safety of consumers are at risk.
However, considering the limited volume of
foundation excavation and aggregate materials
needed for construction; this impact can be
considered as adverse, small and temporary, to
be felt only during the construction period.
2.3Risk of unsafe
conditions to
motorist and
pedestrians using
the commune road
fronting the
temporary market
Yes Small Negative Temporary
Location: The neighboring areas of Van Han
market
Scope: The concentration of traders in the
temporary market (near Van Han market) may
obstruct the flow transport and cause
inconvenience to local commuters, truckers of
merchandize, and local people living along the
village road of Van Han;
The transport of materials and waste during the
construction of the market will put more vehicles
on the communal road thereby slowing down
traffic speed and decreases the mobility of local
traffic and pedestrians.
If the construction site is not protected, local
people including children may stray into the
construction site (market in construction) and
may put themselves in risk of accidents (i.e.
falling into excavations, being hit by falling
objects from construction activities, etc).
The impact is small in view of the short segment
25
of communal road that the temporary market is
located, the short duration of the impact which
is during the construction of the main market.
3. Impacts during operation stage
3.1 No adequate
waste water
pollution control
Yes Significant Negative Temporary
The upgrading of the market has included the
building of a public toilet of 40 m2.
Thai Nguyen PPMU had officially confirmed that
a septic tank will be installed as an important
part of the market facility.
The drainage system of the market will also be
built. The treated effluent of this facility will be
discharged into the drainage system of Van Han
commune.
The drainage system of the commune exists as
drainage canals flow around the commune
without treatment process, diseases and odor
problems may arise as a result of it.
In case the drainage system is not maintained
(cleared) regularly; the obstruction of the
drainage system will cause local water logging,
generating bad odor and insanitary condition in
the market area, affecting the food quality being
sold at the market; Sanitation and food safety
are very important aspects of the subproject
operations as deficiencies in this area may
seriously impact on the public health. Fresh
foods (i.e. meat, fish, vegetables, etc.) require
clean surroundings. Contamination of these
foodstuff due to dirty water used in washing the
merchandize may lead to gastro-intestinal
diseases of local people eaten foods which are
bought from the market.
The adverse impact is significant, and will
remain active until proper sanitation facilities
and practices are put in place.
3.2 Solid Waste Yes Medium Negative Temporary
A solid waste transfer tank will be built during
the construction for collection of garbage in the
market. Refuse will be transferred to the central
dumpsite of the district (Phuc Thanh dumpsite
in Dong Hy district, area of 8ha).
However, if the garbage in the tank is not
regularly collected and allowed to be kept for a
long time, this will lead to bad odor and
insanitary condition which affect households
living near the market.
The impact can be considered medium as
inadequate garbage collection can lead to
serious public health issues. The effect is
however temporary and it will remain until
regular garbage collection is resumed.
3.3 Fire incidents Yes Minor Negative Temporary
The poor awareness of trading households in
terms of fire prevention, especially during winter
when heating utilizing firewood and other
combustion able materials and the lack of strict
26
management of the market management board
are among reasons for the occurrence of fire in
the market, affecting goods sold and putting the
lives of vendors, buyers, and residents of
adjacent areas at risk.
As it is a rural market in a mountainous area
where goods are not kept overnight in the
market stall. If fire does erupt after marketing
day, less flammable materials will be around.
Moreover, the fire can be extinguished quickly
with the use of common fire-fighting equipment
such as fire extinguishers and the participation
of vendors and local people in the market.
27
V.OUTLINE OF ENVIRONMENT MANAGEMENT PLAN (EMP)
A. Environmental impact mitigation plan
Table 41: Environmental impact mitigation plan for Linh Nham – Deo Nhau road
Potential impacts Mitigation Measures Responsibility Cost
1. Pre-construction stage
Impact on affected
households, due to
loss of residential
and agricultural
lands
Implementation of mitigation measures as presented in the Resettlement Plan of the subproject. For impact relating to loss of forest land, some of measures to be applied to reduce effect: - Road alignment to be selected in a manner where minimal trees are to be affected;; - Notify affected people who having forest, trees within acquired areas to cut trees, dismantle assets and relocate crop; - Plant and restore vegetation in temporary borrow land as prior to operations stage. - Disclose environmental grievance redress mechanism to people
PPMU
Refer to the
approved RP
2. Construction stage
2.1 Possibility of
filling up cultivation
areas along the
route
- Before the construction of the next road section, the
contractors need to:
(i) Investigate the topography, vegetation status, cultivated
areas along the road of the next sections:;
(ii) Reinforcing road foundation to avoid landslides leading to
impacts on the nearby cultivation areas and reducing conflicts
between households having cultivation areas.
(iii) Informing the construction plan of the next section to the
heads of related village.
- Cleaning and clearing dropped sand and soil along the
constructed sections.
- At roads along the hill with earth slope higher than 12
degrees or steep slope should be excavated in form of
terraces to stabilize the slope and avoid erosion. At the road
crossing Nhau pass, terraces are excavated with 1m bench
width.
- Disclose environmental grievance redress mechanism to
people
Contractor
Included in
the contract
with
contractor
2.2 Obstruction of
local traveling
- Installing warning signs at strategic location within the
construction site;
- Promptly clean and clear dropped sand and soil along the
constructed sections;
- Disclose the construction plan and schedule to the
communities living at the subproject area through information
boards in CPCs, consultation meetings, etc.;
- In the construction of the river crossing through Cau Mai
stream, provide a temporary earth bypass to allow continued
access of vehicles and pedestrians. Warning signs to be
installed at the two approaches of the overflow bridge.
- Disclose environmental grievance redress mechanism to
people
Contractor
Included in
the contract
with
contractor
2.3 Social disorders - Setting up regulations for off-work hour activities; Contractor Included in
28
at residential areas
near upgrading
roads
Disseminating customs and practices of local people to
workers;
- Disclose environmental grievance redress mechanism to
people
the contract
with
contractor
2.4 Risks to health
and safety of
workers and local
people
- Installing safety signs in the construction site;
- Avoiding construction activities during strong rains and
floods;
- Implement measures to reduce dust (i.e. watering of unpaved
roads during dry days, observed speed limits, etc.);
- Drain and fill stagnant water pools as soon as discovered.
- Organize periodical health checks for workers (once per 3
months during construction stage)
- Popularize the plan for prevention of infectious diseases to
the local people;
- Ensure safety for construction zones and minimize the
access to it by local communities.
- Installation at strategically location, safety warning signs in
work areas;
- Avoid construction activities during heavy rainy conditions;
- Clean up construction site after construction completion to
ensure safety for local people.
- Disclose environmental grievance redress mechanism to
people
Contractor
Included in
the contract
with
contractor
2.5 Risk of natural
hazards
- Roads along the hill with earth slope higher than 12 degrees
or steep slope should be excavated in form of terraces to
stabilize the slope and avoid erosion (proposed by survey and
design consultancy). At the road crossing Nhau pass, terrace
is excavated with 1m bench width.
- Low lands on the road where crossing Cau Mai , Khe Mo and
Ngon Cat streams are leveled with one more sub-base to
avoid inundation and reuse excavated road base.
- Install warning signs at sensitive positions during
construction where risk of landslide and inundation is
temporary (i.e. Cau Mai stream crossing the alignment road,
Nhau pass)
Contractor
Included in
the contract
with
contractor
2.6 Wastes and
sewage generated
from construction
tents
- Install waste bins at construction site and workers camp to
serve as temporary waste receptacles before burning or
burying as local custom,
- Contact local people residing near the road alignment, as to
who are interested to get the redundant food from workers
camp for use as animal feed. Indiscriminate rubbish dumping
on the neighboring areas is prohibited to avoid bad odor and
spread of diseases.
- The contractor is required to install sanitary field toilets that
have septic tanks and sufficient water supply at 3 worker
camps at Km2+094; Km7+730; Km16+730. Only effluent from
these septic tanks can be allowed to flow into streams and
other water bodies.
- Do not discharge untreated effluent directly into water bodies;
- Avoid construction of worker’s tents in areas prone to
frequent floods or near streams along the road, surface ways
that run parallel or cross the road, including Khe Mo, Ngon Cat
and Cau Mai streams
Contractor
Included in
the contract
with
contractor
2.7 Impacts of - Carry out periodic preventive maintenance of construction Contractor Included in
29
noise on the
residential areas
equipment and vehicles;
- Limit construction activities during night time near the
residential areas;
- Disclose the construction plan and schedule, to the heads of
related village and representatives of local communities
the contract
with
contractor
2.8 Air pollution
because of dust or
exhaust (CO, NOx,
SOx, etc.)
- Periodic cleaning of the constructed road surface near the
residential areas which scatter along the road including
hamlets of Khe Mo 2, Tien Phong, Ao Rom 1, Ao Rom 2, Ao
Dau, Hai Ha, Cau Mai, Van Han, Pha Ly, La Dum, Ap Che,
Lang Hoa, Thai Hung in Khe Mo commune and Van Han
commune;
-Regularly water the unpaved road surfaces;
- Covering the cargo of trucks transporting construction
materials and waste, to make sure materials are not dropped
down on road;
- Ensuring that all construction vehicles and equipment are
periodically maintained: regular lubrication, promptly detect
breakdowns;
- Disclose environmental grievance redress mechanism to
people.
Contractor
Included in
the contract
with
contractor
2.9 Soil is polluted
by oil from
construction
equipment and
chemicals.
- Store chemicals in safe areas with concrete floor, roof for
avoiding rainwater and locate in non-flood-prone area/s;
- Ensure vehicles and construction equipment are maintained
in good working condition and promptly repaired for any
damage and/or oil leaks;
- Cover or plant around long-term material storages by
indigenous trees which grow quickly;
- Avoid directly discharge from concrete -mixing equipment to
rivers, stream and water-ways;
- Install wheel-washing equipment at the construction sites.
- Disclose environmental grievance redress mechanism to
people
Contractor
Included in
the contract
with
contractor
2.10 Increased
surface water
pollution
- Waste water, oil and grease leaked during the washing of
vehicles and equipment should be collected and separated
from general waste .
- Regular disposal of wastes to disposal site or wastes are
burned or burried as local custom ,
- Establish at temporary construction grounds secured
temporary storage areas that have concrete flooring and
roofing for toxic and hazardous construction materials (i.e. fuel
& oil,..) avoiding rainwater and preventing flooding
- Ensure that vehicles and construction equipment are
regularly maintained in good condition, promptly detect
breakdowns; machineries are within duration of use and
licensed by competent authority.
Contractor
Included in
the contract
with
contractor
2.11 Impacts on
infrastructure
system such as
communication,
information,
electricity etc.
- Proper coordination with electric company for transfer and
restoration of affected electric poles and transmission lines.
- Ensure that vehicles and construction equipment are
regularly maintained in good condition, promptly detect
breakdowns; machineries are within duration of use and
licensed by competent authority;
- Limiting construction vehicles speed in the residential areas
(under 15km/h) and along the road;
- Raising electricity line where the cable sag down to the road
Contractor
Included in
the contract
with
contractor
30
after local government and electricity management agency
allow;
- Arrange appropriate operating hours of construction vehicles
when using regional traffic road to avoid obstructing the
movement /travel of local people.
- Installing warning signs to avoid collision with such
infrastructure as electric pole, houses
2.12 Management
of waste materials
- Classify excavated materials before reusing them for field
leveling;
- Toxic wastes are collected and gathered in waste bins; oil
and fuel for construction are kept in depot;
- Contract with local sanitation service to transport solid waste
to dumpsite as specified by the locality.
- Consult local governments and households of the elevation
of field leveling;
- Disclose environmental grievance redress mechanism to
people.
Contractor
Included in
the contract
with
contractor
2.13 Impacts on
surrounding
environment of the
borrow pits
- For impacts of dust and noise caused by excavator, shovel
and the transport of exploited soil on households residing near
the hills.
+ Regularly watering the road passing residential area
(during dry season) to reduce dust in the construction site
yet avoiding causing muddy condition;
+ The exploitation and transport of soil during night are
absolutely banned;
+ Washing wheels as the vehicles get out of the
exploitation site is necessary;
- For such impacts as: eroded or collapsed slope threatening
safety of local people cultivating nearby; safety of workers who
are exploiting soil and the possibility of waste soil filling nearby
fields
+ Excavate a trench to collect water around the borrow pit
leading to unused land before carrying out exploitation
activities;
+ Establishing fence to separate the exploitation site from
the outside area;
Cleaning materials spilled on the neighboring area as
soon as field filling is detected;
+ Compensating for damaged crops as agreed with locality
and in accordance with regulations of the state;
- For such impacts as water and soil along the hill filling
drainage canals nearby
+ Regular check and clean the canals which are affected
as soon as the filling is detected;
+ Coordinating with local governments to monitor and
detect impacts;
- Disclose environmental grievance redress mechanism to
people
Contractor
Included in
the contract
with
contractor
3. Operation stage
3.1 Changes in
terms of traffic
safety
Installing speed limit sign, load limit sign for vehicles to ensure
traffic safety
2. Disseminate knowledge about traffic safety to local people
DPC Dong Hy
Local budget
3.2 Changes in - DPC Dong Hy
31
levels of noise,
dust, air quality,
due to traffic
volume increase.
- Plant trees along the road side to reduce the impact of dust,
noise, vibrations and vehicles emissions;
- Work with local officials to ensure regular cleanness of road
surface, shoulders and side ditches;
- Warning signs are to be installed in strategic locations to
warn motorist against excessive use of horn according to
regulations for sensitive areas, especially in areas next to
schools, medical stations, and CPCs;
- Enforce regulations for trucks travelling on the road to cover
cargo to avoid goods from dropping.
- Disclose environmental grievance redress mechanism to
people
Local budget
Table 4.2: Environment management plan for Van Han market upgrading project
Potential
impacts
Mitigation Measures Responsibilit
y
Cost
1. Pre-construction stage
1.1 Increased
waste
materials due
to dismantling
of old market
structures
Classifying waste materials and arrange neatly in one place within the
market grounds; such that waste materials as cement and bamboos can
be provided to local people so that they can be reused.
The materials that cannot be reused will be collected and a district
environment enterprise will be contracted to transport these waste
materials to the dumpsite as required by the local authorities.
Contractor
Included in
the contract
with
Contractor
Increased
noise level
- Dismantling operations during night and afternoon rest of neighboring
households is not allowed
- Ensure all vehicles and construction equipment are being well
maintained
Contractor
Included in
the contract
with
Contractor
2. Construction stage
2.1 Disruption
in the trading
activities and
commercial
transactions in
the area
- Disclose in advance the construction plan of the market to local
government (commune) and trading households in the market;
- Coordinate with local government to establish the temporary market
during construction stage. The responsibility of collecting garbage from
the temporary market will be that of the individual trading households;
Contractor,
Van Han
Communal
Peoples
Committee
Included in
the contract
with
Contractor
2.2 Increased
dust level
- Regularly water the unpaved market construction grounds during dry
days.
- Regularly clean dust in the construction site and spilled soil from
vehicles in the residential areas;
- The cargo of construction vehicles transporting materials should be
covered with canvas to ensure materials are not spilled on the road
during operations;
- Disclose environmental grievance redress mechanism to people
Contractor
Included in
the contract
with
Contractor
2.3 Increased
noise level
- Construction during night and afternoon rest of neighboring households
is not allowed
- Ensure all vehicles and construction equipment are being well
maintained
- Disclose environmental grievance redress mechanism to people.
Contractor
Included in
the contract
with
Contractor
2.4 Risk of
unsafe
- Erect fence to separate the market construction site from residential
and other areas neighboring the subproject site; Contractor
Included in
the contract
32
conditions to
motorist and
pedestrians
using the
commune road
fronting the
temporary
market
- Arrange staff to look after the construction site; not allowing outsiders
to go into the construction site;
- Installing warning signs in areas prone to accidents in the construction
site.
- Vehicles transporting materials should follow traffic regulation, limiting
speed as crossing residential area, schools and temporary market;
- Material transport vehicles are prohibited from carrying load in excess
of road capacity
with
Contractor
3. Operation stage
3.1 Waste
water
- Regularly check and repair the market’s drainage system and its
connections.
- Dredge mud and clear the drainage canals of the market;
- Strictly enforce the no littering of garbage into the market’s drainage
system
Market
Management
Unit (MMU)
Local
budget
3.2 Solid
Waste
- The temporary garbage holding area has to be covered to avoid bad
odor from spreading or intrusion of flies and rodents that can spread
diseases, before these are transported to the local landfill;
- domestic waste water to be channel first to the septic tank and only its
effluent can be discharged into the commune’s drainage canal system;
- Regularly collect garbage and transport them to specified dumpsite of
the commune or district.
MMU Local
budget
3.3 Fire
incident
- Fire extinguishers should be provided and market staff trained in its
use
- Monitoring the neat and safe display of goods in the market.
MMU Local
budget
33
B. Environment monitoring plan
9. Environmental impact monitoring is implemented to assess impacts of the project related to surrounding
environmental conditions.
Table5: Environment impact monitoring plan
Mitigation
measure Parameters Location Method Frequency
Responsibil
ity Cost
1. Construction stage
1.1 Erosion
control
-Soil erosion covering
farm lands;
- Siltation of waterways
- Farmlands and
waterways
adjacent to
unstable road
embankment;
- Farmlands and
residential areas
adjacent to borrow
pits & quarries
Observation After heavy
rain Contractor
Included
in the
contract
1.2 Traffic
management
- Hours delay due to
construction related
vehicular traffic;
- Complaints by local
residents due to
construction traffic.
- Farmlands and
waterways
adjacent to
unstable road
embankment;
- Farmlands and
residential areas
adjacent to borrow
pits & quarries
Observation After heavy
rain Contractor
Included
in the
contract
1.3 Proper
personnel
management
- Complaints by local
residents related to
actions by construction
workers
Residential areas
crossed by road Observation
Every
month and
when
receiving
feedback
from
community
Contractor
Included
in the
contract
1.4 Health and
Safety of
Personnel and
Nearby
residents
- Number of work
stoppages due to work-
related accidents
- Number of
construction site
accidents involving local
residents
Construction site Observation,
interviews
Every
month Contractor
Included
in the
contract
1.5 Proper
maintenance
of construction
equipment
and vehicles
- Number of vehicle and
equipment breakdown
- Volume of waste oil &
lubricants collected at
maintenance area.
Construction area,
Vehicle &
equipment
Maintenance area
Observation,
interviews
Every
month Contractor
Included
in the
contract
34
Mitigation
measure Parameters Location Method Frequency
Responsibil
ity Cost
1. Construction stage
1.2 Noise
reduction Noise level
- Residential sites
along the route
- Van Han market
Observation
Every
month and
when
receiving
feedback
from
community
Contractor
Included
in the
contract
1.2 Dust
reduction Dust level
- Residential sites
along the route
- Van Han market
- work site
Observation
Every
month and
when
receiving
feedback
from
community
Contractor
Included
in the
contract
1.3
Construction
solid waste
management
-Volume of excavation
materials;
- Volume of excavation
materials reused;
- Volume of excavated
materials placed at
disposal site
- Volume of other
construction spoils and
debris delivered to
disposal site
-Construction site;
- Disposal site
Observation,
interviews Weekly Contractor
Included
in the
contract
1.4 Control of
surface water
quality
-Turbidity
- Indicator of oil, bad
odor and other visible
waste water;
- garbage at waterways,
Khe Mo spring,
Ngon Cat and
Cau Mai spring
Peripheral area of
the borrow pit
Observation
Every week
and after
heavy rains
Contractor
Included
in the
contract
2. Operation stage
2.1 Air quality,
noise
Re-suspended dust,
and noise
Residential sites
along the route Observation
Every 6
months in
the first 5
years of
operation
Dong Hy
CPC Provincia
l Budget
2.2 Traffic
safety
Number of
transportation
accidents, causes and
the seriousness of the
accidents
Residential sites
along the route,
intersections with
social
infrastructures,
road crossings
Discussion
with local
management
staff
Every 6
months for
the first 5
years of
operation
Dong Hy
CPC Provincia
l Budget
35
C. Environmental Compliance Monitoring
10.Environmental compliance monitoring was conducted to check compliance with operating procedures, technical standards and/ or specification requirements for contractors in the environmental management plan (EMP)
Table 6.1: Environmental compliance monitoring plan for Linh Nham – Deo Nhau road
Mitigation measures
Parameters Location Methods Frequency Responsibility
Cost
1. Pre-construction stage
1.1 Measures to mitigate impacts due to loss of lands
- Information materials posted at CPC board (i.e. construction schedule; schedule of meetings, etc.) -Payment of compensation and other benefits to APs -Restoration of temporary affected lands; - Resolution of complaints/grievances of APs.
Road alignment
Observation, interviews
Monthly, or when actual payment of compensation & other benefits occur.
PPMU Included in the contract with the contractor
2. Construction stage
2.1 Control soil, rock to avoid impact on erosion, sedimentation into cultivation area, water pollution
- Verify stability of embankment and cut slope. - Verify cleanliness of drainage systems -Cleaning of construction areas of solid waste and debris. - Condition of materials storage areas
Construction site
Observation After heavy rain CSC Included in the contract with the PPMU
2.2 Manage borrow pits and temporary borrow areas (worker tents, storage materials)
Position and condition of material storage areas (away from waterway, concrete floor, covered top…)
Sanitation condition of
worker tents, waste
treatment equipment,
general conditions:
possible water supply,
drainage system
Construction site
Observation Weekly CSC Included in the contract with the PPMU
2.3 Implement traffic management plan
-Traffic warning signs installed at strategic areas - Road by-pass established in critical areas; - Information materials posted at CPC bulletin board to relay construction
Construction site
Observation Weekly CSC Included in the contract with the PPMU
36
schedule; - Traffic aide deployed to assist motorist passing thru construction site;
2.4 Proper Management of personnel most especially migrant workers
- House-rules developed for construction personnel - Orientation held for construction workers on relationship with local population, health and sanitation. - Complaints/ grievances raised by local people and resolved
Workers camp; residences crossed by road.
Observation, interview
Monthly CSC Included in the contract with the PPMU
2.5 Occupational health and safety of Workers and local residents along road alignment
- Health and Safety Orientations held for workers; - Provision of Personal Safety Equipment and training on their use; - Provision of first aid station and arrangements with local health facility for treatment of workers and residents - Provision of sanitary facilities at worker’s camp and its cleanliness.
Workers Camp
Observation, interview
Monthly CSC Included in the contract with the PPMU
2.6 Manage and maintain construction equipment and vehicles in good condition
- Preventive maintenance of construction equipment and vehicles -Noise and exhaust generation by construction equipment and vehicles kept at allowable levels; covering of trucks; -Oil separators and
seal containers installed at vehicle/ equipment site
Residential areas, health centers, schools traversed by road; Worker’s camp/ vehicle maintenance area.
Observation, interviews
Weekly CSC Included in the contract with the PPMU
2.7 Implementation of dust and emissions reduction measures
- Water spraying of
open and unpaved
roads,
- Covered cargo and
limited load of trucks,
- Maintained condition
of construction
vehicles and
equipment for
construction
Planted trees around
Construction site
Observation Weekly Contract
or
Included in the
contract with the
PPMU
37
temporary borrow
areas
2.8 Solid Waste management
- Number and
condition of
construction waste
disposal sites
- Number of condition
of temporary waste
disposal site;
-Number and
condition of
construction materials
storage site
Disposal sites and construction materials storage area
Observation Weekly CSC
Included in the
contract with the
PPMU
2.9 Prevention of damages to local utilities.
- Proper management of construction equipment and vehicles: (i) preventive maintenance of construction vehicles and equipment; (ii) Prompt repair of damaged vehicles and equipment on site; (ii) Establishment and observance of speed limits for construction vehicles and equipment - Coordination between Contractor and public utility company for affected assets requiring relocation/ restoration. - Posting of information materials on CPC board informing the people of schedule utility service disruptions
Construction area with vulnerable public utilities
Observation Weekly CSC
Included in the
contract with the
PPMU
2.7 Quarry sites and Borrow pits
Permits or clearances issued by competent government agencies Measures to reduce dust: regular watering, washing wheels, Trench to collect water,
Construction site
Review of documentation; Observation, interviews
Before start of exploitation; weekly
PPMU Included in the contract with the PPMU
3. Operation stage
3.1 Limit speed and load of vehicles
Number and position of signs along the road Number of accidents on the road
Along alignment road
Observation Once per 06 months during the 5 year of operation
CPCs
Allocated provincial budget for O&M
3.2 Measures to reduce noise, dust, air quality, due to traffic
Planted trees, warning signs to avoid excessive use of horn
Along alignment road
Observation Once per 06 months during the 5 year of operation
CPCs
Allocated provincial budget for O&M
38
volume increase
Table 6.2: Plan for environmental regulation compliance monitoring for Van Han market
Mitigation measures
Parameters Location Methods Frequency Responsibility
Cost
1. Pre-construction stage
1.1 Proper disposal of waste materials after market dismantling
- Type and volume of
waste materials,
-Amount of materials
reused;
-Disposal of inert
waste in Commune or
District landfill
Market
grounds,
landfill
Observation,
community
consultation
At the time of market dismantling
CSC Included in the contract with the contractor
2. Construction stage
2.2 Storage of materials
Condition of material storage areas
Construction site
Observation Weekly CSC Included in the contract with the PPMU
2.3 Construction equipment and vehicles
Noise and exhaust generation; covering of truck cargoes; oil/ fuel leaks; speed of transport vehicles; frequency of truck deliveries
Residential areas around market construction site
Observation Weekly CSC Included in the contract with the PPMU
2.4 Workers’ camp conditions
Cleanness; sanitary toilet, adequate water supply, waste collection facilities, general conditions
Worker’s camp
Observation Weekly CSC Included in the contract with the PPMU
2.5 Waste Management
Amount of reused excavated materials, Proper filling of low-lying areas using excavated materials and temporary waste storage area
Construction site
Observation Weekly CSC Included in the contract with the PPMU
2.6 Quarry sites and Borrowing areas
Approvals related to exploitation of borrow pits and quarry areas
Borrow pits and Quarry Areas
Viewing related documentation
Before starting on natural resources exploitation
PPMU Included in the contract with the PPMU
3. Operation stage
3.1 Waste Management
Frequency of waste collecting, number of rubbish bins in market
market site Observation Once per 06 months during the 2 year of operation
CPCs in subproje
ct area, MMU
Provincial budget
39
D. Assign tasks in implementation of EMP
Table 7: EMP Implementation Plan
Organization
Roles and Responsibilities
Subprojects preparation Subproject implementation Subprojects operation
CPMU
Guide safeguard
consultants during the
preparation of IEE report.
Review and provide
comments on IEE
submitted by Safeguard
consultants
- Guide PPMU safeguards officer
on implementation of EMP during
construction period.
- Monitor progress during
construction period.
- Collect environmental reports
from PPMU
- Prepare 6 month monitoring
report and submit to ADB and
DONREs/DPC for review
- Guide PPMU safeguards
officers on
implementation of EMP in
the first operation year.
- Monitor progress in the
first operation year.
- Prepare Semi-Annual
Project environmental
compliance report based
on progress report
submitted by PPMU
PPC Not applicable
The Project employer with supreme
responsibility for environmental
activities of subproject during the
construction period
The project employer is
responsible for
environmental activities in
the operation stage,
including implementation of
EMP
PPMU
- Assist Safeguard
consultants hired by
CPMU and responsible
for the preparation of
IEE .
- Ensuring PPMU staff
are well trained in
environmental
management
- Responsible for EMP
implementation during pre-
construction and construction
stages;
- Ensure that details of contracts
and bidding invitation documents
include environmental
requirements.
- Implement inspection and
monitoring of environmental
concerns during construction
stage.
- Coordinate with CPMU on
environmental monitoring report
preparations
- Responsible for EMP
implementation during
first year of operation;
- Undertake investigation
and monitoring of
environmental concerns
during first years of
operation.
- Support the project
employer to propose the
environmental
requirements O&M
procedures.
DPC
Integrate
recommendations and
contributions of DONRE in
EMP
Monitor EMP implementation
through their own internal
monitoring system
Monitor EMP
implementation through
their own internal
monitoring system
Commune
Supervision Board
and local community
members
- Involve in consultations
and participate in the
identification and
preparation of
subprojects.
- Contribute ideas to
- Involve in environmental
monitoring activities as directed;
- Participation in the solution of
environmental problems if any
Involve in environmental
monitoring activities as
directed
40
Organization
Roles and Responsibilities
Subprojects preparation Subproject implementation Subprojects operation
(CBSs 5 ) environmental
assessment document
once they receive it.
Contractor Not applicable
- Preparation of site EMP
acceptable to subproject owner to
meet general requirements of
subproject EMP
- Allocate sufficient resources to
meet the requirements and
obligations in site EMP
- Prepare monthly progress report
in their EMP implementation, and
whenever directed by the PPMU
Not applicable
CSC Not applicable
- Ensuring CSC staff are well
trained in environmental
monitoring
- Carry out the EMP monitoring in
accordance to contract TOR
- Prepare regular Monitoring
reports and submit to the PPMU.
Not applicable
5 CBSs, established under Decree 80/2005/QD-TTg Regulation for Participatory investment supervision, dated on 18/04/2005. Article 8
of Decree 80 provides the community with opportunities to inspect the compliance, monitor implementation and evaluate results of investments in commune, including environmental impacts.
41
E. Monitoring and reporting system
Table 8: Monitoring and reporting system
Project Stage Type of Report Frequency Responsibiliti
es Submitted to Whom
Construction
Site Environmental
Performance Report
indicating the compliance with
EMP in field and monitoring
results
Monthly CSC
PPMU
EMP Compliance
Monitoring Reportindicating
compliance withsubproject
EMP and monitoring results
Monthly CSC PPMU
EMP implementation Report
indicating all activities
complying with EMP in field
and monitoring results
Every 6 months PPMU/CPMU ADB/DONRE/DPC
Subproject Environment
Report
indicating the overall
subprojectenvironmental
performance and EMP
compliance
At completion of
subproject CPMU ADB/DONRE/DPC
Operation
EMP implementation Report
indicating the compliance with
the subproject EMP
commitmentsduring the
operations and maintenance
Every 6 months in
first 5 years of
operation
PPMU CPMU, ADB
42
F. Budget for EMP implementation
Table 9: Budget for EMP implementation
Pre-construction
stage Construction stage Operation stage Total
Implementation of
approved
Resettlement Plan
8,744,754,000
VND (see
REMDP)
Included in the contract
with the contractor Provincial budgets Various
Environmental
monitoring Not applicable
Included in the contract
between PPMU and CSC; Local budgets
Included in contract
between investor
and stakeholders
Training for
enhancing capacity
on environmental
monitoring
Not applicable
Included in CPMU training
cost
Total: 40,0000,00 VND
(detail in annex 1)
Not applicable 40,000,000 VND
Community
monitoring Not apply
Local budgets
(as in Decision No.
80/2005/QD-TTg)
Local budgets
(as in Decision
No. 80/2005/QD-
TTg)
Local budgets
Community
consultation
As stated in the
consultant
contract
In the implementation cost
of CSC Not applicable
Included in contract
among investor,
stakeholders and
other sources of
capital
Public disclosure of
information
Consultant of
IEE preparation
and PPMU
Total: 12,300,000 VND
(detail in annex 1) Not applicable
12,300,000 VND
43
VI. COMMUNITY CONSULTATION AND PROJECT INFORMATION DISCLOSURE
A. Description of activities to date
Table 10: Community consultation and information disclosure
Consultation method Details of activities
Consultation Meeting for
Khe Mo commune
Date held 21/04/2012
Location held Khe Mo CPC office
Invitees Khe Mo CPC, Youth Union, Women Union, Farmer
Association, affected people
Methods of invitation PPMU sent invitations to leader of the CPC, CPC
informed chiefs of the villages and the community based
organizations and the affected people.
Meeting agenda attached
(Yes/ No)
Yes
Minutes of meeting attached
(Yes/ No)
Yes
Number of participants 30 (See annex)
Consultation Meeting for
Van Han commune
Organization date 22/04/2012
Organization location Van Han Communal Peoples Committee
Invited people Van Han Communal Peoples Committee, CPC, Youth
Union, Women Union, Farmer Association, affected
people .
Methods of invitation PPMU sent invitations to leader of the CPC, CPC
informed chiefs of the villages and the community based
organizations and the affected people.
Meeting agenda attached
(Yes/ No)
Yes
Minutes of meeting attached
(Yes/ No)
Yes
Number of participants 40 (See annex)
44
B. The results of community consultation up to reporting time
Table 11: The results of community consultation
Description of Issue
raised By Whom? Reference in IEE
Required Follow-up
Actions
Transportation safety during
hauling building materials
which affect local residents
nearby the route
Villagers Risks to health and safety
of residents and
construction workers
When constructing, it is
needed to reduce dust, safe
driving to protect residents
and school children
The rainy season from May
to October, roads are often
flooded and slippery,
difficulties in traveling and
the transportation of
construction materials
Villagers Risks to health or safety of
residents and construction
workers
Minimize the transport of
construction materials in the
rainy season
Possibility to cause
inundation during rainy
season
Villagers Risks of inundation or
pollution of surface water
Provide additional road-
crossover ditches, dredge
irrigation canal and put
concrete lids on the canal
45
C. Community consultation activities in the future
Table 12: Proposed community consultation activities
Activity Participants Expected outcomes Schedule Cost Estimate
Organize direct
consultation meetings
with: (i)
representatives of
commune authorities;
(ii) representatives of
affected households;
(iii) DPC if necessary.
General
community
Notify the community
about activities and
construction schedule,
environmental
management methods,
and how to apply
information system based
on community feedback
Every 3 months
for large-scale
consultation
meeting;
Every week during
the construction
stage for
information
disclosure to CPC
Estimated in the
budget for EMP
Feedback
mechanism/ Fixing
mistakes
General
community
Feedback about
questions or
uncomfortable issues
about construction works
Every week ,
during
construction stage
In the contracts
signed between
stakeholders
46
VII.GRIEVANCE REDRESS MECHANISM
11. The CPMU has developed a grievance redress and resolution mechanism for environment to address grievances and complaints related to EMP implementation in a timely and satisfactory manner for the on-going similar projects (Figure 4).
12. Every attempt should be made to establish a rapport between the affected communities and
the implementing agencies through frequent interactions and transparency thereby maximizing
the resolution of grievances at commune level. A three-stage procedure for redress of
grievances is proposed based on practice as follows:
(i) Stage 1: Complaints from affected people on any environmental damage caused by the project implementation will be lodged verbally or in written form by the affected people (refer to Appendix 8 for sample complaint form). The staff from commune/Commune Supervision Board will assess the level of environmental damage and report to the PPMU within 15 days of the complaint is received.
(ii) Stage 2: If no resolution can be reached or if no response is received from the liaison officer within 15 days of registering the complaint, the affected people can take their complaint to the District People Committee who will conduct a site investigation to assess the damage and discuss with a contractor during the construction stage to determine and immediately take the appropriate remedial measures within 30 days of the complaint is received.
(iii) Stage 3: If the affected people are not satisfied with the decision of District People Committee or in the absence of any response, the affected people can appeal to the DONRE or Provincial People’s Committee (PPC). The DONRE/PPC will provide a decision on the appeal within 45 days but not exceeding 60 days
6, from the day it is
received by the PPC. In this stage, DONRE/PPC will enforce PPMU to take the strong corrective action to resolve the problems either though enforcement of contractor’s duties under the signed contract or providing necessary additional actions under its overall duties of project implementation.
13. A complaint or a case to the Court of Law may be done separately or independently from the Project level Grievance Redress mechanism filing process. Implementers of the mechanism should be guided by appropriate government decrees related to complaints such as: Law on Complaints No. 02/2011/QH13; Article 64 of Government Decree 84/2007/ND-CP; Clause 2, Article 40 of Decree 69/2009; and regulation on grievance at Government Decree 75/2012/ND-CP dated 20/11/2012.
6 Law on Complaints, Article 28, Law No. 02/2011/QH13 dated November 11, 2011
47
Grievance
Commune Supervision
Board/Commune People
Committee (CPC)
District People Committee
(DPC)
Construction Engineer/
Construction Supervision
Consultant (CSC)
CORRECTIVE
ACTION
Environment Police
CPMU/MARD
PPMU
Stage 3
Stage2
Stage1
DONRE/Provincial People
Committee (PPC)
Figure 4. Grievance Redress and Resolution Mechanism
48
VIII.CONCLUSIONS AND RECOMMENDATIONS
II.The Subproject Road improvement Linh Nham - Deo Nhau and Van Han market will be carried
out by PPMU of Thai Nguyen province of SRIDPNMP in Dong Hy district, Thai Nguyen province.
III.Initial Environment Examination (IEE) of the project has been conducted and potential
environmental impactsof the subproject in the construction stage include:
For rural road of Linh Nham – Deo Nhau:
(i) Loss of agricultural and residential land due to land acquisition for road ROW;
(ii) Exploitation activities in the borrow pit and dumping sites in the communes of Van Han, Khe
Mo along the route affect the occupational safety of the workers and safety of the farmers,
also there is a risk of landslide affecting the farming areas together with dust and noise
affecting to the nearby households;
(iii) The construction of road limits the movement of the local residents, especially during sowing
and harvesting times in the farming areas along the roadsides;
(iv) Disturbance in living of the residential sites due to the presence of the migrant workers;
(v) Safety risks to workers and local residents.
For Van Han market:
(i) Increased waste materials from the dismantling of old market structures;
(ii) Increased noise and dust level
(iii) Disruption of vending operations and possible reduced income of market traders due to
dismantling of old market structures and transfer to temporary market stalls.
IV.During the operation stage, possible environmental impacts in Van Han market, include:
generation of waste water and solid waste that may cause bad odor and possible public health
problems to market buyers and adjacent residents if not properly collected and disposed. For the
road component, it is anticipated that improved access brought about by the upgrading works can
increase farm incomes, and uplift the socio-economic conditions of the farming communities along
the road alignment. However, the improved road also has its tendency of inviting vehicular
accidents due to drunk driving and over speeding
V.In general, these adverse environmental impacts are mostly not significant, they are temporary
and can only to be felt within the construction period. Land acquisition is inevitable but the scale of
the impact is not significant since none of the Affected persons require relocation, and none of
them will loose 10% or more of their productive land or livelihood source. Nevertheless, there are
issues identified though not significant, that can be minimized in the process of project
implementation. The mitigation measures have been studied and proposed in this report may apply
to the construction contractor, include the following activities:
(i) Reduce risk of landslide affecting the farming areas together with dust and noise affecting to
the nearby households: Reinforcing embankment to avoid land collapse leading to impacts
on the nearby cultivation areas and reducing conflicts between households having cultivation
areas; Regularly watering the road traversing residential and institutional areas (during dry
season) to reduce dust in the construction site yet avoiding causing muddy condition;
washing wheels as the vehicles get out of the borrow pit site is necessary.
(ii) Limiting the traveling demands of local people: Installing warning signs at the construction
site; Cleaning and clearing dropped sand and soil along the constructed sections; Disclosing
the construction plan and schedule to the communities living along the subproject alignment.
49
(iii) Disturbance in living of the residential sites due to the presence of the migrant workers:
Setting up regulations for off-work hour activities; disseminating customs and practices of
local people to workers;
(iv) Safety risks to workers and local residents: Installing safety signs in the construction site;
Avoiding construction activities during strong rains and floods; Cleaning the construction site
to ensure safety of travelers.
VI.The subproject will promote the socio-economic development and poverty reduction. It increases
access to the public social services such as education, healthcare, rural markets for 40,000 poor
people in the 2 communes of Dong Hy district and 2 neighboring communes of Vo Nhai district
through reducing traveling time, reducing the traveling costs in trading goods and products among
the communes in the districts. Minimize the traffic congestion during rainy season and gradually
improve the cultural life of the local residents, transportation connectivity with many rural
infrastructure development projects and targeted programs of the districts and province on forest
tree planting, agricultural intensification and animal husbandry, to maximize the aggregate
economic benefits.
VII. Based on the institutional arrangements defined, the agencies involved in monitoring will
implement following tasks: Prepare measures and commitment to implement environmental
impacts mitigation measures (construction contractor); offer methods, human resources to
implement EMP monitoring tasks base on tasks built in the IEE (CSC); monitor compliance with
environmental regulations of construction contractors (PPMU).
VIII.Initial Environmental Examination (IEE)findings for the subproject indicates no significant
impacts on the environment, it means the subproject is a category B activity and it is recommended
that further assessment on the environment in the project area is not needed. Recommendation on
mitigation measures in EMP will be put into bidding documents and contractors will estimate total
expenditure for these mitigation activities and be paid when these measures are effectively
implemented.
IX.Based on the IEE, the Investment Project Preparation consultants, PPMU propose the
competent agencies to approve the Initial Environment Examination Report for the subproject on
“Road improvement Linh Nham – Deo Nhau and Van Han market” as a basis for the next steps to
ensure the progress and effective implementation of the project.
Consultant of report
preparation:
PPMU safety policy
official:
Signature: Signature:
Date: Date:
50
APPENDIX
Appendix 1: Cost for EMP implementation
Cost for public information disclosure
Public information disclosure will be implemented by CSC before construction stage.
Information will be disseminated to the commune authorities and local people through following
measures: (i) meetings at the commune headquarters; (ii) send documents on measures, detailed
construction plan in each stage to the CPC. (iii) broadcast news about constructing activities during
construction stage. The documents are publicly posted at the CPC so that local people can read
and understand.
Table 13: Estimated for disclosure information activities
Estimated time: 17months
Activities Frequency Quantity Cost Estimated
cost Source of cost
Broadcasting on
the radio about
the construction
activities
Every 2 weeks
during
construction
process
2 times x 80
weeks = 160
times
30.000 VND
for each news
4.800.000
VND
In the contracts
signed between
investor and
stakeholders
Organizing large-
scale consultation
meeting with
representatives of
commune, district
and the family
involved in
construction
process
Every 3
months during
the
construction
7 times during
17 months
500.000 VND
for each
meeting
3.500.000
VND
In the contracts
signed between
investor and
stakeholders
Stick involved
information to
CPC and
residents
Every week
during
construction
process
80 times during
construction
process
50.000VND for
each news
4.000.000
VND
In the contracts
signed between
investor and
stakeholders
Total 12.300.000
VND
51
Table 14:Cost estimation for implementation of capacity building and training
Contents Trainees Number of
trainees Cost rate (VND) Source of cost
Training on food hygiene,
occupational safety and
environmental protection
Workers and
technicians of
contractors
All workers
and
construction
staff on site
100 persons x
200,000 VND
/person =
20,000,000 VND
Included in the
contract between
contractor and the
stakeholders
Training on
environmenta
l
management
Waste sources
control
PPMU staff
3 persons 500,000
VND/person x 3
person =
1,500,000 VND
Included in the
contract between
contractor and the
stakeholders
Impact
assessment,
environmental
risk control
PPMU Staff
3 persons 500,000
VND/person x 3
person =
1,500,000 VND
Included in the
contract between
contractor and the
stakeholders
Environmental
monitoring
PPMU staff
CSC Staff
8 persons
include 3
persons in
PPMU and 5
persons in
CSC
500,000
VND/person x 8
person =
4,000,000 VND
Included in the
contract between
contractor and the
stakeholders
Enhancing
awareness and
access to
environmental
legal system
PPMU staff
CSC Staff
8 persons
include 3
persons in
PPMU and 5
persons in
CSC
500,000
VND/person x 8
person =
4,000,000 VND
Included in the
contract between
contractor and the
stakeholders
Training for
enhancing
capacity of
environmental
monitoring
CSC Staff 5 persons 5 persons x
1,000,000
VND/person =
5,000,000 VND
Included in the
contract between
contractor and the
stakeholders
Training for CSB CSB Staff 2 persons / 1
commune x 2
communes = 4
persons
4 persons x
1,000,000
VND/person =
4,000,000 VND
Included in the
contract between
contractor and the
stakeholders
Total (VND) 40.000.000
52
Appendix2: Minutes of agreement to get soil for leveling fields and minute of exploitation borrow pits between households and PMU
MINUTE OF EXPLOITATION BORROW PITS
Subproject: Road improvement Linh Nham – Deo Nhau and Van Han market, Dong Hy
district, Thai Nguyen province
At: Km 5
Today is December 2nd
2011, in Khe Mo commune, Dong Hy district.
Consist of participators
I. Representative of borrow pits owners
Mrs. Nguyen Thi Thanh Tam and other members of household in Khe Mo village, Khe Mo
commune, Dong Hy district
II. Representative of Thai Phuong construction consulting stock company
Mr. Vuong Tuan Son Position: Staff
Content:
- Agree to exploit back filling soil on land of Mrs. Nguyen Thi Thanh Tam in Khe Mo village, Khe
Mo commune, Dong Hy district.
- Representative of Thai Phuong construction consulting stock company talked about exploiting
back filling soil for road section at Km8 under the subproject Road improvement Linh Nham –
Deo Nhau and Van Han market, Dong Hy district, Thai Nguyen province.
- Investigate position for borrow pits serving for construction which located on land of Mrs.
Nguyen Thi Thanh Tam household is hill land, capacity of about 30 000m3.
- Conclusion: Agree to exploit soil from borrow pit mentioned above.
- The contractor shall clear and return leveled ground to the household.
Staff survey Representative of Thai Phuong construction
consulting stock company
Certification from locality
53
MINUTE OF AGREEMENT TO GET SOIL FOR LEVELING FIELDS
Subproject: Road improvement Linh Nham – Deo Nhau and Van Han market, Dong Hy
district, Thai Nguyen province
Today is December 12th 2011, in Van Han commune, Dong Hy district.
1. Consist of participators
III. Representative of household
Mr. Hoang Van Khoa and other members of household in Van Han village, Van Han commune,
Dong Hy district
IV. Representative of Thai Phuong construction consulting stock company
Mr. Vuong Tuan Son Position: Staff
Content:
- Agree to dump excavated soil on land of Mr. Hoang Van Khoa in Van Han village, Van Han
commune, Dong Hy district.
- Representative of Thai Phuong construction consulting stock company talked about dump
excavated soil from road section at Km19+700 under the subproject Road improvement Linh
Nham – Deo Nhau and Van Han market, Dong Hy district, Thai Nguyen province.
- Investigate position of dumping site serving for construction which is low-lying field of Mr.
Hoang Van Khoa household, capacity is of about 1800m3.
- Conclusion: Agree to position of dumping site mentioned above.
- The contractor shall clear and return leveled ground to the household.
Staff survey Representative of Thai Phuong construction
consulting stock company
Certification from locality
65
Appendix3: Some pictures on the environment status of Linh Nham – Deo
Nhau road and Van Han market
The starting point of Linh Nham road
(: N 210 38’ 18’’; E 105
051’43’’)
Road crosses Khe Mo Secondary School
(N 210 39’ 54’’; E 105
052’54’’)
Status of the road crossing a residential site in Khe Mo commune
Khe Mo bridge, Khe Mo commune
66
Status of the road which crosses Van Han commune Status of the road which crosses Van Han market (N
210 40’17’’; E 105
056’21’’)
Status of Van Han market (N 21041’15’’; E 105
056’05’’)
Status of Van Han market
67
Appendix4. Consultation activities
Meeting with staff of Khe Mo commune Consultation meeting with women in Khe Mo commune
Community consultation meeting in Khe Mo commune
Community consultation meeting in Van Han commune
Community consultation meeting in Van Han commune
Appendix
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
Sustainable Rural Development Project in the Northern Mountain Provinces
DOCUMENTATION OF PUBLIC CONSULTATION
I. SUBPROJECT:
Upgrading of rural road
Thai Nguyen province
II. DATE, TIME, AND VENUE / LOCATION
Date 21/4/2012 in Khe Mo
Dong Hy district, Thai Nguyen
III. ATTENDANCE:
Communes
Male
Khe Mo 18
Van Han 27
Total 45
IV. PROGRAM:
Topic / Activity
Introduction participants of the commune, and objectives the consultation
meeting
Presentation the project origin, reasons for consultation, the composition
of consultants
Presentation detailed specifications of the
road grades, road types, and etc…
Presention ADB resettlementpolicies, the policy framework of the
Government of Vietnam, provincialpoliciesand the policy framework of
Project: the conditions of eligibilityforcompensationandresettlement
assistance if state revenues land.
Consultation on:
• the compensationandresettlement plan for the subproject,
replacementcost, measuresto support
relocationandresettlementrequiredby the
• the project implementation plan;
• the environmental impacts andmitigationmeasures.
Appendix6: Documentation of public consultation
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
CENTRAL PROJECT MANAGEMENT UNIT
Sustainable Rural Development Project in the Northern Mountain Provinces
(ADB Loans 2682/2683-VIE)
DOCUMENTATION OF PUBLIC CONSULTATION
Upgrading of rural road Linh Nham – Deo Nhau and Van Han market in Dong Hy
province
DATE, TIME, AND VENUE / LOCATION
Khe Mo head quarter CPC, date 22/4/2012 in Van H
Dong Hy district, Thai Nguyen Provinces.
Table 15: Attendance in consultation meetings
Total Attendance Ethnic Minority Attendance
Male Female Male
12 13
13 15
25 28
Topic / Activity Responsible Person / Entity
Introduction participants of the commune, and objectives the consultation A representative of the CPC
Presentation the project origin, reasons for consultation, the composition Representatives of the PPMU
Presentation detailed specifications of the subproject: road length, width,
road grades, road types, and etc…
Project d
Presention ADB resettlementpolicies, the policy framework of the
Government of Vietnam, provincialpoliciesand the policy framework of
: the conditions of eligibilityforcompensationandresettlement
assistance if state revenues land.
Safeguard consulta
the compensationandresettlement plan for the subproject,
replacementcost, measuresto support
relocationandresettlementrequiredby the subproject;
the project implementation plan;
the environmental impacts andmitigationmeasures.
Safeguard consultants
81
: Documentation of public consultation
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
CENTRAL PROJECT MANAGEMENT UNIT
Sustainable Rural Development Project in the Northern Mountain Provinces
DOCUMENTATION OF PUBLIC CONSULTATION
Nhau and Van Han market in Dong Hy district,
Van Han head quarter CPC,
Ethnic Minority Attendance
Female
7
10
17
Responsible Person / Entity
A representative of the CPC
Representatives of the PPMU
Project designer
Safeguard consultants
Safeguard consultants
82
Consultation on the grievancesandgrievancesredress. Safeguard consultants
Consultation on issues relatedto gender. Safeguard consultants
Consultation on issues relatedtoethnicminorities. Safeguard consultants
V. ISSUES AND CONCERNS
Table 16: Matrix of issues and concerns
No.
Issue Raised Response on Issue Raised
Issue
Who Raised the
Issue/ Suggestion Response
Person / Sector Who
Responded to the
Issue/ Suggestion
1
In the
implementation
period,
theremay have
noises, dust,
smoke, whatwill
the project do
tominimizethis
impacts?
We prefernotto
have topay the
tax for the
acquired land.
Dinh Van Loc,
KheMo
commune
PPMU willrequire the contractor
toimplement the
mitigationmeasuressuch as covering the
truck cargosduringtransportingsoil or
othermaterials.
For the tax of the land acquired, it is
beyondour hands, and the tax
willbedone as per the Land Law
Bui Van Huyen,
Safeguard
consultants
2
Traffic during
construction
process
Tran ThiTuong,
ApChe village,
Van Han
commune
While construction, there are requirement
of adjustments, lane-dividing, route-
dividing, arrangement reasonable
construction time.
- Construction of underground combining
overflow through Cau Mai stream, a
temporary earth bypass will be build.
Warning signs will be installed at two
heads of the overflow.
Bui Thi Ban Mai,
Safeguard
consultants
3
During the
construction
time, if the
workersdamag
eourassets,
how the project
willcompensate
?
PhamXuanTruo
ng, President of
KheMoPeople’s
committee
All the
damagecausedbysubprojectconstruction
willbecompensateddepending on the
level of damage.
Bui Thi Ban Mai,
Safeguard
consultants
4
Dust, noise and
vibration
affecting to
people
Vuong Van Do –
Van Hoavillage,
Van Han
commune
The investor perform environmental
commitments.
Contractor seriously implement measures
to minimize environmental impacts during
construction process
Bui Thi Ban Mai,
Safeguard
consultants
5
Participation of
communities in
the activities of
Ly ThiNong – Cau
Mai village, Van han
commune
Local government will cooperate with
construction contractors to hire local
people for unskilled jobs in construction
process, encouraging participation of
Bui Van Huyen,
Safeguard policy
consultants
83
the project women.
6
If some of our
land is acquired
for the
subproject, the
land use rights
certificate
(LURC) for
remaining land
should be re-
issued. Is it ok to
have a new one
in the name of
both husband
and wife?
Nguyen Thi
May, KheMo
commune
Yes, definitelylikethat. Bui Van Huyen,
Safeguard policy
consultants
Otheragreements
(i) Everyone in the meeting supported for and highly agreed with the project implementation of
Upgrading of rural road Linh Nham – Deo Nhau and Van Han market in Dong Hy district,
Thai Nguyen Province. Although these routes are existing, they have been degraded.
Therefore, they are dusty in the dry season and muddy in the rainy season. Some farmers
have agricultural products but not able to sell because it was so difficult to access the market
due to poor roads, while the traders were unable to reach to villages because of the same
problem. The completed new road will help people travelling and transporting their products
easier. It will also create favourable conditions for socio-cultural exchanges. Van Han market
is one of item upgraded in the subproject, play important role in agricultural production
circulation of the region. The new upgraded market will facilitate farmers to sell their goods,
and contribute in socio-economic development of Dong Hy district.
(ii) The APs were all agreed with contents and were informed about project scale of impacts,
possible land acquisition of the AHs, fully agree with the project’s policy on compensation
and resettlement assistance, accept cash compensation at replacement costs.
(iii) It is thought that the environmental impacts of the project during construction are inevitable,
but these effects are not significant, nevertheless these can be overcame with the mitigation
measures as proposed in the meeting.
(iv) Accept supports for vulnerable groups such as poor households, single female-headed
households, and ethnic minority groups.
(v) Encourage the more actively and meaningfully participation of women and ethnic minority
people into the process of REMDP implementation, management and monitoring.
(vi) When compensation payment is made, it must be presented both husband and wife for
witness and receipt.People may represent in the Community Monitoring Board during
subproject construction.
(vii) All agreed with the complaint mechanism and resolve procedure in accordance with current
legislation.
(viii) The women and ethnic minorities are also highly agreed with action plans on gender and
ethnic minority of subproject.
(ix) Participants wish to receive full benefits and rights as specified Project Policy Framework
and in the law and legal documents of Vietnam.
(x) Interests, demands and comments of participants will be considered and addressed in the
project cycle
VI. TIME OF ADJOURNMENT: 21-22/04/2012;
VII. PREPARED BY: Bui Thi Ban Mai ; Tran Kim Cuc ; Bui Van Huyen
84
Appendix 7: Source of data used in there porting process
1. Environmental Status Report of Thai Nguyen in period 2005 - 2010, Thai Nguyen Department of
Natural Resources and Environment 2010
2. Statistical Yearbook2011, Dong Hydistrict
3. The data collected and survey on socio-economic situation the communes of Khe Mo and Van
Han of Dong Hy district, Thai Nguyen province n 2011
4. The documents used in the Investment Project Report on Sustainable Rural Infrastructure
Development Project in Northern Mountain Provinces, Thai Nguyen province, Sub project on
Upgrading Linh Nham – Deo Nhau road and Van Han market of Dong Hy district, Investment
Project Preparation stage.
5. REMDP of the subproject on Upgrading LinhNham- DeoNhau road and Van Han market of Dong
Hy district, 2012
85
Appendix 8. Sample Complaint Form7
MÉu sè: 32 (Ban hµnh kÌm theo QuyÕt ®Þnh sè 1131/2008/Q§ - TTCP ngµy 18 th¸ng 6 n¨m 2008 cña
Tæng thanh tra)
Céng hoµ X/ héi Chñ nghÜa ViÖt Nam
§éc lËp – T− do – H¹nh phóc
......., ngµy....th¸ng .....n¨m...
§¬n khiÕu n¹i
KÝnh göi:................................................(1)
Hä vµ tªn:....................................................................(2); M· sè hå s¬ .......................(3)
§Þa chØ :.............................................................................................................................
KhiÕu n¹i.......................................................................................................................(4)
Néi dung khiÕu n¹i........................................................................................................(5)
...........................................................................................................................................
(Tµi liÖu, chøng cø kÌm theo – nÕu cã)
Ng−êi khiÕu n¹i
(ký vµ ghi râ hä tªn)
(1) Tªn c¬ quan, tæ chøc, c¸ nh©n cã thÈm quyÒn gi¶i quyÕt khiÕu n¹i.
(2) Hä tªn cña ng−êi khiÕu n¹i,
- NÕu lµ ®¹i diÖn khiÕu n¹i cho c¬ quan, tæ chøc th× ghi râ chøc danh, tªn c¬ quan, tæ chøc mµ m×nh ®¹i diÖn.
- NÕu lµ ng−êi ®−îc uû quyÒn khiÕu n¹i th× ghi râ theo uû quyÒn cña c¬ quan, tæ chøc, c¸ nh©n nµo.
(3) Néi dung nµy do c¬ quan gi¶i quyÕt khiÕu n¹i ghi.
(4) KhiÕu n¹i lÇn ®Çu (hoÆc lÇn hai) ®èi víi quyÕt ®Þnh, hµnh vi hµnh chÝnh cña ai?
(5) Néi dung khiÕu n¹i
- Ghi tãm t¾t sù viÖc dÉn ®Õn khiÕu n¹i;
- Yªu cÇu (®Ò nghÞ) cña ng−êi khiÕu n¹i (nÕu cã);
7 State Inspection Form for Complaints and Grievances
86
MÉu sè: 41 (Ban hµnh kÌm theo QuyÕt ®Þnh sè 1131/2008/Q§ - TTCP ngµy 18 th¸ng 6 n¨m 2008 cña
Tæng thanh tra)
Céng hoµ X/ héi Chñ nghÜa ViÖt Nam
§éc lËp – Tù do – H¹nh phóc
......., ngày ....th¸ng..….n¨m ....…
GiÊy uû quyÒn khiÕu n¹i
Hä vµ tªn ng−êi uû quyÒn:............................................................................................(1)
§Þa chØ :.........................................................................................................................(2)
Sè CMND:.....................................................................CÊp ngµy…...th¸ng…...n¨m.......
N¬i cÊp:…..........................................................................................................................
Hä vµ tªn ng−êi ®−îc uû quyÒn………………………………………………………....
§Þa chØ:...………………………………………………………………………………...
Sè CMND:..................................................................CÊp ngµy......th¸ng…..n¨m............
N¬i cÊp:………………………………..............................................................................
Néi dung uû quyÒn:.......................................................................................................(3)
Trong qu¸ tr×nh gi¶i quyÕt khiÕu n¹i, ng−êi ®−îc uû quyÒn cã tr¸ch nhiÖm thùc hiÖn ®óng
néi dung uû quyÒn.
X¸c nhËn cña UBND x/, ph−êng, thÞ trÊn n¬i ng−êi uû quyÒn c− tró
(Ký, ghi râ hä tªn vµ ®ãng dÊu)
Ng−êi uû quyÒn
(Ký vµ ghi râ hä tªn)
(1) NÕu ng−êi uû quyÒn lµ ng−êi ®¹i diÖn cho c¬ quan, tæ chøc uû quyÒn cho ng−êi kh¸c ®Ó khiÕu n¹i th× ph¶i ghi râ chøc vô cña ng−êi uû quyÒn.
(2) N¬i ng−êi uû quyÒn khiÕu n¹i cø tró, tr−êng hîp lµ c¬ quan, tæ chøc uû quyÒn th× ph¶i ghi râ ®Þa chØ cña c¬ quan, tæ chøc ®ã.
(3) Uû quyÒn toµn bé ®Ó khiÕu n¹i hay uû quyÒn mét sè néi dung (Tr−êng hîp uû quyÒn mét sè néi dung th× ph¶i ghi râ néi dung uû quyÒn)