26 June 2001VELO-Overview VELO Overview T. Bowcock University of Liverpool.
VELO Module Mid-Term Review T. Bowcock 11 October, 2006.
-
Upload
luke-mcmillan -
Category
Documents
-
view
214 -
download
1
Transcript of VELO Module Mid-Term Review T. Bowcock 11 October, 2006.
VELO Module Mid-Term Review
T. Bowcock11 October, 2006
Themis Bowcock - MTR
Overview
Introduction Why? Terms of reference Timeline
Project Summary
Themis Bowcock - MTR
IntroductionWhy?
Consolidate and review production STOP before we go too far Produce a revised baseline procedures Larger statistics from PRR
Identify new problems (fix!) Public record Refereed (Tim Jones)
Input of experience from other experiments
Themis Bowcock - MTR
Introduction:Terms of reference
Review documentation checklists, and idiot guides
Review data to identify problems Compile list of issues that need to be
addressed Identify priority items that must be
addressed before production restarted Produce short written report to the
Technical Board of LHCb
Themis Bowcock - MTR
IntroductionTimeline
11th Oct: MTR at Liverpool – Full day
12th Oct: Summary of MTR with CERN VELO management
16th Oct: Written Report of MTR to TB
… Restart production (if possible)
Themis Bowcock - MTR
Project: Resources
PPARC (1998-2006) ~1.1MChf hardware including R&D
42 Si Modules and cables (no large number spares) Note PPARC not paying for FE Chips
R&D ~250kChf or 50kCHf/yr to 2005 Limited ability to produce early prototypes and
modules Liverpool/HEFCE and JIF
Liverpool Semiconductor Detector Centre infrastrure
Limited funding from Department ~50kChf
Themis Bowcock - MTR
Project: Staff
Name Responsibility Activity
Themis Bowcock
Group Leader
John Carroll Project Engineer Assembly Testing Metrology
Torkjell Huse Assembly Qualification
Gianluigi Casse Qualification
Rolf Oldeman Qualification
Mark Tobin Software CERN
Peter Cooke Production
Workshop Staff Production Hybrids/Bonding
Phil Turner Testing
Tara Shears Testing
Lisa Dwyer Testing CERN
Anthony Affolder Testing
Peter Sutcliffe Testing/Metrology
Name Responsibility Activity
David Hutchcroft Software Coordinator Software Testing
David Jones Software Testing
Kurt Rinnert Software Testing
Tony SmithProduction
CoordinatorHybrids
Ashley Greenall Hybrids
Geoff Southern Hybrids
Dave Muskett Testing/Metrology Assembly
Mike Wormald Hybrids/Bonding Assembly
Mark Whitley Hybrids/Bonding
Girish Patel Quality Assurance QA
Karol Hennessy* Software Qualification
Mike Lockwood Operations Assembly
* University College Dublin
Themis Bowcock - MTR
Project: Staff
6%
8%
10%
23%
15%
19%
13%
2% 4%Management
Production Parts
Assembly
Testing/Metrology
Hybrids/Bonding
Qualification
Software
Operations
QA
Themis Bowcock - MTR
Project: Oversight
Themis Bowcock - MTR
Project:Management
Gantt Has been replaced as we move into quasi
DC operation Replaced by detailed time/worksheet
optimized for throughput Areas of competance
Weekly and Daily Meetings e-log (well used)
Risk Register
Themis Bowcock - MTR
Geometry (42 modules R&Phi) R sensors must be positioned within 20 um (gauss
sigma) in X and Y of the nominal position relative to the base.
R sensors must be positioned within 100 um (gauss sigma) in Z of the nominal position relative to the base.
Phi sensors must fit within tolerances given by RF foil. The positioning has no further requirements, but the
actual position must be known to an accuracy of about 10 um relative to the R sensor.
Addition of constraint system See metrology discussion
Project:Modules
Themis Bowcock - MTR
Project: ModuleSpecification
Temperature The sensors operate at a nominal
operational temperature of ~ -5° C.
Themis Bowcock - MTR
Project: ModuleSpecification
Outgassing outgas_one_module < 1e-4 mbar liter
/ s after approx 4 hours in vacuum.
Themis Bowcock - MTR
Project: Module Specification
Electrical The module should be designed to
sustain up to 600 V in vacuum @ < 1e-4mbar.
Channels lost Sensors (20) Final module max 25/side
Themis Bowcock - MTR
Summary
Project approximately at mid-point Are we doing the right things? What more can we do to improve? Are we meeting our goals? Today…
Themis Bowcock - MTR
Summary:Today
Session I: QA & documentation Session II: Data Summaries Session III:
Logistics,Infrastructure… Session IV: Discussion