Prototype Module Schedule
Mechanical Module(2-4 weeks) Two separate bases Paddles(2) Substrates(4-6) Bonding SCTa Hybrids to Substrates
Measurements Alignment of two sides
NAS, JC jig and location facility Thermal Tests
Glues
Investigate glue additives Better thermal properties
Carbon Nanotubes(multiwall 20micron) Boron Nitride(1micron ceramic)
Control resistivity
Easily achieve >2WmK Boron Nitride
Ceramic mix and leakage current (MPI) Test 3 micron size