Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client...

35
Vectrance PMC REFERENCES 1

Transcript of Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client...

Page 1: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

Vectrance PMCREFERENCES

1

Page 2: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

Based on decades of experience from the development and the

management of PMC engineering companies of Dr Denantes, such as

Vectrance, Kappa,…

find here exemples of PMC (proj manangt consutant)contracts, addressing

oilgas companies=

2

VecTrance/references

Page 3: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

WORLDWIDEREFERENCES

3

*

*references

Page 4: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(explor/drilling)

4*Founders'references

*

*Founders’references

Page 5: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(1)

Client Medco, Pertamina, Shell bruneiDate 2002-04Function Drilling superintendentsDetailPreparation of explor drilling program, tendering, contract management of 3 wells onshore drillings (contractor supervision, reporting, coordination with geologists,...)

Client Repsol/PDVDate 2008 to 2010Function Drilling superintendentsDetailPreparation of explor drilling program, tendering, contract management of 3 wells ,on shore drillings (contractor supervision, reporting, coordination with geologists,...)

Client PetronasDate 2004Function drilling engineeringDetailDrilling plan,contract management,supervision of drilling contractors,coordination withgeoscience team

5

*

'references

Page 6: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(2)

Client Cairn,IndiaDate 2010Function

Drilling proj managt, well site geologistDetailDrilling plan, tender, contract management, supervision of drilling contractors,coordination with geoscience team, wellsite geology plan coordination

Client GNPOC,EgyptDate 2004Function drilling engineersDetailEngineering of drilling, planning, contract/tender preparation, coordination on withgeoscience

Client Sakhaline EnergyDate 2007Function Drilling engineersDetailEngineering of drilling, planning, contract/tender preparation, coordination on withgeoscience

6

*references

Page 7: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(3)

Client Medex, PertaminaDate 2001,2008Function Well supervisorsDetailWell intervention preparation, supervision of 2 coiled tubing contractors for wellmaintenance

Client Challenger drilling ,Repsol (Algeria)Date 2004,2005Function Well supervisorsDetailWell intervention preparation, supervision of drilling and coiled tubing contractors

Client Medex, Aioc, PA ResourcesDate 2007 - 09Function Petrophysics supervision/well site geologyDetailPetrophysics program preparing, LWD supervision,contractor supervision, datainterpretation of slicklines loggings, synthesis reports

*

*references

7

Page 8: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(4)

Client BG TrinidadDate 2007Function Petrophysicists supportDetailLWD preparation, contractor supervision, data interpretation of slicklines electrical andgamma ray logging, synthesis reports

Client CanAlaska , Cameco (Uranium)Date 2009 to 2011Function Well site geophys/ geochemistryDetailGeophysics programe, supervision of explor drilling

8

*

*references

Page 9: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(5)

Client Gupco, (Egypt)Date 2008Function Well site geologistDetailSupport to exploration drilling , res planning, prepare well design with drilling team, LWDpreparation, logging supervision and interpretation

Client Waha oil, Petrokazakstan,Date 2006Function Well site geologistDetailSupport to exploration drilling , res planning, prepare well design with drilling team, LWDpreparation, logging supervision and interpretation

Client Challenger drilling (Lybia)Date 2006Function drilling engineersDetail managemt contractPreparation, coordination with Gupco drilling, geoscience teams, and technical support todrilling campaigns 9

*

*references

Page 10: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(6)

Client Afren, Nigeria, Cnooc ,Date 2011,12Function Well site geologist :DetailSupport to exploration drilling , res planning, prepare well design with drilling team, LWDpreparation, logging supervision and interpretation

Client Total(Niger), Tatneft (Russ), Dubai PetroleumDate 2005 to 2007,Function Geol modelling/Seismics interpretingDetailGeological studies review, seismics program preparation and execution(contractmanagement); interpetation studies, synthesis reports

10

*

*references

Page 11: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OILFIELDSERVICESREFERENCES(7)

Client Agoco Libya, BG EgyptDate 2006,7Function Reservoir simulation on Eclypse

Client BP Angola, NexenDate 2001- 2002Function Geol,Seismics interpreting

Geological studies review, seismics program preparation and supervision(contract management); interpetation studies, synthesis reports

11

*

*references

Page 12: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

PMC/ENGINEERINGSERVICESREFERENCES

12

*

*Founders'references

Page 13: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(1)

Client Pan African, JogmecDate 2005, 2006Function Basic geology studies, contract management, wellsitegeol QA/QCDetailPMC of all geophysics/geology, logging: contrat management, planning, supervision ofcontractors

Client AIOC (Azerbaijan), Nimirdate 2005, 2007Function Basic petroleum engineering studies, sow, planning contract

management, well site gelologyDetailPMC contract management, planning, supervision of contractors

13

*

*Founders'references

Page 14: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(2)

Client AGIP,LondonDate 2003-2004Function Engineering,HSE,andprojectcontrolDetail PMCofconceptualstudiesandfeasibilityphaseofKCOmega

project(Kashaganproj,Kazakstan)ofsubseaarchitectureinArticconditions.

Analysed50optionsandevaluatedthemoneconomics,risk,operationmaintenanceandHSEcriteria.Optimisedarchitectureandperformedcostcontrolandplanningmanagement.SupervisionofParsons,FMCandothervendors.

Size 72menmonths.

14

*

*Founders'references

Page 15: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(3)

Client SINCOR(TotalStatoilPDV),Venezuela– 4.3B$Date 2000-2004Functions Engineering,Projectcontrol,HSE,OMpreparationDetail OverallFEED(FrontalEngineeringDesign),supervision

(FosterWheelerUS),Engineeringcontractorssupervision, (FW,Technip, Uhde,…)inCaracas,PuertoLaCruzandSanJosé(Planningcontract

management).Constructionmanagementupstreamfacilities(heavyoil

process).Supervisionmaintenance,operation,preparationprograms

andHSE supervision.UpgradedPMCengineering,procurement,constructionandcommissioning.

Size 1500menmonths

15

*

*references

Page 16: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&REFERENCES(4)

Client Burlington,LondonDate 2001-2002Function Engineering,HSE,ProjectcontrolDetail Conceptualandfeasibilitystudies,basicengineeringofan

Algerianproject.Supervisionofcontractorsinchargeoftheproject.

Size 144menmonths.

Client EDF(ElectricitéDeFrance),MOLDate 1996to2001Functions EngineeringandprojectcontrolDetail PMCofmajorshutdownofallFrancenuclearplants.

Preparationofengineering,shutdownimplementation,costplanning,vendorandcontractorcontractmanagement.

Size 370menmonths.

16

*

*references

Page 17: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(5)

Client Cofathec (Gaz De France subsidiary), DoosanDate 1997 to 2000Functions Engineering, HSE, Project Control, QA/QCDetailPMC of 3 power generators and cogeneration plants in France.Engineering supervision and contractor supervision up to Pre-commissioning.Size 45 men months.

Client Amoco,Houston,BPDate 1992,96Function Engineering, project control, QA/QCDetailSupervision of contractors in charge of conceptual and feasibility studies of a Gulfproduction and semi-sub platform.Size 65 men months.

17

*

*Founders'references

Page 18: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(6)

Client KadunaRefiningandPetrochemicalCompany,NigeriaDate 1991-92Function EngineeringandprojectcontrolDetail FeasibilityandFEED(FrontalEngineeringDesign)ofnew

projects(reforming,hydro-treatments,utilities...).Supervisionofcontractors(Lummus...).

Size 70menmonths

Client Alfolplant,MashinoImportDate 1977-78Function Engineering,ProjectControl,QA/QCDetail FEED(FrontalEngineeringDesign),engineering,procurement

start.Supervisionofcontractors(AlfolprocessfromConoco).Startupsupervision.

18

*

*Founders'references

Page 19: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(7)

Client Conoco, El Paso,Date 1975-76Function Project Control, QA/QCDetail Construction Phase of San Juan Basin BCG gas plant (NGL).

Client RENAULTDate 1991-2007Function Project ControlDetailPMC of car launching projects, engine development projects and automotive plantsconstruction.Size 1030 men months.

Client PSA (PEUGEOT – CITROËN)Date 1998-2007Function Engineering and Project ControlDetailPMC of 4 car launching projects, engine development projects and automotive plantsconstruction.Size 1440 men months.

19

*

*references

Page 20: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

PROCUREMENTServicesREFERENCES(8)

Client Energo Enjam (Turkmenistan), Tadbir proj (Iran)Date 2006Function Supply102unitsCurrenttransformerand9unitsVoltage

Transformer

Client Energo Enjam (Turkmenistan)Date 2006Function Supply42kmCable&5Tone-CopperConductor

Client Turkmen Energo (Turkmenistan)Date 2006Function Supply45UnitsHighVoltageCircuitBreaker

Client Energo Enjam (Turkmenistan)Date 2006Function SupplySwitchGear&145KV

DisconnectingSwitches

20

*

*references

Page 21: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

SERVICES&PROCUREMENTREFERENCES(9)

Client NTDC (Pakistan)Date 2008Function 220/132KVSubstation

Client NTDC (Pakistan)Date 2008Function 220KVTransmissionline

Client NTDC (Pakistan)Date 2008Function Substation&TransmissionProject(Phase1&2)

Client EPCO (Ethiopia)Date 2008Function ExtensionOf230KVSubstation

21

*

*Founders'references

Page 22: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

SERVICES&PROCUREMENTREFERENCES(10)

Client Ministry of irrigation (Syria)Date 2008Function GeotechnicOperations

Client Public Autorithy for Electrical & Water (Oman)Date 2008Function WaterTransmission&SupplySysteminNiabtJabaAkdorin

NizwaProvince

Client CeylonElectricityBoard–CEB(SriLanka)Date 2008Function RuralElectrificationof8regions

Client Ministry of Power (Lebanon)Date 2009Function Supply21unitsofSparkGap&15unitsofCurrents

Transformer

22

*

*Founders'references

Page 23: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(11)

Client GIG Energy (Georgia)Date 2009Function ConstructionofSmallWaterPlant(KhobiHPP2,3)

Client Ministry of Electricity (Iraq)Date 2011Function Al-SadrPowerPlant

Client MinistryofWater(Ghana)Date 2011Function Damongoirrigation

23

*

*Founders'references

Page 24: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

ENGINEERINGSERVICES&PROCUREMENTREFERENCES(12)

OtherPMCreferences:

•ARCO•CASPIANGASCORP•AMOCO,Aramco•ORIENTPETRLOEUM•PEDCO,Crescent•WASCANA,Kelt•PLUSPETROL•MONUMENT,Nimir•WHARFRESOURCES,•BHP•REPSOL•SAKHALINEENERGY•SHELL(Malaysia,Nigeria)

24

*

*Founders'references

Page 25: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES

25

*

*Founders'references

Page 26: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(1)

Client SINCOR Upstream/Downstream, VenezuelaDate Since 1999Function Commissioning servicesDetailParticipation in the Sincor Commissioning team (System Engineers and Specialists)

Client TOTAL South Pars, IranDate since 1999Function Commissioning servicesDetailParticipation in the Commissioning team (System Engineers and Specialists)

Client TOTAL/NIOCDate Sirri project, Iran (1998-2000)Function Commissioning servicesDetailLeading site commissioning of Sirri onshore facilities. Preparation and implementation ofstart-up

26

*

*Founders'references

Page 27: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(2)

Client Hyundai, KoreaDate 1998Function Commissioning packageDetailTeam for performing precommissioning/commissioning preparations on the trackingsystem for 2 large drilling ships for Angola and implementation on site

Client Inelectra, VenezuelaDate 1998Function Commissioning leader x 2DetailCommissioning preparation and implementation of oil field facilities for PDVSA

Client Elf AngolaDate Girassol (deep water project – FPSO/UFL/Subsea) - 1998Function Commissioning services and engineering servicesDetailPreparing pre-commissioning procedures Interface co-ordination on the project

27

*

*Founders'references

Page 28: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(3)

Client Forasol DrillshipDate Angola (1998-99)Function Commissioning servicesDetailPrecommissioning/commissioning preparation and implementation on tracking system‘Belcom’

Client Sedco Forex Drilling platformDate Brest (1999)Function Commissioning servicesDetailPrecommissioning/commissioning preparation and implementation on tracking system‘Belcom’

Client Qatargas LNG, QatarDate 1997-98Function Commissioning servicesDetail Leading commissioning supervision of 3rd compression

train by McDermott 28

*

*Founders'references

Page 29: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(4)

Client TOTAL,ThailandDate 1996-97Function SpecialisedservicesandproductionservicesDetail DefinitionofanHSEplanandconductingimplementation

Engineeringofagasturbinegenerator.Leadcommissioningofaplatform

Client Qatargasupstream,QatarDate 1996-98– Dubai&AbuDhabiFunction Commissioning/start-upservicesDetail Leadingcommissioningstart-upandshut-downofoffshore

facilities

Client ElfCongoDate N.KossaField(1995-96)Function Precommissioning/commissioningservicespackageDetail Preparationofprecommissioning/commissioning

proceduresandengineeringdatabase,co-ordinationforsiteimplementation 29

*

*Founders'references

Page 30: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(5)

Client Total Austral, ArgentinaDate 1992-93Function Project control and commissioning packageDetailProject control of 2 main onshore projects (Hydra etc.)Leading precommissioning/commissioning preparation and performance supervision ofthese projects

Client TOTAL YemenDate 1996-97FunctionSet-up of Opex contract - field management and commissioning services

Client Shell NigeriaDate BOS Waari Refinery - 1990Function Engineering servicesDetail Precommissioning and commissioning of DCS and telecoms

30

*

*Founders'references

Page 31: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(6)

Client Ecopetrol ColombiaDate Refinery - 1997Function Start-up servicesDetail Preparation and implementation of start-up

Client IFPDate Refining units - 1996 - 97 - 98Function start-up services

Client TOTAL IndonesiaDate 1996-2000Function Commissioning servicesDetail Various projects

Client Lasmo VenezuelaDate 1999Function Commissioning Services

31

*

*Founders'references

Page 32: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(7)

Client TOTAL AlgeriaDate Hamra Field -1996Function Commissioning Services

Client Amoco, HoustonDate 1991Function Project managementDetailPlanning of commissioning/start-up maintenance of 3 offshore facilities and datawarehouse computerisation supervision

Client TOTAL AlgeriaDate Tin Fouije Field - 1996-97Function Production servicesDetailPreparation of maintenance and CMMS on oil field installations

32

*

*Founders'references

Page 33: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(8)

Client Repsol, AlgeriaDate Production Sharing Contract Sonatrach/Repsol - 1997-98Function Production servicesDetail Review of operating manuals

Client Total IndonesiaDate Balikpapan - 1992Function Maintenance organisation and Management Manual

Client SonatrachDate Hamra - 1996Function Maintenance guidelines for electrical equipment

Client GascoDate ASAB - 1994Function Work order procedures

33

*

*Founders'references

Page 34: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(9)

Client ADNOCDate Mubaras Island - 1997Function Engineering and implementation of actions groups training

to improve onshore and offshore safety.

Client TOTAL AlgeriaDate HassiMessaoud- 1990-91Function ProductionservicesDetail Trainingofoperators

Client CegelecDate ParisHQ- 1993-94Function Trainingoftrainers,developmentofmodelsandmodules.

Client QatargasDate 1996Function Engineering,implementationandmanagementofoperating

manualsforoffshorenaturalgasproductioninstallation34

*

*Founders'references

Page 35: Vectrance PMC REFERENCES - SteriWave 2refer [1].pdf · OIL FIELD SERVICES REFERENCES (1) Client Medco,Pertamina,Shellbrunei Date 2002-04 Function Drillingsuperintendents Detail Preparationofexplordrillingprogram,tendering

OPERATION&MAINTENANCEREFERENCES(10)

Client Gaz De FranceDate HQ (2000)Function Engineering and implementation of organised training

Network to ease the use of PIDs for operations, betweenoperators and engineers.

35

*

*Founders'references