Utah’s Use of CMGC & Project Delivery
Presented by:Michelle Page, P.E.
UDOT Innovative Contracting
![Page 2: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/2.jpg)
What is CMGC in Utah?
• Consists of a Project Team with Three Participants:– An Owner– A Designer– A General Contractor with a Two Phase
Contract • Phase I – A “Construction Management”
consulting contract to help with Design• Phase II – A “General Contracting “ contract
to build the project
![Page 3: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/3.jpg)
Benefits of CMGC• Public Expectation
– Open Road
• Political Capital– Politicians Take Credit– UDOT utilizes more state funds than
federal
• User Cost Savings– Reduce Construction Time– Reduce Construction Delays– Business Stays Open
![Page 4: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/4.jpg)
Innovative Contracting Program
![Page 5: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/5.jpg)
Engineering Solutions
• Advances in Roadway Geometry:– DDI, CFI, Flex Lanes, Movable Barrier, Reversible
Lanes
• ABC Program:– I-80 Bridge Farm– Precast Structural Elements (Bents, Columns,
Superstructure, Deck, Pavement Slabs)
![Page 6: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/6.jpg)
Owner Controls the Design
UDOT
Plan
Build
Design Consultant
Design
Contractor
UDOT
Bid Build
Contractor
Validate
![Page 7: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/7.jpg)
CMGC Expectations
• Better Designs• Better Schedules• Lower Costs
– Savings in Design– Savings in Construction– Savings from Innovation– Savings from Mitigated Risks
![Page 8: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/8.jpg)
Project Delivery Timelines
Design Adv
Sel
ect
Construct
Traditional
RFP
Design
Sel
ect
Construct
CMGC
Early Construct
Design-Build
ConstructRFP
DesignRFQ S
elec
tDesign
![Page 9: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/9.jpg)
CMGC Project Delivery Results
• Speed– Early start items of work before 100% Design– Early Procurement– Advanced Contractor Planning
• Brevity– 30 to 50 Page RFP
• Control– Owner makes design decisions with Contractor and Designer
inputs
• Flexibility – We can change scope during Design
![Page 10: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/10.jpg)
When UDOT Uses CMGC
• Projects that need Contractor input• Project where UDOT wants to control the design• Projects with a high need for innovation• Projects that can benefit from early
procurement or construction• Projects with third-party risk• Projects to introduce new technology
![Page 11: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/11.jpg)
Cost & Schedule Influences
![Page 12: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/12.jpg)
Mountain View CorridorInfluence of Risk and Innovation on Cost
![Page 13: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/13.jpg)
Innovation Savings
Project Description Anticipated PriceEstimated Direct
SavingsEstimated User
Cost Savings4500 S/I-215 $3,995,048.48 $40,000,000.00ATKINVILLE INTERCHANGE $36,293,458.81 $4,700,000.00Riverdale Road Ph 1-3 $39,601,488.70 $3,260,000.00 $84,000,000.00I-80 State to 1300E $96,806,965.51 $4,000,000.00 $122,000,000.00Virgin River Trail $1,199,522.25 $180,000.00I-15 Bridge Deck in Spanish F $8,657,138.00 $240,000.00 $43,000,000.00SP-River Road to Airport $26,589,972.50 $3,536,000.00Syracuse Rd Ph 1-2 $13,947,531.55 $1,115,000.005th South Bountiful Ph1-4 $839,398.00 $700,000.00Eagle Canyon Bridge $5,294,135.21 $153,500.00Total $233,224,659.01 $17,884,500.00 $289,000,000.00Savings as a Percent of Anticipated Price: 8% 124%
![Page 14: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/14.jpg)
Who Gets the Savings?
DBB DB CMGC
Contractor Risk
Owner Risk
Ris
k
Reduce risk, and share the savings
![Page 15: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/15.jpg)
CMGC Projects Save on Change Orders & Overruns
![Page 16: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/16.jpg)
Owner Implemented Innovation
![Page 17: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/17.jpg)
Flexibility
![Page 18: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/18.jpg)
Fair Price Strategy
• Proposal Items– Prices set inCompetitive Process
• State Averages & Ratio– Comparison to Other projects
• Total Cost Compared to– Independent Cost Estimate – Engineers Estimate
Selection Bid Items
State Average Prices
ICE, EE
![Page 19: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/19.jpg)
We Save on Bid Item CostsCompared to State Averages
![Page 20: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/20.jpg)
Where Owner Spends the Effort
• Define Goals• Describe Project• RFP Development• Proposal Evaluations
• Risk Analysis• Innovation Analysis• Cost Comparisons• Design Decisions• Contractor Construction
![Page 21: Utah’s Use of CMGC & Project Delivery Presented by: Michelle Page, P.E. UDOT Innovative Contracting.](https://reader038.fdocuments.in/reader038/viewer/2022102713/56649cc05503460f949876ef/html5/thumbnails/21.jpg)
Available Tools & Resources• UDOT Website:
http://www.udot.utah.gov/main/f?p=100:pg:0:::1:T,V:1869, – CMGC Description– Advertising Checklists– Analysis and Reports– Process Documents– Sample Documents
• Rudy Alder, UDOT Innovative Contracting Engineer ([email protected])