UPDATE CPC ELEVATOR April 2020 ESTIMATED TIMELINE...
Transcript of UPDATE CPC ELEVATOR April 2020 ESTIMATED TIMELINE...
In this issue we feature:
Elevator Status Report and Floorplans Progress on our Capital Campaign Elevator Manufacturer and Installer
----------------------------------------------------
Mission of Spirit & Space Team as established by Session of Christ Presbyterian Church – Canton, Ohio:
Continue to build up this congregation’s reputation as a warm and welcoming,
“Gather Us In”, community.
MANUFACTURER Established 1946. 2575 Greensburg Rd., North Canton, OH. One of only three custom elevator manufacturers in the U.S. Recognized as a hole-less (no pit) elevator pioneer. Staff expertise in applied engineering, manufacturing, field installation, modernization and preventive maintenance. Projects include elevators at the Rose Bowl; Smithsonian; JFK, Newark, and O’Hare International Airports; Pro Football Hall of Fame; Princeton and Harvard Universities.
INSTALLER Established 1991. Located: Cuyahoga Falls, Gahanna, OH. Co-founded by two cousins of Gable family whose entrepreneurial experience spans three generations. Will coordinate installation efforts with architect –
Chambers, Murphy & Burge, and with General Contractor – Regency Construction Services, Inc.
Projects include elevator installations at Tudor Arms Hotel, Case Western Reserve, both in Cleveland; Riverview Tower in Ohio City.
Mar. 16, 2020
Pledges =
$2.434 Million
GOAL $2.5 million
Matching
Donation
Still
Available!
http://www.cantoncpc.org/spiritandspace
UPDATE April 2020 CPC ELEVATOR
LOCATION Most cost-effective and time-saving option. Only area wide enough to accommodate the size specifications needed for elevator to carry a gurney. Avoids costly changes to church roofline. Allows entire mechanism and elevator doors to be fully inside building.
Floor #2
Youth
Room
SPECIFICATIONS
Capacity: 3,000 lbs. Speed: 100 feet per minute Travel Distance: 21’0” approx. Hoistway Size: 8’0” x 9’6” Openings: Four (3 front, 1 side) Stops: 4 (3 Front, Side Slide; 1 Side, Center Open) Doors: Two Doors. Two-speed. 3’6”w x 7’0”h Stainless Steel Finish Front Door = Side Slide Side Door = Center Opening Accommodates: Hospital Gurney Non-Proprietary Microprocessor Control System Warranty and Maintenance: One Year
ESTIMATED TIMELINE /COST
Start of Construction Project: ~Mid-May Elevator Construction Start: ~Early July Guaranteed Maximum Price: $193,883 includes design, manufacturing and installation
Existing
Kitchen
Floor #1
Ground Floor