Upcoming Experiments at the SPS What to Expect and the Impact on Operation E. Gschwendtner EN/MEF
description
Transcript of Upcoming Experiments at the SPS What to Expect and the Impact on Operation E. Gschwendtner EN/MEF
-
Upcoming Experiments at the SPSWhat to Expect and the Impact on Operation
E. Gschwendtner EN/MEF
-
Many thanks toA. Blondel, H. Breuker , F. Butin , A. Ceccucci, I. Efthymiopoulos, L. Gatignon, M. Gazdzicki, L. Linssen,G. Mallot , S. Maury, A. Rubbia, U. Uggerhoj
-
OutlineIntroductionApproved experiments at SPSNA61 (ion-physics, successor of NA49)NA63 (QED in strong crystalline fields)NA62 (rare Kaon decays, successor of NA48) COMPASS (QCD, hadron structure)In pipeline for approvalIrradiation Facilities: GIF++Neutrino Detector R&DSummary
-
*Beam Facilities at CERN
-
The North Experimental Areas at the SPSThe SPS proton beam (400/450 GeV/c) slowly extracted to North AreaDirected towards the three North Area primary targets T2, T4 and T6NA61NA63GIF++CERF++NA62COMPASST2T4T6T10H2H4H6H8P42K12M2SPS beamEHN1ECN3EHN2Neutrino R&DIon-Exp.(NA49)(NA48)
-
North Experimental Areas (SPS)
-
North Area Beam CharacteristicsH2, H4, H6, H8 (EHN1)10 400 GeV/c (H6: 205 GeV/c)VLE extension in H2, H8: 1-9GeV/cAttenuated primary proton beam at 400 (450) GeV/c for H2, H4, H8electrons, hadrons, muons, photonssecondary target tertiary beammax. 2 108 particles per spill for secondary beam< 1 1011 particles per spill for primary protons if proper shielding (H4)
M2, COMPASS (EHN2)High intensity (polarized) muon beamTypically 4 108 muons at 160 GeV/c for 2.4 1013 protons on T6 targetsecondary hadron beam up to 280 GeV/c
P42/K12, NA62 (ECN3)Primary proton beam to target T10Kaon beam (mixed beam with 6% K+) up to 75 GeV/c
-
User Requests for SPSSPS Secondary Beams Experiments and TestsApprovedexperiments
Sheet2
2006 StatisticsExperimentBeamSatisfaction level
CRYSTALH43.5
AMS/CaloH43.5
AMS/CherH24.01.000
DREAMH42.01.500
DEPFETH64.52.0517.8571428571
CALICEH64.02.513.5714285714
Sum.StudentsH65.03.013.5714285714
LHCfH45.03.5414.2857142857
NA49H25.04.0725
CERFH65.04.5414.2857142857
CREAMH24.55.0621.4285714286
NUCLEONH24.0
RD42H6/H83.0
CHERCAMH23.5
MircopatternH42.0
GLASTH63.5
Mon.PixelH62.5
P-326H64.0
OPERAT70.5
IrradiationsT7/T80.5
SiTRD/PICHT95.0
DIRACT80.0
LHCbH85.0
TOTEMH8
ALICEH62.0
ALICET9/T104.0
CMS/ECALH44.0
CMS/CombH24.5
ATLAS/LumiH84.0
ATLAS/CaloH62.0
COMPASSM24.5
OPERACNGS2.0
ECC
MICE/TPGT9
Sheet2
0
0
0
0
0
0
0
0
0
Sub-periods (graph)
714130
704030
875433
795524
60600
200720072007
Total
North Area
West Area
Year
Sub-periods
SPS North Area Schedule
Graphs
2251252001
2151242002
2852032003
2661732004
3172121
3272131
31101731
2961751
Total
LHC Exp
Test Beams
FT-Exp
CNGS
Year
Number of users
SPS Secondary Beams - Experiments & Tests
Summary
YearTotalLHC-ExpNon-LHCFT-ExpCNGSSub-PeriodsNorth AreaWest-Area
SPS North Area
2001225125714130
2002215124704030
2003285203875433
2004266173795524
2006317212160600
20073272131
200831101731
20092961751
PS East Area
2008172132
200911182
2007
Beam Requests 2007
--------------------------------------------------------------------------------
Experiment ISIEC Type Requested time Request for SPS Beam Responsible / Contact Comment
--------------------------------------------------------------------------------totalLHCNon-LHCFTCNGS
1ALICE-ZDC Calo 1 w June H6A, 50,60,80,100,120,150GeV e - P.Martinengo11
2ALICE-EMCAL Calo 3 w (plus 3 w PS) P.Martinengo, T.Awes1
3ATLAS-3DSi Trk 1 w H8 B. Di Girolamo, K.Einsweiler only general request11
4ATLAS-RP Trk 4 w H8 B. Di Girolamo, P. Grafstrom only general request1
5ATLAS-LUCID Trk 1 w H8 B. Di Girolamo, J. Pinfold only general request1
6ATLAS-ZDC Calo 1 w H8 B. Di Girolamo, S. White only general request1
7ATLAS-BCM Trk 1 w H8 B. Di Girolamo, A. Gorisek only general request1
8BRAN IonCham 1 w H4 H. Matis, E. Bravin11
9CALICE Calo 4 weeks, 2 weeks paras. H6, all part., 6 - 100 GeV J.C. Brient, F. Sefkow11
CERF various 2 x 1 w H6 M. Fuerstner11
CERF++ 3 days H4 (?) M. Fuerstner tests for a new CERF facility11
CHERCAM Cheren. 1 w ~300 GeV hadrons S.Malinin11
CMS-ECAL11
CMS-HCAL1
CMS-SIRaD1
CMS-CASTOR Calo 10 d H2, all part. neg. min to max E A. Panagiotou1
CREAM Calo + Trk 7 d H2, e, h, 50 - 350 GeV S.Malinin11
CRYSTAL Trk 3 weeks H4 U. Uggerhoj11
CRYSTAL-REFL Trk 7 weeks H8 prim p, H4 e M. Fiorini, W. Scandale t.b.submitted to SPSC11
DEPFET Trk 1 w + 1 w paras H6 or H8 J. Velthuis11
DREAM11
ECC Cloud Chamber 4 d H4 low int. e, mu, various E Y. Sato11
GLAST Calo+Trk 1 w H4, all part., 10-280GeV B. Lott11
ILC-MR SiTrk 1 w mu, E>100GeV T. Baroncelli11
LHCb various 3 x 2 weeks H8, 200-400GeV e, h E. Thomas only general request11
LHCf SiTrk 2 weeks H4, all part. 20-250GeV S. Torii11
MEDIPIX Trk 2 x 3 d (+ few days paras.) H6, all part., >100GeV E. Heijne11
MONOPIX Trk 2 w + 1 w paras. H8, h, mu >100GeV M. Winter11
NA49-future various 30 days H2, pos. had. 30GeV Z. Fodor submitted to SPSC11
NUCLEON Calo+Trk 1 week H2B1, e, h 100-450 GeV L. Tkachev11
PAMELA Calo 1 week, October H2, H4, 50-200GeV e+, +,h+11
PHENIX Calo 1 week H2, all part. 10GeV hadronsS. Schael
CLOUDT11J. Kirkby
DIRACT8L. Nemenow, L. Afanasev
IRRADIATIONT7M. Glaser, M. Moll
OPERA-BricksT7U. Moser
SITRD-PICHe, h both pol. T9N. Mazziottaspecial set-up requir.
T2K-TPCT9E. Radicioni
nTOFMemo received, subject to target status and MOU
MERITA. Fabich , I. Efthymiopoulos
Christoph Rembser December 6, 2006
ALICE-ZDC
P.Martinengo
ALICE-EMCAL
only general request
only general request
only general request
only general request
only general request
BRAN
CALICE
CERF
M. Fuerstner
CERF++
M. Fuerstner
CHERCAM
S.Malinin
CMS-ECAL
CMS-HCAL
CMS-SIRaD
CMS-CASTOR
A. Panagiotou
CREAM
S.Malinin
CRYSTAL
U. Uggerhoj
CRYSTAL-REFL
DEPFET
J. Velthuis
DREAM
R. Wigmans
ECC
Y. Sato
GLAST
B. Lott
ILC-MR
T. Baroncelli
LHCb
E. Thomas
LHCf
S. Torii
MEDIPIX
E. Heijne
MONOPIX
M. Winter
NA49-future
Z. Fodor
NUCLEON
L. Tkachev
PAMELA
M. Ricci
PHENIX
J. Lee
RD42
SILCRaD
A, Savoy-Navarro
SITRD-PICH
N. Mazziotta
Summer Students
TOTEM
M. Deile
L. Luquin
COMPASS
G. Mallot
P-326
A. Ceccucci
Y. Declais
ALICE-VZERO
ALICE-TRD
P.Martinengo
only general request
P.Martinengo
only general request
ALICE-EMCAL
AMS
S. Schael
CLOUD
J. Kirkby
DIRAC
IRRADIATION
OPERA-Bricks
U. Moser
SITRD-PICH
N. Mazziotta
T2K-TPC
E. Radicioni
nTOF
MERIT
Christoph Rembser December 6, 2006
2008
Beam Requests 2008
--------------------------------------------------------------------------------
Experiment ISIEC Type Requested time SPS allocated zone Responsible / Contact Comment
--------------------------------------------------------------------------------LHCNon-LHCFT-Exp
ALICE-TRD 1 w, expr.of interest, huge object P.Martinengo General Request1
AMS Flight module 1 month req. H8 V. Plyaskin, S. Ting1
ATLAS-3DSI ISIEC_H6 2x1 w (+1 paras.) B.DiGirolamo General Request1
ATLAS-BCM ISIEC_H6 2x1 w B.DiGirolamo
ATLAS-DIAMONDS ISIEC_H6 2x1 w (+1 paras.) B.DiGirolamo
ATLAS-FP420 ISIEC_H6 2x1 w (+1 paras.) B.DiGirolamo
ATLAS-LUCID 2x1 w (+1 paras.) B.DiGirolamo
ATLAS-MDT ISIEC 1 week B.DiGirolamo, T.Baroncelli
ATLAS-MICROMEGAS ISIEC_H6,ISIEC_MM 3x1 w (one week can be at PS) B.DiGirolamo General Request
ATLAS-TGC 10 days B.DiGirolamo
ATLAS-TRD ISIEC Trk 1 week H8 B.DiGirolamo, H.v. d.Graaf, A. Romaniouk
ATLAS-ROMAN-POTS 2w (+1 paras.) either at SPS or PS, depends on timing! B.DiGirolamo General Request
CALICE Trk 1 w H2 I. Laktineh1
CERF ISIEC various 2 x 1 w H6 E. Feldbaumer1
CERF++ 1 week H4 E. Feldbaumer1
CMS-CASTOR ISIEC Calo 10 d H2 A. Panagiotou1
CMS-ECAL ISIEC Calo 6 weeks H4 P. Bloch if and when depend on LHC start date
CMS-HCAL ISIEC Calo 2 weeks H2 D. Lazic
CMS-SIUPGRADE ISIEC Trk 2 w H2 P. Luukka
COMPASS1
and addendum all year G.Mallot, A.Magnon
COMPASS-SHASHLIK Calo 2 weeks V.Polyakov, G.Mallot1
CREAM Calo + Trk 1 week H2 S.Malinin1
DEPFET ISIEC Si-Tracker 1 week (after 1 week PS) req. H6 or H8 L. Reuen1
DREAM Calorimeter 3 weeks req. H4 R. Wigmans1
ECC ISIEC Emulsion 1 week H4 low int. e, mu, various E Y. Sato1
EUDET-TELESCOPE & EUDET-JRA1 ISIEC SiTrk 2 w +8 w paras H6 I. Gregor1
LCFI ISIEC Silicon 1 week + paras. J. Velthuis1
LHCb Si 2 weeks E. Thomas , P. Collins1
LHC-BLM SEMs 2 x 1 day H4, maybe H6 B. Holzer1
LHCf SiTrk/SiFi 2 weeks H4, all part. 20-250GeV S. Torii1
MEDIPIX ISIEC Trk 3 x 3 d (+ few days paras.) H6, all part., >100GeV E. Heijne1
MONOPIX ISIEC Trk 2 w + 1 w paras. H8 M. Winter1
tr> IRRADIATION ISIEC various 4 months T7 M. Glaser, M. Moll1
NA61
ISIEC various 45 + 5 days H2 Z. Fodor, M. Gazdzicki
NA62 3+3 weeks P0 A. Ceccucci1
NA 631
ISIEC 1 week H4 U. Uggerhoj
NUCLEON ISIEC Calo+Trk 1 week H2B1 L. Tkachev1
OPERA CNGS Y. Declais
RD22 ISIEC_H4, ISIEC_H8 Trk 3 w e + 3 w p H8 prim M. Fiorini, W. Scandale1
RD42 SiTrk 3 x 1 week, 2 weeks paras. H. Kagan, P.Weilhammer1
SILC ISIEC_1,_2 Trk 3 weeks A. Savoy-Navarro1
SITRD/PICH TRk+Calo 2 weeks req. H4 N. Mazziotta1
TOTEM ISIEC Trk 3 w main, more paras. H8 M. Deile1
UBRAN ISIEC IonCham 1 w H4, early! H. Matis, E. Bravin1
--------------------------------------------------------------------------------10173
--------------------------------------------------------------------------------
Experiment ISIEC Type Requested time PS allocated zone Responsible / Contact Comment
ALICE-FARICH 10 days T10 A.Di Mauro General Request1
ALICE-HMPID ISIEC 2 weeks A. Di Mauro
ALICE-PHOS 6 weeks, but depends on installation schedule T10 A. Di Mauro General Request
ALICE-TOF ISIEC 3x2weeks T10 A. Di Mauro
AMS ISIEC Sci-Counters 2 weeks T9 S. Schael1
AMS-TRDUP ISIEC Tracker 2 weeks T9 W. Lustermann
ATLAS-MICROMEGAS maybe 1 w if no place at SPS B.DiGirolamo General Request1
ATLAS-ROMAN-POTS 2w (+1 paras.) either at SPS or PS, depends on timing! B.DiGirolamo
CALICE traking chambers (GRPC and muMEGAS) 1 week T10 I. Laktineh1
CHIC ISIEC Si & calo 2 weeks T9 M. Prest, W. Scandale magnet needed!1
CLOUD Cloud chamber 10 weeks T11 J. Kirkby, A.Onnela1
COMPASS-SHASHLIK Calo 2 weeks T9 V.Polyakov, G.Mallot1
COMPASS-CALO Calo 2 weeks T9 G.Mallot
DEPFET ISIEC Si-Tracker 1 week L. Reuen1
DIRAC ISIEC all year T8 L.Nemenow, L.Afanasev1
EMR ISIEC SiTrk + TOF 2 weeks T9 G. Giannini1
EUDET-PS SiTrk 2 w T9 I. Gregor1
GRIDPIX-GOSSIP ISIEC Trk = 1 week T9 H. van der Graaf, A. Romaniouk1
IRRADIATION ISIEC various 4 months T7 M. Glaser, M. Moll1
KLOE-2 ISIEC GEM 2 w T9 G. Bencivenni1
OPERA-Bricks1
Emulsion+Trk 2x1 week T7 or T9 ? U. Moser
SLIM5 ISIEC Si-Trk 2 weeks T9 S. Bettarini1
T2K-TPC TPC 2 weeks T9 E. Radicioni1
2132
--------------------------------------------------------------------------------
Emmanuelle Perez May 27, 2008
2009
BeamRequests2009
--------------------------------------------------------------------------------
ExperimentISIECTypeRequestedtimeSPSallocatedzoneResponsible/ContactComment
--------------------------------------------------------------------------------
LHCNon-LHcFTCNGS
AMSFlightmodule2monthsreq.H8V.Plyaskin,S.TingOct31:06:40changedtheirmind...nowwantSeptember-October..1
ATLAS-StrawUpgradeB.DiGirolamo1
ATLAS-TGCFullprototypeforSLHC10daysH8-earlyB.DiGirolamo,G.MikenbergNAcutin2008
ATLASB.DiGirolamoATLASGeneralrequest
CALETcalorimeter(spaceexperiment)1weekH2S.ToriiendofAugust1
CALICE-GRPCGRPCdetectors1weekH4orH6I.Laktinehpref.July1
CALICE-MMEGAS-RD51DHcal,MicroMegas12daysH2BC.Adloffw42-43,notbeforew40.NeedsEuDetTelescope.
CALICE-MMEGASDHcal,MicroMegas10daysH2BC.Adloffw41-42,notbeforew39.NeedsEuDetTelescope.
CMS-CASTORCASTORcalorimeter10daysH2A.Panagiotou1stweekofMay1
CMS-ECALSM37+SLHC3weeks+2x10days+2x10daysH4BPh.Bloch,P.Lecoq
CMS-HCALHCalRD(ThickGEMS/SiPMs/quartzplates)1+2weeksH2D.Lazic1winMay-June,2winJuly-August.Werecut(1w)in2008
CMS-SiUpgradeSiliconR&D10daysH2P.Luukkaaftermid-July
COMPASSCOMPASSrunallyearM2G.Mallot1
COMPASS-CALOCalo(leadglassandShashlik)2weeksH4G.Mallot,V.PolyakovAlsoPSrequest.NotbeforeJuly.1
CREAMCalo+Trk1week(2008cut)+1weekH2A.Malinin1stweekearlybutsafe(2008cut...),2ndweekearlyOctober.1
DigiMAPS-PILCSilicon1weekH6BE.SpiritiNeedsEuDetTelescope.JulyorAugust.Additionaldocument1
DEPFETSilicon1weekH6BM.VosEarlyJuly,consectiveofperiodwhereDEPFETistheDUTofEUDET.1
DREAMcalorimeter2weeksH4AS.Popescu,R.WigmansJuly.Wereveryunluckyin20081
EUDETPixeltelescope2weeksH6BI.GregorNotbeforeJulyAdditionaldocument1
INSURADcrystal+calos+chambers7+7daysH4M.Presttwogroups1
LCFISilicon1weekmain+1weekparasH6J.VelthuisNeedsEuDetTelescope.1
LHCfcalorimeters&SiDets2weeksH4Y.ItowAslateaspossible.AftersomeLHCcommiss.1
MediPixPixeldetectors2x4-MardaysH6E.Heijne1
MonoPixCMOSsensors2or3weeksH6AM.Winter1
NA611
NA61run7days(test)+97days(physics)H2M.Gazdzickitest:May18-24.Physics:Aug12-Nov16Runwascutin2008!
NA621
RICH,LASandGigaTracker3x2weeksP0A.Ceccucci2watthebeginning,2waroundJuly,2wattheend.4wcutin2008!
NA631
Leadglass,BGO,driftchambers1w(2008cut)+3weeksH4U.Uggerhoj1weekcutin2008
NUCLEON1
calo&Scint.10daysH2L.TkachevNovember
OPERACNGSRunallyearA.Ereditato1
RD421
PixelR&D3x1week+2wparasiticH6H.KaganNotbeforeJune.SeealsothegeneralATLASrequest.
RD511
micropatterngasdetectors2x3weeksCouldalsobeatthePS.M.AlfonsiSeveralgroups.
SiLCSitrackers2weeksH6BA.Savoy-NavarroWerecut(2w)in2008NeedEuDettelescope.1
SITRD-PICHTrk+Calo+Magnet2weeksH4M.MazziottaEarlyJune.1
TOTEMSiDets,T1&T2telescopes7x3daysH8M.BozzoEarlyJune.1
UA9Prototypecrystal1monthp+10daysleptonH8prim,H4W.ScandaleSep.21toNov15...1
VIPIXSiTrk1weekS.BettariniSeptemberorafter.Ifnomatch,T9couldbeapossibility.Moreinformation1
--------------------------------------------------------------------------------61751
--------------------------------------------------------------------------------
ExperimentISIECTypeRequestedtimePSallocatedzoneResponsible/ContactComment
ALICE-FARICHRICH10daysT10A.diMauroMay-June.1
ALICE-HPTDRDforHMPID(ThGEM)2weeksT10A.diMauroOct-Nov
ALICE-PMDPMDmodules(gasdetectors)10daysT10A.diMauroMay-June.
ALICE-TOFRPC3x2weeksT10A.diMauro2wbeginning,2wJuly,2wOctober.
ALICE-VHMPIDRICH3x1weekT10A.diMauroJune,September,November.Needstable.
CALICE-GRPCGRPC2weeksT9orT10I.LaktinehApril-June.Needstable.1
CALICE-MMEGAS-RD51Micromegas2weeks+5daysT9C.AdloffNeedsEuDettelescope.Weeks29,30,31.NotafterJuly31
CALICE-MMEGASMicromegas2weeks+5daysT9C.AdloffWeeks20,21,32.NotafterJune5
CLOUDnewaerosolchamber15weeksT11J.Kirkby23Apr-7Aug1
COMPASS-CALOCalo(leadglassandShashlik)2weeksT9G.Mallot,V.PolyakovAlsoSPSrequest.NotbeforeJuly.1
DIRACDIRACrunMay14tilltheendT8L.Afanasyev1
MICE-EMRScint.tracker2weeksT9G.GianniniNeedMNP17.NotearlierthanJuly1st1
Irradiations4monthsT7M.Glaser1
NA621
GigaTrackerproto2x2weeksT9A.Ceccucci2wfrommid-Sep,2wfrommid-Oct.
OPERABricksemulsionbricks+tracker1weekT7U.Moser,S.Buontemponotsure...1
PEBS1
SciFiTrk&ECAL2weeksT9S.SchaelNotbeforenovember
T2K-ECALcalo(lead-scint)7weeksT9S.BoydAsearlyaspossible.1
182
--------------------------------------------------------------------------------
EmmanuellePerezNovember12,2008
2009 EG
BeamRequests2009
--------------------------------------------------------------------------------
ExperimentISIECTypeRequestedtimeSPSallocatedzoneResponsible/ContactComment
--------------------------------------------------------------------------------
LHCNon-LHcFTCNGS
ALICE-ZDC1
AMSFlightmodule2monthsreq.H8V.Plyaskin,S.TingOct31:06:40changedtheirmind...nowwantSeptember-October..1
ATLAS-StrawUpgradeB.DiGirolamo1
ATLAS-TGCFullprototypeforSLHC10daysH8-earlyB.DiGirolamo,G.MikenbergNAcutin2008
ATLASB.DiGirolamoATLASGeneralrequest
CALETcalorimeter(spaceexperiment)1weekH2S.ToriiendofAugust1
CALICE-GRPCGRPCdetectors1weekH4orH6I.Laktinehpref.July1
CALICE-MMEGAS-RD51DHcal,MicroMegas12daysH2BC.Adloffw42-43,notbeforew40.NeedsEuDetTelescope.
CALICE-MMEGASDHcal,MicroMegas10daysH2BC.Adloffw41-42,notbeforew39.NeedsEuDetTelescope.
CERF1
CMS-CASTORCASTORcalorimeter10daysH2A.Panagiotou1stweekofMay1
CMS-ECALSM37+SLHC3weeks+2x10days+2x10daysH4BPh.Bloch,P.Lecoq
CMS-HCALHCalRD(ThickGEMS/SiPMs/quartzplates)1+2weeksH2D.Lazic1winMay-June,2winJuly-August.Werecut(1w)in2008
CMS-SiUpgradeSiliconR&D10daysH2P.Luukkaaftermid-July
COMPASSCOMPASSrunallyearM2G.Mallot1
COMPASS-CALOCalo(leadglassandShashlik)2weeksH4G.Mallot,V.PolyakovAlsoPSrequest.NotbeforeJuly.1
CREAMCalo+Trk1week(2008cut)+1weekH2A.Malinin1stweekearlybutsafe(2008cut...),2ndweekearlyOctober.1
DigiMAPS-PILCSilicon1weekH6BE.SpiritiNeedsEuDetTelescope.JulyorAugust.Additionaldocument1
DEPFETSilicon1weekH6BM.VosEarlyJuly,consectiveofperiodwhereDEPFETistheDUTofEUDET.1
DREAMcalorimeter2weeksH4AS.Popescu,R.WigmansJuly.Wereveryunluckyin20081
EUDETPixeltelescope2weeksH6BI.GregorNotbeforeJulyAdditionaldocument1
INSURADcrystal+calos+chambers7+7daysH4M.Presttwogroups1
LCFISilicon1weekmain+1weekparasH6J.VelthuisNeedsEuDetTelescope.1
LHCfcalorimeters&SiDets2weeksH4Y.ItowAslateaspossible.AftersomeLHCcommiss.1
MediPixPixeldetectors2x4-MardaysH6E.Heijne1
MonoPixCMOSsensors2or3weeksH6AM.Winter1
NA611
NA61run7days(test)+97days(physics)H2M.Gazdzickitest:May18-24.Physics:Aug12-Nov16Runwascutin2008!
NA621
RICH,LASandGigaTracker3x2weeksP0A.Ceccucci2watthebeginning,2waroundJuly,2wattheend.4wcutin2008!
NA631
Leadglass,BGO,driftchambers1w(2008cut)+3weeksH4U.Uggerhoj1weekcutin2008
NUCLEON1
calo&Scint.10daysH2L.TkachevNovember
OPERACNGSRunallyearA.Ereditato1
RD421
PixelR&D3x1week+2wparasiticH6H.KaganNotbeforeJune.SeealsothegeneralATLASrequest.
RD511
micropatterngasdetectors2x3weeksCouldalsobeatthePS.M.AlfonsiSeveralgroups.
SEM1
SiLCSitrackers2weeksH6BA.Savoy-NavarroWerecut(2w)in2008NeedEuDettelescope.1
SITRD-PICHTrk+Calo+Magnet2weeksH4M.MazziottaEarlyJune.1
TOTEMSiDets,T1&T2telescopes7x3daysH8M.BozzoEarlyJune.1
UA9Prototypecrystal1monthp+10daysleptonH8prim,H4W.ScandaleSep.21toNov15...1
VIPIXSiTrk1weekS.BettariniSeptemberorafter.Ifnomatch,T9couldbeapossibility.Moreinformation1
--------------------------------------------------------------------------------7185131
--------------------------------------------------------------------------------
ExperimentISIECTypeRequestedtimePSallocatedzoneResponsible/ContactComment
ALICE-FARICHRICH10daysT10A.diMauroMay-June.1
ALICE-HPTDRDforHMPID(ThGEM)2weeksT10A.diMauroOct-Nov
ALICE-PMDPMDmodules(gasdetectors)10daysT10A.diMauroMay-June.
ALICE-TOFRPC3x2weeksT10A.diMauro2wbeginning,2wJuly,2wOctober.
ALICE-VHMPIDRICH3x1weekT10A.diMauroJune,September,November.Needstable.
CALICE-GRPCGRPC2weeksT9orT10I.LaktinehApril-June.Needstable.1
CALICE-MMEGAS-RD51Micromegas2weeks+5daysT9C.AdloffNeedsEuDettelescope.Weeks29,30,31.NotafterJuly31
CALICE-MMEGASMicromegas2weeks+5daysT9C.AdloffWeeks20,21,32.NotafterJune5
CLOUDnewaerosolchamber15weeksT11J.Kirkby23Apr-7Aug1
COMPASS-CALOCalo(leadglassandShashlik)2weeksT9G.Mallot,V.PolyakovAlsoSPSrequest.NotbeforeJuly.1
DIRACDIRACrunMay14tilltheendT8L.Afanasyev1
MICE-EMRScint.tracker2weeksT9G.GianniniNeedMNP17.NotearlierthanJuly1st1
Irradiations4monthsT7M.Glaser1
NA621
GigaTrackerproto2x2weeksT9A.Ceccucci2wfrommid-Sep,2wfrommid-Oct.
OPERABricksemulsionbricks+tracker1weekT7U.Moser,S.Buontemponotsure...1
PEBS1
SciFiTrk&ECAL2weeksT9S.SchaelNotbeforenovember
T2K-ECALcalo(lead-scint)7weeksT9S.BoydAsearlyaspossible.1
182
--------------------------------------------------------------------------------
EmmanuellePerezNovember12,2008
2010 EG
--------------------------------------------------------------------------------
Experiment
--------------------------------------------------------------------------------
LHCNon-LHcFTCNGS
LHCNon-LHcFTCNGS
ALICE-EMCAL1
ALICE_VHMPID
ALICE-SPD
AMS1
ATLAS-3DSi1
ATLAS-ALFA
ATLAS-BCM
ATLAS-Diamond
ATLAS-FP
ATLAS-IBL
ATLAS-MDTMPI
ATLAS-MDTROMA
ATLAS-MMEGAS
ATLAS-PIXEL
ATLAS-STGC
CALET1
CALICE-GRPC1
CALICE-MMEGAS
CALICE-SPIDER
CERF1
CMOSILC1
CMS-ECAL1
CMS-CALO
CMS-HCALVF
CMS-PIXEL
CMS-SiBT
COHERENT1
COMPASS1
COMPASS-CALO
CREAM1
DEPFET1
DREAM1
EUDET1
LHCb1
LHCf1
MediPix1
NA611
NA62_TB1
NA631
NUCLEON1
PEBS1
PHOTAG1
RD421
RD501
RD511
SiLC1
SiLCRD1
SOIPIX1
SUPERB1
TOTEM1
UA91
OPERA1
ICARUS1
SUM:9194234
graph EG
2251252001
2151242002
2852032003
2661732004
3172121
3272131
31101731
3171851
3491942
Total
LHC-Exp
Non-LHC
FT-Exp
CNGS
Summary EG
YearTotalLHC-ExpNon-LHCFT-ExpCNGSSub-PeriodsNorth AreaWest-Area
SPS North Area
2001225125714130
2002215124704030
2003285203875433
2004266173795524
2006317212160600
20073272131
200831101731
20093171851
20103491942
PS East Area
2008172132
200911182
-
Approval Path
-
NA61, successor of NA49Ion-Exp.
-
NA61/SHINESPS Heavy Ion and Neutrino ExperimentStudy of hadron production in hadron nucleus and nucleus-nucleus collisions. Search for critical point of strongly interacting matterDetailed study of the onset of deconfinment in nucleus-nucleus collisionsMeasure hadron production at high transverse momenta in p+p and p+Pb collisions as reference for Pb+Pb resultsData for neutrino and cosmic ray experimentsHadron production reference measurements in p+C interactions needed for neutrino (T2K) and cosmic-ray (Pierre Auger Observatory) and KASCADE experimentsHadron production measurements in the T2K target
-
NA61/SHINE2010 RunTest runs in May in H2 and T9Physics run (18 weeks) in H2 with p+p at 158GeV/c and 10GeV/c and p+T2K target at 31GeV/c
Test of secondary boron ion beam at 20GeV/c and 80 GeV/c in September/October 2010Beam instrumentation: pulse height analyzer to identify boron ions
For each energy (20, 80, 100? GeV/c) :1 MD to set energies in SPS and extraction 1 MD to setup beam-line and data taking Test extraction and beam quality @ 10GeV/c
5-7 MDs
-
Beam line: double spectrometer with 0.04% resolution that helps to separate the ion fragments corresponding to a selected magnetic rigidity : BrNA61 Fragmented Ion Beam2.210-4 /incident Pb ion for the case of 32P15+
~2.2105 selected ions/spill for the maximum intensity of 109 Pb-ions. 2010: 4107 Pb-ions for B-beam2010:converter2010
-
NA61 Program Plan for >2011Fragmented beam: 2010 feasibility studyreal test (target and detector) + data taking: 2011, 158 GeV requires transformer in SPS (extraction only when 1109 < N < 21011)before Chamonix workshop
-
NA63Ion-Exp.
-
NA63Electromagnetic Processes in Strong Crystalline Fields
2010 program approved: 10 days in H4 low-Z LPM (Landau-Pomeranchuk-Migdal) study related to low-Z targetsProposals for > 20112011: 2 weeks in H4Studies of magnetic suppression of incoherent Bremsstrahlung MBWs available, requires area and layout studies and modifications
-
NA632012:2 weeks in H4 with ion beam for heavy ion bremsstrahlung studies when fully stripped Pb ions penetrate amorphous targetsion beam with 158 GeV, so needs transformer in SPSNot possible to have ion beam in both H2 and H4 at the same time, so NA63 request is in addition to NA61 requestPlans for beyond 2012:Strong interest in positron production studies with aligned crystals to be used e.g. in CLICApplication for funding in preparation (FP7)
-
NA62, successor of NA48Ion-Exp.
-
NA62 (P326)Sensitivity to new physics and possibility to determine CKM matrix elements in processes not affected by new physics Measure very rare kaon decay K+ pi+ n n Branching ratio of 10-10Extract a 10% measurement Sensitivity of 55 events/year with 13-17% background
Approved for 2 years 2012/2013
For > 2014: Measure K0L pi0 n n Branching ratio of ~10-12
-
NA62 SPS primary p: 400 GeV/c Unseparated beam: 75 GeV/c 800 MHz p/K/p (~6% K+)4.5 MHz Kaon decays in fiducial regionDismantling NA60, NA48New beam-line
-
NA62: ScheduleVery tight schedule!NA60, NA48 dismantled by mid 2010Beam survey in early 2012 Beam to be rebuiltCosting under way, work packages being defined and discussedFirst full data taking expected in 2012
2010: test- beamLarge Angle Veto (T9, 3 weeks, June)Gigatracker (T9, 2 weeks, September)Straws (H6, 3 weeks, June)
-
COMPASSIon-Exp.
-
IEFC workshop, 11 February 2010E. Gschwendtner, EN/MEF*COMPASS (NA58)2010: COMPASS:Study the hadron structure and hadron spectroscopy with high intensity muon and hadron beams.Planetary model of atoms! nucleus with whole positive charge and atoms mass, electrons circling1910: Rutherford: study atomic structure with alpha particles
-
COMPASS ExperimentTwo-stage spectrometerLarge angular acceptanceBroad kinematical range~250000 readout channels2009: 1.4 PB/year 250 physicists from 28 institutes Polarized beam (~75%) and target (~50%)1998 approved, first data in 20022002-2004: m+ 160 GeV/c2004: 2 weeks p- 190 GeV/c2006-2007: m+ 160 GeV/c2008-2009: p- 190 GeV/c
-
COMPASS ProgramApproved for 2010/2011Longitudinal structure functionTransverse spin structuremuon beam, intensities as now, i.e. as high as possible
ProposalsGeneralised Parton Distribution (GPD)2012 positive and negative beams, minor upgrade2014 only positive beam, new transversely polarized NH3 target4 x higher luminosity?! (upgrade of M2 beam-line) unrealistic!Drell-Yanproduction of leptonantilepton pairs in hadron collisions secondary hadron beam 50-200 GeV/chigher intensities, absorbers after targettwo year data takingRF separated antiproton beam in a second phase? (later)Double Charged Baryons450 GeV/c proton beamneeds design and rebuilt of complete M2 beam line
-
COMPASS Future Plans2008200920102011201220132014HadronSpectroscopy...TransversityDIS / SIDISGPDDrell-YanDCB...m beamm beamp,p,K beamp beamp beamCOMPASS submitted LoI, common proposal to follow Strong wish to involve new groups approved
-
GIF++Ion-Exp.
-
Radiation FacilitiesCERN wide irradiation facilities working group (DG, PH, BE, TE, EN)
2008: Survey on future needs Memorandum on status report and conclusion to management in December 2008
Identified needs from survey:High-energy and high-intensity proton (ion) irradiations HiRadMatHigh-intensity proton irradiation PS East AreaMixed field irradiations CERF++Gamma irradiations with beam GIF++
-
Gamma Irradiation Facility GIF++Proposal submitted to SPSC in September 2009Proposal presented to Research Board in December 2009Presentation to the IEFC to be prepared in order to evaluate the exact location of the GIF++ areaOn hold to find budget; conditioned with new LHC upgrade schedule?When approved: ~1.5 years for installationGIF++Powerful photon source (Cs137) to irradiate detectors and other equipment for performance, radiation and ageing studiesIn addition: presence of particle beam to check detector performance on top of a photon backgroundGIF: Present installation in Bat 190Phased out due to dismantling of the West Area no beamUsers Muon trackers of LHC experiments, detector or accelerator electronics components, beam diagnostic equipment
-
GIF++ Impact on Beam and Facility
-
GIF++ in North Area/H4 beam lineOther test areas ~100m upstream the GIF++ bunker:e.g. NA63, RD51, COMPASS-Calo, CALET, INSURAD, CMS-ECAL/BCM, LHCf, SiTRD
-
Other (Semi-permanent) Facilities in the PipelineNeutrino Detector R&D ProjectsLiquid Argon TPC DetectorIon Experiments (NA60-Future,.), CERF++, DREAM, Linear Collider
-
SummaryCERN has a worldwide unique opportunity for versatile physics programs and detector testsPS and SPS beam-linesTechnical support and infrastructure provided by CERN
Facilities are heavily used, very popularAlways fully bookedList of priorities for requests might be needed
Very broad Fixed Target programLifetime >10 years
Many more proposals in pipelineLarge objectsLooking for more permanent installationAdditional infrastructure (magnets, cryogenics)Consolidation
-
Additional Slides
-
CERF++Mixed field irradiations:Study impact on system components exposed in radiation fieldsPrimary use: LHC accelerator and detector components (SEE studies), radiation monitoring calibrationToday: CERFSPS H6 secondary beam, 120 GeV/c hadronsMax 108protons/pulseIn operations since 1991, 1-2 weeks/yrTest/calibration of passive and active detectors for dosimetry or radiation monitoringFLUKA benchmarking, beam loss monitor studies but: limited dose rate, muons from TCC2
- CERF++ Mixed Field Irradiation Facility Beam intensity :