Universal telescopic 2 & 3 door system - P C Henderson€¦ · Universal telescopic 2 & 3 door...
Transcript of Universal telescopic 2 & 3 door system - P C Henderson€¦ · Universal telescopic 2 & 3 door...
Universal telescopic 2 & 3 door system
FITTING INSRUCTIONS – NOTICE DE POSE – MONTAGE HANDLEIDING – MONTAGEANLEITUNG
ISTRUZIONI DI MONTAGGIO – INSTUCCIONES DE MONTAJE
Short Arm Belt Joint bracket Belt retain block Belt clamp 2 Door x 1 x 1 x 1 x 3 3 Door x 2 x 2 x 1 x 6
Long Arm Fixed Floor guide Adjustable floor guide bracket Adjustable floor guide foot 2 Door x 1 x 1 x 1 x 1 3 Door x 2 x 1 x 2 x 2
Datum Block Spanner Toothed belt
(Metres) Second door bracket
2 Door x 1 x 1 x 3 m x 0 3 Door x 1 x 1 x 5 m x 1
System Specification
Maximum Door Width = 1200mm Minimum Door Width = 500mm
Husky system door thickness = 32 - 47mm Soltaire system door thickness = 35 – 47mm
Husky Panel Weight = 80kg Soltaire Panel Weight = 120kg
Contents of Kit
Screw pack contents
Tape
Measure
2, 3, 4 & 5 mm
Allen keys Posi drive
screwdriver
Spirit level
Tools required
Scissors
PLEASE NOTE
These instructions are to be read in conjunction with instructions specific to
your chosen system.
System Overview & Track Installation
Husky End Elevation
Door Floor guide routing detail
(DT – 10) /2
Soltaire End Elevation
APP = (2 X DW ) – ( 2 X OL)
PCH RECOMMEND OL = 70mm
APP = 2 X DW – 140
DW = (APP + 140) / 2
APP = (3 x DW ) – ( 3 X OL)
PCH RECOMMEND OL = 70mm
APP = 3 x DW – 210
DW = (APP + 210) / 3
Two Door System Overview
Three Door System Overview
= Apron plate position
= Apron plate position
1. Attach long arm on follower door
Atta
2. Attach short arm on follower doors
DT
(DT-20) / 2
4.5 x 30 Wood Screws
(DT-20) / 2
4.5 x 30 Wood Screws
3. Remove bearing caps
4. Loop belt around bearing wheels & cut belt to length
Loop belt around bearing wheels
Apron Plates to be butt up to bearing arm
base, see system specific fitting instructions
for additional installation details
IMPORTANT
Belt tension should be sufficient
to allow connection between
doors
6. Clamp bracket should be free to traverse between bearings
5. Attach both ends to belt joint bracket
M6 x 12 CSK HD
HD
Belt clamp
Approx 10 to 22mm
depending upon door
thickness
7. Re attach bearing caps
8. Position retain block on Lead door
4.5 x 30 Wood Screws
(DT – 20 ) / 2
Lead door
Follower door
Fixed floor guide Adjustable floor
guide
9. Floor guide overview
10. Align doors with spirit level to position fixed floor guide
Datum Wall
Spirit level
11. Position floor guide on follower door
13. Ensure floor guide correctly aligned
4.5 x 30Wood screws
(DT – 10) / 2 + 3
Tighten
M4 x 6 Grub screw
12. Hang Doors, Follow fitting instructions specific to your hanger
35
14. Connect doors
Ensure belt bracket
is secured in place
Bracket clamped to bracket Bracket clamped to door
15. Two & Three Door belt Overview
M6 X 12 CSK HD
Second door
clamp bracket
16. THREE DOOR SYSTEM ONLY – Add second door bracket to long arm – See system overview
Follower Door 1
Follower Door 2 Clamp Block
M6x12 CSK HD
17. Three Door System Only – Connect doors
Mark position of datum
block by aligning with edge
of Follower door
19. With doors in fully closed position mark position for datum block
18. Three Door Belt connection overview
Follower door 2
Follower door 1
Belt runs in front of belt bracket
Bracket to be clamped
to door
Belt runs behind
second door bracket
20. Affix datum block – ensuring doors are able to fully traverse the track
21. Connect belt to datum block
Datum block
4.5x30 Wood Screws
4.5x30 Wood Screws
Soffit fix Face fix
668684 REV 2 – MARCH 2015
Woodscrews
locate on inside
of datum block
Installed Track
22. Position track stops to ensure all panels are aligned
in the fully open position