Under-Spend: An Earned Value Analysis of 60 Projects in ... · Under-Spend: An Earned Value...
Transcript of Under-Spend: An Earned Value Analysis of 60 Projects in ... · Under-Spend: An Earned Value...
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 1 of 21
Under-Spend: An Earned Value Analysis of 60 Projects in the Sahel
Stephen Fierbaugh, PMP
IMPORTANT: This analysis is ONLY as accurate and up-to-date as the data in
internal reporting systems.
Abstract Earned Value Management (EVM) is a rigorous and widely used analysis technique that provides
valuable information about projects' costs and schedules. A brief introduction is provided in this
paper.
Two superficially similar projects in the Sahel are compared using EVM, and then conclusions are
shared for all of the analyzed projects. EVM is used to answer the following questions:
1. How is each project progressing?
2. How significant is the under-spending?
3. Is each project using resources efficiently?
4. Is there a way to compare the projects to each other?
5. How much funding is necessary to complete each project?
KEY FINDING: If present trends continue, most Sahel projects will complete reasonably close to
their original budget but take longer than planned.
KEY FINDING: Only 26 of 60 projects contained data suitable for analysis. Progress tracking
systems need improvement.
KEY FINDING: EVM provides a useful way for Field Coordinators and Area Directors to
determine which projects need additional focus. Dev Reps may use it to assess future investment
opportunities.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 2 of 21
Introduction Seed Company is a $40M/year grant-making organization affiliated with Wycliffe Bible Translators.
It encourages, funds, and monitors over 800 minority language1 development projects per year,
scattered around the world. The projects are generally planned and ran by local nationals. They
report quarterly to Seed Company about finances and progress.
Many translation projects that Seed
Company sponsors are struggling with
under-spending. They have approved
budgets but are not spending available
funds. This has negative implications for
investor relations and Development
Representative workloads. This paper is an
analysis of sixty projects in the Sahel area.
It uses the Earned Value Management
technique to rank the projects and look for
insights into underspending.
The Sahel is the semi-arid region of Africa
south of the Sahara Desert and north of the
tropical coastal region. It stretches from
Guinea in the west to the Red Sea on the
east. As a practical matter, it encompasses
most of the countries overlapping these
regions.
Redaction
In keeping with standard and established Seed Company policy regarding projects in sensitive
areas, this paper has been redacted from the original. The redactions are of specific project names
and a few other details for safety purposes. Redactions are noted with square braces:
[REDACTED]
Methodology
Earned Value Management (EVM) is a mathematical technique widely used to measure
performance and progress of projects in an objective manner. It is included in the Project
Management Institute's PMBOK standard. EVM is academically rigorous and is commonly used in
the largest projects. It is standardized as ANSI EIA 748-B.
1 There are 7099 living languages in the world. The top 10 languages (Chinese, Spanish, English, Arabic, Hindi,
Bengali, Portuguese, Russian, Japanese, and Lahnda) combined are spoken by slightly less than half of the world's
population. ( https://www.ethnologue.com/statistics/size )
Illustration 1: Map of the Sahel. Wikimedia Commons,
the free media repository.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 3 of 21
See the Inputs and Outputs sections for descriptions of key values and computations used in Earned
Value Management.
Assumptions
1 All projects in Seed Company's record-keeping system are up to date as of mid-July 2017.
2 The ProjectExpenseVariance and LanguageProgress reports are accurate reflections of field
reality.
2.1 The expense value on the ProjectExpenseVariance report is derived from transfers to
the field + direct charges. (An example of a direct charge is a new computer purchased
& billed in the United States, then shipped to the project overseas.)
2.2 There is a many-to-many relationship between languages and projects. Seed
Company tracks budgets per project but progress per language. This analysis assumes
that each language comprises an equal part of the project budget.
Simple Under-Spend Intuitively, spending less money seems like a good thing. But if it causes the organization to exert
too much effort on unnecessary investment, this can unduly stress the Development Team. It also
skews administrative cost ratios and raises potential audit compliance issues on designated funds.
The Seed Company's goal is the same as the Project Management Institute PMBOK standard: that
actual spending matches planned spending.
Planned Value (PV) = Budget At Completion (BAC) * Planned % Complete (PPC)
Simple Over/Under-Spend = Actual Cost (AC) – Planned Value (PV)
A simple approach to the under-spend issue is to multiply the overall budget by the planned
complete value to generate the amount that the project should have spent by this date2, and then
compare that to actual spending. Indeed, it turns out that nearly all of the Sahel projects are under-
spent by this measure. Appendix B contains the simple under-spend data for this analysis.
However, this gross under-spend masks a distressing lack of insight. There is a big difference
between a project which has only spent 25% of its budget because it isn't doing anything and a
project which is just being fiscally frugal and efficient.
It would be helpful to know things like:
How significant is the under-spend?
Are there any trends?
2 This computation is one of the key metrics of Earned Value management, called Planned Value; see below for more
details.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 4 of 21
Which projects are better or worse?
Earned Value Management provides a toolset for answering these questions by considering another
important variable: Earned Value. Planned Value tells us how much the project planned to get done.
Earned Value tells us how much work the project actually accomplished. “Are we doing what we
said we would?”
Progress Tracking Systems Need Improvement The Sahel Area team has 60 open projects in July 2017. However, one or more of the key inputs are
missing for just over half of them. These have not been included in this analysis.
The un-analysable projects fall into three broad categories:
1. Internships
2. Non-written translation (Stories, Oral, Trauma-healing)
3. Transitions and brand new projects
For transitions3 and brand new projects, there simply isn't sufficient financial data available yet.
Seed Company's financial oversight systems for projects seem to provide good data in appropriate
formats and quantities. The projects which lacked this were just too new to have a track record yet.
However, Seed Company's systems and methodology for tracking progress are not at the same
maturity as its systems for tracking finances. For Internships and non-written projects, Seed
Company lacks strong metrics for judging progress, and there was no easy way to generate a “%
Complete”.
Even some of the traditional written translation projects struggled with good progress tracking. A
sophisticated methodology has been built in the Plan and Progress spreadsheet, but is not carried
over to the newer online app. The data points look similar but lack key behind the scenes “business
knowledge” of what the tracking data actually means, which prevents correct calculation. With its
newer systems, Seed Company has lost abilities that it once had. UBS's ParaTExt 8 promises to
automate some of this in the future, but additional work is needed in Seed Company's internal
systems as well.
On projects which are continuations of previous work4, Field Coordinators must choose how to
initially account for work already completed. This requires judgment calls on complex issues The
existing systems don't facilitate this entry, and even if they did, the choices will necessarily be
somewhat arbitrary.
Lastly, updating progress is rarely high on anyone's TODO list. Additional emphasis on this
3 Transitions would potentially have ample data, but the systems seem to be treating them as a new project from a
reporting standpoint. It is possible that a custom EVM report could take this into account.
4 Some projects pick up where a previous effort left off. It might be a recent Seed Company-sponsored project, or it
may have been done many decades in the past. This category encompasses a wide variety of situations.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 5 of 21
mundane chore would enable more accurate future analysis.
Inputs to EVM One of the major advantages of Earned Value Management is that it requires only a limited set of
data in order to compare otherwise different projects in a way that is “apples to apples”.
This analysis needs only four inputs:
1. Budget At Completion (BAC) – The full budgeted cost of the project when all pre-planned
expenses over its lifetime are included. Seed Company calls this “SC Lifetime Field
Budget”.
2. Actual Cost (AC) – How much money has been spent on the project to date? See the
Assumptions for an important note about how this has been calculated for this analysis.
3. % Complete (PC) – How many of the project's goals have actually been accomplished to
date?
4. Planned % Complete (PPC)5 – How many of the project's goals were planned to have been
accomplished by now?
Data for this whitepaper was collected in mid-July from the ProjectExpenseVariance and
LanguageProgress reports. This process required repeated manual running of the reports. A
custom-made EVM report could extract similar data from Seed Company systems with higher
efficiency in the future.
Appendix C contains the input data for this analysis.
Overview of EVM Earned Value Management is able to produce a variety of metrics which may prove useful in
analysis. The index numbers may be compared or ranked even when the projects are quite different.
Earned Value Management gets its name from the comparison of Planned Value (PV) to Earned
Value (EV), which is at its core. These lead to the Cost Performance Index (CPI) and Schedule
Performance Index (SPI), which measure how efficiently the project is spending money and how
quickly the work is being accomplished.
Each project is judged only by its own planned budget (“How much did we spend/get done?” vs
“How much did we say we were going to spend/get done?”). In a project that is on time & on
budget, both CPI and SPI are exactly 1.0 (one). Less than one is bad, while greater than one is
generally good.
Another useful metric for translation projects is Estimate To Complete (ETC). If present
5 Depending on how the data is organized, PC and PPC may be one or two numbers. Because of the organization of
the SC data, it was most convenient to use two numbers. This does not affect the output or conclusions.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 6 of 21
performance trends continue, how much money is it actually going to take to finish this project?
This may be vastly different than the budgeted amount.
The following are some common Earned Value metrics, how they are computed, and what their
implications are for translation projects:
Metric Formula Explanation
Key Metrics
PV Planned Value BAC * PPC How much work did we plan on accomplishing by
now?
EV Earned Value BAC * PC How much work did we actually accomplish?
CPI Cost Performance
Index
EV / Actual
Cost (AC)
How much work is being done compared to what we
said would be done for this amount of money?
(> 1 = good)
SPI Schedule
Performance Index
EV / PV How efficiently are we progressing compared to our
planned schedule?
(> 1 = ahead of schedule)
Secondary Metrics
CV Cost Variance EV - AC The difference between the value of the work we've
actually done and how much it has actually cost us.
(> $0 = good)
SV Schedule Variance EV - PV The difference between the value of the work we've
actually done and the work we scheduled. I.e. how
far behind or ahead are we?
(> $0 = good)
Completion
Projections
EAC Estimate At
Completion
Budget At
Completion
BAC / CPI
If present trends continue, how much is the project
going to cost when complete?
ETC Estimate To
Complete
EAC - AC If present trends continue, how much more money
will be needed in order to finish the project?
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 7 of 21
Metric Formula Explanation
VAC Variance At
Completion
BAC - EAC How much over or under budget will the project be
at completion?
Appendix D contains the output data for this analysis.
Earned Value Analysis of the Sahel
IMPORTANT: This analysis is ONLY as accurate and up-to-date as the data in internal
reporting systems.
Twenty-six Sahel Area projects appear to contain sufficient data in internal reporting systems to
analyze them using Earned Value Management. These are all written translation projects with
various goals.
[REDACTION: The two projects of focus have been relabeled AAA and BBB.]
AAA and BBB
Let's begin by considering two projects, the AAA (#21095) and the BBB (#20154). These projects
are both in West Africa and were originally scheduled to last three years. The AAA is an Initial
Goals project based on [REDACTED], while the BBB is a [REDACTED]. The AAA's total budget
is $70,088 over three years, while the BBB are budgeted at $74,119. As of July, 2017, the AAA are
scheduled to be 61% complete while the BBB should be 86% complete.6
The AAA have only spent $17,050 while the BBB have spent $43,719, but the BBB are schedule to
be further along (86% vs 61%), so both are significantly under-spent relative to what they were
scheduled to spend by this time. The AAA are under-spent $25,704 while the BBB are under-spent
$20,023.
6 See the section “What now?” for a discussion of the accuracy of this data. This study assumes that Seed Company
reports are accurate.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 8 of 21
# Project BAC (SC Lifetime
Field Budget) Planned %
Complete
(PPC)
Actual
Cost (AC) Planned Value
(BAC * PPC)
Simple Over/Under
Spend (AC - PV)
21095 AAA $70,088 61% $17,050 $42,754 -$25,704
20154 BBB $74,119 86% $43,719 $63,742 -$20,023
The AAA and BBB appear to be broadly similar projects in many ways related to scope, size, and
finances, even though they have different goals. Seed Company would like to be able to compare
the projects and answer the following questions:
1. How is each project progressing?
2. How significant is the under-spending?
3. Is each project using resources efficiently?
4. Is there a way to compare the projects to each other?
5. How much funding is necessary to complete each project?
How is each project progressing?
The LanguageProgress report indicates that the AAA should be at 61% but are only at 16%. The
BBB should be at 86% but are only at 71%. At a superficial glance, both projects are behind
schedule and may be in trouble.
Earned Value Management paints a more complex picture. The AAA had planned on spending
$42,754 (61% of their $70,088 lifetime field budget). The BBB had planned on spending $63,742
(86% of their $74,119 budget). These are their Planned Values (PV). In reality, the AAA have spent
$17,050 while the BBB have spent $43,719 (Actual Cost AC). Both are significantly under-spent
from their plan.
# Project BAC (SC
Lifetime Field
Budget)
Planned %
Complete
(PPC)
Actual Cost
(AC) Planned Value
(BAC * PPC)
% Complete
(PC) Earned Value
(BAC * PC)
21095 AAA $70,088 61% $17,050 $42,754 16% $11,214
20154 BBB $74,119 86% $43,719 $63,742 71% $52,624
However, a better question might be, “How are they doing compared to how they planned to be
doing?” Multiplying the project budget by the actual progress reveals how much Earned Value
(EV) the projects have generated: $11,214 for the AAA and $52,624 for the BBB.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 9 of 21
How significant is the underspending?
Earned Value is an important metric. Instead of asking, “How much money have they spent?”, the
question becomes “How much value have they delivered?” The AAA have spent $17,050 but only
generated $11,214 of value, while the BBB have spent $43,719 but have generated $52,624 of
value.
By this more sophisticated spending analysis, called Cost Variance (CV), the AAA have not under-
spent at all, but rather overspent $5,836! The BBB, on the other hand, have actually under-spent,
$8,905, but only because they have delivered more value for their budget money.
# Project Actual Cost (AC) Earned Value (BAC * PC) Cost Variance (EV - AC)
21095 AAA $17,050 $11,214 -$5,836
20154 BBB $43,719 $52,624 $8,905
Is each project using resources efficiently?
Knowing the Planned Value and the Earned Value allow calculation of a number of other useful
metrics. The ratio of Earned Value to Actual Cost is the Cost Performance Index, or CPI. This is a
number that tells how efficiently the project is getting its work done. In an ideal project, the CPI is
1.0 (one). A CPI less than one is spending more money than budgeted to do the planned work. A
CPI of greater than one indicates that the work is getting done with less money.
The AAA's CPI is 0.66 while the BBB's is 1.20. Another way of looking at this is the AAA are only
getting 66 cents worth of work for every dollar spent while the BBB are getting $1.20 of planned
work for every dollar actually spent.
# Project Earned Value (BAC * PC) Actual Cost (AC) Cost Performance
Index (EV / AC)
21095 AAA $11,214 $17,050 0.66
20154 BBB $52,624 $43,719 1.20
Is there a way to compare the projects to each other?
The CPI is computed relative only to what is in an individual project's plan, but it is an index, not a
dollar value. This means that it can be compared legitimately across projects. The CPI says that the
BBB are almost twice as efficient in their work as the AAA!
The ratio of Earned Value to Planned Value is another helpful metric called the Schedule
Performance Index (SPI). CPI measures how efficiently a project spends money, but SPI measures
whether it is getting work accomplished on time.
In an ideal project, the SPI is 1.0 (one). An SPI less than one indicates that the project has not
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 10 of 21
completed as much as they planned on; they are behind schedule. An SPI of greater than one
indicates that the project has completed more work than they planned on at this point; they are
ahead of schedule. The AAA's SPI is 0.26, while the BBB's is 0.83. Both projects are behind
schedule: the BBB slightly, but the AAA badly.
# Project Earned Value
(BAC * PC) Actual Cost
(AC) Cost
Performance
Index (EV /
AC)
Planned
Value
(BAC *
PPC)
Schedule
Performance
Index (EV /
PV)
Schedule
Variance (EV
- PV)
21095 AAA $11,214 $17,050 0.66 $42,754 0.26 -$31,540
20154 BBB $52,624 $43,719 1.20 $63,742 0.83 -$11,118
What does it mean that the BBB's CPI is good but their SPI is bad? The BBB are not doing as
much work as planned, but the work they are doing is being completed cost-efficiently. They will
take longer than planned to complete but will finish under budget.
Schedule Variance (SV) is another way of looking at the same information. It is the difference
between the Earned Value and the Planned Value. Numbers below zero are bad and above zero are
good. The AAA's SV is $-31,540, while the BBB's is $-11,118. At first glance, it might be
tempting to treat this as a third way of figuring under-spending. However, it is actually a measure
of schedule, not cost. As previously stated, the AAA are badly behind schedule while the BBB are
slightly behind.
How much funding is necessary to complete each project?
The last set of metrics which are helpful in this situation are the completion metrics. Estimate At
Completion (EAC) is figured by comparing the original budget to how efficiently the project is
working (CPI). If present trends continue, the entire AAA project will cost $106,563 and the entire
BBB project will cost $61,576.
Given what they've already spent, the Estimate To Complete (ETC) for the AAA is $89,513 (more
than their entire original budget), while the BBB need only $17,857 to finish. That's a handy
number for a Dev Rep to know! The AAA will need $36,475 over and above the original budget of
$70,088, while the BBB will spend $12,543 less than originally estimated (Variance At Completion
(VAC)).
# Project BAC (SC
Lifetime
Field
Budget)
Cost
Performance
Index (EV /
AC)
Estimate At
Completion
(BAC * CPI)
Actual Cost
(AC) Estimate To
Complete
(EAC - AC)
Variance At
Completion
(BAC - ETC)
21095 AAA $70,088 0.66 $106,563 $17,050 $89,513 $36,475
20154 BBB $74,119 1.20 $61,576 $43,719 $17,857 -$12,543
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 11 of 21
While the AAA and BBB projects might look similar to begin with, in reality they are performing
significantly differently. The AAA will need a different approach than the BBB. Likewise, the
progress reports from the Dev Reps to investors should level-set differently about the two projects.
The Broader Sahel...
These same techniques hold true in the broader picture for all of the Sahel projects. The Cost
Performance Index and Schedule Performance Index may both be directly compared across projects
to determine which ones are performing well and which ones are ahead of schedule.
Are Sahel Projects Delivering Good Value?
Of the 26 Sahel projects with data available for analysis, 10 had CPIs above 1, indicating that they
are efficiently delivering good value for their investment. 6 more had CPIs above 0.85, indicating
they could improve but were still performing reasonably. 10 had CPIs below 0.85, indicating that
they were performing poorly; for every dollar invested, less than 85 cents worth of work was being
done.
Of the poor performing projects, there were a cluster around 0.66 CPI and another cluster at the
bottom around 0.10. It is worth investigating to see if there are common reasons they are
struggling. It is likely that the data available in internal reporting systems for the ones around 0.10
was incomplete or the projects were too new for any trends in data.
Are Sahel Projects On Schedule?
Only 2 Sahel projects had SPIs of 1 or more, but many more were in the upper .80's and .90's,
indicating they were only slightly behind schedule. There was a fairly even spread of projects down
to an SPI of 0.62. Then there was a sharp cliff, with 9 projects below 0.35.
Are Sahel Projects Going to Complete On Budget?
Because of their CPIs, 10 Sahel projects will complete under budget, while 16 will complete over
budget, but 15 of them will complete near their budget. Most of the outliers are probably caused by
inconsistent data, but if not, some of them require drastic intervention.
It is possible to predict the amount of additional money necessary to complete each project, and in
some cases this value is quite different (either above or below) the originally budgeted amount.
Conclusion If present trends continue, most Sahel projects will complete reasonably close to their original
budget but take longer than anticipated.
As detailed in the “Progress Tracking Systems Need Improvements” section, Seed Company needs
improved systems to track project progress.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 12 of 21
What now?
IMPORTANT: This analysis is ONLY as accurate and up-to-date as the data in
internal reporting systems.
It cannot be reiterated strongly enough, this analysis is only as good as the data it is based on. It
would be poor judgment to take action solely based upon internal reporting systems. The best
people to use this data are the Area Directors and individual Field Coordinators, who are familiar
with individual projects and can validate and verify before taking action on issues.
As a concrete example of this, the analysis indicates that the AAA are under-performing while the
BBB are over-performing. Based upon available report data, that is a valid conclusion. However,
discussions with the AD and FC reveal that the AAA have actually accomplished more than
indicated because Seed Company's progress reports currently measure only direct translation while
ignoring “Other Goals” such as startup tasks. The BBB performance, on the other hand, may be
overstated because of how previous work was credited and because timeliness of their financials is
difficult (several different organizations' reports must be integrated).
Future Improvements
A carefully designed report could make assembling Earned Value Management analysis much
easier. In fact, Seed Company's systems appear to contain information to produce historical EVM
reports that may shed additional light on project efficiencies.
EVM depends upon accurate financials and accurate progress. Seed Company has excellent
financial controls and reporting in place. It has basic progress measurement for traditional written
translations, but it is sometimes out of date. It lacks rigorous tracking of progress for internships or
non-traditional projects such as oral translation.
There is a many-to-many relationship between languages and projects. Seed Company currently
tracks budgets on a per-project basis but progress on a per language basis. This analysis assumes
that each language in a project contributes an equal amount to its costs. In an ideal world, these
would be tracked at the same level.
With additional experience, it should be possible to fine-tune Seed Company's EVM analysis to
establish data-driven benchmarks indicating at which CPI and SPI levels project managers should
become concerned.
Appendix A: Raw Data URL The spreadsheet containing the raw data is located at
https://docs.google.com/spreadsheets/[Redacted]
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 13 of 21
Appendix B: Simple Under-Spend Data
Budget At
Completio
n
Actual
Cost
Planne
d %
Compl
ete
Planned
Value
Simple
Over/Unde
r Spend
Account
Number Name BAC AC PPC PV
From Reports
(SC Lifetime
Field Budget)
From
Reports From
Reports BAC *
PPC AC - PV
21144 [Redacted] $113,399 $19,314 28% $31,752 -$12,438
20374 [Redacted] $87,471 $36,728 82% $71,726 -$34,998
20324 [Redacted] $94,804 $31,578 55% $52,142 -$20,564
26232 [Redacted] $579,064 $227,612 77% $445,879 -$218,267
20224 [Redacted] $257,352 $95,991 96% $247,058 -$151,067
25711 [Redacted] $491,392 $425,587 52% $257,489 $168,098
26994 [Redacted] $171,053 $92,355 99% $168,915 -$76,560
26192 [Redacted] $453,070 $208,104 87% $394,171 -$186,067
20376 [Redacted] $63,428 $7,737 30% $19,028 -$11,291
21095 AAA $70,088 $17,050 61% $42,754 -$25,704
25360 [Redacted] $261,419 $244,587 100% $261,419 -$16,832
26593 [Redacted] $153,516 $128,678 100% $153,516 -$24,838
21064 [Redacted] $93,065 $85,246 90% $83,759 $1,488
20705 [Redacted] $116,194 $35,019 35% $40,668 -$5,649
26743 [Redacted] $238,123 $178,497 98% $233,956 -$55,459
25440 [Redacted] $166,321 $168,669 100% $166,321 $2,348
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 14 of 21
Budget At
Completio
n
Actual
Cost
Planne
d %
Compl
ete
Planned
Value
Simple
Over/Unde
r Spend
Account
Number Name BAC AC PPC PV
From Reports
(SC Lifetime
Field Budget)
From
Reports From
Reports BAC *
PPC AC - PV
26202 [Redacted] $300,195 $204,131 100% $300,195 -$96,064
26943 [Redacted] $111,883 $76,379 93% $104,051 -$27,672
28300 [Redacted] $359,794 $330,020 100% $359,794 -$29,774
26693 [Redacted] $57,233 $45,948 98% $56,088 -$10,140
26913 [Redacted] $242,465 $78,586 53% $128,506 -$49,920
20154 BBB $74,119 $43,719 86% $63,742 -$20,023
20454 [Redacted] $64,660 $37,534 100% $64,660 -$27,126
20765 [Redacted] $317,604 $114,462 96% $303,312 -$188,850
20375 [Redacted] $125,529 $58,308 86% $107,955 -$49,647
21066 [Redacted] $111,185 $19,474 36% $40,027 -$20,553
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 15 of 21
Appendix C: Input Data for Sahel Projects
Budget At
Completion Actual Cost
%
Complete
Planned
%
Complete
Account
Number Name BAC AC PC PPC
From Reports
(SC Lifetime
Field Budget)
From Reports From
Reports From
Reports
21144 [Redacted] $113,399 $19,314 0% 28%
20374 [Redacted] $87,471 $36,728 4% 82%
20324 [Redacted] $94,804 $31,578 4% 55%
26232 [Redacted] $579,064 $227,612 14% 77%
20224 [Redacted] $257,352 $95,991 17% 96%
25711 [Redacted] $491,392 $425,587 42% 52%
26994 [Redacted] $171,053 $92,355 35% 99%
26192 [Redacted] $453,070 $208,104 30% 87%
20376 [Redacted] $63,428 $7,737 8% 30%
21095 AAA $70,088 $17,050 16% 61%
25360 [Redacted] $261,419 $244,587 82% 100%
26593 [Redacted] $153,516 $128,678 75% 100%
21064 [Redacted] $93,065 $85,246 82% 90%
20705 [Redacted] $116,194 $35,019 28% 35%
26743 [Redacted] $238,123 $178,497 73% 98%
25440 [Redacted] $166,321 $168,669 100% 100%
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 16 of 21
Budget At
Completion Actual Cost
%
Complete
Planned
%
Complete
Account
Number Name BAC AC PC PPC
From Reports
(SC Lifetime
Field Budget)
From Reports From
Reports From
Reports
26202 [Redacted] $300,195 $204,131 70% 100%
26943 [Redacted] $111,883 $76,379 71% 93%
28300 [Redacted] $359,794 $330,020 97% 100%
26693 [Redacted] $57,233 $45,948 86% 98%
26913 [Redacted] $242,465 $78,586 37% 53%
20154 BBB $74,119 $43,719 71% 86%
20454 [Redacted] $64,660 $37,534 76% 100%
20765 [Redacted] $317,604 $114,462 59% 96%
20375 [Redacted] $125,529 $58,308 80% 86%
21066 [Redacted] $111,185 $19,474 38% 36%
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 17 of 21
Appendix D: Output Data for Sahel Projects
Primary Metrics
Planned
Value
Earned
Value
Cost
Performance
Index
Schedule
Performance
Index
Account
Number Name PV EV CPI SPI
BAC * PPC BAC * PC EV / AC EV / PV
21144 [Redacted] $31,752 $0 0.00 0.00
20374 [Redacted] $71,726 $3,499 0.10 0.05
20324 [Redacted] $52,142 $3,792 0.12 0.07
26232 [Redacted] $445,879 $81,069 0.36 0.18
20224 [Redacted] $247,058 $43,750 0.46 0.18
25711 [Redacted] $257,489 $204,419 0.48 0.79
26994 [Redacted] $168,915 $59,869 0.65 0.35
26192 [Redacted] $394,171 $135,921 0.65 0.34
20376 [Redacted] $19,028 $5,074 0.66 0.27
21095 AAA $42,754 $11,214 0.66 0.26
25360 [Redacted] $261,419 $214,364 0.88 0.82
26593 [Redacted] $153,516 $114,369 0.89 0.75
21064 [Redacted] $83,759 $76,313 0.90 0.91
20705 [Redacted] $40,668 $32,534 0.93 0.80
26743 [Redacted] $233,956 $173,234 0.97 0.74
25440 [Redacted] $166,321 $166,321 0.99 1.00
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 18 of 21
Planned
Value
Earned
Value
Cost
Performance
Index
Schedule
Performance
Index
Account
Number Name PV EV CPI SPI
BAC * PPC BAC * PC EV / AC EV / PV
26202 [Redacted] $300,195 $210,137 1.03 0.70
26943 [Redacted] $104,051 $79,437 1.04 0.76
28300 [Redacted] $359,794 $349,000 1.06 0.97
26693 [Redacted] $56,088 $49,220 1.07 0.88
26913 [Redacted] $128,506 $89,712 1.14 0.70
20154 BBB $63,742 $52,624 1.20 0.83
20454 [Redacted] $64,660 $49,142 1.31 0.76
20765 [Redacted] $303,312 $187,386 1.64 0.62
20375 [Redacted] $107,955 $100,423 1.72 0.93
21066 [Redacted] $40,027 $42,250 2.17 1.06
Secondary Metrics
Cost
Variance
Schedule
Variance
Estimate At
Completion
Estimate To
Completion
Variance At
Completion
Account
Number Name CV SV EAC ETC VAC
EV - AC EV - PV BAC / CPI EAC - AC BAC - EAC
21144 [Redacted] -$19,314 -$31,752 #DIV/0! #DIV/0! #DIV/0!
20374 [Redacted] -$33,229 -$68,227 $918,200 $881,472 -$830,729
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 19 of 21
Cost
Variance
Schedule
Variance
Estimate At
Completion
Estimate To
Completion
Variance At
Completion
Account
Number Name CV SV EAC ETC VAC
EV - AC EV - PV BAC / CPI EAC - AC BAC - EAC
20324 [Redacted] -$27,786 -$48,350 $789,450 $757,872 -$694,646
26232 [Redacted] -$146,543 -$364,810 $1,625,800 $1,398,188 -$1,046,736
20224 [Redacted] -$52,241 -$203,308 $564,653 $468,662 -$307,301
25711 [Redacted] -$221,168 -$53,070 $1,023,046 $597,459 -$531,654
26994 [Redacted] -$32,486 -$109,046 $263,871 $171,516 -$92,818
26192 [Redacted] -$72,183 -$258,250 $693,680 $485,576 -$240,610
20376 [Redacted] -$2,663 -$13,954 $96,713 $88,976 -$33,285
21095 AAA -$5,836 -$31,540 $106,563 $89,513 -$36,475
25360 [Redacted] -$30,223 -$47,055 $298,277 $53,690 -$36,858
26593 [Redacted] -$14,309 -$39,147 $172,722 $44,044 -$19,206
21064 [Redacted] -$8,933 -$7,445 $103,959 $18,713 -$10,894
20705 [Redacted] -$2,485 -$8,134 $125,068 $90,049 -$8,874
26743 [Redacted] -$5,263 -$60,721 $245,357 $66,860 -$7,234
25440 [Redacted] -$2,348 $0 $168,669 $0 -$2,348
26202 [Redacted] $6,006 -$90,059 $291,616 $87,485 $8,579
26943 [Redacted] $3,058 -$24,614 $107,576 $31,197 $4,307
28300 [Redacted] $18,980 -$10,794 $340,227 $10,207 $19,567
26693 [Redacted] $3,272 -$6,868 $53,428 $7,480 $3,805
26913 [Redacted] $11,126 -$38,794 $212,395 $133,809 $30,070
20154 BBB $8,905 -$11,118 $61,576 $17,857 $12,543
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 20 of 21
Cost
Variance
Schedule
Variance
Estimate At
Completion
Estimate To
Completion
Variance At
Completion
Account
Number Name CV SV EAC ETC VAC
EV - AC EV - PV BAC / CPI EAC - AC BAC - EAC
20454 [Redacted] $11,608 -$15,518 $49,387 $11,853 $15,273
20765 [Redacted] $72,924 -$115,925 $194,003 $79,541 $123,601
20375 [Redacted] $42,115 -$7,532 $72,885 $14,577 $52,644
21066 [Redacted] $22,776 $2,224 $51,247 $31,773 $59,938
Bibliography
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)–Sixth Edition. (2017).
Newtown Square, Pennsylvania: Project Management Institute
ANSI/EIA. (2005). Standard for Earned Value Management Systems (748-B). Arlington, Virginia:
National Defense Industrial Association
Summary by language size. (n.d.). Ethnologue. Retrieved November 6, 2017, from
https://www.ethnologue.com/statistics/size
File:Map of the Sahel.png. (2015, August 31). Wikimedia Commons, the free media repository.
Retrieved 22:29, November 6, 2017 from
https://commons.wikimedia.org/w/index.php?title=File:Map_of_the_Sahel.png&oldid=170292957.
.
PM World Journal Under-Spend: An Earned Value Analysis of Vol. VI, Issue XII – December 2017 60 Projects in the Sahel www.pmworldjournal.net Featured Paper by Stephen Fierbaugh
© 2017 Stephen Fierbaugh www.pmworldlibrary.net Page 21 of 21
About the Author
Stephen Fierbaugh, PMP Texas, USA
Stephen Fierbaugh is a PMI-certified Project Management Professional (PMP). He holds an MA in Intercultural Studies with a focus on Information and Communication Technologies (ICT). Stephen has extensive experience with projects which involve cross-cultural communications and geographically diverse project teams. Past roles include Director of Software Development and Director of IT. Stephen also has six years of experience as a consultant with IBM Global Services. Stephen can be contacted at [email protected]