Umpp(ultra mega power plant and international bidding )
-
Upload
gurparvesh-kaur -
Category
Technology
-
view
354 -
download
0
description
Transcript of Umpp(ultra mega power plant and international bidding )
ULTRA MEGA POWER PLANTS AND POLICY
BACKGROUND With India being a country of chronic power
deficits, the Government of India has planned to provide "power for all" by the end of the Eleventh Five-Year Plan (2007–2012).
This would entail the creation of an additional capacity of at least 100,000 MW by 2012
Ultra Mega Power projects, each with a capacity of 4000 MW or above, are being developed with the aim of bridging this gap
Launched by Ministry of Power in 2005-06
Central government has taken the initiative under tariff based competitive bidding route using super critical technology on BOO basis
Central Electricity Authority is the technical partner & Power finance corporation is the nodal agency
Separate SPVs were provided for each project to undertake project development activities including bid process management
In addition to Ultra Mega thermal power Projects, Ministry of Power is also taking steps for bringing up large Hydro Projects and large size Transmission Projects on the fast track
ROLE OF MINISTRY OF POWER
Ministry of Power to be facilitator for coordination with concerned Ministries/ agencies and State Government for ensuring:Coal block allotment for pithead projectsEnvironment/ forest clearancesFacilitate acquisition of landRequired support from State Govt. & its
agenciesTo facilitate proper payment security
mechanism with State Govt./ State utilities
CONCEPT Setting up of large projects of 4000 MW at a
single location: ensuring economies of scale Award of projects to developer through tariff
based competitive bidding : ensuring cheaper power
Utilization of super critical technology: ensuring higher efficiency and lower CO2 emissions
The first UMPP, developed by TATA Power at Mundra, Gujarat has been commissioned and contributes 4,000 MW in power to the northern grid.
Total number of UMPPs viewed are 16 ,out of which awarded are 4-
I. Sasan UMPP, Madhya Pradesh
II. Mundra UMPP, Gujarat
III. Krishnapatnam UMPP, Andhra Pradesh
IV. Tilaiya UMPP, Jharkhand
POLICIES FOR DEVELOPMENT OF UMPP
PROVISION OF ELECTRICITY ACT, 2003
Provides that regulatory commissions shall adopt the tariff if it is determined through transparent process of bidding accordance with guidelines issued by central government
Aims at moving away from cost plus approach for tariff determination & expected to encourage private sector investment
NATIONAL ELECTRICITY POLICY
Aim of this policy is to supply reliable & quality power of specified standard in an efficient manner & at reasonable rates
Policy recognizes that competition will bring significant benefits to consumers
Policy stipulates that all efforts will need to bring the power industry as early as possible in the overall interest of consumers
OBJECTIVES OF THE POLICY
Access to Electricity Available for all households in next five years.
Availability of Power Demand to be fully met by 2012.
Shortages to be overcome and spinning reserve to be available.
Per capita availability of electricity to be increased to over 1000 units by 2012.
Minimum lifeline consumption of 1 unit/ household/day as a merit good by year 2012.
Financial Turnaround and Commercial Viability of Electricity Sector.
ELECTRICITY TARIFF POLICY
Objective is to promote competition, efficiency in operations & improvement in quality of supply
To ensure availability of electricity to consumers at reasonable and competitive rates
Policy stipulates that all future requirement of power needs to be procured competitively by distribution licenses except in cases of expansion of existing projects
11
GUIDING PRINCIPLES FOR COMPETITIVE BIDDING
Competitive bidding process should ensure
• Free fair and effective competition
• Transparency
• Simplicity and cost effectiveness of process
• Minimal burden on regulator and other stakeholders
• Flexibility to adapt to varying needs of power procurement according to the structure of the sector
The new guidelines should adequately build on GOI
guidelines issued earlier by incorporating new inputs from
EA 2003 and the Task Force report
12
BIDDING PROCESS WOULD START WITH THE REGULATOR APPROVING THE DEMAND FORECAST FOR THE DISTRIBUTION COMPANIES
Demand forecast for short / medium / long term
Regulatory approval of forecast
Procurement process
Path 1
Using non-standard bid documents
Using standard bid documents
Path 2
13
PROPOSED POWER PROCUREMENT BIDDING PROCESS IF STANDARD DOCUMENTS ARE USED
Key activities/Salient points
At each stage we may specify
minimum number of bids to proceed to
next stage
Requirement definition
Initiate RFQ
Shortlist bidders
RFP Bidding Evaluation of bids
Award of bid(s)
Post bid negotiations
• Specification of – Quantum– Timing– Duration
of contract
• Publish notice
• Issue RFQ
• Evaluate responses to RFQs
• Shortlist bidders
• For short term contracts bidders may be pre- qualified
• Issue RFP to selected bidders
• Conduct pre-bid conference
• Short listed bidders invited to submit bids
• Technical compliance must for any bid to be considered
• Determination of winner on bases of price bids
• Use of independent observer if necessary • RFQ/RFP process may be combined into
single step, especially for short term contracts
Regulator kept informed at all stages of the process
14
PROPOSED POWER PROCUREMENT BIDDING PROCESS IN CASE OF DEVIATIONS FROM STANDARD BIDDING DOCUMENTS
• Any modifications suggested by bidders, or due to any other reasons to be approved by regulator – possibly over several rounds of iterations
Requirement definition
Prepare bidding documents
Initiate RFQ
Shortlist bidders
Seek regulatory approval
Iterations on development of bid documents
Regulatory clearance of forecast
A
RFP Bidding Evaluation of bids
Awards of bid
Post bid negotiations
ARegulator’s comments on process and go ahead
Even though active regulatory approval
needed in only certain stages, but the
regulator is always kept informed of all
developments
Regulatory approval if required
15
IN THE RFQ STAGE, BIDDERS SHOULD BE SCREENED ON THE BASIS OF AN ARRAY OF METRICS
Financial metricsTechnical metrics Past record
To ensure supply contracts, in case of default
To minimise risk of delay/shortfall
To prevent frivolous/mischievous bidders
• To ensure supply contracts, in case of default Net worth
• Credit worthiness • Bank/other financial
guarantees
• For new plants – Past infrastructure
project execution– Resource raising
• For existing plants– Reliability – Performance in the
past• Tie ups with
transmission companies preferred
• Should be an organization of repute
• No default on previous contracts
• Net worth • Credit worthiness • Bank/other financial
guarantees• For long term contracts
trader should show the capability/history to source 70-80% of contract amount
• Tie ups with generators and transmission companies are preferred
• Source of power has to be specified
• Trader of repute • No default on past
contracts• Past litigation record • No conflict of interest
between other obligations and contract being bid
Limits to vary by duration of contract and amount of load contracted
To be suitably relaxed in initial stages for traders, as they would have no history of trading operations
For generators
For traders
16
FOR MEDIUM/LONG TERM CONTRACTS, AT RFP STAGE, BIDS SHOULD BE SCREENED BASED ON NON PRICE EVALUATION PRIOR TO PRICE COMPARISONSElement for evaluation Details
• Financial guarantee covering supply default
• Different bidders could be capable of delivering power at different points in grid
• Most reliable/least bottlenecked point most preferable
• Relevant for time of day contracts, or for parts of long term contract
• Best fit to demand should get preference
• Bidder asking for least financial guarantee from buyer would be preferred
• Risk sharing mechanism in case of forced outages/unforeseen circumstances
Supplier’s guarantee
Delivery point
Delivery dates/period
Buyer’s guarantee
Force majeure /risk sharing
All these aspects need to be sufficiently detailed in the standard bid
documents and processes, to enable bids to be efficiently
and transparently
evaluated/ rejected on
technical merits
17
BUYER SHOULD SPECIFY THE BID STRUCTURE IN DETAIL
Whether part bidding is allowed?
What is being bid for?
What is the tariff structure used?
• No part bidding• Part bidding allowed• Part bidding allowed in multiples of some pre-specified minimum bid unit (preferred option)
• Energy• Capacity• Percentage of load (varying)
• Single part tariff• Two part tariff with suitable indexation (preferred)
Elements of a bid
Illustrative examples
Element
18
INTERNATIONAL PRECEDENTS OFFER SEVERAL USEFUL TIPS FOR FORMULATING THE COMPETITIVE GUIDELINES
Aspect International examplesReference document Issue date/number
Bidding for part of the contract
• RFP for Central Maine Power Company allows bidders to bid in multiples of 20% of total contract amount
• November 18, 2003; issued by Maine PUC
Use of Independent observer
• Independent observer was used for overseeing the process of RFP’s for Portland General Electric Company
• January 20, 2004; Interim report of independent observer
Use of discounting/ NPV calculations for evaluation
• Public service commission of Maryland approved use of single discounted average term price (DATP) for evaluation of bids in the phase II settlement proceedings
• Order no. 78710 Case no. 8908; Phase II September 2003
Pre-qualification of bidders to form a panel
• Rules of the Florida Public Service Commission on general purchasing procedures allow the prequalification of bidders to form a panel
• Ch.25-25 Sup no.194
Financial guarantees from bidders
• RFP for Central Maine Power Company required bidders to provide financial guarantees upto US$ 1.21 million/month and 1.50 million/month while bidding for service to 2 classes of consumers
• November 18, 2003; issued by Maine PUC
Bidding for percentage of load
• Rather than a fixed load (in MW/ MWh) the bid may be asked for the percentage of the utility’s load, so as to offload some risk to the suppliers
• EPSA guidebook for design implementation and monitoring of competitive power supply solicitations
Bidding for partial duration
• EPSA guidelines mention use of annuity based calculations while comparing bids for unequal (part) duration and choosing a lower overall bid portfolio
• EPSA guidebook for design implementation and monitoring of competitive power supply solicitations
19
INTERNATIONAL BIDDING PROCESS - EXAMPLE
US long term bid process
• Posting of information publicly
• Request for Expressions of Interest (EoI)
• FERC qualification
• Credit application and financial information received
• Pre-bid conference
• Eligible bidders qualified and issued certification
• Request for detailed proposals from eligible bidders
• Price proposals received
• Bids evaluated
• Award of bids
• More rounds if previous rounds fail to meet objectives
• Iteration continues till satisfactory solution reached
• Retail prices published 6 months before start of contract
Receiving proposals
Process start
Receiving EOIs
Regulatory Validation
Bidder selection
Round 1
Revision/Round 2
Contract start
Steps
Timeline
Details
3½ months
15 days
15 days
15 days
2 months
9 months
Source: Allegheny power RFPs and RFQs