Üretim 8.2-MRP Structure

download Üretim 8.2-MRP Structure

of 44

Transcript of Üretim 8.2-MRP Structure

  • 8/2/2019 retim 8.2-MRP Structure

    1/44

    MRP Structure (Contd)

  • 8/2/2019 retim 8.2-MRP Structure

    2/44

    Example 2 The Firm in Example 1 produces all

    items in Product A.

    Using Lead times and MPS, weconstruct the Gross MaterialRequirements Planas follows:

  • 8/2/2019 retim 8.2-MRP Structure

    3/44

    Example 2

  • 8/2/2019 retim 8.2-MRP Structure

    4/44

    Example 2 So far we assumed there is no

    Inventory on hand.

    If there is inventory on handfor aParent item, The requirements for theparent item and all its components will

    decrease.

  • 8/2/2019 retim 8.2-MRP Structure

    5/44

    Example 3

    Given the

    following on-handinventory, Weconstruct a Net

    RequirementsPlan:

  • 8/2/2019 retim 8.2-MRP Structure

    6/44

    Example 3 Net Requirements plan includes

    following:

    1) Gross Requirements, 2) On handinventory, 3) Net requirements, 4)Planned Order Receipt, and 5) Planned

    Order Release for each item.

  • 8/2/2019 retim 8.2-MRP Structure

    7/44

    Example 3 We now begin with A and work

    backward through the components:

  • 8/2/2019 retim 8.2-MRP Structure

    8/44

  • 8/2/2019 retim 8.2-MRP Structure

    9/44

    Example 3A: We need 80 units of B at week 7

    because we need 40 units of A at this

    week, and one unit of A requires 2 unitsof B. Therefore 2 times 40 = 80.

  • 8/2/2019 retim 8.2-MRP Structure

    10/44

    Example 3

  • 8/2/2019 retim 8.2-MRP Structure

    11/44

    Example 3 Scheduled receipts are empty because

    it is the products that we get from

    Outside. In this example, we assume that we do

    not buy any of the parts.

  • 8/2/2019 retim 8.2-MRP Structure

    12/44

    Example 3

  • 8/2/2019 retim 8.2-MRP Structure

    13/44

    Example 3

  • 8/2/2019 retim 8.2-MRP Structure

    14/44

    Example 3

  • 8/2/2019 retim 8.2-MRP Structure

    15/44

    Example 3

  • 8/2/2019 retim 8.2-MRP Structure

    16/44

    Example 3

    This example considered only product A.

    Normally, there is demand for many

    products. Scheduled program of each product

    contributes to the Master Schedule ANDultimately to the Net Material RequirementsPlan(which includes all components for allproducts).

  • 8/2/2019 retim 8.2-MRP Structure

    17/44

    Example

    Lets combine several products into asingle plan.

    Assume that product B is used inmaking products of A and S.

    It is also sold directly to the market.

  • 8/2/2019 retim 8.2-MRP Structure

    18/44

    Example

    Now we will prepare a GrossRequirements Plan for B,

    by combining the master schedules ofA,S, and B

    Master schedules for A, S, and B are as

    follows:

  • 8/2/2019 retim 8.2-MRP Structure

    19/44

    Example

  • 8/2/2019 retim 8.2-MRP Structure

    20/44

    Example

    Now we will combine all three schedules ANDcreate Gross Requirements for B:

    At period 1: we sell 10 units of B directly,therefore we should produce 10 units B.

    At period 2: we sell 10 units of B directly.Plus, We also need 40 units of B forproducing A at period 6. Because lead timefor A is 4 periods.

  • 8/2/2019 retim 8.2-MRP Structure

    21/44

    Example

    At period 3: we need 40 units of Bbecause we will use them to produce 40

    units of S at period 9.

    Therefore:

    Gross Requirements for B is as follows:

  • 8/2/2019 retim 8.2-MRP Structure

    22/44

    Example

    Period 1 2 3 4 5 67 8

    Gross Req. 10 50 40 50 2045

  • 8/2/2019 retim 8.2-MRP Structure

    23/44

    Example

    In this example, we calculated only thegross requirements for B.

    However, Remember that:

    Net Requirements = (Gross Req.) -[(On hand) + (Scheduled Receipts)]

  • 8/2/2019 retim 8.2-MRP Structure

    24/44

    Example

    Therefore, we should also consider theInventory on hand for B AND also

    Scheduled Receipts for B (if we buysome of B from other suppliers).

    Remember that, Scheduled receipts are

    the ones we do not produce and buyfrom Outside.

  • 8/2/2019 retim 8.2-MRP Structure

    25/44

    Example

    Scrapped components, Missed receivingdates, and Machine breakdowns

    May Cause changes in the MaterialRequirements Plan.

    Similarly, changes occur in MRP When

    MPS changes.

  • 8/2/2019 retim 8.2-MRP Structure

    26/44

    Example

    Computerized programs perform all thecalculations and such changes.

    So far we assumed that we produceexactly What we Need. No more or No

    less.

  • 8/2/2019 retim 8.2-MRP Structure

    27/44

    Example

    The objective in an MRP system is toproduce units only as needed, With no

    safety stock AND no anticipation offurther orders.

    Such a procedure is consistent with

    small lot sizes, frequent orders, lowinventory, and dependent demand.

  • 8/2/2019 retim 8.2-MRP Structure

    28/44

    Example

    However, when independent demandexists, A lot sizing technique called

    Economic Order Quantity ispreferable.

    EOQ technique provides a formula that

    averages (or smooths) demand over anextended time horizon.

  • 8/2/2019 retim 8.2-MRP Structure

    29/44

    Example

    Now we will compare the traditionalMRP technique (produce as needed)

    with EOQ technique in the followingexample:

  • 8/2/2019 retim 8.2-MRP Structure

    30/44

    Example 4

    Suppose that for product B, lead time is1 week, and inventory on hand is 35

    units. We will first apply the produce as

    needed approach. (traditional MRP)

  • 8/2/2019 retim 8.2-MRP Structure

    31/44

    Example 4

  • 8/2/2019 retim 8.2-MRP Structure

    32/44

    Example 4

    Now we will apply the EOQ formula:

    Economic Order Quantity (Q*) = [(2 D

    S) / H]

  • 8/2/2019 retim 8.2-MRP Structure

    33/44

    Example 4

    Here, D is annual demand for B = 1404units

    S is annual Setup cost = $100

    H is annual inventory Holding cost =$52

  • 8/2/2019 retim 8.2-MRP Structure

    34/44

    Example 4

    Therefore: Q* = [(2 (1404) (100)) /52] = 73 units per order.

    This means that, every time we give aproduction order, it should be 73 units.

    In this case, Order releases for product

    B will be as follows:

  • 8/2/2019 retim 8.2-MRP Structure

    35/44

    Example 4

  • 8/2/2019 retim 8.2-MRP Structure

    36/44

    Closed-Loop MRP

    This implies an MRP system thatprovides Feedback to scheduling from

    the Inventory Control System.All new and sophisticated computerized

    MRP systems are now closed-loop

    systems.

  • 8/2/2019 retim 8.2-MRP Structure

    37/44

    Closed-Loop MRP

    A closed-loop MRP system also providesfeedback to the 1) Capacity Plan, 2)

    Master Production Schedule, andultimately 3) to the Production Plan.

    In the Capacity Planning, For each work

    center, Load reports are required.

  • 8/2/2019 retim 8.2-MRP Structure

    38/44

    Closed-Loop MRP

    Load reports show the ResourceRequirements (in hours) in a work

    center For all work currently assigned tothat work center.

    For example, suppose that initial load of

    a work center exceeds the capacity ofthat work center (say 150hours/period).

  • 8/2/2019 retim 8.2-MRP Structure

    39/44

    Closed-Loop MRP

    Here, closed loop MRP systems allowproduction planners to Move the work

    to other periods IN ORDER TO smooththe work load in each period.

  • 8/2/2019 retim 8.2-MRP Structure

    40/44

    Closed-Loop MRP

  • 8/2/2019 retim 8.2-MRP Structure

    41/44

    Closed-Loop MRP

    Some tactics for Smoothing the workload are as follows:

    1) Sending a lot to two differentmachines for the same operation. Thisis called splitting the lot. This process

    involves additional setup for themachines, but results in a shorter time.

  • 8/2/2019 retim 8.2-MRP Structure

    42/44

    Closed-Loop MRP

    2) Moving the entire lot to anotherperiod which is near to the current

    period. Today, the most sophisticated version

    of Material Requirements Planning

    (which is called MRP II) has substantialapplications beyond Scheduling andInventory Management.

  • 8/2/2019 retim 8.2-MRP Structure

    43/44

    Closed-Loop MRP

    Once a firm has MRP system, Inventorydata can be changed by Labor Hours,

    by Material Costs, by Capital Cost, or byany Resource Variable.

    When MRP is used in this manner, It is

    usually referred as Material RESOURCEPlanning.

  • 8/2/2019 retim 8.2-MRP Structure

    44/44

    Closed-Loop MRP

    MRP II computer programs aregenerally tied into other computer

    programs. It receives such data as Order Entry,

    Inventory, Billing, Purchasing,

    Scheduling, Capacity Planning,Accounting, Warehouse Management,etc.