Typical Horizontal Formworkformwork.com.sg/catalogue/HorizontalFormwork.pdf · Typical Horizontal...

9
Typical Horizontal Formwork 2-1 7 Prop inner 1 Plywood 18mm thk 2 Secondary bearer lipped channel Primary bearer (I beam) 3 Top spigot 4 Crossbrace 5 6 Scaffold pipe 8 Swivel coupler Heavy duty frame 9 Slide on bracket 10 Bklet_v5.indd 11 8/15/08 6:48:22 PM

Transcript of Typical Horizontal Formworkformwork.com.sg/catalogue/HorizontalFormwork.pdf · Typical Horizontal...

Typical Horizontal Formwork

2-1

7Prop inner

1 Plywood 18mm thk

2 Secondary bearerlipped channel

Primary bearer (I beam)

3

Top spigot4

Crossbrace5

6 Scaffold pipe

8Swivel coupler

Heavy duty frame 9

Slide on bracket 10

Bklet_v5.indd 11 8/15/08 6:48:22 PM

2-2

Max Width 1000mmMin Width 750mm

Secondary steel bearer

Primary steel bearer

Self taping screwto lipped channel (by Site)

Slide on bracket & M12 x 30mm bolt

Universal clamp

M16 x 100 Heavy duty prop pin

WalkwayMax permissible liveload 1.5KN/m2

Steel Packer

ScaffoldPipes

(by Site)

Advantages of Tableform

Bklet_v5.indd 12 8/15/08 6:48:22 PM

Heavy Duty Support Work

2-3

Standard frames are cross braced to provide increase strength and limit differential settlement of legs in soft ground. Additional special frames are not required.

Base JackAlternately fixed base plate may be used where the foundation is level.

Maximum safe load10,000 LB (4,536 KG)

Max extension = 350mm for 44.5KN

U Head Jack

660

4’

HD

Fra

me

2’

5.6’

600

HD

Fra

me

4’

Max extension = 350mm for 44.5KN

2’, 3’, 4’, 5’, 6’, 7’4’

Bklet_v5.indd 13 8/15/08 6:48:23 PM

A typical fl at slab/capital design shows clearly the requirement of only two types of tableform to be used for typical bay.

Horizontal Formwork

2-4

Tableform using steel primaries and steel secondaries.

GL

GL

GL GL

Bklet_v5.indd 14 8/15/08 6:48:29 PM

Steel packers are used in tableform for difference in thickness between flat slab and capital to reduce convention timber box-out.

2-5

Horizontal Formwork

Using standard components such as heavy duty frames, prop frames, steel primary and secondary bearers virtually assures just about any height and size configuration required and on a limited number of re-uses assures the contractor of the most cost efficient system.

Bklet_v5.indd 15 8/15/08 6:48:33 PM

Transfering of tableform

2-6

Transport Wheel (Trolley)

Transporter

Lower the table slightly to break the bond

of the concrete by turning the prop collar

downward( approx. 50mm).

Push transporter into position and set until

it supports the tableform.

Once transporter carries the tableform

weight, release the prop inner by taking out

the prop pins and pusing the prop inner into

the frame.

The transporter can then be removed once the tableform rests on the transporter wheel (trolleys).

STAGE - 1

STAGE - 3

Bklet_v5.indd 16 8/15/08 6:48:33 PM

2-7

Insert 4 numbers of transport wheel (or 6

when required) underneath the main

corner of tableform bottom prop inner.

Lower the transporter which supports the

tableform slowly.

Once the tableform rests on the transport wheel, the tableform can be pushed into the loading platform.

STAGE - 4

STAGE - 2

Bklet_v5.indd 17 8/15/08 6:48:34 PM

Hoisting Of Edge Tableform By lifting Fork

2-8

Liftingfork type

3A

3B

3C

4A

4C

L(mm)

W(mm)

H(mm)

SWL(mm)

3000

3300

4200

3000

4200

1680

1680

1680

2600

2600

2150

2150

2150

2150

2150

1.8

1.5

1.0

1.5

1.0

Bklet_v5.indd 18 8/15/08 6:48:34 PM

Hoisting Of Tableform By Loading Platform

2-9

4

2

1

S.W.L 5.0-TON

5

150x75 RHS loading platform bracket

T20-U-Shape rebar (by site)

3 20mm wire rope (LW)

6 Timber planks (50mm thk) (by site)

5500mmClear Length

5000mm

Clear Width

Guard rail (by site)

Steel chain 13mm (SWL 5 ton)

Bklet_v5.indd 19 8/15/08 6:48:35 PM