TWO YEAR DEVELOPMENT PLAN: June 2011 - June 2013
FUNCTIONAL AREA:
PROPGRAM/PROJECT/ACTIVITY: GENERAL ADMINISTRATION AND SUPPORT SERVICES
SUB-PROGRAM/SUB-PROJECT/SUB-ACTIVITY: COLLECTING OFFICE
GOALS OBJECTIVES PROJECT/ACTIVITIES STRATEGIES TARGET/ DURATION
OUTPUT (YEAR)
1 2
Computerization of Enroll Assess the result of Admin.- collection Printing of reports June 2011 to X
ment system under Prince the previous comp regarding collection, Nov. 2011
Tech will end till the Preli of enrollment system accounts receivable,
of Second Semester. and recommend some scholarship funds and
modification. assistance.
The New Computerization Prepare for the new Admin.- collection 1. Trainings Nov. 2011 X
system start. method with some 2. Hands on prep on Nov. 2011 X
modification. ther new system
3. Enhancement of Nov. 2011 X X
the new system June 2013
Support the IGP in collecti Prepare list of IGP All fees collected Receipting of Monthly sched. X X
rentals and other fees. fund accounts. are included in the payments.
computerization.
Collection is on a manual As per no. of enroll campus cashiers. manual issuance of daily and per
method for other campusement. official receipts. enrollment periodX X
Prepared by :
NORMA L. RAGUINI, MPA
Dir., Financial Mgt. Services
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 2/10
UNIT(S)
BUDGET RESPONSIBLE
Finance Officer
Collecting Off.
Finance OfficerCollecting Office
Finance Officer
Collecting Office
Cashiers or de
putized coll. Off.
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 3/10
TWO YEAR DEVELOPMENT PLAN: June 2011 - June 2013
FUNCTIONAL AREA:
PROPGRAM/PROJECT/ACTIVITY: GENERAL ADMINISTRATION AND SUPPORT SERVICES
SUB-PROGRAM/SUB-PROJECT/SUB-ACTIVITY: Budgeting Office
GOALS OBJECTIVES PROJECT/ACTIVITIE STRATEGIES TARGET/ DURATION
OUTPUT (YEAR) BUDGET
1 2
Preparation of the BudgetBudget Proposal readyAdmin.-Budget DepComputation of budgJune 2011 to X
Proposal for CY 2012 for presentation using the guidelines Nov. 2011
and CY 2013 and defense in the set by the DBM and
respective offices such NEDA.
as DBM, Congress, and
Senate X
Prreparation of Monthly, Finished reports submi Admin.-Budget Prepare reports baseYear round X
Quarterly, and Year-End ted to the concerned on ALOBS and
Reports. authorities like the Disbursement. X X
DBM, COA, Congress
and Senate.
Prepare request of needeTo comply with the DBPreparation of APP Consolidate request Oct. 2011 X
supplies, materials, and circular of procuring prior to procureme of needed supplies and year
equipment. Commonly used sup and materials from after X
plies. different campuses.
Posting of procurement For transparency in Posting of approve 1. GAA, Prog of Exp.
regarding MOOE, Eqpt. transactions procurement by th 2. APP prepared
Outlay and Capital Outlay. head of agency an 3. Post in PhilGEPS
the BOR
Prepared by:
NORMA L. RAGUINI
Dir. Financial Mgt. Services
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 4/10
UNIT(S)
RESPONSIBLE
Budget Officer
Budget OfficerBudget Aide
Budget Officer
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 5/10
TWO YEAR DEVELOPMENT PLAN: June 2011 - June 2013
FUNCTIONAL AREA:
PROPGRAM/PROJECT/ACTIVITY: GENERAL ADMINISTRATION AND SUPPORT SERVICES
SUB-PROGRAM/SUB-PROJECT/SUB-ACTIVITY: Accounting Office
GOALS OBJECTIVES PROJECT/ACTIVITIES STRATEGIES TARGET/ DURATION
OUTPUT (YEAR)
1 2
Certification of availabilit Prepared vouchers Admin.-Accounting Based on GAA release Year round X
of funds based on GAA,
Program of Expenditures
approved by the BOR
Preparation of reports on For submission to the Prepare Trial BalanceBased on General July 2011 X
quarterly and yearly basi COA and other pertinent Ledgers, Journals Oct. 2011 X
reports. Jan. 2012 X
Preparation of payrolls For payment of service Prepare payroll. Based on every week
including NBC 461 cycle of regular employees. services rendered
and 3, bonuses and cash May & Nov. X X
gifts.
Computerization of acctg.To facilitate preparatio 1. Training of 1. Training Jan. 2012 X
process. of acctg. Process for accountant, acctg. 2. On hand usage Dec. 2013 X
easy access by stake clerks 3. Enhancementholders
Prepared by:
NORMA L. RAGUINI. MPA
Dir. Financial Mgt. Services
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 6/10
UNIT(S)
BUDGET RESPONSIBLE
Accountant
Accountant
Accounting Cler
Payroll clerk
Accountant
Accounting Cler
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 7/10
TWO YEAR DEVELOPMENT PLAN: June 2011 - June 2013
FUNCTIONAL AREA:
PROPGRAM/PROJECT/ACTIVITY: GENERAL ADMINISTRATION AND SUPPORT SERVICES
SUB-PROGRAM/SUB-PROJECT/SUB-ACTIVITY: Cashier's Office
GOALS OBJECTIVES PROJECT/ACTIVITIES STRATEGIES TARGET/ DURATION
OUTPUT (YEAR) BUDGET
1 2
Distribute payments of To facilitate paymentPrepare checks. See to it that payrollevery week. X X As per Release
employees - regular and of salaries and wage Encash Checks. are prepared as GAA for regu-
casual. of employees. Distribute salaries basis for payment of lar employees.
and wages to salaries. As per BOR ap
employees, For Wages - paymenevery collection proved budget
from Prelim for contractual
Midterm and employees.
Finals. X X
Payment of other expensPayment of expense Prepare checks for Follow the Program every re subject to
reimbursement and cash based on released said payees. of Expenditures. quest for availability of
advances to employees, GAA and BOR approved payment. funds.
suppliers and contractorsProgram of Exp.
Distribute payments of Salaries of regular Submit list of emploPreparation of sche every X X
regular employees using employees maybe yees and their salardule of payment. payday.
the ATM. withdrawn to the schedule to the
bank of any ATM servicing bank of
machine outlet. choice.
Prepared by:
NORMA L. RAGUINI, MPA
Dir. Financial Mgt. Services
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 8/10
UNIT(S)
RESPONSIBLE
Cashier
-
Cashier
Clerk
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 9/10
TWO YEAR DEVELOPMENT PLAN: June 2011 - June 2013
FUNCTIONAL AREA:
PROPGRAM/PROJECT/ACTIVITY: GENERAL ADMINISTRATION AND SUPPORT SERVICES
SUB-PROGRAM/SUB-PROJECT/SUB-ACTIVITY: Financial and Management Services
GOALS OBJECTIVES PROJECT/ACTIVITIE STRATEGIES TARGET/ DURATION
OUTPUT (YEAR)
1 2
Preparation of the Progra Program of Expendi Prepare estimate ofComputation of Oct 30, 2011 X
of Expenditures for CY 20 tures for Use of income as bases fo wages of contractual Nov. 2, 2011
and CY 2013. Income including allocations to diff. teachers, contractual
Fiduciary Funds ready.campuses. laborers, honoraria
of personnel, excess
load, personnel deve X
lopment fund, incen X
tives and Christmas
Gifts. X X
Financing the program Provide for wages of Day to day collectioPrepare schedule of Jan. 2012 X X
based on collection of regular contractuals, payment to June 2013
use of income and trust laborers, MOOE,
funds. Equipment Outlay
and Capital Outlay.
Prepared by:
NORMA L. RAGUINI, MPA
Dir. Financial Mgt. Services
8/3/2019 Two Year Development Plan
http://slidepdf.com/reader/full/two-year-development-plan 10/10
UNIT(S)
BUDGET RESPONSIBLE
As per attach Finance Officer
Program of
Expenditure
for CY 2012
and CY 2013
and suppor
ting document
-do- Finance Officer